BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: April 17, 2000
Action Agenda
Item No. .. ~,
SUBJECT: Approval of Capital Project Ordinances for Chapel Hill-Carrboro City Schools
DEPARTMENT: Budget Office
PUBLIC HEARING: (YIN) No
ATTACHMENT(S):
1. Glenwood Elementary School Renovations
Capital Project Ordinance
2. Scroggs Elementary School Construction
Capital Project Ordinance
3. Smith Middle School Construction/K-12
Campus Capital Project Ordinance
INFORMATION CONTACT:
Donna Dean, extension 2151
TELEPHONE NUMBERS:
Hillsborough 732-8181
Chapel HIII 968-4501
Durham 688-7331
Mebane 336-227-2031
PURPOSE: To approve capital project ordinances for the Chapel Hill-Carrboro City Schools.
BACKGROUND:
Glenwood Elementary School Renovations Capital Project
Renovations at Glenwood Elementary School are a high priority project for the Chapel Hill-
Carrboro City Schools. School staff estimates the project to cost about $1.5 million with
$950,000 being funded from the 1997 voter approved bonds and the remaining $450,000
coming from savings realized in the Scroggs Elementary construction project.
At the April 4, 2000 meeting, the Board of Commissioners approved a capital project ordinance
for the construction bids related to the renovations at Glenwood Elementary School. The
amount of the bids totaled $1,077,176 bringing the projects total funding to $1,177,176 for
planning, design and major renovations (Phase 1). Since the date of approval, the Budget
Director has met with the District's Director of Facilities Management, Bill Mullin for an update
on the renovation project. The District's plans include completing the renovations in two phases
during summer breaks this year and next.
Phase One -The first phase of renovations is the most significant phase of the project.
Contractors plan to get work underway less than one week after the summer break
begins in June 2000 and conclude in August 2000 before children return from break.
Phase 1 includes replacement of the HVAC system, building structure improvements,
upgrades to classrooms and restrooms, and installation of a new fire alarm system. All
of these items were included in the construction bids the Board of Commissioners
provided funding for with approval April 4 capital project ordinance. In addition to the
major work, there is a need to complete several smaller cost components of the project.
Doors and Hardware Replacement: A small component of the building structure
improvements includes replacing exterior doors and hardware. Due to its cost,
this component was not part of the major construction contracts. The
replacement cost is $17,004. The District requests that the Board of
Commissioners approve this amount for inclusion in the construction line item of
the project.
• Consultants: In addition to the major architect/engineer contract of $100,000
(approved by the Commissioners on December 7, 1999) there is also a need to
receive services from structural and mechanical consultants. The District
requests that Commissioners approve costs for these consultants ($2,750) for
inclusion in the planning/architect/engineer line item of the project ordinance.
• Contingency: As the renovations begin, there are concerns regarding the age of
the facility and the 'potential for unforeseen problems. Included the District's
original Glenwood renovations project budget was a contingency account of just
over $103,000 to cover unanticipated items that construction crews may
encounter in a project of this nature. In an event such as .this, it is critical that a
change order be issued in a timely manner so that work does not stop and throw
the project off schedule. Since work will take place during the period when no
Board of Commissioner meetings are scheduled, the District asks that the
Commissioners approve funding for a project contingency.. The District requests
the Board to appropriate three-fourths of the original contingency or $77,250 at
this time (included in the capital project ordinance on page 6 of this abstract).
The District understands that it is to spend no contingency funds without
prior approval from the County. In order to avoid project delays during the
period when Commissioners meetings are not scheduled, the School
Superintendent must receive approval from the County Manager before the
District issues a change order. In turn, the County Manager will inform the
Board at its August 22 meeting of the use of the funds.
Funding for the requested components outlined above comes from savings realized in
the construction project for Scroggs Elementary. As the Board may recall, actual
construction costs for Scroggs Elementary School total $12.6 million compared to the
original project budget of $14.1 million. The Commissioners have approved use of
these savings for other District projects including the renovations at Glenwood
Elementary.
The attached Glenwood Elementary School Renovations Capital Project Ordinance
increases the project's appropriation by $97,004 (as outlined above). The school district
will bring additional components of the project forward as work progresses. The
attached Scroggs Elementary School Construction Capital Project Ordinance provides
for the transfer of $97,004 to the. Glenwood Project.
Phase Two -This phase, scheduled for summer 2001, includes installing canopies over
exterior doors and creating an outdoor learning area. Completion of this phase is
included in the Manager's Recommended 2000-2010 for the upcoming fiscal year.
However, in keeping with the Board's phased approval process, the District will not
request funding for this phase until next spring. The Board of Commissioners is not
being asked to act on Phase 2 in this request.
Smith Middle School Construction/K-12 Campus
When the original concept of a new middle school in the Chapel Hill-Carrboro City Schools
district was proposed, the anticipated location was the Meadowmont development (on land
donated by the developer). Since that time, the original concept has changed and the District
has decided upon a new site for the middle school. Current plans include constructing the new
school, now known as Smith Middle School, on a site occupied by Chapel Hill High School and
Seawell Elementary School, thereby creating a shared campus for kindergarten through twelfth
grade (K-12).
To that end, the project's scope has transformed from solely a middle school construction
project to a campus-wide project. The District had to undertake several site preparation details
in order to locate the new school in an appropriate location on the campus. Many of the special
site preparations include relocating and/or reassigning playing fields and playgrounds of the
existing schools to other areas on the site. For example, in order to locate the middle school
physical education field adjacent to the new building, the District has to relocate Seawell
Elementary's playground. Other project evolutions include the request from the Town of
Carrboro and Orange County to develop an additional playing field for community use. Staff will
address this part of the project in the 2000-2010 Capital Investment Plan when Orange County
receives funds from the recent sale of the first installment of the 1997 bond.
The project budget totals $19.8 million with funding coming from the 1997 voter approved
bonds ($18 million) and the remainder coming from the District's impact fees. To date, the
Commissioners hage approved funding for the following components of the project:
Planning/Architect/Engineer $1,505,000
Site Development $1,000,000
New School Construction (per bids
received by Board of Education) $12,688,924
Contingency $250,000
Total Project Budget Before This
Request $15,443,924
Since the date of the last Commissioner's update on this project in late January 2000, work as
the site has progressed.
• Site Development and Survey Work: When the Commissioners approved the original
ordinance for the project in June 1998, estimated site development costs were $1
million. As mentioned previously, the project concept has undergone much
transformation since that time. Relocation of many of the playing fields and construction
of new ones have caused site development costs to increase. The total contract for site
development now totals $2,061,197. In addition, costs for survey work at the project site
total $22,600. Therefore the District requests that the Board approve an additional
$1,083,797 for these two items.
Construction: The District has a need for two small scope contracts that were not
included in the phase approved by the Commissioners in fate January 2000. The two
contracts cover balancing the HVAC system and installing the security system. The
4
District requests that the Commissioners increase the construction line item of this
project by the amount of the two contracts, $60,000.
• Athletic Field Upgrades: As the Board may recall, the District planned upgrades for
Chapel Hill High's playing fields before to the locating Smith Middle School on the
shared campus. The plans, included installation of new bleachers to accommodate
1,500 spectators, new restrooms for the spectators and resurfacing the existing tennis
courts. Original plans provided funding totaling $785,000 for the upgrades in the
District's Athletic Fields Capital Project Ordinance.
The District installed bleachers last year at the football stadium and the baseball and
soccer fields at a cost of $265,000. The District paid for the seating from .the Athletic
i=fields Capital Project in accordance with the project ordinance approved by the County
Commissioners. Remaining ,project funds to complete restroom construction and tennis
court resurfacing equal $520,000 ($785,000 less $265,000).
The District recently received bids for the remaining components of the upgrades, and
they total $567,000 or $47,000 more than budget. The scope of the upgrades has
changed slightly due to the sharing of the entire campus including several of the playing
fields. The District requests that the Commissioners approve $47,000 in the Smith
Middle School/K-12 Campus project to complete the restrooms and tennis courts. It is
critical that the project begins as soon after the last day of this school year as possible in
order for it to remain on schedule and completed by the beginning of the upcoming
school year.,
• Seawell Elementary Playground: As mentioned earlier in this abstract, relocation of the
playground at Seawell is necessary so that the new middle school's physical education
field can be sited appropriately. The cost to relocate the playground, including grading
work and installing protective ground coverings, totals $97,000. It is requested that the
Commissioners approve funds for this purpose.
Projecf Contingency Update: Included in the original project ordinance was $250,000 for
Contingency purposes. To date, it has been necessary for the District to use $31,000
out of the account to cover unanticipated cost related to relocating electrical lines. As
contractors began work, they found that some buried electrical wires had to be relocated
in order for the project to comply with state electrical codes. The attached capital project
ordinance reflects the transfer of funds from the Contingency account to the
Construction line item.
5
In summary, the District requests that the Commissioners approve additional funding for the
following project components:
Land & Associated Fees: Surveys $22,600
Land ~ Associated Fees: Additional funds
required to complete site preparation for entire $1,061,197
campus
Construction: Installation of security system, $81,000
balancing HVAC, and relocation of electrical wires
Playground Construction: Relocation of Seawell $97,000
Playground
Athletic Field Upgrades: Planning, design,
construction of restrooms at stadium and resurfacing $47,000
existing tennis courts
Contingency: Relocation of electrical wires
(transferred to Construction line item) ($31,000)
Additional Allocation Requested by CHCCS
(4/17/00) 51,287,797
As the project progresses, the District will request Commissioner approval of additional phases
of the campus project.
FINANCIAL IMPACT: Financial impacts are included in the background information above.
RECOMMENDATION (S): The Manager recommends that the Board of County Commissioners
approve the capital project ordinances for the Chapel Hill Carrboro City Schools.
Smith Middle School Construction/K-12 Campus ~
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section 13.2 of
Chapter 159 of the General Statutes of North Carolina, the following capital project is hereby adopted.
Section 1. .The project authorized provides funds to construct Smith Middle School, co-located on
the Seawell Elementary School and Chapel Hill High School campus. This project will
be financed with proceeds from the 1997 bond referendum and impact fees.
Section 2. The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
roug
1998-99 -
Appropriation roug
1999-00
a es ax
mpac ees
on un s ,
o a un ng , , , ,
Section 4. The following amount is appropriated for this project:
roug
1998-99
Appropriation oug
1999-00
annmg rc ngtn ,
an ssoc ees- ,
rte eve opmen ,
ons ruc ton ,
eawe emen ary
Playground Construction ,
$0
$97,000
$97,000
e tc to Agra es ,
qutpmen urnts tngs
ec no ogy
ontmgency ,
oa oss ,
Section 5. This ordinance supersedes all previous Smith Middle School Capital Project
Ordinances.
Section 6. This Ordinance shall remain in effect from July 1, 1998 until June 30, 2000.
Adopted this seventeenth day of Apri12000
r
Glenwood Elementary School Major Renovation
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section 13.2
of Chapter 159 of the General Statutes of North Carolina, the following capital project is hereby
adopted.
Section 1. The project authorized provides funds for a major renovation of Glenwood Elementary
School that was originally constructed 1952. Other buildings were added to the campus in
1954 and 1959. This project is financed with proceeds from the 1997 Local Bonds and
savings from the Scroggs Elementary School Construction and East Chapel Hill High
Addition projects.
Section 2. The officers of the County are hereby directed to proceed with the project within the budget
contained herein.
Section 3. The following revenue is anticipated to complete phasesl and 2 of this project:
1998-99 Appropriation 1999-00
ax
ees
C,orntruction Savings $0 $324,180 $324,180
J ,
Section 4. The following amount is appropriated for this project:
roug
1998-99
Appropriation roug
1999-00
arming rc agtn ,
an ssoc ees
oas ruc ion ,
uip en urnis ing
er
on ingency ,
ota ,
Section 5. This ordinance supersedes all previous Glenwood Elementary School Major Renovations
Capital Project Ordinances.
Section 6. This ordinance shall remain in effect until June 30, 2000.
Adopted this seventeenth day of Apri12000.
Scroggs Elementary School Construction ~
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Project Number 64-880-7716
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section 13.2 of
Chapter 159 of the General Statutes of North Carolina, the following capital project is hereby adopted.
Section 1. The project authorized provides. funds to build Scroggs Elementary School. Proceeds
from a private placement loan obtained by Orange County and from Impact Fees
finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
ug
1998-99
FY 1999-00 roug
1999-00
es ax
ac ees ,
on un
on un
nva a cemen mancing ,
o a ro~ec n Ong ,
Section 4. A portion of the available funds for this project has been transferred to Phillips Middle
School Renovations Capital Project, Culbreth Middle School Renovations Capital Project,
Planning for Future Projects Capital Project, and Athletic Facilities Capital Project.
Section 5. The following amount remains appropriated for this project:
oug
1998-99
FY 1999-00 rou
1999-00
mm~g c ngm ,
an ssoc ees
ons ruc ion ,
quipmen urms wigs ,
er- ec no ogy ,
ontmgency _ ,
oa ,
Scroggs Elementary School Construction
Capital Project Ordinance
Page 2
Section 6. A portion of the funds appropriated for this project are transferred to the following
projects.
Middle School
Renovations (Locker
Room and Major
Improvements) $0 $25,000 $25,000
Middle School
Renovations (Labs, Gym,
Auditorium) $0 $25,000 $25,000
rans er o annmg or
Future Projects $0 $50,000 $50,000
rans er o e is
Facilities $0 $70,000 $70,000
rans er o enwoo
Elementary $0 $324,180 $324,180
Total $0 $494,180 $494,180
Section 7. The following amount remains appropriated to this project:
croggs emen ary
School Capital Project $14,100,000 ($494,180) $13,605,820
Section 8. This ordinance supersedes all previous Scroggs Elementary School Construction
Capital Project Ordinances.
Section 9. This Ordinance, originally adopted June 30, 1997, shall remain in effect until June 30,
2000.
Adopted this seventeeth day of Apri12000.