HomeMy WebLinkAboutAgenda - 10-05-1999 - 9hORANGE COUNTY.
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: October 5, 1999
i
Action Agenda
Item No. ~_
SUBJECT: Corbin Downs
DEPARTMENT: Planning
PUBLIC HEARING: (Y/N) No
ATTACHMENT(S):
None
INFORMATION CONTACT:
Craig Benedict, ext 2585
TELEPHONE NUMBERS:
Hillsborough 732-8181
Chapel Hill 968-4501
Durham . 688-7331
Mebane 336-227-2031
PURPOSE: To discuss BOCC recommendations regarding the proposed Corbin Downs
development.
BACKGROUND: The BOCC is slated to discuss the Corbin Downs project during its
September 30 work session. Additional materials related to this topic for the October 5 meeting
will be developed following that work session.
FINANCIAL IMPACT: To be determined.
RECOMMENDATION(S): To be determined.
10f05f1999 @4:08 9196443002 OR. CTY. PLANNING
ORANGE COUNTY
BOARD QF COMMISSIONERS
WORK SESSION ITEM ABSTRACT
Meeting Date; October 5, 1999
PAGE 02f14
1
Action Agenda
Item No.
SUBJECT: CORBIN DOWNS IMPACT REPORT
DEPARTMENT: Planning and Inspections
ATTACHMENTS}:
1. Letter to the Town of Hillsborough
2. Corbin Downs Impact Report
PUBLIC HEARING: {YIN) No
INFORMATION CONTACT:
Craig N. Benedict, ext. 2592
TELEPHQNE NUMBERS:
Hillsborough 732-8181
Chapel Hill 968-4509
Durham 688-7331
Mebane (336}22T-2031
PURPOSE: To forward letter and recommendations to the Town of Hillsborough regarding Corbin
bowns.
BACKC3ROUND: As a follow-up to the September 8, 1999, Joint Public Hearing and the
September 34, 1999, Board of County Commissioners work sessions.
FINANCIAL IMPACT: A preliminary fiscal impact statistical report is attached. The tables note
expenditures (Table 1) and revenues (Table 2)_
RECOMMENDATION{S}: To receive as a report and forward letter to the Town of Hillsborough.
10f05f1999 04:0$ 9196443002 OR. CTY. PLANNING PAGE 03f14
ORANGE COUN~~'" PLANNE\TG DEEARTMENT
3061 REVEL ROAD
HILLSBOROUGH,1vORTH CARQL~NA 27278
September 30, 1999
Mayor Horace Johnsozt
p.0. Bax 429
Hillsborough, NC 27278
lte: Corbin Downs
Dear Mayor:
~~~nR er e
~i
Y ~
a u
w~ r t~sc~~
P
~-
O
The Board of County Commissioners thanks you and your council for the opportunity to
hear fram your staff anal the developer regarding the proposed Corbin Dawns
development. The level of cooperation regarding the planning and impact of this project
is sincerely appreciated.
At the September 8, 1999 joint public hearing all participants offered some important and
eonstzuctive input concerning the impact of the project. The Board of County
Commissioners and our staff continued reseazch and reviewed additional material on
Corbin Downs at a special work session on September 34, 1999,
Based on information received at the meeting and subsequent material from N.C.
Departxxi.ent of Transportation, Orange County Planning staff has continued their atzalysis
of the project as it zelates to Orange County impacts.
We would respectfully request that the additional recommendations and comment by staff
and Commissioners at our work sessions and the October S, 1999 Board of
Commissioners meeting be incorporated in the public record of your public hearing
process.
Again we thank you for the continued coordination in the review of this project that will
lead to the best possible outcomes for the residents of the Town of Hillsborough and the
citizens of Orange County.
Sincerely,
Alice Gordon, Chair
Orange County Board of Commissioners
g:ScraiglhJohnson110-5-99k1g
10!05/1999 04:08 9196443002 OR. CTY. PLANNING PAGE 04/14
CURBIN ~QWNS
Note: R = Recozxxcxxendation
C =Comment
RECQMMENDA.~'~ONS
l.. 'TRANSP0~2TA'x'TON
'flee timing of these improvements should be noted ixl the Development Order.
OLD NC 86
Rl A four lane divided cross-section with turn lanes should be provided along
Old NC $6 for a distance 300 feet north of the Lafayette Dxive/N W
Project Drive ezttrance to Interstate 40.
R2 Signalization should be required at the Hillsborough Place Parkway
Intersection and the Lafayette DrivelNW Project Drive Intersection an Old
NC 86.
R3 Right and left turn lanes should be provided on NW Project Drive at the
Intersection with Old NC 86.
Ra A left turn lane should be provided on Hillsborough Place Parkway at the
Intersection with (}ld NC 86.
RS Access points along Qld NC 86 should be limited by a platted non-
vehicular access line. The access drive directly north of Hillsborough
Flare Parkway onto Old NC 86 should be controlled by a limited access
median opening (i.e., right irr -right out and southbound left-in).
NC 86
R6 An improved four lane divided cross-section with. turn lanes should be
provided along NC 86 fox a distance 300 feet north and 300 feet south of
the Intersection of Hillsborough Place Parkway and NC 86.
R~ A left turn lane should be provided on Hillsboxough Place Parkway at the
Intersection with NC $6.
R$ Signalizaxion should be required at the Hillsborough Place Parkway and
NC $6 Intersection.
g:\craiglcd-trans110-4-99~dg
101@511999 ®4:08 9196443002 QR. CTY. PLANNING PAGE @5/14
COR,BIN DOWNS
(continued)
l[NTERNAL
R9 Access points along Corbin Downs (CD) Parkway and NW project loop
road should be limited and located directly across frozxt each other. Left
and right turn lanes should be considered at these intezsections.
Rxp A traffic light should be considered at the intezsection of Corbin Downs
Parkway and the NW project loop road.
R, ~ Stubouts should be considered for the lot directly south of the proposed
Hotel and the undeveloped lot directly south o£ Site Drive.
R12 Also, anothez stubout should be considered east which could eventually
provide another coxu~ection to NC 86. (Use Pletcher Drive and new zvad
along northern perimeter.)
R~3 Park and Ride lots should be indicated and potential Tzansit stops shown.
Rta Genexal -Please see attached letter dated August 26, 1999 from North
Carolina Department o£Txansportation from Mr. Faulkner to T.J. Dyer.
Orange County concurs with their ftndings and strongly zecozz~ends the
information noted under the category "Other" vo. page 3.
COM1VxEN'~'S
C~ The project does not have a center core to promote a txausit-oziezxted
development axtd to assist in a pedestrian friendly environment. Suggest
relocating multi-family land uses to a central area surrounded by
towzthozxtes and single family. The central area could include transit stops
and village (neotraditivnal) greens.
C2 The application does not show i£ownership is in place £ax the NW Project
Drive.
C3 Transportation Systems Management (TSM) and Parking Managezaaent
(FM) aim at getting the best use of existing transportation resources at
least cost.
Ca Other TSM strategies include: preferential parl~ing £or carpooIers;
prozx~.otions for transit, carpooling, biking, walking and flextime;
designation v£ Transportation Coozdix~ators at employment sites; and
shuttle sezvice to and from pazk-and-tide lots.
g:\craig\cd-trans110.4-99~dg 2
10f05f1999 04:08 9196443002 OR. CTY. PLANNING PAGE 06/14
CORBIN DOWNS
(coptizrued)
Cs Communities with spot congestion pzoblems attributable to new
development should consider special permits, and developer agreements
secured by covenants. These instruments may involve less tune
consuming review and consensus building with decision makers to gain
passage. They also may require only staff review and negotiations to
carry out. Developer agreements also are mote appropriate for securing
specific physical facilities such as bike racks, transit turn outs or parking
areas devoted to carpoolers.
Z. SCHOOL - (DIRECT COUNTY SERVICES)
R~ Developer to purchase a 30-acre feasible Middle School site that is in a
location acceptable to Orange County anal the Orange County School
District. The site must have cost effective access to utilities and major
transportation routes and be primarily free from environmental
encumbrances.
R2 Developer should agree to $200 above the ezcisting Orange County School
District school impact fee at the tune a building permit is issued.
R3 The developer should complete an affected school capacity analysis aver
the residential schedule of the project to determine potential over-capacity
situations and suggest azzd offer mitigation strategies-
Ca The school impact of the project does not address the full capital needs of
school construction and capacity. The developer should offer capital site
or building improvements for the middle school site in Borne form to
reduce the overall future costs.
3. BUILDING PLAN REVIEW & INSPECTIONS SERVICES
R~ The Town of Hillsborough and Orange County should sign a formal
agreement for services. Orange County planning & Inspections
Department Building Inspections Division is responsible for the
enforcement of the NC Building Code in Hillsborough and additional staff
would be required for this project.
4. PAINS AND RECREATION - (IaIRECT COUNTY SERVICE)
R~ Oran;ge County provides the majority of recreation opportunity within
Hillsborough. There would be an immpact on programs anal sport field
activities and the need far Active Park space.
g:lcraiglcd-trans110-4-99~dg
10f05f1999 04:08 9196443002 OR. CTY. PLANNING PAGE 07f14
CO~BIN DOWNS
(continued)
Ra The active park location should be relocated to provide for community
access, amelioration from sports lighting on residential properkies, and
shared working opportunities.
R3 An established standard of active parks and recreation acreage per 1004
population is 5 acres. Therefore, approximately 10 acres should be
dedicated.
5. ERASION CONTROL - (DIRECT COUNTY SERVICE)
R1 The Plazuiing and Inspections Department, Erosion Control Division is
responsible for permitting and inspections. A project of this scale -and use
should develop a high itatensity erosion control program including full use
of phasing and BMP's.
ZZ,2 Additional persoztnel may be necessary.
R3 A phasing prograzaa should be developed to decrease the total- amount of
unvegetated areas at any one time.
6. PUBLIC ~'~:A-NSIT' - (DIRECT COUNTX SERVICE)
Ri The QPT would be impacted for the variety of uses that are anticipated;
senior citizens, apartment housing, hotel, industry, offices, retail
destinations, and the suggested development of a pazk and ride lot.
7. LANDFILL - (LOG IJIItECT SERVICES)
R~ The construction phase would include a high amount of Construction and
Demolition t~-aterial with later ongoing garbage generation and recycling
needs. Recycling Center area to be added to the site.
$. PHASING OF PROTECT
12.1 The sequence o!f construction, buildzng use type and infrastructure is
critical to the cost(benefit of the entire proposal.
g:lcraig\cd-txan~s~ I Oy4-99\dg
1@f05f1999 @4:@8 9196443@@2 OR. GTY. PLANNING PAGE @8f 14
C~RB~N DOWNS
(continued}
9. ECONOMIC DEVEI,,OPMENT - (EDDIMTC)
Rl This development is within the County's Economic Development District
of the County's Land Use Element. The project is appropriately located
for non-residential development once adjacent local road improvements
are made to safely connect this project to Interstate I-40 and I-85. 'his
project would be the anchor of ecozzomic developzx~ent efforts of the
County since it is a prime location. In that regard, the adherence of the
project to the adopted EDD design guidelines and the MTC {Major
Transportation Corridor} rules is paramount to ensure an excellent
precedent fax quality non-residemial development in Hallsboxough and the
County.
R2 Indications are present within the application, that aesthetics of the entry
feature, site plan concepts and landscaped streetseapes are important to the
developer. The County can assist in developing a prominent entry feature
to an EDD with great potential.
10. OPEN SPACE
Ri Specify percentage required overall and per phase, exclusive of setbacks,
buffers and pedestrian ways;
Rz Differentiate recreational and low-impact open space, and require a mix of
both;
R3 Protection plan for existing vegetaion, especially specimen trees and
sigxtihcant forest stands;
Ito Can require cormzzzexcial buildings to go up, not out;
Rs Require buffer along Qld 86 by hotel where currently not required to
screen from roadway.
I1. COMMUNITY VALUES
Ri Integrate affordable housiatg into this development, not on separate parcel
unless that can be served by water arld sewer;
Rz Prohibit open burxiing of debris from site clearing as a health and
environmental issue.
R3 Study the impact on downtown Hillsborough.
g:\craiglcd-transll U-4-991dg
10f05/1999 04:08 9196443002 OR. CTY. PLANNING PAGE 09f14
CORBIN nowNs
(continued)
1.2. TAX REVENUE
Genexal -The project is estimated as revenue neutral at this paiwt assuming full buildvut
of projected square footage and assuzx~ed taxable values. Any decrease in revenue
vaziables would create a de~.cit county fiscal service cast situation.
R~ Developer and/or Town of Hillsborough should reevaluate the project
using county Tax Assessor's criteria. The esti~onates from the applicant of
property/building value seem. high at this tirzte and should be subject of
further review using comparable and market value vs. tax rate ratios.
C1 The projected property value at project completion is $239,109,467. Tlae
chart below analyses the dwelling uxtit values, non-residential scl. ft. value
and the value per acre.
YEAR 3
DWELLINGS SPEIt UNIT OR AG FAR
UR SQ. FT. PER SQ. FT.
60 $2oo,aoo SF 22.6 $s31,0ooJAc
s4 $140,000 TH 6.77 $1,116,700/AC
100 $150,000 AL 10.6 $1,415,100/AC
30 $120,OOOIt. 5.0 $720,000/AC
230 $65,700 MF 19.2 $788,6041AC
100,000 SF $70 SF OFFICE 10 $700,000/AC .28
50,000 SF $100 SF RETAIL 7.17 $697,000JAC .16
200 $60,000 HOTELJRiVI s.0* $2,000,000/AC
$70 SF OFFICE 3.0* $1,167,OOOlAC .38
*XEAR 2
The projected values noted by the applicant should be considered with the following
caution,;
a} The property values are the basis of summaryJxevenue benefit analysis tax
b) The values appear high for various uses and could distort the expected
revenue amount.
c) The market values could be further reduced by taxable value assessment
which at times does not fully reflect market value.
d) The actual amount of building squaze footage is likely to be less after site
plan constraints.
g:lcraiglcd-tzans\10-4-99~dg 6
1. Community Maintenance Total
2. General Adrainistrasion Total
3. Taxation and Records Total
4. Cornrnunity Planning Tool
5. Nurnan Service Total
Social Services Total
Health Total
Othef {Aging, Iabrary,
PBcR, etc.)
5. Public Safety Total
7. Public WorlCS Total
8. Educaition Total
9. Non-Departmental Total
Total Expenditures
Expenditures '
1999-00 Manager Percentage Per Capita ~ 110,004 Per Capita Q 4S,000 NOTE Per Capita
Reconomendatioa
' 5erv. Pop. Mix
$ 1,139,006 I.13 14 $25.31 $I0
35
S 3,584,887 3.56 532.59 $79.6b .
$32
59
S 2,305,096 2.29
0. b
$51.22 .
$20
96
S2,099,527 2.09 $19.09 4.66 25"/,' .
$11.67
522,112,944 21.98' Ol. 3 $491.40 $201.03
$12,280,575 12.20 S 111.64 5272.90
$ 4,757,088 4.73 $43.25 $105.71
$ 5,075,281 5.04 S46.14 ~ $112.78 10°/,~
$ 8,992.764 8.94 $81.75 99.84 65°/d $129.89
$ 3,431,552 3.41 $31.20 $76.26 576
26
$36,580,779 36.35 $322.55 $812.91 .
$812 91
$20,374,947 20.25 18 3 $452.78 40°14 $185.23
$100,621,502 100 $914.74 $2,236.03 51,293.49
Realdent Pepulat5ion
Type NO. PPH TOTAL.
Underline=applicable service population
ti?Sfi Share o(Gow~ty tieamL swieeo) aooe~eelso eo bodldiu~ impeeNoa aerviea,
mondoualon witlf n~ionalkangiurttlfbe PlmniaS and seoamode @cabpaient auoaieEeA
aerv6uct
'~sSSS shoe of C:aen~ ¢mm s setvl°se) ooeO raYla b ytgl s6a~smy.N.,na ooru~lo0e
ix(s ~.
'-~G share e(Gouat7 °cadept o°+a edaroe lap W at ioepaero m oehGde sgety Sodine,dsDt servlea
(ao6oa6, ooontyNideAuitdl~t,e~e.)
~-lost share olCaanty for rhle avaifolipry of nay (iae x~niaea sow r library > bm, pr(o k gee
Single Family 180 x 3.5 630
Town house 91 x 2.5 = 228
~ Alns ~~ ~ x 2.0 920
Assisted Living 100 x 1.0 = 100
Retirement 60 x 1.0 = 60
TOTAL, 1,938
SubWtal Cast to provide Services to Resident Pop = (],,293.44 x 1,938)
Non-Rexident Population
Trips/Day
Employees` 4,632 9,264
Patrons 13,052 26,103
TOTAL 17,684 35,367
{17,bE4 ~ 4) = 4,421
Per Capita Non-
Itesident
11.6?
>Z~
99.92
122.87
_$2,506,784.00
x $122.87 $543,208.27
GT $3,049,992.27
10/05/1999 04:08 9196443002 OR. CTY. PLANNING
TABLE
REVENUE
I999-00 Maaager Recommendation Percentage
A. Total Property Tax $64,872,798 64
47
8. Total Sales tax $13,948,795 .
13
86
C. Total Licenses and permits $ . gQ7,400 .
90
D. Total. intergovernmental $11 677 669 1 I
61
E. Total Charges Service $ 4,938 837 .
4
91
F. Total Miscellaneous $ 4,275,503 .
4
25
G. Total Revenue $100,621,502 .
1Q0
PA
$243,000,000 (Estimated Value of Project)
.00917 (County Tax Raie)
$ 2,22$,310 A 64.47% prnperty Tax
479,206 B 13.86% Sales Tax
345.b35 X 10% {Mix of C, D, E, F) Misc. Revenue
$ 3,053,151 88.33% (Less than 100% Because all Revenue Sources
are not Completely applicable)
10i05f1999 @4:08 9196443002 t]R. CTY. PLANNING PAGE 12f14
f o ~ ~~~
~..--._
~. _.
s SEP 2 ~9°
~-~~~, ~
STATE Ot+ NORTkI CAROLINA ~ ~' ~~~ ~ TRAN.SPORf~~lO>i
DlV1Si4i~ OF HIGHWAYS ~ 1in ~ ~~~
DEPARTMENT OF TRANSPORTA~~ 1 ~ ~'°~:"_~:s -.
.~.
Jaynes B. Hunt Jr. ~.o. Box zszat, RALEIGH, tv.c. 27b1 t-5201 David McCoy
CiaVERNOR SECRETARY
August 26, 1999
MEMORANDUM
In reply refer to
File No. SC-99-123
TO: T.J. Dyer, P.E., District Engineer
(Attention: M. Venable)
FROM: G.C. Faulkner, Design Review Engineer ~ ~~,_,_,_
Congestion Management Section
SUBJECT: Proposed Hillsborough Assemblage Access onto NC 86, SR 1009
Orange County
Per your request, the Access Review Squad of the NCDOT Traffic Engineering Stanch has
corripleted a preliminary review of the subject site. Based an our analysis of the site plan and the
submitted portion of the TIA performed by Kimley-Horn and Associates, Inc. w-th consideration
to its impacts on the adjacent traffic facilities, we offer the following cana.ments:
Background
SR 1006 (Old NC 8b) is a two-lane major thoroughfare with a 1997 ADT value of 1 x,700
vehicles per day. NC $6 is a two-lane major thoroughfare, with a 1947 ADT of 11,500 vehicles
per day and a posted speed limit of 45 miles per Dour. SR 1224 is a service road which connects
to Old NC 86 from the west approximately 1,400 feet north of the westbound rarzzp terminal of
the I-40 t Old NC 86 interchange.
Proposed Development
The multi-use development is proposed to be located between NC 8t5 anal Old NC 86, north of
I-40, and is proposed to include single-family homes, towtaltouses, apartments, a hotel. an
assisted living community, a day care facility, a fire station, and extensive retail and office
development. Requested access to the site is includes a full movement access connection onto
Odd NC 86 opposite Lafayette Drive, a full movement access onto Old NC 8d between the I"40 /
Old NC 86 interchange and SR 1224, and a full movement access onto NC 86.
10!05!1999 04:08 9196443002 DR. CTY. PLANNING PAGE 13!14
T.J. Dyer
August 26, 1999
Page 2
Thoroughfare Pign
The 1997 Transportation Flan for the Town of Hillsborough indicates the zteed for NC $6 and
Old NC $6 to be widened to multi-lane facilities within the project vicinity.
Trip Generation
Based on the methodology of the ITE Trip Generation Manual {6th i;dition), the proposed
development is expected to generate approximately 35,36? trips per average weekday. The
breakdown of entering and exiting traffic at peak hours is listed below.
PEAK HOUR ENTER E.X,j1T
.~~ ,
A.M 1,450 835
PM 1,SZ0 2.008
ObservationslReeommendatio~as
Given the rnafznitude of this development anal its proximity to I-40 and l-$5, we recommend a
complete Traffic Impact Analysis (TIA) be performed which identifies current land use proposals
within the site, and addresses the capacity of the I-40 I Old NC 86 interchange as it stands to be
affected by the proposed development. Given the limited information available addressing land
use, the location of the proposed driveway caztnections, and the lane geometry of these
connections, it should be noted that the following traffic related eonnxnents are preliminary.
Old NC 86 Access. Southern Drive
Given, the high traffic volumes expected on Old NC 86 and the function of Old NC $6 as a
major north-south connector between I-40 and the Town of Hillsborough, it appears a multi-
lane divided t ~~
_ _ ype.facility is appropriate for Old NC 86 in the vicinity of the project. In order
to provide ~fuIl moveizaent access onto Oid NC 86 it will be necessary to eompIy with the
current t1~Iedian Crossover Guidelines {June, 1998}, should a divided type facility be
implemented. With a 55 mile per hoax speed limit postine, a minimum of 1,500 feet is
required between median openings; with a 45 mile per hour speed limit pasting, a minimum
of 1,000 feet is required between median openings. This criterion should be considered when
determining the final location of the proposed driveway connection onto OId NC 8b.
• We recommend the existing service road Located approximately 1,400 feet north of the I-~0 /
Old NC 86 interchange and the proposed driveway be aligned.
• Given the high traffic volumes associated with the site and its southernmost access
connection, a multilane facility should be constructed {as a rzainimum) betweexx the southern
I-40 !Old NC 86 ramp terminal and the main development entrance.
OId NC 86 Access, Northern Drive
• We concur with the proposed location of the driveway Located opposite Lafayette Drive.
• We recommend providing a northbound right-turn lane on Old NC 86 to renaot-e turning
vehicles from the through ctzavement.
• We concur with the proposed Southbound left-turn lane on Old NC 86.
10!05!1999 04:08 9196443002 DR. CTY. PLANNING PAGE 14/14
T.J. Dyer
August 26, 1999
Page 3
NC 86 Access
We concur with the proposed southbound right-turn lane and northbound lefr-turn lane at this
driveway.
Other
• The traffic information provided did rat address any traffic impacts this development will
have on the critical 1-40 /Old NC 8b interchange area. We strongly recommend traffic
impacts to this interchange be determined and addressed before any access connections to
this development are considered.
• We have concerns with the proposed new internal road connecting NC 8b to Old NC 8b
through the site. This new facility would function as a major connector between these roads
and is expected to serve a significant volume of traffic not associated with the proposed
development. It appears from the current development sketch plan that this new road is
proposed as a two-lane divided facility with many closely spaced median breaks, which could
pose operational and safety problems. If the developer anticipates addins~ or petitioning? for
addition to the State System, all roads should be designed and constructed in conformance
with, the eurzent North Carolina Department of Transportation design and construction
guidelines.
• We also have concerns with the impact this development will have on the I-85 /Old NC 8b
interchange. Although there is considerable distance between this interchange and the
northernmost development driveway, much of the traffic entering and exiting the site is
expected to utilize the 1-85 !Old NC 86 interchange. Consideration should be given to
including capacity analysis for this interchange as part of the recommended TIA.
Closing
In addition to the above recommendations, reference should also be made to the information
included in the General Recommendations Attachment. If we can provide further assistance.
please contact G.C. Faulkner or myself at 25~-41ST .
CrCFlRWSlMAD:md
Attachment
cc: J.W. Watkins, P.E. (Attention: V.E. Barham)
J.F. Permar, P.E.
T.A. Peoples, P.E. (Attention: E.Y. Stafford P.E.)
T.M. Hopkins, P.E.