Item No.
SUBJECT: Authorization To Contract For Professional Services Construction Document
Preparation for Health Department Clinic Renovation
DEPARTMENT: Purchasing ~ Central Services
and Health Department
PUBLIC HEARING: (YIN) No
ATTACHMENT(S):
Corley Redfoot Zack Proposal
INFORMATION CONTACT:
Pam Jones 245-2fi52
Dr. Rosemary Summers, 245-2400
TELEPHONE NUMBERS:
Hillsborough 732-8181
Chapel Hill 9fi8~501
Durham 688-7331
Mebane 336-227-2031
PURPOSE: To consider authorizing the Manager to contract with Corley Redfoot Zack to
finalize preliminary drawings for Health Department Clinic Renovations, prepare documents
suitable for bidding and provide construction administration.
BACKGROUND: The Orange County Health Department has the opportunity to draw down
additional Medicaid Maximization funds to fund renovation of the health clinic in the Whitted
Building. he current layout of the clinic area does not allow for an efficient operation, nor does it
support good patient flow through the various service delivery areas within the clinic. Through
the efforts of Dr. Rosemary Summers, Health Director, staff was able to obtain architectural
services from the North Carolina Division of Public Health--local Health Services Division to
complete the preliminary design of the clinic. The State, however, is unable to provide
architectural services to complete the construction documents or to provide any level of
supervision during construction. For that purpose, staff is requesting that the Board authorize
the Manager to contract with Corley Redfoot Zack (CRZ) to complete this work. Staff feels that
CRTs experience in the design of the Clinic space at the Southern Human Services Center
provides a strong basis of understanding of the Orange County Health Clinic operations and will
allow staff to move the project along expeditiously. The Clinic space at SHSC has proven to be
very functional and well thought out space and staff anticipates a replication of that in the
design of the Hillsborough space as well.
CRZ has submitted a cost proposal to accomplish the work as follows:
• $1,865: Finalize design
• $17,158: Prepare construction documents, bidding and construction administration
• Total of $19,023
This renovation project is fairly complex in the work that is to be perFormed, but it will also
present significant challenges in that the dental clinic will need to continue operations while
renovation is underway. Staff is exploring, the possibility of other suitable space in which to
relocate the health clinic for the approximate 90-120 days needed for the renovation. This is
desirable in order to minimize any service delivery disruptions to the Hillsborough patients.
Staff would anticipate bidding this project sometime early Fall 2000.
FINANCIAL IMPACT: Sufficient funding for this contract is included in the approved Medicaid
Maximization Capital Project Ordinance. Unexpended funds in this project total approximately
$200,000. With the Board's approval of this contract, approximately $180,000 will remain in the
project to address renovations. It is likely that the Health Department will receive additional
Medicaid Maximization funds in the future to address further renovations.
RECOMMENDATION(S): The Manager recommends that the Board authorize the Manager to
sign a contract with Corley Redfoot Zack, subject to final review by staff and the County
Attorney, to finalize preliminary drawings for Health Department Clinic Renovations, prepare
documents suitable for bidding and provide construction administration in an amount not to
exceed $19,023.
~~~
1 1 1
CORLEY REDFOOT
ARCHITECTS 6 N G I N E E R 5 PLAN N
GLHNN D. CORLEY,AIA
President, CEO
KBPINEI'EI & REDFOOT, AU
Vice President
MARK zACK,AU-
vice President
MIClIAHL HAMMERSLSI4 PE
Principal
c~uRENCE w. su>vcH, AlA
Associate
HARRY M. lENSEN
Associate
KENNBI'H E. SMITH
Associate
PO Box 2368
Chapel Hill, NC 27515-2368
121 South Estes Drive
Suite 206
Chapel Hill, NC 27514-28b8
May 24, 2000
Ms. Pamela Jones, Director
Purchasing & Central Services
Ctrange County
Post Office Box 81$1
Hillsborough, North Carolina 27278
3
••na~
S
~ ~6`7
~~. - ~~~
1ZE: Orange County Health Department Renovations
Richard E. Whined Human Services Complex
Hillsborough, North Carolina
PROPOSAL FOR PROFESSIONAL DESIGN SERVICES
Dear Ms. Jones:
I enjoyed meeting with you and some of the Health Department staff at our
recent visit to the building. Shortly after my initial walk-through, I returned for
a second visit to get a better idea of the scope of the work. During these visits,
we noted Functional and technical issues related to the schematic floor plan
dated 11/lb/99 (revised 3/2/00) drawn by the NC Division of Public Health
Local Health Services you provided to us. Resolution of these issues will be
necessary prior to our producing Construction Documents far the proposed
renovations.
Thank you for the opportunity to submit our proposal fvr the design work on
the above-referenced project.
The first phase of the design work will be to outline the work necessary to
resolve these open issues.
(919) 942-8586 Telephone
(919)929-4802 Fax
4
Ms. Pamela Jones May 24, 2000
RE: Qrange County Health Dept. Renovations
SCOPE o>r wolz.Ic
A. Phase I:
1. We will produce a dimensioned floor plan of the existing clinic to be used as a
background for design meetings and Construction Documents. This will require a
site visit and in-office production time.
8 hours ®$b5/hour = $520.00 $ 520
2. Two meetings with you .and Health Department staff to redesign areas where problems
exist, according to our discussions with the staff at our initial visit. Meeting
time, design time and production kime will be required.
Design time: 4 hrs. ®$90/hr.
Production time: 8 hrs. ®$65/hr.
Two meetings: Principal's time: 3 hrs. ®$90/hr.
Assistant's time: 3 hrs. ®$65/hr.
Subtotal:
PHASE I TOTAL:
_ $ 3b0.00
_ $ 520.00
$ 270.00
= 195.00
$1,345.00 1.345
$1,865
At the completion of Phase I, and with your approval to proceed to the next phase, we will
begin work on Phase II of the project, which includes the preparation of Construction
Documents, the bidding process, and Construction Admiztistration.
B. Phase II:
1. Construction Document Phase: $ 8580•
2. Bidding Frocess: 1,372.00
3. Construction Administration: 7,206.00
PHASE II TOTAL: $17,158.00 $17,158
The Please II total includes Architectural and Construction Administration services provided
by Corley Reelfoot Zack, Inc., and Mechanical, Electrical and Plumbing design services
provided by Reece, Noland & McElrath, Inc., Consulting Engineers. The cost is based on the
scope of work as we understand it at this time, and on the work proceeding in a timely
fashion with all of the work being completed within eight months of the approval of this
proposal.
C. TOTAL COST OF 516RVICES - FHA58S I AND II:
ADDITIONAL SERVICES
$19,023
Additional services over and above those described above will be billed at the following rates:
Principal's Time: $9p/~'•
Designer's Time: $~/~'•
CADD/Drafting: $65/hr.
Construction Administration: $65/hr.
~~~
~ ~ ~ COTiLEY REDFOOT ZACK ~
5
Ms. Pamela Jones May 24, 2000
RE: Orange County Health Dept. Renovations
ITEM5 NOT INCLI7DED:
Items not included in the above fee are charges for the following:
A. Printing, reproduction and postage will be billed at direct cost.
B. Legal fees
C. Perspectives, renderings or models
D. Construction Administration beyond a reasonable construction period (3 months)
E. Interior and furniture design
We will bill on a monthly basis, with payment due by the 21st of the month the invoice is dated.
Pam, we appreciate the opportunity to continue our working relationship with you on this very
important project. Please le! us know if you have any questions concerning this proposal.
If the abave is acceptable to you, please sign below and return one copy for our records.
Sinter y,
~~~.
eth E. Redf , AIA
Vice President
KEResw\oc-lveal.th
AGREED: DATE:
for Orange Caunty
~~~ CORLEY RE>x~r ZacK we