HomeMy WebLinkAboutAgenda - 11-21-2002-4JOINT MEETING
ORANGE COUNTY BOARD OF COUNTY COMMISSIONERS/
HILLSBOROUGH BOARD OF COMMISSIONERS
WORKSESSION AGENDA ITEM ABSTRACT
Meeting Date: November 21, 2002
Action Agenda
Item No. ~_
SUBJECT: Joint County/Town Projects
DEPARTMENT: Environment and Resource
Conservation, Recreation and
Parks, Purchasing
PUBLIC HEARING: (Y/N) No
ATTACHMENT
1) Fairview Park Summary Sheet
2) Map of Fairview Park Area
INFORMATION CONTACT:
Pam Jones, 245-2650
David Stancil, 245-2590
Lori Taft, 245-2660
TELEPHONE NUMBERS:
Hillsborough 732-8181
Chapel Hill 968-4501
Durham 688-7331
Mebane 336-227-2031
PURPOSE: To discuss joint projects or initiatives of the County and Town.
BACKGROUND: Over the years, Orange County and the Town of Hillsborough have shared
many projects and initiatives of joint concern. Tonight's agenda offers opportunities to
discuss three potential joint projects:
1) Fairview Park
2) Other Parks and Recreation Projects
3) Justice Facilities Update
1. Fairview Park
Orange County owns 41 acres of land in the Fairview community north of Hillsborough slated
for a community park. A playground and youth baseball field currently exists at the park,
which has received a suitable geo-technical evaluation for use as a park. In the voter-
approved 2001 County Parks and Open Space bond, $850,000 was allocated for
construction of additional recreation facilities at Fairview Park. The inclusion of this project
was requested by the Town and approved by the Capital Needs Task Force and the County
Board of Commissioners.
2
On September 9`h and again on November 11 `h, the Board of Commissioners reviewed
potential project timetables, including the attached Park Summary Sheet for Fairview Park.
As noted on the summary sheet, a few key questions remain to be addressed before the
park project can get underway. In general, these questions relate to the size and scope of
the plan for the park, whether or not it will include the Town's adjoining 25 acres, and the
context of a joint project. The preliminary timetable on the draft summary sheet proposes
that, after the two boards agree on the scope, nature and scale of the project, that a Concept
Pfan/Master Plan Committee be appointed to begin developing a plan for the site(s) in the
summer of 2003.
A map of the area, showing County and Town owned land and the adjacent County public
works facility, is also attached.
2. Other Parks and Recreation Projects
The Boards may wish to discuss the potential for other joint parks and recreation projects, as
desired.
3. Justice Facilities Update
Culminating several years of study involving various judicial officials, citizens, elected County
and Town officials, staff and consultants, the BOCC endorsed a phased approach to the
expansion of judicial facilities in downtown Hillsborough. Although various iterations of the
expansion have been presented, the County Commissioners have endorsed expansion of
judicial facilities as well as other County facilities on the downtown Hillsborough campus only
to the extent that parking needs can be met with surface parking. The current operating
assumption indicates that no deck parking will be constructed.
As was reported to the Town Board of Commissioners on May 6, 2002, the County
Commissioners have identified three planning groups that will carry out the design and
construction of Phase I of the proposed expansion of the Courthouse; one for architect
selection, another for exterior design review, and a third for interior design review. The
planning process, originally slated to begin in July 2002 was delayed by six-months in an
effort to overcome obstacles created by budgeting methods employed by the State of North
Carolina for FY 2002-2003.
Discussion by the BOCC concerning the next steps in justice facilities planning was
scheduled to be heard during a recent work session; however, time precluded the
presentation. The County Commissioners will reschedule the discussion in the near future
and will apprise the Town Board of any material outcomes.
FINANCIAL IMPACT: There is no financial impact involved in discussion of these projects.
If and when the projects are initiated, capital project ordinances will be considered and
adopted outlining the individual financial impacts. The amount allocated from the 2001 bond
for Fairview Park is $850,000. The adopted Capital Funding Schedule and CIP would
appropriate these funds as follows: $200,000 in this fiscal year, $500,000 in FY 03-04, and
$150,000 in FY 04-05.
RECOMMENDATION(S): The Manager recommends that the boards discuss the projects
and provide feedback as desired.
Project Name: Fairview Park
Project Cost: 850 000
Pre-Concept Plan Completed? IVo
Project Status: Existing playground and playing field. Decisions needed on 1)
whether park will include both County and Town of Hillsborough portions or
County only, 2) whether a joint County/Town park or a County park, and 3)
whether park plan will be folded info master plan for other public facilities at site.
Funds from 2001 bond, appropriated accordingly in 2002-2012 CIP, consistent
with following timetable. There is no pre-concept plan (a 1986 concept plan was
prepared). Meeting being scheduled between County and Town representatives
to discuss issues.
Scope of Work: Discuss outstanding issues with Town of Hillsborough. Develop
pre-concept plan. Form concept plan committee to design park and any overall
facility, using pre-concept plan and operating principles adopted as part of the
char e b the Board of Co
Estimated Cost mmissioners.
•
$11,500 for detailed to o ra hic and location surve
Project Partners? Town of Hillsborough
Fairview Park Commissioner Jacobs
Concept Plan Committee Commissioner Halkiotis
Membership Hillsborough Town Commissioners
1 OC Recreation and Parks Advisory Council member
1 Hillsborough Parks and Recreation Board member
1 Commission for the Environment member
Area Citizens
_
1 citizen design professional/ other expertise
Additional members if a Master Plan Work Grou ?
Staff Resources Primary: County Manager (or designee), Open Space
Design Specialist, ERC Director, Recreation and
Parks Management Director, Town Manager (or
designee)
Other (Primary, if Master Plan approach selected):
Land Conservation Manager, County Engineer,
Planning Director (County and Town), Purchasing
Director, Public Works Director
2003
Town/County Work Group (Process): December 2002 - February
BOCC Approval of Scope of Project: March-June 2003
Projected Concept Plan Timetable*: July 2003 -April 2004
Target Date BOCC/Town Consideration*: May-Auqust 2004
* - As per current proposed schedule.
D~ euelop construction drawings and bids, gain Town site plan approval,
award bid to contractor(s) and construct the park facilities according to the
BOCC-adopted plan.
Estimated Cost $838,500
Construction Project Commissioner Halkiotis
Team Commissioner Jacobs
County Manager (or designee)
Recreation and Parks Management Director
Purchasing Director
Open Space Design Specialist
County Engineer
ERC Director
Planning Director
Park Services Director
(Town staff if Joint Master Plan process)
BOCC Review of Construction Drawin s Au ust-October 2004
BOCC Bid`A royal
"Best-case" Construction Be ins November 2004
December 2004
"Best-Case" Park Opening: _ November 2005
~tction //eeclecl to ~roceec~at this time:
If the Board is ready to proceed with planning for this park:
1. BOCC representatives to meet with like contingent from Hillsborough
Board to discuss joint park, Master Plan opportunities, and scope of
project
2. Once key decisions made, the two Boards might develop and adopt a
pre-concept plan and scope of work
3. Appoint Fairview Park Concept Plan (or Fairview Campus Master Plan)
Committee, with charge and mission based on pre-concept plan and any
operating principles the Board wishes to apply.
5
County Park Sibe - 41 Acres
0 Town of Hillsborough - 25 Acres
Orange County Public Works - 26 Acres
Panel Boundary
Hillsborough Town limits