HomeMy WebLinkAboutORD-2026-015-Approval of the Guaranteed Maximum Price for the Construction of the Crisis Diversion Facility, and Approval of Budget Amendment #12-A 1
ORD-2026 -015
ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date : June 16 , 2026
Action Agenda
Item No . 6-c
SUBJECT : Approval of the Guaranteed Maximum Price for the Construction of the Crisis
Diversion Facility , and Approval of Budget Amendment # 12 -A
DEPARTMENT : Asset Management Services
ATTACHMENT (S ) : INFORMATION CONTACT .
I . Gilbane Contract Amendment Alan Dorman , AMS Director, 919-245 -
2 . Gilbane GMP Cost Summary 2627
3 . Year-to - Date Budget Summary
4 . Presentation
PURPOSE : To :
1 . ) Review and approve the final design of the Crisis Diversion Facility ;
2 . ) Review and approve the Guaranteed Maximum Price for the Construction of the Crisis
Diversion Facility as submitted by Gilbane ;
3 . ) Review and approve an amendment to the existing Gilbane Contract for Construction
Manager-at- Risk services to incorporate the Guaranteed Maximum Price as well as other
changes ;
4 . ) Approve Budget Amendment # 12 -A ; and
5 . ) Authorize the County Manager to execute the Gilbane contract amendment , subject to final
review by the County Attorney , and any subsequent amendments for contingent and
unforeseen requirements up to the approved budget amount on behalf of the Board of
County Commissioners .
BACKGROUND : The County has been developing a plan to build a Crisis Diversion Facility since
2019 . These plans culminated in the selection of the architecture firm CPL to design the facility in
2024 and the selection of Gilbane Construction Company to provide Construction Management
at Risk Services in 2025 .
Initial design and cost estimates showed that the final project would exceed the original budget .
of $26 , 053 , 350 . In October 2025 , the Board reviewed a series of design options to reduce the
overall project budget . The Board approved Option C , a design with an estimated construction
cost of $27 , 180 , 542 . The total estimated project cost , including land aquistion , design , and other
construction costs , based on Option C , was $ 30 , 749 , 007 , This would have required an additional
$4 , 695 , 657 in funding .
In April 2026 , Gilbane completed the formal bid process for the project and proposed a
Guaranteed Maximum Price (" GMP " ) of $ 22 , 906 , 906 . Including project costs already spent or
encumbered for professional services and land acquisition , the new project budget will be
$ 29 , 412 , 035 . To address the increased cost , the the Board will need to approve $ 3 , 358 , 685 in
2
additional funding . While the intention had been to provide the Board with a series of additional
construction options , including more daylighting and solar installation , due to the tremendous cost
savings achieved through the bidding process , these elements have already been incorporated
into the GMP .
Crisis Diversion Facility - Final Project Budget - June 6th
GMP ( Construction and Indirect Costs ) $22, 906, 906
Land $ 1, 353, 266
Design / Other Services $2, 142, 227
Furniture $ 5253983
Environmental Impact and Related Fees $ 132 , 785
Special Inspections $75 , 000
Commissioning $ 100 , 868
Owner ' s Contingency $ 10850 , 000
Offsite lighting $ 100 , 000
AN $25 , 000
Low Voltage $75 , 000
Security $ 125 , 000
Total: $29,412, 035
The current project schedule , as shown below , projects construction starting in August and
occupancy expected in the spring of 2028 .
Project Schedule
Schedule for the Construction of the Crisis
Diversion Facilit
Board Approval of GMP June 2026
Start of Construction August 2026
Construction Completed Winter 2028
Occupancy Spring 2028
FINANCIAL IMPACT : Budget Amendment # 12 -A allocates $ 3 , 358 , 685 in additional funding to
cover the increased cost for the construction of the facility over the original project funded in the
FY 2025 -35 Capital Investment Plan . Staff also worked with Alliance and confirmed that
$ 1 , 100 , 000 of the Cardinal Reserve could be dedicated towards the Crisis Diversion Facility .
These two (2 ) changes are reflected in the amended project ordinance :
Crisis Diversion Facility ($3, 358, 685) - Project # 10080
Revenues for this project :
Current FY 2025-26 FY 2025-26
FY 2025-26 Amendment Revised
Cardinal Reserve $ 1 , 823 , 121 ($ 7231121 ) $ 1 , 100 , 000
From General Fund $250 , 000 $0 $250 , 000
Alternative Financing $23 , 980 , 229 $4 , 081 , 806 $ 28 , 062 , 035
Total Project Funding $26, 053 , 350 $ 3 , 358 , 685 $29 , 412 , 035
3
Appropriated for this project :
Current FY 2025-26 FY 2025-26
FY 2025-26 Amendment Revised
Project Expenditures $26 , 053 , 350 $3 , 358 , 685 $29 , 412 , 035
Total Costs $26, 053 , 350 $3 , 358 , 685 $29 , 412 , 035
As previously noted , this increase was lower than the amount initially anticipated in the debt model
after the approval of Option C . This will result in decreasing the anticipated tax increase in FY
2028 to fund debt service by 0 . 18 cents .
ALIGNMENT WITH STRATEGIC PLAN . This item supports :
• GOAL 2 : HEALTHY COMMUNITY
OBJECTIVE 1 . Improve harm reduction , prevention , and support services for adults and
children experiencing behavioral health issues , substance use disorder, and intellectual or
developmental disability .
OBJECTIVE 4. Reduce impacts and barriers for justice -involved children and adults
through deflection , diversion , therapeutic interventions , and re -entry support , including
housing .
RECOMMENDATION (S ) : The Manager recommends that the Board :
1 . ) Approve the final design of the Crisis Diversion Facility ;
2 . ) Approve the Guaranteed Maximum Price for the Construction of the Crisis Diversion
Facility as submitted by Gilbane ;
3 . ) Approve an amendment to the existing Gilbane Contract for Construction Manager-at- Risk
services to incorporate the Guaranteed Maximum Price as well as other changes ;
4 . ) Approve Budget Amendment # 12 -A which increases the authority in the County Capital
Fund by $ 3 , 358 , 685 ; and
5 . ) Authorize the County Manager to execute the Gilbane contract amendment , subject to final
review by the County Attorney , and any subsequent amendments for contingent and
unforeseen requirements up to the approved budget amount on behalf of the Board of
County Commissioners .
4
Attachment I
NORTH CAROLINA
CONTRACT AMENDMENT
ORANGE COUNTY
THIS CONTRACT AMENDMENT ("Amendment") is made and entered into this _ day of 20_ by
and between ORANGE COUNTY (hereinafter referred to as "County") and Gilbane Building Company (hereinafter the
"Construction Manager at Risk" or "CM" or "CMAR") .
WITNESSETH :
THAT WHEREAS , the County and CMAR entered into a contract dated April 22 , 2025 (hereinafter the "Original
Agreement") , for the procurement of hardware and provision of services and
WHEREAS , the County and CMAR desire to amend the Original Agreement while keeping in effect all terms and
conditions of the Original Agreement not inconsistent with the terms and conditions set forth below .
NOW THEREFORE, for and in consideration of the mutual covenants and agreements made herein , the parties agree to
amend the Original Agreement as follows :
1 . Section 2 . 6 . The "Total Construction Budget" is first described in the RFQ Data Sheet, and consists of the
Cost of the Work, as more fully defined in section 4 below, the CMAR-GMP Contingency, as more fully
defined in section 5 below, the Early Completion Bonus Fund , if offered and made part of this Contract, as
more fully defined in section 24 below, the CMAR General Conditions , as more fiilly defined in section 3
below . Upon approval by the Owner of the Total Construction Budget as presented on June 16" , 2026 , the I
Total Construction Budget will not be allowed to exceed the agreed upon Total Construction Budget
("TCB ") . The Owner reserves the right to adjust the Total Construction Budget at any time prior to agreement
on the final GMP .
2 . Section 3 . 2 . Provided that the Total Construction Budget remains $ 22 , 906 , 906 , the CMAR Fee shall not
exceed $ 850 , 820 , subject to modification and limitation as set forth herein . If the Owner changes the Total
Construction Budget, the CMAR Fee shall not exceed three percent (3 . 75 %) of the sum of (i) the Cost of the
Work, ( ii ) the CMAR-GMP Contingency, and (iii) the CMAR General Conditions , (but not including the
Early Completion Bonus Fund) all as more fully defined in this Contract, as of the date when the final GMP is
established and approved by the Owner, subject to modification and limitation as set forth herein . The CMAR
Fee will include all CMAR home office personnel costs , including officers as well as home office and local
office support staff not included in General Conditions below, together with all other CMAR overhead costs
and profit. This Fee shall also include all home office quality control and safety reviews , as well as all
required services of a home office Project executive, by whatever name called . CMAR costs which are not to
be included in the CMAR Fee are the costs of all Subcontracts , on-site field staff, General Conditions costs j
(as provided below) , and the CMAR-GMP Contingency described below.
3 . Section 3 . 4 . In addition to the foregoing Fee, an allowance for the General Conditions on a "not-to-exceed"
basis will be submitted by the CMAR with each GMP for the Owner ' s approval . No costs associated with the
CMAR ' s main office or its main office or other off-site personnel , including the costs associated with the use
of items or equipment of the main office , are covered under the General Conditions allowance . All such costs
are deemed to have been included in the CMAR Fee . Subject to approval by the Owner ' s Representative , each
GMP may include special designated allowances for defined expenses . Each GMP shall contain an allowance
for General Conditions fixed as an estimated lump sum for each GMP . The entire General Conditions
allowance shall be fixed based on the Total Construction Budget at the time of the final GMP , after which the
General Conditions shall not be adjusted unless an amount is negotiated with Owner-requested Change
Orders to the Work of the Project. The sum of the entire General Conditions at the time the final GMP is
i
3
s