HomeMy WebLinkAboutAgenda - 12/11/2008 - 4hORANGE COUNTY.
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: December 11, 2008
Action Agenda
Item No. 4 - h
SUBJECT: Capital Project Funding
DEPARTMENT: Finance
PUBLIC HEARING: (Y/N) No
ATTACHMENT(S):
INFORMATION CONTACT:
Gary Humphreys, 245-2453
PURPOSE: To approve a plan addressing additional funding needs related to the School and
County Capital Project Funds by appropriating fund balance of $3.5 million in FY08-09 and $2.4
million in FY 2009-10.
BACKGROUND: As previously discussed with the Board at work sessions on October 28th
and November 18th in preparation for year end reconciliation, areview of the School and
County capital project funds revealed a difference in budgeted and actual revenues. In general,
the differences in budgeted and actual revenues exist because:
1. Differences existing prior to the transition from the financial legacy system to MUNIS
business system in 2003 were never corrected;
2. Proceeds from past debt financings were set aside in an unallocated account or line item
instead of being allocated to specific projects;
3. Grant monies were budgeted and not awarded/received;
4. Total expenditures exceeded the project budget by varying amounts;
5. Specific projects were budgeted but monies were never transferred from the General
Fund; or
6. Bond monies to be issued are already budgeted but the revenue has not yet been
received.
Based on staff's internal analysis, unallocated revenues within the capital project funds can be
transferred to projects where there are shortfalls. This will leave a revenue shortfall of $5.9
million. The following chart summarizes the funds available and net shortfall by capital fund.
Source of Funds School Capital County Capital
Pro'ect Fund Pro'ect Fund
Additional Funds Needed $8,430,000 $9,291,944
Unallocated Alternative Financing $1,347,000
Unallocated Bonds 907,000
School Capital Reserve Funds 580,000
From Closed Projects 455,000
Interest Earnings $ 875,000
Revenue Available within Projects 2,136,255
Total Funds Available b Fund $3,289,000 $3,011,255
Grand Total Funds Available $6,280,689
Park Bonds to be issued to com lete ro'ect fundin 5,500,000
Net Shortfall $5,141,000 $780,689
Total Both Funds $5,921,689
Staff Proposal for Covering Remaining Shortfall
As stated earlier, $5.9 million in additional capital funding is needed to cover the shortfall.
Based on current year cash flow needs, at least $3.5 million of the shortfall is needed in the
current fiscal year. The remaining $2.4 million will be needed in FY 2009-10.
Staff s analysis shows the majority of the remaining shortfalls resulted from differences between
the pay-as-you-go funds budgeted for projects in the two capital project funds and the amount of
money transferred to the two capital projects funds from the General Fund. Most of these
differences existed when the conversion to MUNIS was made. This means they occurred prior
to the end of fiscal year 2003 over one or more fiscal years. If those additional amounts of pay-
as-you-go revenue had been transferred from the General Fund, the fund balance would be less
than it currently stands.
Staff recommends the Board approve atwo-year funding plan to .replenish the shortfall by
appropriating General Fund available fund balance.
Based on preliminary estimates, the County's General Fund available fund balance at the end of
FY 2007-08 is projected to be approximately 14.4% of expenditures or $24.7 million. If this plan
is implemented, based on conservative projections, the projected available fund balance at the
end of FY 2008-09 could be approximately 12% of expenditures or $21.85 million. The
appropriation of $2.4 million in FY 2009-10 would decrease the fund balance to 11.1 % or $21.64
million. While this percentage amount is higher than the Local Government Commission
recommendation of a minimum 8 percent of expenditures, it is below the staffs recommended
target of 15 percent of expenditures.
Staff will bring budget amendments to the Board to implement the recommended action if
approved by the Board. Additionally, budget amendments will be brought to the Board in those
cases where project expenditures have exceeded the project budgets and where appropriation
of other identified sources, such as the transfer of the remaining School Capital Reserve Funds,
is necessary.
3
As best practice, local governments should only appropriate fund balance for non-recurring
purposes such as capital. While it is preferable to be able to achieve the fund balance goal in
order to meet needs in time of fiscal stress, the use of the fund balance to meet non-recurring
priorities is understandable. It would be prudent to not let the fund balance fall below 11 % in
order to provide for cash flow as well as maintaining the County's excellent bond rating. Once
funding the shortfall is completed, it is recommended that steps be taken to rebuild the fund
balance of the General Fund.
FINANCIAL IMPACT: The financial impact of the recommended action is the projected
reduction of the fund balance of the General Fund to as low as 11.1 % of projected FY 2009-10
expenditures.
RECOMMENDATION(S): The County Manager recommends that the Board approve the two
year funding plan which includes: 1) Appropriating $3.5 million from the fund balance of the
General Fund for transfer to the School Capital Project Fund and County Capital Project Fund;
2) Include the remaining appropriation of $2.4 million from the fund balance of the General Fund
needed to complete the correction of the shortfall in the Fiscal Year 2009-10 budget; and 3)
Direct staff to take those actions necessary to reallocate available funding to correct the project
shortfalls and to bring back to the Board the budget amendments necessary to implement this
plan.