HomeMy WebLinkAboutAgenda 06-16-2026; 6-f - FY 2027 Transit Tax Annual Work Program and Financial Model Update 1 ORANGE COUNTY BOARD OF COMMISSIONERS ACTION AGENDA ITEM ABSTRACT Meeting Date: June 16, 2026 Action Agenda Item Number: 6-f SUBJECT: FY 2027 Transit Tax Annual Work Program and Financial Model Update DEPARTMENT: Transportation ATTACHMENT(S): INFORMATION CONTACT: 1. Recommended FY 2027 Annual Sarah Williamson, Interim Work Program for Transit Transportation Director, 919-245- 2. Presentation 2008 3. Financial Model PURPOSE: To consider the FY 2027 Annual Work Program (AWP) for Public Transportation BACKGROUND: In 2011, Orange County voters approved a half-cent sales tax to fund public transportation improvements. The sales tax proceeds can only be used for projects that have been approved by the Orange County Board of Commissioners (BOCC) and the GoTriangle Board of Directors. The Annual Work Program identifies funding for the fiscal year and is approved by the BOCC and GoTriangle Board. The Fiscal Year 2027 Annual Work Program (AWP) was developed in accordance with the process and schedule as recommended by the Staff Working Group (SWG) on June 17, 2024. To Date • April 1, 2026: SWG released the FY 2027 AWP for a 21-day public review period, no public comments were received • April 21, 2026: SWG recommended the BOCC approve the FY 2027 AWP FY 2027 AWP Article 43 Transit Sales and Use Tax proceeds are expected to grow 5% in FY 2026, and are budgeted to have no growth in FY 2027. The budgeted rate of growth, paired with already planned and approved projects has created a gap between planned projects and available funding, resulting in very little capacity for new projects in FY 2027. The recommended FY 2027 investment totals $15.53 million ($9.49 million operating and $6.04 million capital), and includes a 2.5% increase for all operating and administration projects. $2.259 million Orange Transit Tax fund balance is utilized for capital projects, anticipated to leave a fund balance of about $10.4 million at the end of FY 2027. Orange County has one new transit project planned and funded in the FY 2027 AWP, an update to the Transit Plan. This is in accordance with the Interlocal Agreement that calls for the Transit Plan to be updated at least every four years. The Orange County Transportation Department does 2 not have any new service or program offering that can be fully funded by the Transit Tax without a Transit Plan update. Recommended FY 2027 O eratin - Agency FY2027 Funding Requests Chapel Hill $4,090,487 GoTriangle $3,365,272 Orange County $1,615,868 Tax District Administration $374,841 Triangle West Transportation $42,867 Planning Organization (TPO) Total $9,489,335 Recommended FY 2027 Capital Agency FY 2027 Funding Requests Carrboro $244,829 for West Main St and 203 Connector Sidewalks Chapel Hill $122,132 for Bus Purchases GoTriangle $5,174,000 for Regional Bus Operations & Maintenance Facility ($2.1 million), Mobility Hub ($210,000), and Fordham Blvd Access Improvements ($2.5 million), Bus Purchases ($364,000) Orange County $300,000 for Multi-Agency Transit Plan Development Triangle West TPO $200,758 for a Transit Plan Staffing Study Total $6,041,719 Under the financial policy, Orange County would have a unassigned reserve target of$4.0 million. Based on the expenditures recommended in the annual work program, the financial model shows a balance of$3,960,858, which is $39,142 below policy targets. Next Steps Before the FY 2027 AWP can be implemented it must be approved by the Orange County Board of Commissioners and the Transit Tax District fiduciary, the GoTriangle Board of Directors. It will concurrently be sent to the Triangle West Transportation Planning Organization for approval. FINANCIAL IMPACT: The financial impact of the Transit Tax District will be $15.53 million, $9.49 million for operating and $6.04 million for capital, and a fund balance reduction of $2.259 million. Orange County receives quarterly reimbursements from GoTriangle for all Orange County specific projects approved in the AWP. ALIGNMENT WITH STRATEGIC PLAN: This item supports: • GOAL 4: MULTI-MODAL TRANSPORTATION OBJECTIVE 1. Identify priorities and resources necessary to implement the Orange County Transit Plan. OBJECTIVE 2. Increase community awareness of all modes of transportation including transit, bike and pedestrian, vehicle, and all other modes. OBJECTIVE 3. Support road projects that address congestion and reduce commute time using the County's Complete Streets policy. 3 OBJECTIVE 4. Coordinate transit investments with municipal and county land use planning to reduce vehicle miles travelled and to provide more equitable access to shopping, employment, medical centers, college campuses, etc. OBJECTIVE 5. Invest in implementing the County' s Safe Routes to Schools plan. OBJECTIVE 6. Update transportation related plans to provide more multi-modal options including rural Orange County. RECOMMENDATION(S): The Manager recommends that the Board approve the FY27 Annual Work Program for transit (Attachment 1). 4 FORWARD ACOMMUNITY INVESTMENT IN TRANSIT ORANGE COUNTY FY27 TRANSIT WORK PROGRAM ORANGE COUNTY :4 TRIANGLE WEST NORTH CAROLINA 4m Transportation Planning Organization PV GO Triangle 5 TABLE OF CONTENTS SUMMARY 4 BACKGROUND 7 Project Sponsors and Project Benefactors FY27 Regional Tax District Model Unfunded Priorities FY27 OPERATING PROJECTS 18 Tax District Administration 19 1. Tax District Administration Finance Team 2. Financial Consulting and Overhead Administrative Costs GoTriangle 21 1. Transit Plan Administration — Program Management Staff 2. Transit Plan Administration— Program Implementation Staff 3. TPA—Transit Planning Support—Support Services 4. TPA— Legal and Real Estate Support Staff 5. TPA— Marketing, Communication and PE Support Staff 6. TPA— Marketing, Communication and PE Support Services 7. TPA— Regional Technology and Administration Support Staff 8. Customer Surveys 9. Route 800 Improvements— UNC Hospitals RTC 10. Route 400 Improvements— UNC Hospitals— Durham 11. Route ODX-Efland-Durham Express 12. Route CRX Improvements Chapel Hill-Raleigh Express 13. Paratransit Expansion 14. Youth GoPass 15. Fare Collection Improvements 16. Income-qualified GoPasses (TAP) 17. Bus Stop & Property 0&M Triangle West Transportation Planning Organization 38 1. Orange County Staff Working Group Participation* Orange County Transportation Services 39 1. Transit Plan Administration 2. Continuation of Transit Services Fixed Routes 3. Continuation of Transit Services Demand Response and Paratransit 4. Hillsborough Circulator 2.0 5. Mobility on Demand 6. Increased Cost of Existing Service 2 6 Chapel Hill Transit 45 1. Transit Planner 1 2. Bus Stop Amenities Technician 3. Onboard Technology QA/QC Technician (Project Implementation Staff) 4. Chapel Hill Transit Service Expansion FY13-21 5. CW Route— Improve Mid-Day Service 6. HS—Weekend Service 7. Increased Cost of Existing Service 8. Route D: UNC-Patterson Place 9. NS Route— Frequency and Span Improvements (Eubanks-Southern Village) FY27 CAPITAL PROJECTS 54 GoTriangle 55 1. Triangle Mobility Hub (Orange County Share) 2. Vehicle Acquisition and Replacement 3. Regional Bus Operations and Maintenance Facility 4. Fordham Blvd. Transit Access Improvements Orange County 59 1. Transit Plan Update 2. Operational Improvements Triangle West Transportation Planning Organization 60 1. Staff Study Chapel Hill Transit 61 1. Bus Purchases Expansion-Renewals Town of Carrboro 62 1. 203 Connector Sidewalk 2. West Main Street Sidewalk 3 7 SUMMARY The Orange County FY27 Annual Work Program (AWP) emphasizes fiscal responsibility while continuing key transit priorities throughout Orange County and its partner jurisdictions. This program reflects a transition from earlier implementation efforts toward sustaining existing services, managing cost pressures, and advancing selected initiatives aligned with the Orange County Transit Plan. Planning and development for the Chapel Hill Transit North-South Bus Rapid Transit (N-S BRT) project is currently underway as a regional priority. The work program also includes enhancements to GoTriangle routes 400,405, and 800, as well as preliminary planning for the launch of Orange County's transit service in Mebane in 2026. Capital investments, including replacement bus purchases and vehicle acquisition, focus on maintaining a state of good repair and supporting long-term system reliability. These investments reinforce the Work Program's commitment to preserving service quality while maintaining a balanced and fiscally responsible financial framework. This plan sustains the commitments established in FY26, incorporating a 2.5% increase in funding, along with a one-time allocation to support the Transit Plan and Staffing Study. The FY27 Annual Work Program designates funding to six (6) agencies: Orange County/OPT, Carrboro, Chapel Hill/CHT, Hillsborough, GoTriangle, and Triangle West Transportation Planning Organization (TWTPO). Programmed expenditures by agency are summarized in the sections that follow: 4 8 Capital Summary Operations and Administration Summary Prior Year FY27 Funding FY27 Funding Agency Carryover Requests Agency Requests Carrboro $ 1,932,339 $ 244,829 Chapel Hill $4,090,487 Chapel Hill $ 6,979,256 $ 122,132 GoTriangle $3,365,272 GoTriangle $4,740,335 $ 5,174,000 Orange County $1,615,868 Hillsborough $1,125,806 $ -- Triangle West TPO $42,867 Orange County $275,320 $300,000 Tax District Administration $374,841 Triangle West TPO $ -- $200,758 Total $9,489,335 Total $15,053,056 $6,041,719 Category Prior Year FY27 Funding Category FY27 Funding Carryover Requests Requests Bus Acquisition $3,235,907 $486,132 Tax District Administration $374,841 Bus Rapid Transit $4,679,857 -- Transit Plan Administration $930,982 Capital Planning $227,690 $300,000 Transit Operations $8,183,512 Transit Infrastructure $6,909,602 $5,054,829 Total $15,053,056 $5,840,961 Tot411111L $9,489. Capital Funding Categories (Long-term investments in vehicles, facilities, and infrastructure) Bus Acquisition: Purchasing new buses or replacing old ones to enable transit agencies to maintain reliable service. Examples: • Purchasing new fixed-route buses. • Replacing aging buses that have reached the end of their useful life. • Buying buses that are more accessible for riders with disabilities. Bus Rapid Transit (BRT): Purchasing buses and equipment specifically for BRT service, which operates more like rail, faster, more frequent, and more reliable. Examples: • High-capacity buses designed for frequent service. • Buses with multiple doors for quicker boarding. • Vehicles used on BRT routes with dedicated lanes or priority signals. Capital Planning: Planning and technical work are needed before major transit investments can move forward. Examples: 5 9 • Transit corridor studies. • Engineering and design for future transit facilities. • Environmental reviews and feasibility studies. • Long-range or systemwide transit planning efforts. Transit Infrastructure: Building or improving the physical infrastructure that supports transit service. Examples: • Bus stops and shelters. • Park-and-ride lots. • Transit stations or hubs. • Maintenance and operations facilities. • Sidewalks, lighting, and accessibility improvements near transit stops. Operations &Administration Categories (Day-to-day service and program management) Tax District Administration: Managing the voter-approved transit tax program and ensuring funds are collected, tracked, and distributed correctly. Examples: • Financial management and audits. • Processing reimbursements. • Compliance and reporting requirements. • Administrative oversight of transit tax funds. Transit Plan Administration: Managing and updating the transit plan that guides how transit tax funds are spent. Examples: • Updating the Orange County Transit Plan. • Public engagement and outreach related to transit planning. • Financial modeling and analysis • Coordinating with municipalities, MPOs, and transit agencies. Transit Operations:The cost of running buses and providing transit service. Examples: • Driver wages and benefits. • Fuel or electricity • Vehicle maintenance. • Daily route operations. • Service frequency and span of service. 6 10 BACKGROUND The Orange County transit program is guided by a regional governance framework established following voter approval of the Orange County transit sales tax in 2012. That same year, the governing boards of GoTriangle, the Triangle West Transportation Planning Organization (TWTPO), and Orange County adopted the first Bus and Rail Investment Plan. In 2013, the three parties entered into an Interlocal Agreement (ILA) to guide the use of transit tax revenues and the development of an expanded regional transit network. The Interlocal Agreement (ILA) was updated in 2023 to strengthen coordination, transparency, and accountability in transit planning and implementation. As part of this update, the Staff Working Group (SWG) was expanded to include representatives from Chapel Hill, Carrboro, Hillsborough, and Mebane, ensuring broader regional participation. The SWG serves as the administrative and advisory body responsible for developing a recommended Annual Work Program (AWP) for consideration by the governing boards. Also in 2023, a Comprehensive Participation Agreement (CPA) was approved by all project sponsors to further define participation and implementation roles. Together, the ILA and CPA establish requirements for project planning, reporting, and oversight, including the use of multi-year agreements and regular project updates to support transparency and accountability. Together, the ILA and CPA define the governance framework and implementation roles for the transit program, including coordination responsibilities of the Staff Working Group (SWG). Orange County serves as the SWG Administrator, overseeing coordination, reporting, and accountability. The Annual Work Program, which includes operating and capital funding recommendations and associated financial assumptions, must be adopted by both the Orange County Board of Commissioners and the GoTriangle Board of Trustees. The FY27 Annual Work Program operates within the framework of the adopted Orange County Transit Plan. 7 11 Project Sponsors and Project Beneficiaries Transit work plan requests are typically grouped by project sponsor. This is a common approach to considering project requests and tracking results from implemented projects. However, this approach obscures a very important consideration, which is that the benefit to transit passengers often goes beyond the sponsor's boundary. Many projects benefit more than one geographical entity, and transit users do not necessarily know or care which agency is providing the service they ride. The following is an example of considering FY27 and ongoing projects by beneficiary, or area served, rather than by sponsor alone. Town of Hillsborough Hillsborough does not operate transit. The town had submitted a request for a project in the draft FY27 plan, a greenway connecting its downtown with the future train station. However, the town is provided with transit service through the following projects implemented by other sponsors with transit plan funding: FY 27 Transit Work Plan New or Revised Protects: Orange County Transportation operates the Hillsborough Circulator 1; Hillsborough Circulator 2, Orange County Mobility on Demand, Orange County Demand Response, and Paratransit. Ongoing Transit Plan Protects/Services: Orange-Durham Express (ODX); Orange-Chapel Hill Connector (Hill to Hill). Orange Alamance Connector. Other Protects/Services: Hillsborough Park and Ride; Hillsborough Train Station. Town of Chapel Hill: Chapel Hill operates transit in Chapel Hill, Carrboro, and parts of unincorporated Orange County. In addition to its own services, the town benefits from the following projects implemented by other sponsors with transit plan funds: FY 27 Transit Work Plan New or Revised Projects: Route 800 (Chapel Hill-RTP). Ongoing Transit Plan Projects/Services: Routes 400 (Chapel Hill-Durham) and Chapel-Hill Raleigh Express (CRX). Other Projects/Services: Routes 405 (Carrboro-Chapel Hill-Durham), 805 (Chapel Hill-Southpoint). Town of Carrboro Carrboro does not operate transit but contributes to CHT annual budget and receives substantial service from Chapel Hill Transit. The town is a sponsor of a handful of FY27 projects that improve sidewalk and greenway connectivity. In addition to those services, the town benefits from the following projects implemented by other sponsors: 8 12 FY 27 Transit Work Plan New or Revised Projects: Chapel Hill projects that connect to Carrboro via transfers. Ongoing Transit Plan Protects/Services: Route CW. Other Protects/Services: Route 405. CRX via PNR at Eubanks. City of Mebane Mebane does not operate transit. Mebane city limits are in both Alamance County (70%) and Orange County (30%). The Mebane community receives transit services from the following projects implemented by other sponsors. Ongoing Transit Plan Projects/Services: Route ODX, Orange-Alamance Connector. Other Projects/Services: Alamance-Burlington Express (PART), Orange Route (Link Transit) All Orange County Jurisdictions All jurisdictions in Orange County benefit from projects provided by other sponsors. Operating examples include staffing for transit service planning and administration, outreach, technology improvements, bus stop improvements, and other critical functions. Capital project examples include new vehicles, expanded bus operations and maintenance facilities for partners to be able to service increased transit provision in Orange and across the Triangle; a new Triangle Mobility Hub to improve transfers to regional services and future rail service; an updated Orange transit plan; and more. 9 13 FY27 Triangle Regional Transit Tax District : Orange Transit Plan Revenues Tax District Revenues Article 43 Half-Cent Sales and Use Tax $ 11,845,000 Article 51 Three-Dollar Regional Vehicle Registration Tax $ 369,050 Article 52 Seven-Dollar County Vehicle Registration Tax $ 856,301 Allocation From Fund Balance $ 2,259,945 Total Revenues $ 15,330,296 Expenditures Tax District Administration Staff Costs $ 318,988 Audit Services $ 55,853 Transit Plan Administration Chapel Hill $ 240,000 GoTriangle $ 582,317 Orange County $ 65,798 Triangle West $ 42,867 Transit Operations Chapel Hill $ 3,850,487 GoTriangle $ 2,782,955 Orange County $ 1,550,070 Total Operating Allocation $ 9,489,335 Capital Planning Orange County $ 300,000 Triangle West $ 200,758 Transit Infrastructure Carrboro $ 244,829 GoTriangle $ 4,810,000 Vehicle Acquisition Chapel Hill $ 122,132 GoTriangle $ 364,000 Total Capital Allocation $ 5,840,961 Total Programmed Expenditures* $ 15,531,054 Revenues over Expenditures I $ - 10 FY27 Orange Transit Plan :Operating Fund Expenses 14 Orange Transit Orange Triangle Total Tax District Chapel Hill GoTriangle County West Orange Tran Operating Operatingsk Revenues Tax District Revenues Article 43 Half-Cent Sales and Use Tax $ 8,263,984 $ 8,263,984 Article 51 Three-Dollar Regional Vehicle Registration Tax $ 369,050 $ 369,050 Article 52 Seven-Dollar County Vehicle Registration Tax $ 856,301 $ 856,301 Allocations from Tax District Revenues to Agencies Transit Plan Administration $ 240,000 $ 582,317 $ 65,798 $ 42,867 Transit Operations $ 3,850,487 $ 2,782,955 $ 1,550,070 $ - Total Revenues $ 9,489,335 $ 4,090,487 $ 3,365,272 $ 1,615,868 $ 42,867 $ 9,489,335 Expenditures Tax District Administration Finance Team $ 318,988 $ - $ - $ - $ - $ 318,988 Audit Services $ 55,853 $ - $ $ $ $ 55,853 Transit Plan Administration 1.0 FTE:Transit Planner 1 $ - $ 90,000 $ $ $ $ 90,000 1.0 FTE:Bus Stop Amenities Technician $ $ 60,000 $ $ $ $ 60,000 1.0 FTE:QA/QC Technician Staff $ $ 90,000 $ $ $ $ 90,000 Transit Customer Surveys $ $ - $ 12,804 $ $ $ 12,804 Program Management Staff $ $ $ 27,595 $ $ $ 27,595 Project Implementation Staff $ $ $ 186,876 $ $ $ 186,876 Legal and Real Estate $ $ $ 129,977 $ $ $ 129,977 Marketing Support Staff $ $ $ 57,619 $ $ $ 57,619 Regional Technology Support Staff $ $ $ 84,331 $ $ $ 84,331 Marketing Support Services $ $ $ 34,881 $ $ $ 34,881 Transit Planning Support Services $ $ $ 48,233 $ $ $ 48,233 Staff Working Group Administrator $ $ $ - $ 65,798 $ $ 65,798 Staff Working Group Participation $ $ $ $ - $ 42,867 $ 42,867 Transit Operations Increased Cost of Existing Services $ $ 814,514 $ $ $ - $ 814,514 Chapel Hill Transit Expansion $ $ 1,873,099 $ $ $ $ 1,873,099 Route CW:Improve Midday Service $ $ 210,443 $ $ $ $ 210,443 Route HS:Weekend Service $ $ 176,600 $ $ $ $ 176,600 Route NS:Eubanks-Southern Village $ $ 322,679 $ $ $ $ 322,679 Route D:UNC-Patterson Place $ $ 453,153 $ $ $ $ 453,153 Paratransit Services $ $ - $ 25,827 $ $ $ 25,827 Route 800:UNC Hospitals-RTC $ $ $ 658,082 $ $ $ 658,082 Route 400:UNC Hospitals-Durham $ $ $ 1,599,561 $ $ $ 1,599,561 ODX:Efland-Durham Express $ $ $ 273,782 $ $ $ 273,782 CRX:Chapel Hill-Raleigh Express $ $ $ 81,668 $ $ $ 81,668 Youth GoPass $ $ $ 19,537 $ $ $ 19,537 Fare Collection Technology $ $ $ 20,972 $ $ $ 20,972 TAP Low Wealth GoPass $ $ $ 84,563 $ $ $ 84,563 Bus Stop&Property 0&M $ $ $ 18,963 $ $ $ 18,963 Increased Cost of Existing Services $ $ $ - $ 41,787 $ $ 41,787 Transit Services Fixed Route $ $ $ $ 186,550 $ $ 186,550 Hillsborough Circulator $ $ $ $ 388,983 $ $ 388,983 Mobility on Demand $ $ $ $ 466,375 $ $ 466,375 Transit Services Rural Route $ $ $ $ 466,375 $ $ 466,375 Allocations from Tax District Revenues to Agencies Transit Plan Administration $ 930,981 Transit Operations $ 8,183,512 Total Expenditures $ 91489,335 $ 4,090,487 $ 3,365,272 $ 1,615,868 $ 42,867 $ 9,489,335 Revenues over Expenditures $ - $ - $ - $ - $ $ - 11 15 FY27 Orange Transit Plan : Capital Fund Expenses Orange Tax District Carrb0d "JL County OrangeTransit Capital Capital Revenues Tax District Revenues Article 43 Half-Cent Sales and Use Tax $ 3,581,016 $ 3,581,016 Allocation From Capital Fund Balance $ 2,259,945 $ 2,259,945 Allocations from Tax District Revenues to Agencies Capital Planning $ - $ - $ - $ 300,000 Transit Infrastructure $ 244,829 $ - $ 4,810,000 $ - Vehicle Acquisitions $ - $ 122,132 $ 364,000 $ - Total Revenues $ 5,840,961 $ 244,829 $ 122,132 $ 5,174,000 $ 300,000 $ 5,840,961 Expenditures Capital Planning Transit Plan Update $ - $ - $ - $ - $ 300,000 $ 300,000 Staffing Study $ 200,758 $ 200,758 Transit Infrastructure 203 Connector Sidewalk $ - $ 105,911 $ - $ - $ - $ 105,911 West Main Street Sidewalk $ - $ 138,918 $ - $ - $ - $ 138,918 Regional Bus Operation & Maint Facility $ - $ - $ - $ 2,100,000 $ - $ 2,100,000 Triangle Mobility Hub $ - $ - $ - $ 210,000 $ - $ 210,000 Fordham Blvd Access Improvement $ - $ - $ - $ 2,500,000 $ - $ 2,500,000 Vehicle Acquisitions Bus Purchases $ - $ - $ - $ 364,000 $ - $ 364,000 Bus Purchases Expansion-Renewals $ - $ - $ 122,132 $ - $ - $ 122,132 Allocations from Tax District Revenues to Agencies Capital Planning $ 300,000 Transit Infrastructure $ 5,054,829 Vehicle Acquisitions $ 486,132 Total Expenditures $ 5,840,961 $ 244,829 $ 122,132 $ 5,174,000 $ 500,078 $ 6,041,719 Revenues over Expenditures $ - $ - $ - $ - $ - $ - 12 16 Unfunded Priorities The revenue generated by the Transit Tax District is not enough to meet all the region's transit needs. This section identifies those unfunded needs. Documenting these projects can help prioritize investments if additional transit funding becomes available. Projects were provided by transit service providers and by reviewing each agency's short-range transit plan. Estimated project costs are provided when available. This list of projects is subject to change as agencies and municipalities continue to evaluate transit needs and available resources. 13 UNFUNDED PRIORITIES Type Chapel Hill Transit US 15-501 BRT Major Investment Study and Alternatives Analysis Planning for potential B0 RT or high-capacity transit on US 15-501 F v Route CL** Add weekend service 6:30 AM-10:00 PM(M-F),8:00 AM-9:00 PM(Sat),8:00 AM-7:00 PM(Sun) $130,000 New weekday peak-only service from White Cross to UNC-Chapel Hill 6:30 AM-9:30 AM;3:30 PM- O New Service:West NC 54 6:30 PM(M-F) $150,000 New service connecting UNC-Chapel Hill,University Place,and Glen Lennox via Estes Drive 6:30 AM New Service: Estes Drive Crosstown -8:30 PM(M-F),8:00 AM-7:00 PM(Sat-Sun) $129,000 Same Day Customer Trips 6:30 AM-10:00 PM(M-F)8:00 AM-7:00 PM(Sat)8:00 AM-7:00 PM (Sun) EZ Rider $624,000 Midday/Evening trips to/from service area with no bus routes, 10:00 AM-2:00 PM;6:00 PM-11:00 On-Demand Service PM(M-F) $850,000 Senior Shuttle Bi-Directional Service utilizing 2nd vehicle,8:00 AM-7:00 PM $220,000 Improve weekday service to 30 minutes frequency,6:30 AM-10:00 PM(M-F)8:00 AM-7:00 PM Route A (Sat)8:00 AM-7:00 PM(Sun) $340,000 Route CL Improve weekday peak service to 10 minutes frequency,6:30 AM-10:00 PM $900,000 Route D* Improve weekday peak service to 10 minutes frequency,6:00 AM-11:00 PM $900,000 Improve weekday service to 30 minutes frequency 6:30 AM-10:00 PM(M-F);add Weekend $740,000(weekday) Route F service.8:00 AM-9:00 PM (Sat)8:00 AM-7:00 PM(Sun) $130,000(weekend) Route G Extend evening service to 9:00 PM,7:00 AM-9:00 PM(M-F) $75,000 improve weekday service to 30-minute frequency,6:30 AM-10:00 PM(M-F)8:00 AM 7:00 Route N PM(Sat)8:00 AM-7:00 PM (Sun) $330,000 Operation of N-S BRT,5:30 AM-11:30 PM(M-F)8:00 AM-11:00 PM(Sat)8:00 AM-9:00 PM N-S-BRT (Sun) $1,400,000 Service to/from Chatham Park and UNC campus(weekday only),6:00 AM-9:00 AM(M-F) New Service Chatham Park Express 4:00 PM-7:00 PM(M-F) $625,000 Improve weekend service on A, CM, CW, D,J, N, NS and NU (Saturday and Sunday; increased Improve Weekend Service** *** frequency on existing routes 8:00 AM-9:00 PM(Sat)8:00 AM-7:00 PM(Sun) $1,200,000 Improve Weekday Service Improve weekday service;7:00 PM-11:30 PM(M-F) $500,000 Seamless Regional Paratransit** Partnership with GoTriangle to provide seamless paratransit service. $500,000 * Estimated costs are in 2020 dollars ** Identified by CHT as a priority unfunded project *** Connected to proposed projects 14 UNFUNDED PRIORITIES Type Proj Descripti At Estimate Orange County Public Transportation Vanpool Subsidy Program Providing additional vanpool subsidy for Orange County residents 0 Expand service span and frequency on existing route to operate Monday to Saturday from 7:00 OExpand Hillsborough Circulator Service AM-8:00 PM jAdditional Hillsborough Circulator Route Alternative alignment for the Hillsborough Circulator with two partially overlapping loops New fixed-route service between Hillsborough and Durham with connections to Duke VA illsborough-Durham Connection Hospital,operating hourly on weekdays between 9:00 AM-4:00 PM New peak only fixed-route service between Hillsborough and Cedar Grove on weekdays edar Grove Peak Connection between 6:00 AM-9:00 AM and 3:30 PM-7:00 PM New peak only fixed-route service between Chapel Hill and White Cross operating on White Cross Commuter Service weekdays between 6:30 AM-9:30 AM and between 3:30 PM 6:30 PM m CL u New transit amenities in Hillsborough include a new transfer center and a new park and-ride Transit Amenities facility 15 19 UNFUNDED PRIORITIES Type 10 0001 GoTriangle c Major Investment Study,Alternatives Analysis,and design and operational concepts as a US 15-501 BRT Study follow-up to DCHC's draft 15-501 Corridor Study $1,000,000 Midday and Evening service on route Make route more user friendly by providing a consistent service pattern between peak and off- s 1420 peak service(coordinate with OCPT service) Provide all-day service on Route 805 Weekend Service on 420 Increase route frequency to support higher ridership,future BRT as included in the 2050 MTP,and transit-oriented development at Southpoint, HUB RTP and other locations in south Increase Frequency on Route 800 Durham(medium—long term) Planning and engineering, right of way, and construction of ten (10) bus stops serving GoTriangle,CHT and/or OCPT(selected based on ridership,demographics,and community Bus stop improvements(10 stops) assets);can be scaled and phased in batches $500,000 Shared charging facility with Chapel Hill Transit; local match (20/80)for federal grant application for Lo-No Emission vehicles and fleet transition,including on-route charging Chapel Hill / Carrboro Layover and facilities;location/scope to be determined in ongoing Regional Fleet and Facilities Study; Electric Charging Facility cost accounts for escalation through 2030 $2,000,000 Additional Park and ride capacity in NC 54/1-40 corridor serving UNC and Raleigh;includes $1,000,000 (Orange NC 54/Farrington Park and Ride(property owned by bus ramp to 1-40 EB; requires coordination with UNC, Durham,and NCDOT project 1-6006; County portion of GoTriangle) cost accounts for escalation through 2030 cost share) Arterial Bus Rapid Transit on US 15-501 Incremental step towards BRT on US 15-501 corridor; includes shoulder widening, transit (UNC Hospitals to Orange County Line) signal priority,potential queue jump lanes, premium transit stations;coordinate with $25,000,000(est. 2030+ NCDOT Project(STIP ID U-5304);cost accounts for escalation $5,000,000/mi.) Arterial Bus Rapid Transit on NC 54 Incremental step towards BRT on NC 54 East corridor. Includes shoulder widening,transit $5,000,000 East(US 15-501 to Orange County Line) signal priority, potential queue jump lanes, premium transit stations; coordinate with (est.$5,000,000/ 2027+ NCDOT project(STIP ID-U774);cost accounts for escalation. mi.) Full BRT on NC 54 and US 15-501 Build on incremental projects to achieve full BRT build-out(silver or better on ITDP scale]as $300,000,000(est. 2040+ envisioned in the 2050 MTP Implement;cost accounts for escalation. $50 million/mi.) * Estimated costs are in 2020 dollars ** Identified by CHT as a priority unfunded project *** Connected to proposed projects 16 20 UNFUNDED PRIORITIES Type Town of Carrboro Short section of multi-use path and crossing; identified as a priority in Carrboro's bicycle U Homestead Road multi-use path and crossing plan update(2020) $938,437 Complete the missing sections of sidewalk on Old Fayetteville Road(behind Carrboro Old Fayetteville Road sidewalk connections Plaza); identified as an unfunded priority in 2017 transit plan $750,000 Pedestrian safety improvements on Starlite Drive,sidewalk on north side or roadway; Starlite Drive sidewalk identified as a priority by residents of Starlite Drive $270,106 10-foot-wide multi-use path, approximately 0.7 mi long,extending through Baldwin Park Baldwin Park connector and connecting Carrboro and Chapel Hill. $299,000 Bike and pedestrian connection from East Main Street to Roberson(new public facilities 203 Connector including library) $172,500 2 20%local match; provides off-road access to University Lake and eventually Carrboro High Morgan Creek Greenway Phase 2 School for residents living in apartments along NC 54 $366,800 BPW Road sidewalk connections Complete missing sections of sidewalk $170,000 17 21 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 21GOTAD01 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost GoTriangle-Tax District Steven Schlossberg Base Year Tax District Administration Administration sschlossberg@gotriangle.org FY 2028 ales Finance Team Cumulative Estimated Orange Transit Estimated Estimated Start Date Completion Notes Capital Cost Base Year July 1,2018 Ongoing Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. GoTriangle will employ staff to manage various financial and administrative tasks, including producing annual budgets, updating the Transit financial plan, coordinating funding agreements, generating reports, and monitoring spending. Staff will also review reimbursement submissions,track projects, and manage local revenue. Costs will cover salaries, benefits, professional development, supplies, and administrative expenses. The team will focus on improving financial policies, providing analysis for Transit plans, and leading the year-end financial audit. Additionally,staff will oversee transit plan accounting, audit processes,fund investments, revenue collection, and provide financial support services. The total Full Time Equivalent (FTE) staff across the three transit plans will be 7.2 FTEs, broken down as follows: Wake Transit Plan 3.0, Durham Transit Plan 2.3, and Orange Transit Plan 1.9. Allocation breakdown is based on a combination of: 70%of tasks are consistent between the three transit plans, and 30%which vary for each plan. The variable 30% is allocated as follows: 60%to Wake, 30%to Durham, and 10%to Orange. This request consolidates two projects adopted in the previous work program (21GOTADI &AD11) 18 22 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 21GOTAD22 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year Tax District Administration GoTriangle-Tax Steven Schlossberg FY 2028 e5ti1 Audit Services District Administration sschlossberg@gotriangle.orse Cumulative Estimated OrangeTransit Estimated Estimated Start Date Completion Notes Capital Cost July 1,2018 Ongoing Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description Description/Scope in the FY 2027 Work Plan. The project request is a continuation of ongoing operations and reflects the consolidation of 21GOTAD21 and 21GOTAD22. The Tax District will continue to utilize financial consultants in support of the Orange Transit Plan to address fiduciary responsibilities and other related needs required to carry out the responsibilities of the Tax District. The project will also provide advisory services and costs related to potential debt issuance for projects in the Orange Transit Plan. In addition, project funds may be used to cover Orange Transit bank and service fees charged to the Tax District,as well as audits or other financial reviews that are determined to be necessary or appropriate by the Tax District administrator. Funds may also support any other financial, administrative or advisory services deemed necessary to effectively manage Orange Transit's financial obligations. 19 23 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 20GOTAD02 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Transit Plan Base Year Administration- Pro GoTriangle Katharine Eggleston FY 2028 Program ages g keggleston@gotriangle.or Management Cumulative Staff Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost July 1,2020 Ongoing Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. NOTE:The project request is a continuation of ongoing operating:Specifically,consolidation of Program Management functions from 20GOT_AD2 support services submissions approved in the FY20 Workplan. GoTriangle will continue to allocate 0.1 FTE of GoTriangle program management staff to the Orange Transit Plan. In FY25, this staffing will provide oversight and program management support for GoTriangle's bus facilities and bus stop amenities planning and development programs, and oversight and program management support for GoTriangle's efforts in support of the Orange Transit Plan update. Specific tasks include oversight of project planning; oversight of project scope,schedule,and budget development and monitoring; oversight of quarterly reporting; and supervision of GoTriangle's planning and project delivery teams. 20 24 REQUEST# FY2027 FYSTART DATE Orange Transit Work Plan Jul 2026 20GOTAD03 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Transit Plan Base Year Administration- GoTriangle Katharine Eggleston FY 2028 ages Program keggleston@gotriangle.or Implementation Staff Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost July 1,2020 Ongoing Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description Description/Scope in the FY 2027 Work Plan. NOTE:The project request is a continuation of ongoing operating:Specifically,consolidation of Project Implementation functions from 20GOT_AD2 support services submissions approved in the FY20 Workplan. GoTriangle will continue to allocate 0.8 FTE for project implementation activities for the Orange Transit Plan.In FY25, this team will manage and execute planning, design, and construction management activities for GoTriangle's bus facilities and bus stop amenities programs and participate in capital planning, coordination, and support activities for the Orange Transit Plan update. Specific tasks include but are not limited to project scope, schedule, and budget development and monitoring; quarterly reporting; and management of consultants and contractors. Planning tasks: planning/prioritization forbus stop and park-and-ride improvements;management and technical consultant oversight; environmental planning and coordination with regulatory agencies for federally funded projects; and coordination to support CHT's N-S BRT project. Design/Engineering/Architecture tasks: field investigations,feasibility analysis, consultant oversight,and technical supportfor bus stop and park-and-ride improvements;design management,project coordination, and technical support for major facilities projects; and feasibility analysis and implementation oversight for BOSS. Construction Management tasks: project management, contractor oversight, and construction inspection. Project Coordination tasks: managing coordination with GoTriangle's partners; facilitating productive partnering; promoting schedule and budget adherence and fostering timely conflict resolution. Project Controls Support tasks: eBuilder administration; document management; contract administration; project controls support including budget and schedule monitoring, risk management support, and reporting." 21 25 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 21GOTAD13 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost TPA-Transit Planning Base Year Support-Support Services GoTriangle Meg Scully FY 2028 ages mscully@gotriangle.or Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost July 1,2018 Ongoing Base Year Cumulative Project Enter below a summary of the project that may later be used as the project Description/Scope description in the FY 2027 Work Plan. NOTE:The project request is a continuation of on-going operating: Consolidation of regional transit planning functions from 20GOT_AD3 (support consultants) submissions approved in FY20 Workplan. GoTriangle is requesting reimbursement for ongoing support costs (including indirect costs)that benefit the Orange County Tax District.The Support Consultant cost are split 50% Durham and 50% Orange,which include regional contracts. FY25 Update: GoTriangle is requesting reimbursement for on-going support costs(including indirect costs)that benefit the Wake County Tax District.This includes the Orange County share of the$31,775 (base year of FY25)of the Triangle Regional Model Service Bureau contract.The revised split for this contract is split as follows:70-20-10 Wake-Durham- Orange. This split reflects the ratio of population and employment that benefits from this support service among the counties. 22 26 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 21GOTAD04 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year TPA-Legal and 1 GoTriangle Katharine Eggleston FY 2028 ages Real Estate keggleston@gotriangle.or Cumulative Estimated OrangeTransit Estimated Estimated Start Date Completion Notes Capital Cost July 1,2018 Ongoing Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. The project request is a continuation of ongoing operations and reflects the consolidation of 21GOTAD21 and 21GOTAD22.TheTax District will continue to utilize financial consultants in supportof the Orange Transit Plan to address fiduciary responsibilities and other related needs required to carry out the responsibilities of the Tax District.The project will also provide advisory services and costs related to potential debt issuance for projects in the Orange Transit Plan. In addition, project funds may be used to cover Orange Transit bank and service fees charged to the Tax District,as well as audits or other financial reviews that are determined to be necessary or appropriate by the Tax District administrator. Funds may also support any other financial,administrative or advisory services deemed necessaryto effectively manage Orange Transit financial obligations. 23 27 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 21GOTAD05 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost TPD-Markatina Base Year GoTriangle Meg Scully FY 2028 51ti'1 Support Staff mscully@gotriangle.or ee Cumulative 5 VAe Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost July 1,2018 Ongoing Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. NOTE:The project request is a continuation of ongoing operating: Specifically, consolidation of Marketing, Communication, and Public Engagement functions from 20GOT_AD2 support services submissions approved in the FY20 Workplan.GoTriangle is requesting funding for.5 FTEs that will be dedicated to public engagement.The Public Engagement Specialist will work under the Community Engagement Manager, in the Communications&Public Affairs department at GoTriangle,directly collaborating with project teams to plan and execute public involvement activities related to the development and implementation of the Orange County Transit Plan.They will support the establishment and maintenance of relationships with community stakeholders that include public officials, strategic partners, community groups, property owners, and businesses. 24 28 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 21GOTAD12 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost 1.12 Ton _ r%A­I­i-;­ Base Year GoTriangle Meg Scully FY 2028 Seepa� -Support Services mscully@gotriangle.or Cumulative Estimated OrangeTransit Estimated Capital Estimated Start Date Completion Notes Cost July 1,2018 Ongoing Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. NOTE:The project request is a continuation of on-going operating: Specifically, consolidation of Marketing, Communication and Public Engagement functions from 20GOT_AD2 support services submissions approved in the FY20 Workplan. GoTriangle is requesting funding for support services that will be dedicated to engaging equitably with the community.This project will support ongoing community engagement efforts, marketing, and communications activities related to the Orange Transit Plan. Funding will also support our capacityto utilize creative consultant services,orexpand the scope of service through current consultants,to support materials for community outreach, public meetings, marketing campaigns, information kits,web elements,translation and interpretation,etc. 25 29 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 21GOTAD06 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost TPA - Regional Base Year _12 Technology Meg Scully GoTriangle mscully@gotriangle.or FY 2028 Se Support Staffpad Cumulative Estimated OrangeTransit Estimated Estimated Start Date Completion Notes Capital Cost July 1,2018 Ongoing Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. NOTE:The project request is a continuation of ongoing operating:Specifically,consolidation of technology and contract administration functions from 20GOT_AD2 support services submissions approved in the FY20 Workplan. GoTriangle will continue to allocate 0.2 FTE of Regional Technology and Administration - support staff to the Orange Transit Plan. Staffing includes budgeted time for the Regional Technology Manager, Contract and Grants Coordinator, and Contract Administrator. In FY25,the Technology and Administration functions will continue : •Proposed continuation of the outcomes of the Regional Technology study that assess existing technology within all participating transit agencies, in order to design a coordinated technology integration plan. One such outcome is the mobile-ticketing transition that will be in the process of implementation. •Assist with the strategic capital improvement of the regional park and ride program, proposed RTC relocation, and other infrastructure projects 26 30 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2025 19GOT002 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Proje=NameRequesting Agency Project Contact Operating Cost Base Year 1-tit Transit GoTriangle Meg Scully FY 2028 Ce P, 9a�es Customer Surveys mscully@gotriangle.or Cumulative Estimated Orange Transit Estimated Estimated Start Date Completion Notes Capital Cost July 1,2018 Ongoing Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. GoTriangle will use these funds to continue the development and implementation of annual transit customer surveys that help to continually evaluate user experiences as additional services are implemented. Routes surveyed include the 400,405,800,805,CRX,and the ODX,all of which provide service to Orange County. 27 31 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 2000TTS2 Request Form Total Project Cost Operating and/or Capital see pages 11-12 Orange Transit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year Route 800 -UNC Hositals RTC GoTriangle Jay Heikes FY 2028 seeQ aces iheikes@otrainle.or� Cumulative Estimated Estimated Start Date Completion Notes Orange Transit Estimated Capital Cost August 19,2013 Ongoing Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. Route 800 provides all-day/every-day regional connections along NC-54 and 1-40 between UNC Hospitals and the Regional Transit Center and serves people traveling between Chapel Hill, Southpoint, RTP, and Raleigh at off-peak times. Substantial growth continues to occur along the corridor, driving demand for Orange County residents, employees, and visitors to travel along this corridor.This project includes all off-peak span and frequency improvements to GoTriangle Route800(Chapel Hill-Southpoint-RTC)since the Tax District began providing funding for it. Orange County Transit Plan funding will continue to support the following improvements to Route 800: - Weekday midday frequency was increased from 60 to 30 minutes. - Saturday daytime frequency was increased from 60 to 30 minutes. - Saturday evening service was extended from 7:15 PM to 11:20 PM. - Sunday service was added from 6:45 AM to 10 PM. - Costs are allocated50%to Durham County and 50%to Orange. Weekday frequency 6:00 am—11:10 pm Weekend frequency 6:50 am—11:20 pm (Sat) Weekend frequency 6:50 am-9:10 pm (Sun) Bus Operations FY27 FY28 Estimated Hours 5,501 5,501 Cost Per Hour 173 178 28 32 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 20GOTTS6 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year 2 Route400 GoTriangle Jay Heikes FY 2028 ePages UNC Hospitals-Durham Iheikes@�otrainle.ore Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost Base Year August 16,2014 Ongoing Cumulative Project Enter below a summary of the project that may later be used as the project Description/Scope description in the FY 2027 Work Plan. UPDATE 231213: This sheet includes FY26 and future year costs for Orange Transit Plan Route 400/405 improvements. This project consolidates all off-peak span and frequency improvements to GoTriangle Route 400 (Durham -Chapel Hill) since the Tax District began providing funding for it. On Route 400: -Weekday midday frequency was increased from 60to 30minutes. -Saturday daytime frequency was increased from 60to 30minutes. -Saturday evening service was extended from 6:55 PM to 10:55 PM. -Sunday service was added from 7:00 AM to 6:55 PM. It also includes former 19GOT_TS1 extending service to 8:55 PM (the 400 component). Costs are allocatec150%to Durham County and50%to Orange. Weekday frequency 5:30 am—12:00 am Weekend frequency 6:00 am—12:00 pm (Sat) Weekend frequency 6:00 am—11:00 pm (Sun) Bus Operations FY27 FY28 Estimated Hours 9,238 9,238 Cost Per Hour 169 173 29 33 REQUEST# FY2027 FYSTART DATE Orange Transit Work Plan Jul 2026 2000TTs5 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Route ODX-Efland- Base Year Durham Express GoTriangle Jay Heikes FY 2028 see ales iheikes@otrianle.or Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost Base Year August 16,2014 Ongoing Cumulative Project Enter below a summary of the project that may later be used as the project description Description/Scope in the FY 2027 Work Plan. UPDATE 231213: Updated to reflect future year service to transit-plan funded new Hillsborough Park and Ride lot (FY27).A new Orange-Durham Express route was implemented,linking Mebane,Efland,and Hillsborough in Orange County to the Duke &VA Medical Centers and downtown Durham during weekday peak hours. Costs areallocated50%to Durham County and50%to Orange. Weekday frequency 5:45 am—9:30 am Weekend frequency 4:00 pm—8:00 pm Bus Operations FY27 FY28 Estimated Hours 1,370 1,581 Cost Per Hour 169 173 30 34 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 20GOTTS6 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year 2 Route CRX GoTriangle Jay Heikes FY 2028 p31 ages Chapel Hill-Raleigh Express Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost Base Year August 16,2015 Ongoing Cumulative Project Enter below a summary of the project that may later be used as the project description Description/Scope in the FY 2027 Work Plan. Due to high demand for express service between Chapel Hill and Raleigh,additional trips were added to Route CRX (Chapel Hill -Raleigh Express).This project was originally charged 100%to Orange County, but proportionate additional investment from Wake County started in Wake's FY 2019 work plan. Weekday frequency 5:45 am—9:55 pm Weekday frequency 3:00 am—7:40 pm Bus Operations FY27 FY28 Estimated Hours 472 472 Cost Per Hour 169 173 31 35 REQUEST# FY2027 FYSTART DATE Orange Transit Work Plan Jul 2026 19GOTTS8 Request Form Total Project Cost Operating and/or Capital see pages 11-12 Orange Transit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year Paratransit Services GoTriangle Jay Heikes FY 2028 age51 iheikes@gotraingle.or Cumulative Estimated Estimated Start Date Completion Notes Orange Transit Estimated Capital Cost Base Year August 16,2014 Ongoing Cumulative Project Enter below a summary of the project that may later be used as the project description Description/Scope in the FY 2027 Work Plan. Due to span increaseson Saturdays,Sundays,and holidays for Routes400,700,and 800,there are additional ADA paratransit costs incurred.These costs are split 64%to Durham County and 36%to Orange County. Weekend frequency 9:00 am—11:00 pm (Sat) Weekend frequency 7:00 am-9:00 pm (Sun) Bus Operations FY27 FY28 Estimated Hours 162 162 Cost Per Hour 155 159 32 36 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 21GOT001 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year A-1 Austin Stanion Youth GoPass GoTriangle astanion@gotraingle.or� FY 2028 epages Cumulative Estimated Orange TransitEstimated Capital Estimated Start Date Completion Notes Cost July 1,2020 N/A Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description Description/Scope in the FY 2027 Work Plan. For youth ages 13-18,transit agencies across Orange,Wake,and Durham County will continue to offer a 'Youth GoPass' program.These fare passes are issued by GoTriangle,GoDurham, GoRaleigh, or GoCary with valid K-12 School ID Cards or with transit agency-issued identification cards. GoTriangle, GoDurham, GoRaleigh, GoCary, and, in partnership with the respective counties,will continue to work with schools along Triangle County's bus network to issue the passes. Passes will also continue to be available to those with a valid ID at GoDurham Station, GoRaleigh Station,the Town of Cary Finance Department, the GoTriangle Regional Transportation Center, public libraries, and regional centers. This project covers the cost of offsetting fares that would have been collected by GoTriangle in the county share of routes, in addition to purchasing the supplies needed for this program.The estimated cost is the allocation of GoTriangle-Orange share of Youth GoPass boardings in Orange County. 33 37 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 21GOT002 Request Form Tot aIPro'ec o Operating and/or Capital OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Yearestil-1 Fare Collection GoTriangle Jay Heikes FY 2028 Se e Technology iheikes@�otrainle.or Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost July 1,2020 N/A Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. This project will coverthe annual costs associated with updated mobile ticketing technology for GoTriangle buses.Share of cost based on FY19 boardings reported in Orange County.This project request also allocates a portion of hold harmlessagainst any reduction of fare revenue as a result of implementing this uniform fare strategy.The regional fare- working groups priorities include(1) Improving Pass Distribution and Sales; (2) Balance Revenue and Ridership Goals;(3) Improve the Passenger Experience; (4) Improve Regional Coordination; (5) Make Transit an Affordable Option; and (6) Explore New Fare Technologies.These earmarked funds will be estimated and will be dependent on the final methodology developed by a Fare Working Group. 34 38 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 25GOTTS21 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost TAP Low Wealth Base Year ,12 Austin Stanion ale GoPass GoTriangle astanion@gotraingle.or FY 2028 eP Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost July1, 2024 Base Year Ongoing Cumulative Project Enter below a summary of the project that may later be used as the project description in the Description/Scope FY 2027 Work Plan. The Transit Assistance Program (TAP) expands mobility and ensures equitable access to public transit by funding fully subsidized fixed-route and paratransit trips for adults with low or no income.TAP supports the goals of the Orange County Transit Plan while advancing regional priorities such as climate sustainability and transportation demand management. In FY25,TAP riders took over 400,000 trips on GoTriangle routes.The 2025 TAP Evaluation (attached)found that the most common trip purposes for TAP rides were: Work (77%), Running Errands (79%), Visiting Family (73%), Medical Appointments (74%), and School (34%). Over 50% of TAP riders said that without the program, they would not be able to continue riding at the same level as they currently do.Without the TAP Program,thousands of riders across Orange County would lose access to affordable transit and ultimately connect less with their communities. Program objectives include: - Maximizing program use among eligible individuals. -Minimizing administrative costs relative to the overall program. - Gathering data to continually improve service for low-income riders. 35 39 REQUEST It FY 2026 FY START DATE Orange Transit Work Plan Jul 2027 Request Form Total Project Cost Operating and/or Capital See pages 11-12 Project Name Requesting Agency Project Contact Orange Transit Estimated Operating Cost GoTriangle Bus Stop and Property Jay Heikes Base Year operations and maintenance GoTriangle jheikesLa)ggohian l�e.org FY 2027 e5 Cumulative ee Estimated Start Date Estimated Completion Notes Orange Transit Estimated Capital Cost FY25Q2 Ongoing This project is a continuation of a FY25 Q2 Base Year I$ - Amendment Request Cumulative I$ - Project Description/Scope Enter below a summary of the project that may later be used as the project description in the FY 2026 Work Plan. The upkeep,cleaning,operations and maintenance,replacement,and miscellaneous costs for transit plan funded,GoTriangle-served bus stops,park and rides,and properties.This project is a companion to an existing Wake County project and a requested FY26 Durham County project. Project Justification/Business Case Provide responses to EACH of the questions below.Answer the questions as fully as possible. Enter Not Applicable (N/A)as appropriate. Please detail project justification This project will provide for the maintenance and upkeep of GoTriangle bus stops served by transit-plan-funded expansion service and transit plan-funded properties in Orange County. The project will improve overall customer satisfaction by improving the function,appearance,and cleanliness of bus stops,parks,and rides-consistently identified by transit riders as a priority for improvement. 1. Is this a New Project,Scope Change or Financial Change? New 0 Scope ❑ Financial ❑ see msm.mo.:fo def t... Ia.If Scope Change or Financial Change-Indicate previous project ID 2. Is this project Operating,Capital or Both? Operating 0 Capital ❑ Both ❑ 3. Is this a one-time request? Yes ❑ No 0 4. What is the timeframe for the request?Are you requesting a full year of funds in FY26 or a partial year to be annualized in future fiscal years? Full Year S. Where is this project located,who will this project serve and how will it improve service or overall implementation of the Orange Transit Plan? GoTriangle-served bus stops in Orange County 6. Is this project programmed in the adopted Transit Plan FYs 2026-2032 Multi-Year Operating Program or CIP? Yes ❑ No ❑ 6a. If yes,how does this request relate to what was envisioned in the adopted Multi-Year Operating Program,CIP,or Orange Transit Plan? Specify which component(s)of the Multi- Year Operating Program,CIP,or Orange Transit Plan the request supports. This project reprograms funds from the removal of the DOLRT Closeout project,included in the Orange Transit Plan and CIP to support function,appearance,and cleanliness of bus stops and park and rides. 6b. If no,is this project in addition to projects and services included in the adopted Multi-Year Operating Program,CIP,or Orange Transit Plan or in lieu of projects and services included in those programs/plans? 36 40 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 24MPOADI Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year Orange County Staff Triangle West Doug Plachcinski FY 2028 a�e5 Working Group Transportation doug.plachcinski@twtpo.or Participation Cumulative Planning Organization(TWTPO) Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost July 1,2025 Ongoing Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in the Description/Scope FY 2027 Work Plan. The Staff Working Group Participation request provides resources for MPO participation on the body, including meeting preparation, attendance, and follow-up. MPO staff will also complete necessary research, support, and reporting for full engagement with SWG activities. 37 41 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 240PTTS1 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Orange County Base Year Transit Plan Administration Transportation Sarah Williamson FY 2028 ales Services will iamson-baker@oran ecountync. o Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost Julyj 2024 Ongoing Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in the Description/Scope FY 2027 Work Plan. The Staff Working Group Administrator supports the Staff Working Group,which is made up of Orange County,GoTriangle, Local Parties, and the TWTPO. Meeting responsibilities include planning, coordination, and record keeping. Additional responsibilities include fulfilling mutually agreed-upon Staff Working Group demands, such as website maintenance and information archiving. 38 42 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 190PTTS1 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Continuation ofTransit Orange County Base Year Services Fixed Route Transportation Jamael Wiley FY 2028 ages Services Iwiley@orangecountync.gov Cumulative Estimated Orange Transit Estimated Estimated Start Date Completion Notes Capital Cost July 1,2018 Ongoing Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. This project advances "Continuation of Transit Services" (190PTS1) as previously approved in each annual work program and in accordance with the new 2022 Orange County Transit Plan.The Orange County Transit service area boundary was updated two times prior to its most recent expansion on January 16, 2024. FY25 Fixed Routes funded by this Increased Cost of Existing Services (ICES) include, *Orange-Alamance Connector,and *Orange-Chapel Hill connector(AKA: Hill-to-Hill). Weekday frequency: 7:00 am—5:30 pm Bus Operations FY27 FY28 Estimated Hours 2000 2000 Cost Per Hour 93 96 39 43 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 250PTTS12 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year eSti1-1 Continuation ofTransit See Services Demand Orange County JamaelWiley FY 2027 Response and Paratransit Transportation Services jwiley@orangecountync.gov Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost July1,2023 Ongoing Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description Description/Scope in the FY 2027 Work Plan. Rural Transit Services and ADA Paratransit Improvements:All rural transit services, including ADA Paratransit and Demand Response, will continue in alignment with the 2015 Paratransit Plan.These services are part of a broader initiative to improve transportation options in rural areas, following the approval of the transit tax in 2013. The plan and related services were further advanced in 2022 with the release of the updated Orange County ADA Paratransit Plan and Demand Response Service Improvements.This includes collaboration with other county departments such as the Department of Aging,Social Services, Library, and the Criminal Justice Resource Department to enhance accessibility and service delivery. Expanded operations to accompany vehicles provided by Orange County Commissioners for expanding Demand Response Services This project furthers the objectives of the "Continuation of Transit Services" (190PTS1), as previously approved in annual work programs,and is fully in accordance with the goals of the new 2022 Orange County Transit Plan. It aligns closely with BOCC Strategic Plan,Transportation performance measure#1,"Increase ridership by 5%each year on fixed route,demand response, and mobility on demand transportation services." Orange County has purchased vehicles for this program, and is seeking authorization from the Transit Plan to hire operators and expand this much needed service in early FY26. Weekday frequency: 7:00 am—5:30 pm Bus Operations FY27 FY28 Estimated Hours 5000 5000 Cost Per Hour 165 169 40 44 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 20OPTTS4 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Orange County Base Year Hillsborough Circulator 1 2.0 Transportation Jamael Wiley FY 2028 ages Services iwiley@orangecountync.gov Cumulative Estimated OrangeTransit Estimated Estimated Start Date Completion Notes Capital Cost September 20,2017 Ongoing Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. In June 2025, bus services in Hillsborough were enhanced to offer a second route.This reduced headways and added service to the Health Department. Previous improvements have included extending service hours to 8 a.m.to 5 p.m. M-F.Work to evaluate the effectiveness of these enhancements and future additional enhancements to provide more flexible service options and better accommodate the needs of passengers will continue.OCPTwill study opportunities in the second half of FY26 and seeks funding to enhance service in Hillsborough in FY27.This project represents the consolidation of three previously approved projects: Hillsborough Circulator, Hillsborough Expansion, and Hillsborough Circulator II.The service expansion isthrough FY27.This consolidation aimsto improve service coverage, reduce waiting times, and enhance overall efficiency for the Hillsborough area. Weekday frequency: 6:30 am—6:00 pm Bus Operations FY27 FY28 Estimated Hours 5000 5000 Cost Per Hour 103 105 41 45 REQUEST# FY2027 FYSTART DATE Orange Transit Work Plan Jul 2026 20OPTTS6 Request Form Total Project Cost Operating and/or Capital see pages 11-12 Orange Transit Estimated Project Name Requesting Agency Project Contact Operating Cost Orange County Base Year Mobility on Demand Transportation Jamael Wiley FY 2028 ages Services lwiley@orangecountync.gov Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost July1,2019 Ongoing Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. Demand for Mobility-on-Demand(MOD),OCPT's micro-transit service offering same-day reservations and utilizes ADA- accessible vehicles to serve both rural and urban areas, currently exceeds demand. Weekday frequency 9:00 am—5:00 pm. Bus Operations FY27 FY28 Estimated Hours 5000 5000 Cost Per Hour 105 107 42 46 REQUEST# FY 2026 FY START DATE Orange Transit Work Plan Jul 2027 190PTTS2 Request Form Total Project Cost Operating and/or Capital see pages 11-12 Project Name Requesting Agency Project Contact Orange Transit Estimated Operating Cost Base Year 1 512 Increase Cost of Existing Services(ICES) Orange County Transportaion Sarah Williamson FY 2027 ages Cumulative Estimated Start Date Estimated Completion Notes Orange Transit Estimated Capital Cost Jul-18 N/A Base Year Cumulative Project Description/Scope Enter below a summary of the project that may later be used as the project description in the FY 2026 Work Plan. The Increased Cost of Existing Services(ICES)program helps offset the rising costs associated with maintaining and operating existing transit services.By providing financial relief,ICES ensures that these services remain sustainable and accessible to the community,despite the challenges posed by increasing operational costs. Project Justification/Business Case Provide responses to EACH of the questions below.Answer the questions as fully as possible.Enter Not Applicable(N/A)as appropriate. Please detail project justification Project adopted in previous workprogram 1. Is this a New Project,Scope Change or Financial Change? New ❑ Scope ❑ Financial ❑ S,,instructions for definitions la.If Scope Change or Financial Change-Indicate previous project ID 2. Is this project Operating,Capital or Both? Operating o Capital ❑ Both ❑ 3. Is this a one-time request? Yes ❑ No ❑ 4. What is the timeframe for the request?Are you requesting a full year of funds in FY26 or a partial year to be annualized in future fiscal years? Full Year Funding S. Where is this project located,who will this project serve and how will it improve service or overall implementation of the Orange Transit Plan? m ❑ 6. Is this project programmed in the adopted Transit Plan FYs 2026-2032 Multi-Year Operating Program or CIP? Yes No 6a. If yes,how does this request relate to what was envisioned in the adopted Multi-Year Operating Program,CIP,or Orange Transit Plan?Specify which component(s)of the Multi-Year Operating Program,CIP,or Orange Transit Plan the request supports. Project adopted in previous workprogram 6b. If no,is this project in addition to projects and services included in the adopted Multi-Year Operating Program,CIP,or Orange Transit Plan or in lieu of projects and services included in those programs/plans? 43 47 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 24CHTTS13 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year 2 1.0 FTE: Chapel Hill Transit Caroline Dwyer FY 2028 es� Transit Planner I cdwyer@townofchapelhill.org Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost July1j 2025 Ongoing Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in the Description/Scope FY 2027 Work Plan. Staff member supporting the implementation of OCTP projects.This person will primarily focus on CHT's SRTP update project and day-to-day operating and service planning. 44 48 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 24CHTTS14 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost 1.0 FTE: Base Year Bus Stop Amenities Chapel Hill Transit Caroline Dwyer FY 2028 002!5- Technician cdwyer@townofchapelhill.org Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost July1,2025 Ongoing Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in the Description/Scope FY 2027 Work Plan. The Bus Stop Amenities Technician directly supports our maintenance team, enhancing CHT's ability to clean, maintain, and repair our 535+transit stops and amenities. Well-maintained stop amenities also extend the life of transit plan investments in bus stops, reducing future funding needs. 45 49 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 26CHTTSI6 Request Form Total Project Cost Operating and/or Capital see pages 11-12 Orange Transit Estimated Operating Project Name Requesting Agency Project Contact Cost 1.0 FTE Onboard Base Year Technology QA/ Chapel Hill Transit Caroline Dwyer FY 2028 ages QC Technician cdwyer@townofchapelhill.org Cumulative Estimated Estimated Start Date Completion Notes Orange Transit Estimated Capital Cost Base Year July:,2025 N/A Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. The Onboard Technology QA/QC Technician provides critical support to Chapel Hill Transit and enhances customer experience by ensuring proper maintenance and operations of real-time tracking equipment and software. 46 50 REQUEST# FY2027 FYSTART DATE Orange Transit Work Plan Jul 2026 22CHTTS01 Request Form Total Project Cost Operating and/or Capital I see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year Chapel Hill Transit Caroline Dwyer FY 2028 agesl Chapel Hill Transit Y Expansion cdwyer@townofchapelhill.org5 Cumulative FY13-21 Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost July1,2013 OngoingT_ Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. This project culminates in service improvements to Chapel Hill Transit operations using Orange Transit Tax funds from its inception in 2013.These funds provide additional hours of operation at times that were most demanded by the public: evenings and weekends.This project funds evening and weekend service on the following routes: A, CM, CW, D, F, HS,J, and NS.This project allowed Chapel Hill Transit to operate Sunday service for the first time. In addition,this project funds the expansion of the on-demand EZ Rider service. Weekday frequency: Bus Operations FY27 FY28 Estimated Hours 14,166 14,166 Cost Per Hour 132 135 47 51 REQUEST# FY2027 FYSTART DATE Orange Transit Work Plan Jul 2026 23CHTTSI Request Form Total Project Cost Operating and/or Capital I see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year CW Route- FY 2028 a0.es1 " Improve Mid-Day Chapel Hill Transit Caroline Dwyer s cdwyer@townofchapelhill.org Cumulative Service Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost July 1, 2026 OngoingT_ Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. This project improves the CW route, based on customer feedback. Weekday frequency 7:00 am—9:30 pm Weekend frequency 8:00 am—6:30 pm Bus Operations FY27 FY28 Estimated Hours 1500 1500 Cost Per Hour 140 144 48 52 REQUEST# FY2027 FYSTART DATE Orange Transit Work Plan Jul 2026 24CHTTSI Request Form Total Project Cost Operating and/or Capital I see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year 2 HS-Weekend Servicees Chapel Hill Transit Caroline Dwyer FY 2028 see pa� cdwyer@townofchapelhill.org Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost July1,2026 OngoingT_ Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. Improvements to the HS route add weekend transit services, provide connections to higher-density neighborhoods and multifamily housing, and improve transit access to key destinations along Martin Luther King Jr. Boulevard. The service improvement benefits lower-income communities and fulfills a stated public need for weekend service in transit reliant neighborhoods. Weekday frequency 5:30 am—6:30 pm Weekend frequency 8:00 am—6:30 pm Bus Operations FY27 FY28 Estimated Hours 1177 1177 Cost Per Hour 127 130 49 53 REQUEST# FY2027 FYSTART DATE Orange Transit Work Plan Jul 2026 19CHTTS2 Request Form Total Project Cost Operating and/or Capital I see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year Increased Cost of Caroline Dwyer FY 2028 ales ExistingServices Chapel Hill Transit ysee cdwyer@townofchapelhill.org Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost July1,2013 N/A Base Year Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. The original Orange County Bus and Rail Investment Plan based operating cost on$103 per hour.Since then, operating costs have risen to$140.Chapel Hill Transit utilizes funds from the Orange County Transit Plan to offset these costs. 50 54 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 26CHTTS14 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year Route D: UNC-Patterson Chapel Hill Transit cdw\/er@townofchapeIhiI1.org Dwyer FY FY 2028 Seepage5 1 Place Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost Base Year July1,2026 N/A Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope I the FY 2027 Work Plan. Extend D Route to Patterson Place and extend Saturday service until 9 PM. This project funds 5,300 hours of service in FY27 and each subsequent year. 51 55 REQUEST# FY2027 FYSTART DATE Orange Transit Work Plan Jul 2026 26CHTTSI3 Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year NS Route- Chapel Hill Transit Caroline Dwyer FY 2028 epagesti Eubanks-Southern cdwyer@townofchapelhill.org se Village Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost Base Year July1,2026 N/A Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. Increases NS Route morning peak frequency to every 6 minutes;extends Saturdayservice until 11 PM;and extends Sunday service until 9 PM. Funds 2,300 hours of service in FY27 and each subsequent year 52 FY27 CAPITAL PROJECTS 57 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 23GOTCD4 Request Form Total Project Cost Operating and/or Capital see pages 11-12 Orange Transit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year Triangle Mobility Hub GoTriangle Catherine Miller FY 2028 cmiller@gotriangle.org Cumulative Estimated Estimated Start Date Completion Notes Orange Transit Estimated Capital Cost FY20 FY29 Base Year es Cumulative see Project Enter below a summary of the project that may later be used as the project description Description/Scope in the FY 2027 Work Plan. Phase II of the new Regional Transit Center (RTC), known as the Triangle Mobility Hub, will continue in FY 2027. The scope of Phase II includes design (e.g., architectural &engineering services), right-of-way acquisition and permitting, construction (e.g., site development, corridor improvements, facility construction, and construction administration), and project management. The completed feasibility study for the relocation of the RTC included an evaluation of the current facility and identification of necessary passenger amenities and infrastructure improvements,and a feasibility study to evaluate the potential new locations for the RTC,taking into consideration current and future planned routes, land use,supply, and price.The current location of the RTC on Slater Road in Durham creates overlapping routes leading to inefficiency and is not proximate to 1-40, which causes delays and reduced reliability during peak commuting times.The feasibility study evaluated location optionsthat improve operating efficiency and reliability,connections to planned BRT and rail,as well as potential for transit-oriented development.The study concluded that the preferred location of the relocated RTC is the SW quadrant of the intersection of NC 54 and Miami Blvd.The feasibility study was funded by county transit plans in Wake, Durham, and Orange counties. The GoTriangle Regional Transit Center (RTC) is the primary hub for GoTriangle regional bus services connecting Wake, Durham, and Orange Counties.The project will improve operating efficiency and reliability, connections to planned BRT and future passenger rail, as well as potential for transit-oriented development. 54 58 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 23GOTVPI Request Form Total Project Cost Operating and/or Capital see pages 11-12 Orange Transit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year Bus Purchases GoTriangle Jay Heikes FY 2028 jheikes@�otrain�le.or� Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost e511, FY23 Ongoing Base Year e Cumulative Se Project Enter below a summary of the project that may later be used as the project description Description/Scope in the FY 2027 Work Plan. Orange Transit's share of the GoTriangle level buying bus strategy. FY27 update:Adjust vehicle purchases to match services funded by transit plans. GoTriangle will serve as the project sponsor as these new buses will replace existing buses that have reached its useful life.There has been an increase in maintenance cost due to maintaining high mileage vehicles and a reduction in reliability.Vehicle purchase requests correspond to the fleet replacement plan. 55 59 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 23GOTCD2 Request Form Total Project Cost Operating and/or Capital see pages 11-12 Orange Transit Estimated Project Name Requesting Agency Project Contact Operating Cost Regional Bus Base Year Operation and Maintenance GoTriangle Bryan Hammond FY 2028 Facility bhammond@gotriangle.org Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost FY20 FY29 Base Year 511' Cumulative see Project Enter below a summary of the project that may later be used as the project description Description/Scope in the FY 2027 Work Plan. The project sheet requests funding for phases of design and construction required to operate services identified in the Transit Plan. FY26 Update - revised cost estimate and cost curve in progress, estimates provided for submittal, to be updated when cost estimate update is completed. The fleet and facilities study evaluated constraints and needs for maintenance, storage,fueling and servicing capacity as well as work-flow efficiency at the GoTriangle Nelson Road bus operations and maintenance facility. The outcome of this study will include site selection, schematic design, and cost estimates for a new and/or expanded facility.The study included a regional coordination element to identify opportunities for shared facilities for vehicle storage, servicing and/or repairs.The study has identified onsite expansion and renovation of the current Nelson Road facility as the most cost effective option to address current needs and provide an opportunity to address future fleet needs over the course of the useful life of the renovated facility:40+years. The completed study will include phases and associated costs of handling the fleet required to operate the services identified in the Bus Plan. 56 60 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 26GOTCD15 Request Form Total Project Cost Operating and/or Capital see pages 11-12 Orange Transit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year Fordham Blvd.Transit GoTriangle Paul Black FY 2028 Access Improvements pblack@gotriangle.org Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost This project is also known as 400 Base Yeartit FY26 FY29 DIF Connections in Orange Transit Cumulative See9agec, Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. Crossing, stop, and shelter improvements near the intersection of Ephesus Church Road and US 15-501/ Fordham Blvd and at other locations along Fordham Blvd to support the Adopted Orange Transit Plan realignment of 400/405 service to Fordham Blvd. in FY29.GoTriangle proposes to combine this project with the Adopted OTP project in Fordham/US 15- 501 at Manning project(27GOTCDI6)to create a single project for bus stop,transit access, and transit speed and reliability improvements along Fordham Blvd between E. Franklin St and Manning Drive. 57 61 REQUEST# FY2027 FYSTART DATE Orange Transit Work Plan Jul 2026 260PTCP07 Request Form Total Project Cost Operating and/or Capital see pages 11-12 Orange Transit Project Name Requesting Agency Project Contact Estimated Operating Cost Base Year Orange County Sarah Williamson FY 2028 Transit Plan Update Transportation Services swilliamson- baker@orangecountync.gov Cumulative Estimated Orange Transit Estimated Estimated Start Date Completion Notes Capital Cost Base Year July1,2026 N/A see page"1 Cumulative Project Enter below a summary of the project that may later be used as the project description Description/Scope in the FY 2027 Work Plan. Capital Item every four years, to be scoped by a subcommittee that includes the ILA partners and at least two other voting members of SWG.All non-voting members will also be invited to the subcommittee.This is a request from County Commissioners and a placeholder to ensure funding. Further work to be led by the future OC Transportation Director. 58 62 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2026 270PTCD03 Request Form Total Project Cost Operating and/or Capital see pages 11-12 Orange Transit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year Operational Orange County Jamael Wiley FY 2028 Improvements Transportation jwiley@orangeccountync.gov Cumulative Services Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost July1,2025 July1,2028 Base Yearec, Cumulative See Project Enter below a summary of the project that may later be used as the project description in the Description/Scope FY 2027 Work Plan. For annual operational improvements to support transit plan work.In FY27,this will include upgrades to the bus lot to accommodate additional vehicles,support an onboard survey,and provide the local match for stop improvements such as benches, as well as branding and QR codes linking to timetables at all stops. 59 63 Project ID FY 2026 FY START DATE Orange Transit Work Plan Jul 2025 Project Amendment RequestForm Operating and/or Capital Type of Amendment Minor ❑ Major ❑ Minor Amendments: a.An amendment that requires a transfer between budget ordinance appropriations but requires less than a 20%change to a project appropriation for projects equal to or less than$250,000; b.Changes to any adopted financial assumptions supporting the applicable Work Program that does not have a significant Impact on the overall revenue or expenditure forecast, which is defined to be no more than a one percent(1%)over the life of the plan; c.Changes in reporting requirements for performance on implementation elements authorized in the applicable Work Program; d.Changes in funding amounts less than$250,000 for implementation elements programmed in future fiscal years; e.Any other change that does not meet any of the criteria of a Minor Amendment is a Major Amendment. Major Amendments are required when: a.A project requested to be added to the Work Plan b.A project requested to be removed from the Work Plan c.Changes to any adopted financial assumptions supporting the applicable Work Program that does have a significant impact on the overall revenue or expenditure forecast, which is defined to be over one percent(1%)over the life of the plan; d.Changes in scope for implementation elements programmed in current and future fiscal years; e.Any amendment that requires a transfer of funds between capital or operating funding categories I.Any change that requires a change in budgeted reserves or fund balance. These definitions are based on the Orange County Transit Work Plan Amendment Policy Update,which gives more clarity to the definitions without changing their meaning. New/Amended Project Name Requesting Agency Project Contact Orange Transit Estimated Operating Cost Base Year(FY 2026) $ FY 2027 $ Cumulative FY28-FY32 $ Orange Transit Esti mated Capital Cost Staffing Study TW on behalf of OC Base Year(FY 2026) $ 200,758 Doug Plachcinski Cumulative FY27-FY32 $ Project Description/Scope Enter below a summary of the project amendment and impact on approved plan. The Staffing Analysis will consist of three parts:(1)an analysis of existing positions funded(wholly or partially)with Orange Transit funds among a 11 agencies,(2)an analysis of future staffing needs,and(31 a recommendation for Performance Metrics that can be used to evaluate new staff ng requests and ongoing staffing levels.The analysis is expected to take 6-8 1.Enter Orange Transit Project ID(s)to Increase Appropriation Amount Recurring Notes Project ID Project Category Amount TOTAL $ $ 2.Orange Transit Project ID(s)to Reduce Project ID Project Appropriation Amount Recurring Notes Category Amount TOTAL $ - $ - 3.Impact on Transit Plan Project Costs From above,indicate whether amounts impact operating or capital budgets in Orange Estimated Operating Cost Current year $ - TransitPlan. Recurring $ Estimated Capital Cost Base Year $ 200,758 cumulative $ 4. Is this project Operating,Capital or Both? Operating ❑ Capital ❑ Both S. What is the timeframe for the request?Are you requesting a full year of funds or a partial year to be annualized in future fiscal years? FY-Authorization to begin'March and last a months. 6.What Is the expected outcome(s)if this request is funded?What is the alternative if the request is not funded? 1.List any other relevant information not addressed. $183,570 proposed consultant fee,$17,188 proposed TW project management time reimbursement. 8.Please enter estimated appropriations to support expenses.Enter FY 2026 and the estimated annualized cost in FY 2027 using the 2.5%growth factor,if applicable.The spreadsheet will calculate 2028 and beyond by 2.5%.If your project is not expected to have recurring costs in FY 2027 and/or beyond,delete the calculation(s)in columns EI. Cost Break Dow,of Project Request OPERATING COSTS FY26 FY27 FY28 FY29 FY iFY31 FV32 Growth Factors 2.50% 2.50% 2.50% 2.50% 2.50% Salary&Fringes Contracts Bus Oerations: Estimated Hours Caster Hour ma Estited Operating Cost Bus Leases Park&Ride Lease Other Other Subtotal:Bus Operations Operatin Fare Collection Operating Youth GOPass TOTAL OPERATING COSTS 9.Please enter estimated appropriations to support contractual commitments and other expenses related to proposed capital projects. CAPITAL COSTS FY26 FY27 FY28 FY29 FY30 FY31 FY32 Planning Design Construction Equipment Land-Right of Way Other TOTAL CAPITAL COSTS $ 200,758 Assumptlonsfor Costs and Revenues Above: 10.Please state any assumption(s)used to calculate the capital and operating dollars and revenues shown above.(include details) 64 30 Hours for Executive Director,30 hours for Planning Manager,86 hours to planners 65 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jan 2027 30CHTVP15 Request Form Total Project Cost Operating and/or Capital see pages 11-12 Orange Transit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year Bus Purchases Caroline Dwyer Town of Chapel Hill y FY 2028 Expansion-Renewals cdwyer@townofchapelhill.org Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost January 1,2027 June 1,2027 Base Year esti Cumulative e Project Enter below a summary of the project that may later be used as the project description in the Description/Scope FY 2027 Work Plan. Vehicle acquisitions,repowers,and replacements for services funded by Orange County Transit Tax revenues. 61 66 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jul 2025 26TOCCDI Request Form Total Project Cost Operating and/or Capital see pages 11-12 OrangeTransit Estimated Project Name Requesting Agency Project Contact Operating Cost Base Year 203 Connector Sidewalk Town of Carrboro Tina Moon FY 2028 cmoon@carrboronc.gov Cumulative Estimated Orange Transit Estimated Capital Estimated Start Date Completion Notes Cost Base Year es Ju 1,2025 December 1,2026 N See Cumulative Project Enter below a summary of the project that may later be used as the project description in Description/Scope the FY 2027 Work Plan. Design and construct a 6-foot wide meandering sidewalk to connect the new Drakeford Library Complex (203 South Green/Roberson St)to East Main St,and construct a new bus shelter pad at East Main as part of the installation of new enhanced bus shelters for Chapel Hill Transit and GoTriangle (405 to Durham). 62 67 REQUEST# FY2027 FY START DATE Orange Transit Work Plan Jun 2026 26TOCCD2 Request Form Total Project Cost Operating and/or Capital Orange Transit Estimated Operating Project Name Requesting Agency Project Contact Cost Base Year West Main Street Sidewalk Town of Carrboro Tina Moon FY 2028 cmoon@carrboronc.gov Cumulative Estimated Estimated Start Date Completion Notes Orange Transit Estimated Capital Cost Base Year Cktoberl,2025 December 1,2028 e511, Cumulative See Project Enter below a summary of the project that may later be used as the project description Description/Scope in the FY 2027 Work Plan. Design and construct 10-footwide sidewalkon the south side of West Main St from Fidelity Stto West PoplarAve. 63 E Ilkr � �' � r v , ' ` 69 Recommended FY 2027 Transit Work Ptan Proposed FY27 Investment $ 15 . 53 Million $9 . 49M $6 . 04M Operating Capital 1 Where Your Investments Are Going Bus Operations & Service Expansion: 53% Bus Stops & Transit Centers: 33% Transit Plan Administration: 7% Bus & Vehicle Purchases: 3% Tax District Administration: 2% Transit Plan Development: 2% 71 Operating $9,,49M Agency FY27 Funding Requests Chapel Hill $4,090,487 GoTriangle $3,365,272 - g - Orange County $1 ,615,868 � � Tax District Administration $374,841 -� Triangle West TPO $42,867 �,, Total $9,489,335 72 Agency FY27 Funding Requests Carrboro $244,829 for West Main St and 203 Connector Sidewalks Chapel Hill $122, 132 for Bus Purchases GoTriangle $5, 174,000 for Regional Bus Operations & Maintenance Facility ($2. 1 M), Mobility Hub ($210K), Fordham Blvd Access Improvements ($2.5M), and Bus Purchases ($364K) Orange County $300,000 for Multi-Agency Transit Plan Development Triangle West $200,758 for a Transit Plan Staffing Study Total $690419719 73 Tax District Financial Model Ending Balances and Reserves $30,000,000 $25,000,000 $20,000,000 $15,000,000 $10,000,000 $5,000,000 $0 FY25 FY26 FY27 FY28 FY29 FY30A tota I financialpolicy � • • ■Total Reserves ■ Ending Balance ��, O million _ • _ • New Since FY 2026 AWP Approval FY27 AWP • 2.5% growth for operating • Multi-Agency Transit Plan Development • Staffing Study across Transit Tax District Annual Work Program Process E Ilkr � �' � r v , ' ` 77 I 7L I '14 78 .. ....... ....... 79 , o I 9 80 81 1E EE 12 ii- IE a E 12 E E a a E i a ... ....... HIM NO isli ME HIM OR Ml OWN Zl' �.'A .�ril —'M dill All HNIN ilk! kill MIN ."No "Ifil AM "ll Al d1m As so .0 011 .2111