Meeting Date: August 15, 2000
Action Agenda
Item No. ~°Q
SUBJECT: Oran, a Coun ,'s__Appointed OWASA Board Members
DEPARTMENT: County Commissioners PUBLIC HEARING: (Y/N) No
ATTACHMENT(S): INFORMATION CONTACT:
Moses Carey, Jr., Chair
Two-Page Outline on Presentation
Topics TELEPHONE NUMBERS:
Hillsborough 732-8181
Chapel Hill 9fi8-0~501
Durham 688-7331
Mebane 33fi-227-2031
PURPOSE: To receive a presentation and information an the recent activities of Orange Water
and Sewer Authority (OWASA) from Marc Marcoplos and Bernadette Pelissier, Orange
County's appointed representatives on the OWASA Board of Directors.
BACKGROUND: Marc Marcoplos and Bernadette Pelissier, Orange County's appointed
representatives on the OWASA Board of Directors, will make a presentation to the Board
discussing the topics outlined on the Attachment.
FINANCIAL IMPACT: None
RECOMMENDATION(S): The Manager recommends that the Board receive the presentation
as information.
2
Orange County Appointed OWASA Board Members
Bernadette Pelissier and Mark Marcoplos
Presentation to the Orange County Board of Commissioners
August 15, 2000
Comprehensive Water and Sewer Master Plan
Encompassing a 50-year planning horizon, OWASA's comprehensive
,Water and Sewer Master Plan projects water and sewer demands, and
identifies resources, facility, and infrastructure improvements needed to
reliably meet customer needs through the planning period. The initial draft
of the final report is expected in the fall.
Conservation Rates
OWASA is currently evaluating several types ofi conservation rate
structures, which are designed to send a price signal to residential,
commercial, and University customers discouraging wasteful use of water.
Quarry Reservoir
The Town of Carrboro is ,scheduled to consider the extended quarry
reservoir on August 29, 2000.
Water and Sewer Boundary Agreement
The OWASA Board of Directors will discuss this at their August 24, 2000
meeting.
Mason Farm Wastewater Treatment Plant (WWTP) Renovation
and Expansion
The $17 million renovation and expansion of the WWTP is substantially
complete. Treatment capacity has been increased from 9 to 12 million
gallons per day, meeting our needs for the next 6 to 10 years.
Rogers Road Water Extension
OWASA will manage the Rogers Road Water Extension project and will
work closely with Orange County's engineer, Paul Thames throughout the
project.
3
Orange County Board of Commissioners
August 15, 2000
Page 2
University Service Availability Fees
OWASA staff has been meeting with University officials during the past
year to attempt to resolve this matter, but discussions have been
unsuccessful to date. Staff is continuing to meet with University officials to
seek a resolution.
Clean Water Management Trust Fund (CWMTF)
OWASA executed a grant agreement with the CWMTF in July 1998, which
provided up to $1,042,500 to pay the casts of acquiring land and
conservation easements within 300 feet of the Cane Creek Reservoir or
within 300 feet of any tributaries to the reservoir. To date, OWASA has
purchased approximately 169 acres in fee simple and approximately 130
acres of conservation easements for a total cost of $1,524,069, of which
$809,463 is eligible for reimbursement.