Agenda 06-16-2026; 6-c - Approval of the Guaranteed Maximum Price for the Construction of the Crisis Diversion Facility, and Approval of Budget Amendment #12-A
1 ORD-2026-015 ORANGE COUNTY BOARD OF COMMISSIONERS ACTION AGENDA ITEM ABSTRACT Meeting Date: June 16, 2026 Action Agenda Item No. 6-c SUBJECT: Approval of the Guaranteed Maximum Price for the Construction of the Crisis Diversion Facility, and Approval of Budget Amendment #12-A DEPARTMENT: Asset Management Services ATTACHMENT(S): INFORMATION CONTACT: 1. Gilbane Contract Amendment Alan Dorman, AMS Director, 919-245- 2. Gilbane GMP Cost Summary 2627 3. Year-to-Date Budget Summary 4. Presentation PURPOSE: To: 1.) Review and approve the final design of the Crisis Diversion Facility; 2.) Review and approve the Guaranteed Maximum Price for the Construction of the Crisis Diversion Facility as submitted by Gilbane; 3.) Review and approve an amendment to the existing Gilbane Contract for Construction Manager-at-Risk services to incorporate the Guaranteed Maximum Price as well as other changes; 4.) Approve Budget Amendment #12-A; and 5.) Authorize the County Manager to execute the Gilbane contract amendment, subject to final review by the County Attorney, and any subsequent amendments for contingent and unforeseen requirements up to the approved budget amount on behalf of the Board of County Commissioners. BACKGROUND: The County has been developing a plan to build a Crisis Diversion Facility since 2019. These plans culminated in the selection of the architecture firm CPL to design the facility in 2024 and the selection of Gilbane Construction Company to provide Construction Management at Risk Services in 2025. Initial design and cost estimates showed that the final project would exceed the original budget. of $26,053,350. In October 2025, the Board reviewed a series of design options to reduce the overall project budget. The Board approved Option C, a design with an estimated construction cost of$27,180,542. The total estimated project cost, including land aquistion, design, and other construction costs, based on Option C, was $30,749,007. This would have required an additional $4,695,657 in funding. In April 2026, Gilbane completed the formal bid process for the project and proposed a Guaranteed Maximum Price ("GMP") of $22,906,906. Including project costs already spent or encumbered for professional services and land acquisition, the new project budget will be $29,412,035. To address the increased cost, the the Board will need to approve $3,358,685 in 2 additional funding. While the intention had been to provide the Board with a series of additional construction options, including more daylighting and solar installation, due to the tremendous cost savings achieved through the bidding process, these elements have already been incorporated into the GMP. Crisis Diversion Facility- Final Project Budget-June 6th GMP (Construction and Indirect Costs) $22,906,906 Land $1,353,266 Design/Other Services $2,142,227 Furniture $525,983 Environmental Impact and Related Fees $132,785 Special Inspections $75,000 Commissioning $100,868 Owner's Contingency $1,850,000 Offsite lighting $100,000 AN $25,000 Low Voltage $75,000 Security $125,000 Total: $29,412,035 The current project schedule, as shown below, projects construction starting in August and occupancy expected in the spring of 2028. Project Schedule Schedule for the Construction of the Crisis Diversion Facility Board Approval of GMP June 2026 Start of Construction August 2026 Construction Completed Winter 2028 Occupancy Spring 2028 FINANCIAL IMPACT: Budget Amendment #12-A allocates $3,358,685 in additional funding to cover the increased cost for the construction of the facility over the original project funded in the FY 2025-35 Capital Investment Plan. Staff also worked with Alliance and confirmed that $1,100,000 of the Cardinal Reserve could be dedicated towards the Crisis Diversion Facility. These two (2) changes are reflected in the amended project ordinance: Crisis Diversion Facility($3,358,685) - Project# 10080 Revenues for this project: Current FY 2025-26 FY 2025-26 FY 2025-26 Amendment Revised Cardinal Reserve $1,823,121 ($723,121) $1,100,000 From General Fund $250,000 $0 $250,000 Alternative Financing $23,980,229 $4,081,806 $28,062,035 Total Project Funding $26,053,350 $3,358,685 $29,412,035 3 Appropriated for this project: Current FY 2025-26 FY 2025-26 FY 2025-26 Amendment Revised Project Expenditures $26,053,350 $3,358,685 $29,412,035 Total Costs $26,053,350 $3,358,685 $29,412,035 As previously noted, this increase was lower than the amount initially anticipated in the debt model after the approval of Option C. This will result in decreasing the anticipated tax increase in FY 2028 to fund debt service by 0.18 cents. ALIGNMENT WITH STRATEGIC PLAN: This item supports: • GOAL 2: HEALTHY COMMUNITY OBJECTIVE 1. Improve harm reduction, prevention, and support services for adults and children experiencing behavioral health issues, substance use disorder, and intellectual or developmental disability. OBJECTIVE 4. Reduce impacts and barriers for justice-involved children and adults through deflection, diversion, therapeutic interventions, and re-entry support, including housing. RECOMMENDATION(S): The Manager recommends that the Board: 1.) Approve the final design of the Crisis Diversion Facility; 2.) Approve the Guaranteed Maximum Price for the Construction of the Crisis Diversion Facility as submitted by Gilbane; 3.) Approve an amendment to the existing Gilbane Contract for Construction Manager-at-Risk services to incorporate the Guaranteed Maximum Price as well as other changes; 4.) Approve Budget Amendment #12-A which increases the authority in the County Capital Fund by $3,358,685; and 5.) Authorize the County Manager to execute the Gilbane contract amendment, subject to final review by the County Attorney, and any subsequent amendments for contingent and unforeseen requirements up to the approved budget amount on behalf of the Board of County Commissioners. 4 Attachment 1 NORTH CAROLINA CONTRACT AMENDMENT ORANGE COUNTY THIS CONTRACT AMENDMENT ("Amendment") is made and entered into this_day of 120 by and between ORANGE COUNTY(hereinafter referred to as "County") and Gilbane Building Company(hereinafter the "Construction Manager at Risk"or"CM"or"CMAR"). WITNESSETH: THAT WHEREAS, the County and CMAR entered into a contract dated April 22, 2025 (hereinafter the "Original Agreement"), for the procurement of hardware and provision of services and WHEREAS, the County and CMAR desire to amend the Original Agreement while keeping in effect all terms and conditions of the Original Agreement not inconsistent with the terms and conditions set forth below. NOW THEREFORE, for and in consideration of the mutual covenants and agreements made herein, the parties agree to amend the Original Agreement as follows: 1. Section 2.6. The "Total Construction Budget" is first described in the RFQ Data Sheet, and consists of the Cost of the Work, as more fully defined in section 4 below, the CMAR-GMP Contingency, as more fully defined in section 5 below, the Early Completion Bonus Fund, if offered and made part of this Contract, as more fully defined in section 24 below, the CMAR General Conditions, as more fully defined in section 3 below. Upon approval by the Owner of the Total Construction Budget as presented on June 16th, 2026, the Total Construction Budget will not be allowed to exceed the agreed upon Total Construction Budget ("TCB"). The Owner reserves the right to adjust the Total Construction Budget at any time prior to agreement on the final GMP. 2. Section 3.2. Provided that the Total Construction Budget remains $22,906,906, the CMAR Fee shall not exceed $850,820, subject to modification and limitation as set forth herein. If the Owner changes the Total Construction Budget, the CMAR Fee shall not exceed three percent (3.75%) of the sum of(i) the Cost of the Work, (ii) the CMAR-GMP Contingency, and (iii) the CMAR General Conditions, (but not including the Early Completion Bonus Fund) all as more fully defined in this Contract, as of the date when the final GMP is established and approved by the Owner, subject to modification and limitation as set forth herein. The CMAR Fee will include all CMAR home office personnel costs, including officers as well as home office and local office support staff not included in General Conditions below, together with all other CMAR overhead costs and profit. This Fee shall also include all home office quality control and safety reviews, as well as all required services of a home office Project executive, by whatever name called. CMAR costs which are not to be included in the CMAR Fee are the costs of all Subcontracts, on-site field staff, General Conditions costs (as provided below), and the CMAR-GMP Contingency described below. 3. Section 3.4. In addition to the foregoing Fee, an allowance for the General Conditions on a "not-to-exceed" basis will be submitted by the CMAR with each GMP for the Owner's approval.No costs associated with the CMAR's main office or its main office or other off-site personnel, including the costs associated with the use of items or equipment of the main office, are covered under the General Conditions allowance. All such costs are deemed to have been included in the CMAR Fee. Subject to approval by the Owner's Representative, each GMP may include special designated allowances for defined expenses. Each GMP shall contain an allowance for General Conditions fixed as an estimated lump sum for each GMP. The entire General Conditions allowance shall be fixed based on the Total Construction Budget at the time of the final GMP, after which the General Conditions shall not be adjusted unless an amount is negotiated with Owner-requested Change Orders to the Work of the Project. The sum of the entire General Conditions at the time the final GMP is 5 fixed, including all allowances for General Conditions for each GMP for a defined phase of Work, shall not exceed $1,214,194, subject to approval by the Owner and modification and limitation as further set forth herein. Owner reserves the right to inspect and/or audit all General Conditions services cost documentation. 4. Section 4.4. At no time shall the CMAR Fee, General Conditions, CMAR-GMP Contingency, or the Early Completion Bonus Fund exceed the amounts for these respective items within the Total Construction Budget. The sum of all GMP must not exceed the Total Construction Budget, including CMAR Fees, overhead, and escalation as set forth on the RFQ Data Sheet, unless and to the extent that the Total Construction Budget is increased or decreased by the Board. 5. Section 5.6.Unless otherwise agreed by the Owner, and provided that the Total Construction Budget remains TCB, the total CMAR-GMP Contingency for the Project shall not exceed$752,099. If the Owner changes the Total Construction Budget, the CMAR-GMP Contingency shall not exceed four percent (4.0%), as a value line item of the sum of the Cost of the Work and the CMAR General Conditions, all as more fully defined in this Contract, as of the date when the final GMP is established and approved by the Owner, subject to modification and limitation as set forth herein. When each GMP is fixed, the CMAR-GMP Contingency for that GMP shall be converted to a lump sum. The entire CMAR Contingency shall be fixed in the final GMP, based on the Total Construction Budget at the time of the final GMP, after which the CMAR Contingency shall not be adjusted unless an amount is negotiated with Owner requested Change Orders to the Work of the Project. 6. Section 7.3. Owner will bear the reasonable cost of reproduction and distribution of drawings, sketches, specifications and other Construction Documents for use on the project development and by the CMAR and its Subcontractors for bidding and administrative purposes, up to an allowance of$5,000. The CMAR shall receive clean sets of black line prints on white paper of all drawings provided by the Owner, the CMAR shall clearly and legibly record in redline all work-in-place that is at variance with the Contract Documents. 7. Section 24.1.Paragraphs 24.1.1 through 24.1.19 are stricken. a. 24.1.20. Board approval of GMP#5 June 16th, 2026 24.1.21. Substantial Completion November 30th,2027 24.1.22. Punch List Completion December 31St, 2027 24.1.23 Project Final Completion January 30th,2027 24.1.24. Completion of Closeout and Warranty November 30th,2028 8. Section 47.1.1 - Commercial General Liability: The CMAR shall ensure that it shall provide commercial general liability insurance with a limit of not less than $3,000,000 per occurrence and $6,000,000 aggregate. All Subcontractors shall provide commercial general liability insurance with a limit of not less than $1,000,000 per occurrence and $2,000,000 aggregate. Coverage must be in a form providing coverage not less than the standard Insurance Services Office Form CG 00 01 and include products and completed operations,property damage,bodily injury,and personal&advertising injury. The products-completed operations coverage shall be provided for a minimum of six (6)years following final acceptance of the work. The liability limits required under this Agreement for the primary Commercial General Liability insurance, Business Automobile Liability insurance and Umbrella/Excess Liability insurance may be satisfied through any combination of limits contained on either the primary or excess liability or combined policies of insurance. 9. Section 47.1.2 - Commercial Automobile Liability: The CMAR shall ensure that it and all Subcontractors shall provide commercial automobile liability insurance of not less than $1,000,000 per occurrence for any vehicle. 6 10. Section 47.1.4-Professional Liability: The CMAR shall ensure that it and all professional service providers under this contract provide professional liability insurance with a limited of not less than $5,000,000 per occurrence or claim, and $5,000,000 aggregate. All professional service providers in contract with CMAR will follow tier system requirement within CMAR Trade Contract where minimum professional liability required limits are $2,000,000 per occurrence or claim and $2,000,000 per aggregate. There shall be an extended reporting period of not less than six(6)years. 11. Section 47.1.5 - Builders Risk: Builder's Risk: The CMAR shall purchase and maintain property insurance during the life of this Contract,upon the entire Work at the site in amount equal to the completed value of the project with no coinsurance penalty provisions utilizing an "All Risk" (Special Perils) coverage form. This insurance shall include the Owner and CMAR as Named Insured, the Subcontractors and sub-subcontractors as Additional Insureds, in the Work. If the Owner is damaged by failure of the CMAR to purchase or maintain such insurance, then the CMAR shall bear all reasonable costs properly attributable thereto; the CMAR shall effect and maintain similar property insurance on portions of the Work stored off the site when request for payment per articles so includes such portions.The builders risk insurance shall provide coverage, insurance against perils of fire (with extended coverage) and physical loss or damage including, without duplication of coverage, for direct physical loss or damage, and shall not exclude the risks of fire, explosion, theft,vandalism,malicious mischief, collapse, earth movement, subsidence, earthquake, flood,named and un- named windstorm, wind-driven rain, release of water steam or fluid, falsework, hot and cold testing and startup, resulting loss from faulty workmanship and/or faulty design, equipment breakdown, . The insurance shall also provide coverage for ensuing loss or resulting damage from error, omission, or deficiency in construction methods, design, specifications, workmanship, or materials. The property insurance shall also include coverage for expediting expenses, soft costs, foundations, underground pipes, site preparation, and excavation. This property insurance shall cover portions of the Work stored off the site, and also portions of the Work in transit. If the property insurance requires deductibles, the Contractor shall be responsible as a Cost of the Work for costs not covered due to such deductibles, except that Owner shall be solely responsible for any and all costs not covered due to deductibles arising out of any loss due to flood(including inundation, seepage and sewer back-up), earthquake, named and un-named windstorm, hail, volcanic eruption or terrorism. 12. Section 47.1.6 - Pollution Legal Liability: The CMAR shall ensure that it and Subcontractors whose scope of work includes providing pollution services shall provide Pollution legal liability insurance in an amount not less than$5,000,000 per occurrence or claim and$5,000,000 aggregate. 13. Section 47.1.8 - Public Liability and Property Damage: The CMAR shall ensure that it and all Subcontractors provide and maintain, during the life of the Contract, comprehensive general liability insurance, including coverage for premises operations, completed operations, products and contractual exposures. Such insurance shall protect the CMAR and the Subcontractors from claims arising out of any bodily injury, including accidental death, and claims for property damages which may arise from operations under this Contract, whether such operations are by the CMAR or by any Subcontractor, or by anyone directly or indirectly employed by either of them. The minimum limits of such insurance shall be $1,000,000 for each occurrence and $2,000,000 aggregate, or such lower limits as may be agreed to by the Owner on a case-by- case basis. Such coverage for completed operations must be maintained for at least two (2) years following final acceptance of the Work performed under the Contract. 14. The attached "Orange County Crisis Diversion Center GMP Deliverable Rev 0 Dated June 3rd, 2026" is attached as Exhibit A to this amendment. 7 15. Signatures. This Agreement, together with any amendments or modifications, may be executed electronically. All electronic signatures affixed hereto evidence the intent of the Parties to comply with Article I IA and Article 40 of North Carolina General Statute Chapter 66. 16. Except for the changes made herein,the Original Agreement shall remain in full force and effect to the extent it is not inconsistent with this Amendment. In the event there is a conflict between the terms of the Original Agreement and the terms of this Amendment,this Amendment shall control. [SIGNATURES ON FOLLOWING PAGE] IN TESTIMONY WHEREOF, this Amendment has been executed by the parties hereto, as of the date first above written. ORANGE COUNTY CMAR Chair Orange County Board of Commissioners 8 ORANGE COUNTY-DEPARTMENT USE ONLY Party/Vendor Name: Party/Vendor Contact Person: Contact Phone: Party/Vendor Address: City State: Zip: Department: Amount: Purpose: Budget Code(s): Vendor# (N/A if new vendor) Vendor is a BOCC consultant? Yes ❑ No❑ Contract Type: (Check one) New ❑ Renewal ❑ Amendment ❑ Effective Date Approved by Board Yes❑ No❑ Agenda Date: --- For Section XIV. c. contracts only, Approved by Board in Current FY Budget Yes❑No❑ This agreement is approved as to technical form and content and I as Department Director affirmatively state work on this project has not been initiated prior to execution of the agreement: Department Director's Signature Date: Agreements for emergency services or repair are not subject to the above affirmation. If services related to this agreement have already begun or been completed please briefly describe the nature of the emergency condition that was addressed: Information Technologies (Applicable only to hardware/software purchases or related services)This agreement has been reviewed and is approved as to information technology content and specifications: Office of the Chief Information Officer Date: Risk Management This agreement is approved for sufficiency of insurance standards, specifications, and requirements: Office of the Risk Management Officer Date: Financial Services This instrument has been pre-audited in the manner required by the Local Government Budget and Fiscal Control Act: Office of the Chief Financial Officer Date: Legal Services This agreement is approved as to legal form and sufficiency: Office of the County Attorney Date: Clerk to the Board Received for record retention: All Docusign contracts must be copied to the Clerk upon completion: occlerkdocs@orangecountync.gov The following signature block is for hard copies only and is not required for Docusign contracts: Office of the Clerk to the Board Date: 9 Gilbane Building Company Orange County Crisis Diversion Center GMP Deliverable Rev 0 ORANGE COUNTY Published 6/3/2026 NORTH CAROLINA i ` wcM1 7r)� N I 1 ^� 1� A v.5/1/2023 10 Gilbane Building Company June Yd- 2026 Jeff Lewis Gilbane Building Company 150 Fayetteville St. Raleigh NC 276 01 RE: Alan Dorman Orange County 300 W.Tryon St., Hillsborough, NC 27278 Project Number:J10801.000 Dear Alan: Thank you for the opportunity to collaborate with you in the development of the project. Please find attached the Guaranteed Maximum Price in accordance with the Agreement. We look forward to building on this relationship as we construct your project. If you have any questions, please do not hesitate to contact us at any time. Sincerely, Gilbane Building Company Jeff Lewis Raleigh Business Leader v.5/1/2023 11 ane Building Company Table of Contents 1 . GMP Cost Summary a. Cost Summary b. Owner Allowance Log 2. Assumptions and Clarifications a. Pre-Bid RFI Log b. Trade Contractor Insurance Requirements 3. Schedule 4. Document Logs S. Site Logistics 6. Bid Tabs and Leveling v.5/1/2023 12 ORANGECOUNTY Orange County Crisis Diversion Center Hillsborough,NC ca= Guaranteed Maximum Price May 21,2026 RO GMP Summary by Bid Package Orange County Crisis Diversion Center Description [100%CD-GMP] Comments Base Budget SORT BY-Bid Package 21,146 $per SF 01A Site Services $ 675,562 $ 31.95 01B Final Cleaning $ 19,280 $ 0.91 03A Cast-In-Place Concrete $ 499,000 $ 23.60 04A Masonry $ 459,000 $ 21.71 05A Structural Steel $ 782,645 $ 37.01 06A Millwork&Casework $ 329,300 $ 15.57 07A Roofing $ 484,845 $ 22.93 07B Caulking&Sealants $ 209,738 $ 9.92 07D Fiber Cement Panels $ 422,000 $ 19.96 08A Doors/Frames/Hardware $ 361,122 $ 17.08 08B Glass&Glazing $ 873,820 $ 41.32 09A Framing&Drywall $ 904,824 $ 42.79 09B Tiling $ 63,022 $ 2.98 09C Ceilings $ 227,317 $ 10.75 09D Painting $ 68,815 $ 3.25 09E Flooring $ 164,595 $ 7.78 10A Specialties $ 189,990 $ 8.98 10B Signage $ 40,349 $ 1.91 11A Equipment $ 54,233 $ 2.56 12A Window Treatments $ 42,422 $ 2.01 21A Fire Protection $ 185,500 $ 8.77 22A Plumbing $ 1,189,000 $ 56.23 23A HVAC $ 1,528,000 $ 72.26 25A Controls&Fire Alarm $ - Included in 23A&26A 26A Electrical $ 2,955,895 $ 139.79 31A Sitework $ 5,346,675 $ 252.85 32A Landscaping $ 525,516 $ 24.85 32B Fences&Gates $ 200,000 $ 9.46 Subtotal Direct Costs $ :0 Indirect Costs Amount Design and Estimating Contingency 4.00% $ - Not Included Subtotal $ 18,802,465 Escalation 2.00% $ - Not Included Projected Cost of Work $ 18,802,465 Subcontractor Default Insurance 1.30% $ 244,432 Insurances 1.25% $ 286,336 Builders Risk 0.20% $ 45,814 Payment&Performance Bond 0.60% $ 137,441 Subtotal Insurances $ 19,516,489 CM Contingency 4.00% $ 752,099 Building Permits-Allowance $ 150,000 CM General Conditions Lump Sum $ 1,214,194 PreConstruction Services Lump Sum $ 204,928 Includes Preconstruction Agreement of$179,928 Subtotal $ 21,837,709 CM Fee 3.75% $ 850,820 Early Completion Bonus 1.00% $ 218,377 Total Guaranteed Maximum Price(GMP) $ 22,906,9061,083.27 13 ORANGE COUNTY Orange County Crisis Diversion Center , _ a Hillsborough,NC Owner Budget May 21,2026 RO Total Guaranteed Maximum Price(GMP) $ 22,906,906 The"Owner Budget"line items below are owner request budgets to illustrate overall project cost/budget. These line items are not included within the Guaranteed Maximum Price. Costs to manage these owner budgets are not included in the Guaranteed Maximum Price. Owner Budget-Not Included in GMP Amount FFE-Owner Budget $ 525,983 DHSR Review Fees-Owner Budget $ 3,447 Site Impact Fees-Owner Budget Allowance $ 100,000 Stream&Wetland Mitigation Fees-Owner Budget $ 7,672 Nutrient Buydown $ 21,666 Commissioning $ 100,868 Owners Contingency $ 1,850,000 Offisite Lighting Allowance $ 100,000 Low Voltage-Audiovisual Allowance $ 25,000 Low Voltage-Tele/Data Allowance $ 75,000 Low Voltage-Security Cameras&Access Control Allowance $ 125,000 Construction Materials Testing&Special Inspections $ 75,000 Total Owner Budget $ 3,009,636 14 Owner Allowances Orange County Crisis Diversion Center Hillsborough,NC The following Owner Allowances are included within the GMP. Any cost overruns or savings shall be reconciled via Owner Change Order to the Guaranteed Maximum Price. eBp# BP Description Type Value - 1 Permitting OOA Gilbane Owner $ 150,000.00 2 Dewatering 03A CIP Concrete Owner $ 20,000.00 3 Art Panel Coordination&Specification Clarification 07D Fiber-Cement Panel Owner $ 50,000.00 4 Sign Specifications 10B Signage Owner $ 20,000.00 5 Appliance Specifications 11A Appliances Owner $ 20,000.00 6 lPermitting Coordination&Sprinkler Head Relocations 21A Fire Protection Owner $ 10,000.00 7 Temp Cooling&Heating for 6 Months-Warranty Extension 23A Mechanical Owner $ 250,000.00 8 EV Charging Stations 26A Electrical Owner $ 30,000.00 9 2-Way Communication Allowance per Spec 26A Electrical Owner $ 75,000.00 10 Survey for 2-Way Communication Allowance Per Spec 26A Electrical Owner $ 2,500.00 11 Sanitary Sewer Material Change 31A Sitework Owner $ 15,000.00 12 Storm Filter Changes and Final Site Changes 31A Sitework Owner $ 900,000.00 13 Sitwork Allowances-Rock and Additional Excavation Per Spec 31A Sitework Owner $ 192,300.00 14 Asphalt Binder Index Allowance 31A Sitework Owner $ 75,000.00 15 Additional Watering Beyond Substantial Completion 32A Landscaping Owner $ 15,000.00 16 ISite Furnishings IL2A ILandscaping I Owner 1 $ 50,000.00 Total 1 $ 1,874,800.00 15 Clarifications CLARIFICATIONS & ASSUMPTIONS GMP CLARIFICATIONS GENERAL > This GMP is based on CPL's Orange County Crisis Diversion Center Construction Documents Drawings dated 03/25/2026, and Timmon's Orange County Crisis Diversion Facility Site Construction Drawings 100% Pricing Set dated 03/25/26. o The GMP also includes Addendum 01 from CPL dated 4/20/2026 > Costs for the following items are not included within the construction cost GMP. These items are assumed to be under the Owner's Budget or not required: • Land Acquisition • Professional Service Fees and Reimbursables (Architect, Engineering, Consulting) • Geotechnical Surveys and Testing • Independent Material testing during construction • Building Envelope Consultant • Environmental Costs—Treatment, Removal, etc. of Contaminated Soils, Environmental Remediation, Asbestos, etc. • Utility Consumption (Power, Gas, Telephone, Data...) after Substantial Completion • Utility Infrastructure and Connection Fees (power, gas, telephone, data... • Traffic Study • LEED Accreditation • Third Party Commissioning > Cost for the following items are included in the Owner's Budget and reflected in this latest Gilbane GMP for total project budget reference. Please note the items listed below are not part of Gilbane's cost and are assumed to be by Owner. Cost for these items was provided by CPL, Timmons, or Orange County: • FFE— Furniture, Fixtures, and Equipment • Site Impact Fees • DHSR Review Fees • Stream and Wetland Mitigation Fees • Commissioning • Owner's Contingency > The GMP includes Owner Allowances as identified in the Owner Allowance Log. Any cost overruns or savings within these allowances shall be reconciled via Owner Change Order to the Guaranteed Maximum Price. The Construction Manager shall notify the Owner of Allowance use in writing and reflect Owner Allowances balance in each Monthly Report. > The Construction Manager shall notify the Owner of Construction Contingency use in writing and reflect Construction Contingency balance in each Monthly Report. > Building Permit and plan review fees with the AHJ are included as an Owner Allowance. > This is not a "line-item" GMP. It is understood that, although Gilbane will guarantee the overall cost of the final GMP, we do not guarantee the costs for any individual line items within the GMP Cost Summary. Gilbane may offset any Orange County Crisis Diversion 100%Design Development ! 16 Clarifications cost savings from any individual line item against possible overruns of any other line items. All items except Owner Allowances will reconcile to Construction Contingency. > Sales Tax is included. > Prevailing wages are excluded. > Escalation is excluded. > This GMP does not include costs for any third-party monitoring or adjacent properties and existing facilities and improvements. Any third-party testing or monitoring are assumed to be provided by Owner. > The Construction Schedule is based on current lead times on equipment/materials. If these lead times change, Gilbane will need the opportunity to seek alternate manufacturers or adjust project schedule accordingly. > A cost and resource loaded scheduled is excluded. All cost will be submitted and reviewed via an approved schedule of value with the monthly payment application. > Gilbane has excluded any Design Costs or Contract Administration Cost(Submittal Review, RFI's, Site Visits, etc.)for CPL, Timmons, and any other design consultants. > The GMP includes insurance requirements from Gilbane to the Owner per the Prime Contract. Insurance Requirements from Gilbane to its subcontractors are included in the GMP per the attached Trade Contractor Insurance Requirements Exhibit. > The GMP includes Builder's Risk insurance coverage by Gilbane. Builder's Risk Insurance coverage is not included by Gilbane's subcontractors. > The GMP does not include a minimum percentage of minority or small business participation. > The GMP includes clarifications from the Pre-Bid RFI Log attached below. > The GMP does not include providing identification cards/badges for Gilbane nor trade personnel while onsite. > The GMP does not include providing a fire proof safe, nor onsite physical copies of as-builts stored in the construction trailer. > The GMP assumes Overhead and Profit of change orders for Gilbane shall be as follows in addition to the allowable 15% markup of the subcontractor: a SDI @ 1.3%of the cost of work. o Insurance @ 1.25%of the overall cost of the change order. o P&P Bond @.6% of the overall cost of the change order. o Fee @3.75% of the overall cost of the change order. SITEWORK > The GMP assumes that all site and building components being demolished can be hauled away as standard construction waste. > The GMP includes an Owner Allowance for Rock Removal. > The GMP does not include removal of any contaminated soils or groundwater. > The GMP assumes all onsite material is suitable for construction use/backfill. > The GMP assumes screening of existing topsoil for use in landscape areas. Orange County Crisis Diversion 100%Design Development • 17 Clarifications > Asphalt prices are based on NC DOT Monthly Terminal Prices for asphalt binder at $685.00/liquid TN of asphalt cement is included. For each 1.00 variance in the index cost of a ton of liquid asphalt, price will increase $0.05 per ton of hot asphalt used on the project FOUNDATION &SUPERSTRUCTURE > The GMP does not include any Deep Foundations (piles, caissons, piers, etc.). LANDSCAPING > The GMP does not include any irrigation. Maintenance of installed landscaping is included for the duration of Gilbane's work until substantial completion. > The GMP includes an Owner Allowance for site furnishings. BUILDING INTERIORS& EQUIPMENT > Code Required and Monument signage is included. An Owner Allowance is included for room signage. > The GMP includes appliances per the Responsibility Matrix on A700. An Owner Allowance is included for additional appliances. FIRE PROTECTION > The GMP does not include a Fire Pump and assumes the existing GPM feeding the site Fire Water Line is sufficient. > The GMP does not include Fire Sprinkler coverage at Exterior Canopies. PLUMBING > The GMP excludes any Natural Gas. HEATING,VENTILATING &AIR CONDITIONING > The GMP includes an Owner Allowance to provide extended manufacturer's warranty coverage to start mechanical equipment prior to substantial completion. ELECTRICAL, COMMUNICATIONS, SAFETY&SECURITY > The GMP does not include cabling,terminations,jacks, devices, for Access Control, Video Surveillance, Security, Telecom, Nurse Call, and Audiovisual as these are assumed by the Owner. > The GMP does not include a DAS Cell Boost System. > The GMP includes an Owner Allowance for a BDA System (Bidirectional Amplification System). > The GMP includes an Owner Allowance for(2) EV Charging Stations. > The GMP includes (4) non-traffic rated test wells for the grounding loop. > The GMP includes plenum rated cable for Fire Alarm scope of work per Pre-Bid RFI Log. Conduit and raceways are not included above ceilings. Orange County Crisis Diversion 100%Design Development r 18 ORANGE COUNTY CRISIS DIVERSION CENTER HILLSBOROUGH,NC Pre-Bid RFI Log Comment# Discipline Reference Comments/Concerns/Questions Answered By: Response 001 Civil Is there a SWPP available or does this need to be generated by the Civil Subcontractor? Caleb Robinson No,there will not be a SWPPP.The contractor is responsible for the NOI to comply with NCDEQ requirements. The Civil Drawings indicate Benches within the Patient Courtyard.Please provide details or Bench cut sheet is attached.Price it as standard colors/finishes,no 002 Civil specifications n Bench Type. Caleb Robinson accessories.Timmons will coordinate with CPL and Orange County to confine the selected bench is suitable for this facility. Drawing C3.2 references a Shade Structure in the Patient Courtyard with the note,See Please disregard the reference to the architectural plans.The shade structure 003 Civil/Arch Sheet C3.2 Architectural Plans.There are no details in the Architectural Plan for this Shade Structure. Caleb Robinson pricing and specs were emailed to Gilbane.Price the shade structure as an Please confirm if this Shade Structure is part of the project scope.If so,please provide alternate item. associated Drawings and Details. Drawing A231 notes that Canopy Downspouts must tie into the Storm Sewer.Please provide Refer to C5.1(Drainage Plan)for the roof leader connection to the storm 004 Civil/Arch Sheet A231 routing or connection paints from the Canopy Downspouts to the nearest Storm Sewer. Caleb Robinson drainage system. 005 Architectural Can rigid lactation underslab around perimeter foundations be removed for cost savings? Danielle Scesney No,perimeter foundation rigid insulation is required by NC energy code. 006 Electrical Is lightning protection required for this building? Justice Harris Yes. 007 Electrical/Civil Drawing E800/Detail 1 Drawing E800/Detail 1 shows a Bollard with Electrical/Lighting components.Please confirm Justice Harris Detail has been removed.Lighted/power bollards are not required for this where these bollards occur. project as of now. 008 Civil/Arch Please confirm if any bolllards are desired at or around the dumpster enclosure.If yes, Danielle Scesney No bollards around dumpster enclosure. confirm which a and where. Provide dumpster enclosure double gate to infill 18'-0"wide opening.Gates to 009 Architectural Provide details and sizing for the dumpster enclosure gates. Danielle Scesney be 8'-0"tall from grade.Provide painted tube steel frame with x bracing and Fluted sheet metal panel.Attach to 6"steel pipe bollard each side with hinges, latch and steel drop cane bolt on each door. Detail 6/A801 and all similar parapet details—shows exterior fluid applied air and vapor barrier 010 Architectural Detail 6/A801 and all applied to inside face of parapet.This is not an acceptable substrate for TPO membrane Danielle Scesney 6/A801 and all similar parapet details will be revised in an upcoming addendum. similar parapet details flashings nor a warrantable or constructible detail.This product should end at the outside edge of blocking and TPO membrane lap over. 011 Architectural There are no signage specifications.Please provide signage specifications and details. Danielle Scesney Signage specifications are listed in specification 1014 00 Signage.The specification and details will be provided in an upcoming addendum. Appliance specifications are listed in specification section 1140 00 Foodservice There are no appliance specifications or manufacturer/model numbers listed in schedule. Equipment.All other contractor provided equipment is listed in the equipment 012 Architectural A700 Please provide specifications and manufacturer and model numbers for equipment Danielle Scesney schedule on A700.The specification section will be provided in an upcoming addendum. A401,has many details showing some sort of Slab on Deck,Confirming that this is a All details on this sheet are representative of the top of wall condition for rated 013 Architectural Sheet A401 composite slab and not a CIP SOMD for details 1-8/A401 as noted on 2/A401 Danielle Scesney and STC partitions and are not project specific.Refer to the structural drawings for structural systems. Specification:28 46 00 Specification:28 46 00 2.04 A7-Spec calls out for white ceiling mounted devices and red 014 Controls/Fire Alarm Justice Hams All devices should be white. 2.04 A7 wall mounted.Please confirm they want different colors for wall vs ceiling mounted. Utility transformer housekeeping pad is by utility company.All other electrical& 015 Electrical/Structural Please verify housekeeping pads for utility equipment(Electrical gear,transformers,water Justice Hams transformer housekeeping pads to be determined once final equipment has heaters)Please indicate size and location. been selected.Generator pad will be offset V-0"on all sides and a1I other pads to be offset 4"on all sides.Water heater pad should be 36"06". 016 Electrical/Civil E050,E052,Cvil Dwgs. EV Charger stations do not align with the Civil drawing locations.(E050&E052 and all Civil Justice Harris Electrical drawings have been updated to indicate the spaces required for EV. dwgs.) Drawing E050,Key Note 4 indicates to provide"each"EV Location(2)1"conduits to a handhole. The location with(2)EV parking spaces is assumed to be a dual charging Drawing E050,Key Note Question:One location indicates(2)EV parking spaces with(2)dashed lines to the handhole, station and requires(2)1"conduits.The additional location is assumed to have 017 Electrical/Civil 4 Is this assumed to be a future Dual Charger and only requiring the(2)conduits for one unit? Justice Harris (2)dual charging stations and will require(2)1"conduits to each location. The other location indicates does not identify any EV parking spaces but has(4)dashed lines Drawings have been updated. to the handhole.Is this assumed to be for(2)future Dual Charger and requiring the(4) conduits? Drawing E902 indicates(6)circuit breakers for Future EV Chargers. Drawing E050,Keynote 4 indicates conduit runs for Future EV Chargers,but does not clearly panel schedules have been updated to show a need for(3)EV chargers per 018 Electrical/Civil E902&E050 Keynote 4 indicate the EV parking spaces. Justice Harris sheet E050. Question:Will there be(2)EV Chargers at the plan Northeast location and(4)EV Chargers at the plan Southeast location?If so,we will need to run(4)1"conduits and(8)1"conduits Is the complete Nurse Call System equipment,cabling,devices,etc to be provided by the 019 Electrical Owner? Justice Harris Nurse call is not in-scope for this building and has been removed from the drawings. Please also specify BOD.Is"Rauland Responder 5000"system acceptable? Panic buttons are located at both main entrances registration/check-in desks as Is there a separate Intercom/Paging System or is it only referring to the intercom referenced well as the FBC Nurse Station Desk and BHUC Nurse Station Desk.Panic 020 Electrical E400 Keynote 1 in Keynote 1 on drawing E400 at the Security pedestal?No Panic Buttons were found.Is Justice Harris buttons to contact security upon activation of button.A separate Intercom there any requirement for them and where would they be located system is located at the main entrance,reg/security,entrance,exterior warming kitchen entrance and back door into Corridor 1312. 1 of 4 19 ORANGE COUNTY CRISIS DIVERSION CENTER HILLSBOROUGH,NC Pre-Bid RFI Log Comment# Discipline Reference Comments/Concerns/Questions Answered By: Response Drawing E400,General Note F indicates that all Communication,AV,Security,and Access Control devices and cabling shown shall be by Division 27 and Division 28 Contractor and Division 26 to only provide conduit,boxes and power. The scope of work is to provide boxes and conduit for each device indicated on 021 Electrical E400 General Note F Gilbane Comment:Gilbane is purchasing security and fire alarm via BP 26A,and purchasing Justice Harris the drawings and owner to purchase and install devices.A responsibility matrix mechanical controls via 23A.However,it is unclear what other low voltage scopes of work has been added to E000 to indicate who is responsible for each scope. need to be procured i.e.AV,Data Question:Please let us know what the owner is providing and what Gilbane needs to provide. Drawing E400,Key Note 2 indicates Cameras furnished by owner and to provide CAT 6 UTP Cabling and to coordinate enact cabling requirements with owner,as well as the card readers 022 Electrical E400 Keynote 2 and hardware shown in Keynote#3. Justice Hants As of now,no AV is part of the scope. Question:Audio Visual(AV)is mentioned but have not seen any requirements.Please confirm that there are not any AV requirements in BP 26A. Specification Section 28 Specification Section 28 20 00 lists cameras by(7)different manufacturers,none of which are 023 Electrical 2000 Avigilon.If Orange County prefers compatible with existing Avigilon Systems,then Video Justice Harris Specifications will be updated in an upcoming addendum. Surveillance should be listed as Preferred Brand Alternate. A Lighting controller panel is located in Elec Room 1702 but not shown anywhere else or what circuits it is controlling or how it is controlling those circuit via zones or time clock/photocell. There are no specifications on a lighting controller. Sheet E200,Detail 2 1.Are we to assume that it is for the exterior lighting types'PW'and'PA'since the fixtures Lighting controller detail with make/model has been added(10/E802).All 024 Electrical Sheet E050 have no individual photocells? Justice Harris exterior parking,pathway,and wall packs will be controlled through the timeclock.E050 has been updated to reflect panel/circuit numbers. 2.Can specifications be provided for the Lighting Controller? 3.Dmwing E050 does not identify the panel and circuit numbers for the site lighting and breakers could not be identified in the Panels schedules.Please provide circuit designations Spec Section 26 05 26,201,3 indicates a Ground Ring around the building,but there is not a grounding drawing to show it.There are grounding details on drawing E801,but they may only 025 Electrical Spec Section 26 05 26, be related to the Service Transformer Grounding Detail. Justice Harris A perimeter building ground ring is required for the building.Grounding drawing 2.01,E801 has been added to the set. 1.Please confirm if a Perimeter Building Ground Loop will be required for this building?9 so, please provide any relative drawings and details. The PV alternate on E701 shows a 150 amp feed directly tapping into the utility service 026 Electrical E701 conductors that can potentially be back fed with no means of disconnecting between the PV Justice Harris E001 and E701 have been updated.PV disconnect to be fed from a 200A disconnect and utility service in the CT Cabinet.Can you confirm that this is how they want it circuit breaker in switchboard NMSB. installed instead of a breaker in the switchboard? Please advise if As-Built drawings are required to be updated in the BIM Model or if just Close out procedures are indicated in the specification section 0178 00. 027 MEP "Redlined"As-Builts are required to be submitted.There is an additional cost to update the Danielle Scesney"Redlined"As-Buills are to be submitted that meet the requirements outlined in Model,and it isjust used for coordination purposes. this specification section.The BIM model is for Coordination purposes only. The secondary on E001 show Piedmont EMC providing up to the SW BD.There are no Piedmont EMC is providing primary and secondary up to building mounted 028 Electrical E001 conduits or wire sizes for the secondary on any other print.There are 3 dashed lines Justice Harris meter.Contractor to provide service from meter to the switchboard.One-line indicating a route but no conduit size or wire size.Can you confirm the conduit size and diagram has been updated to reflect this and conductors required. conductor size? 029 Electrical Confirm Piedmont EMC is the electric utility in lieu of Duke Energy. Justice Hams Piedmont EMC is the electric utility company. Duct spec 233100,2.01 states low pressure supply duct at 2 inch wg pressure class.RTU schedule has 2.5 external static pressure... Supply ductwork upstream of VAV boxes is to be SMACNA 3"Medium 030 Mechanical 233100,2.01 Greg Kyzer Commercial Class construction. Please confirm if supply ductwork fross m RTU to VAV boxes is to be buil[for low pressure class or medium pressure class. 031 Electrical E300,Room#1208 Please refer to dwg#E300 Lighting Floor Plan Room#1208-TLT/SHWR—missing fixture tag Justice Harris M1 fixture tag is shown on latest drawings. type M1 is missing over the sink/vanity? Does the electrical contractor need to include Equipotencial ground testing of PAT Rooms, Equipment bonding has been added to critical and normal panels serving patient 032 Observations Areas,Toilets/Showers or any other rooms?If so-please specify which rooms Michael Ranieri care areas. to include? 033 Electrical E600,Room#1323 Tag for SSI-3 is missing from IT Room#1323 Justice Harris Tag has been added to plans. Piedmont EMC providing the secondary feeder cable from transformer to meter?Is Piedmont Piedmont EMC is providing primary and secondary up to building mounted Providing the conduits from the transformer to the meter or does the electical contractor to meter and CT cabinet.Contractor to provide service from CT cabinet to the 034 Electrical E001-power riser provide duct bank/empty conduits? Michael Ranieri switchboard.One-line diagram has been updated to reflect this and conductors Please confirm Piedmont is providing both transformer pit and pad. required.Piedmont EMC is providing transformer pit and pad. 035 Electrical E001,E200 Please clarify who is providing the utility meter/CT Enclosure.Will this be provided by the Michael Ranieri Contractor to provide CT enclosure in accordance with Piedmont EMC Electrical contractor or Piedmont? requirements. Gilbane would propose a VE alternate to decrease the size of the generator,can the EE 036 Electrical Michael Ranieri Not at this time. provide guidance on a decreased generator size? 037 Electrical Please provide a Low Voltage Matrix for systems,equipment,devices,cabling,etc.showing Justice Harris This has been added to E000. CFCI and OFOI 038 Electrical E805,#2 1.Please refer to dwg#E805 detail#2-Cable tray not shown on the drawings.Is there any Justice Harris Cable tray was VE'd. cable they for his project to ran low voltage cables? 039 Electrical Fire alarm is in-W EMT conduit or Plenum Rated cable on J Hooks.Please confirm? Justice Hams Provide plenum rated cable on j-hooks. 2 of 20 ORANGE COUNTY CRISIS DIVERSION CENTER HILLSBOROUGH,NC Pre-Bid RFI Log Comment# Discipline Reference Comments/Concerns/Questions Answered By: Response Please refer to dwg#E800-detail#1 gives Bollard Base Detail for a 42"High Bollard.In our Bollard detail is incorrect.Install'PW'fixture per manufacturers 040 Electrical E800,#1 case the Bollard is 7"Diameter and 11"High.Is a bollard Base 4'deep necessary? Justice Harris recommendations. Please refer to Fixture Schedule on dwg#E900 what the Pole Length for Pole Lights PA,PB 041 Electrical E900 and PC is? Justice Harris Pole base detail has been added to E800.Pole length should be 20'. Also,provide details of Pole Base for Pole Lights PA,PB and PC Please clarify dwg#E802 detail#2-there is a reference to existing building-the same 042 Electrical E802 Detail#2 reference is also there on other drawings-are we in anyway connecting this new building/work Justice Harris Detail has been updated. with some other building/buildings. The contractor is to provide the rigid conduit roof penetration for the donor 043 Electrical Is the electrical contractor to provide rough in and power for the potential future BDA system Michael Ranieri antenna cabling to the head end.Conduit sleeves over hard ceilings for antenna cabling.Monitoring modules and points for connection to the fire alarm system. 044 Electrical/Civil No power or FACP conduit for Back Flow Preventer on the site plan-is it required?If so, Justice Harris Fire alarm connection to backflow preventer on the site is not required. please provide location,size of conduit and circuit#etc 045 Architectural Please provide Roof top mechanical screen wall specifications Danielle Scesney Mechanical screen wall specification to be provided in upcoming addendum. 046 Architectural 101/A831 Reference 101/A831-Please confirm"Unistrut pipe support assembly" Danielle Scesney This is not required. 047 Architectural 101/A832 1011AB31(and sim)-Cabinets are drawn with shelf standards.Specs call for in-line bore Danielle Scesney Provide shelf pin as indicated in the specifications. pegs 048 Architectural 151/A831 151/A831-Please confirm steel is required at front of cabinet unit.This is self supporting and Danielle Scesney Steel is not required. not required if drawn 049 Architectural 1541A832 154/A831-Please confirm 9 steel is required.No gang restrooms and most aprons do not Danielle Scesney Steel is not required. anchor into adjacent wall Trim is not required R the roll up door hood is fully enclosed in the selected 050 Architectural 9/A831 9/A831-please clarify trim is required at head/jamb of roll up door Danielle Scesney manufacturer details and there is not a significant gap between the face of the door in a closed position and the adjacent attachment wall. 051 Architectural 10-11/A831 10-1l/A831-Is melamine required on the underside of countertops?This will put Danielle Scesney Melamine is not required on the underside of countertops. considerable costs on a concealed surface of a cabinet 052 Structural 0330002'G4 J Please provide areas where this admixture is required. Brian Cooney Delete Rem;Not Required on project Waterproofing dmixture Is a Moisture Emission Reducing Curing and Sealing Compound,Penetrating with Warranty Yes,use of the Moisture Emission Reducing Curing and Sealing Compound is 053 Structural 033000 1.06 B for 20 yrs Brian Cooney required,regardless.Contractor to coordinate use of ancillary items with sealer Is this required if a moisture retaining cover per 2.07D is used? manufacturer's guidelines. 054 Structural 033000 2.01 b.2 Are Earth formed footings not allowed for this project? Brian Cooney Footings shall be formed. 055 Structural 33000 3.11 Which floor treatments are used and where as referenced in this spec section. Brian Cooney Delete Paragraph;Not Required on project. At least 40%of the total cost of manufactured products must be U.S.-made. 056 Electrical Is there a domestic content requirement for the solar PV scope?If so,please confirm the Michael Ranieri This includes components such as modules,inverters,racking and other system required percentage. equipment. 100%of steel andiron used in the project must be produced in the United States. At least 40%of the total cost of manufactured products must be U.S.-made. 057 Electrical Do the solar PV components—including modules,racking,and inverters—need to comply with Michael Ranieri This includes components such as modules,inverters,racking and other system FEOC requirements? equipment.100%of steel and iron used in the project must be produced in the United States. Please confirm whether it is acceptable to utilize a single inverter of approximately 100 kW 058 Electrical E701 capacity in lieu of the three smaller inverters,provided that all other system performance and Michael Ranieri At least(2)inverters must be used. design requirements are met. We understand that the solar PV system is currently listed as an alternate for this project. 059 Electrical E701 Please clarify whether any portion of the solar scope—specifically,conduit installation( Michael Ranieri Entire solar PV system scope is to be included as pan of the alternate. associated with the PV system)—is required to be included in the base bid,or if the entire solar PV system scope,including all conduit,wiring,and associated infrastructure,is to be included only as part of the aftemate. 060 Electrical E701 Please confirm the preferred location for the AC disconnect and the AC combiner panel PV? Justice Harris Locate AC disconnect and AC combiner panel to be located on exterior wall outside Warthin Kitchen. Please confirm the exact point of interconnection for the solar PV system. 061 Electrical E701 Additionally,please clarify the required method of connection,specifically whether the Michael Ranieri Construction Manager to provide response. interconnection is to be made via a line-side tap,load-side connection(breaker),or load-side tap.Who will be responsible for this connection,the solar contractor or the electrical contractor? Module Substitution Request 062 Electrical E701 8 Photovoltaic Spec Michael Ranieri Hyundai Solar HiN is acceptable.ImnRidge Racking is acceptable. 26 31 00-4 2.01 Proposed Module:Module#1:Hyundai Solar HiN-T595NI-595W Proposed Racking system:IronRidg Racking Systems Yes,refer to specification section 0140 00 Quality Requirements for testing 063 Architectural 084313,3.04,C Is water spray testing per this spec section required to be by third party? Danielle Scesney agency requirements.Water spray testing could be incorporated into the special inspections agency scope if the selected agency is qualified to perform the test. 064 Architectural Missing 08 80 00 Glazing Specification Danielle Scesney Glazing specification to be provided in an upcoming addendum. 3of4 21 ORANGE COUNTY CRISIS DIVERSION CENTER HILLSBOROUGH,NC Pre-Bid RFI Log Comment# Discipline Reference Comments/Concerns/Questions Answered By: Response 065 Electrical Does the fire alarm system need to tie into the existing Orange County Desigo CC sy Justice Harris Yes,the fire alarm system will need to tie into the existing Desigo System. 066 Civil L3.0 Please provide details&specifications for river rock/metal edging,etc. Caleb Robinson Use attached detail. Please provide details&specifications for site furnishings 067 Civil L3.0 Caleb Robinson Include 3 waste receptacles and 3 U-bike racks.Specification sheets attached. If there are any other site furnishing,please provide speffications&Details Substitution Request: 068 Electrical Proposed Generator Substitution:Curtis Power Solutions MTU Michael Ranieri MTU is acceptable. See attached Please refer to dwg#E200 detail#2—shows"ECB-EV"in Electrical Room#1702 by the side of 069 Electrical E200 Detail 2 Panel EV.But we do not see it on the power riser-is it required?Please Confirm, Justice Harris Enclosed circuit breaker not required.Drawing has been updated. Please refer to dwg#E050—Keynote#3 Calls for 3 Cell Maxell Innerduct-but does not mention 070 Electrical E050 Keynote 3 the size of innerduct—is it 1",1.25"or 1.5".Please confirm the size of inner dud.Please also Justice Harris Innerduct should be 1.5"and fabric mesh. confirm it is Fabric or Fabric Mesh Please refer to site plan dwg#E050-clarify 9 the Secondary Dud bank is concrete encased or not? Secondary ductbank is by Piedmont EMC.Generator dud bank not required to 071 Electrical E050 Justice Harris be encased in concrete.Encase generator duct bank in pea gravel. Is the Generator Ductbank Concrete Encased? 072 Electrical Can MC Cable be used between light fixtures above ceiling and Home Runs in EMT for Justice Hams The intent is for a junction box and 6'whip for each fixture.Do not"daisy chain" lighting branch? the fixtures with MC. Are any Hospital Grade Receptacles anywhere on this project.If so,please specify areas in All receptacles throughout facility to be hospital grade.Specifications have been 073 Electrical which we are to use Hospital Grade Receptacles.As specifications are not calling for Hospital Justice Hams updated. grade receptacles.Please clarify? 074 Architectural H1/A701 Do patient rooms receive a SSM1 Windowsill?Reference H1/A701 Danielle Scesney Yes,provide ssm window sills at patient room windows. SC-1 on the finish schedule is shown as Metalworks Linear Perforated,in the specifications it Metalworks Linear Perforated as indicated on Finish Schedule is correct product 075 Architectural is listed as Linear wood planks.Could you verify which one is to be used?Additionally,what is Kelley Mock _NRC is 0.70 the NRC rating for this ceiling? ACT-3 is the Amstrong woodworks ceiling tile,the specfication/fnish schedule shows to install 076 Architectural with white grid.Is this the finish intended for this area?Or is there to be a custom color grid to Kelley Mock White Grid match the wood? 077 Architectural Has a wood species has been selected forthe flush wood doors?The Flush Wood Door Kelley Mock Plain Sliced White Maple(Color to be selected from manufacturers standard specification advises seeing the finish schedule which states to be determined by the architect. line) 078 Architectural Glazing film at vestibule entry.I still see it on the finish schedule Danielle Scesney Correct,there is not glazing film on the project. Please confirm if any undergound conduits need to be concrete encased(fiber telecom fiber conduits,generator,etc.)Detail 4/E800 states fiber is concrete encased. 079 Electrical 4/E800 Justice Harris Concrete encasement is not required. RFI response 71 states generator duct bank does not need to be concrete encased,but detail 1/E800 says this detail does not apply to generators. Please confirm if ground rod&test well locations.Ground rods and test stations are shown at every connection.Typically we use the four corners of the building for test wells. 080 Electrical E060,2&3/E801 Please confirm if traffic rated test wells are necessary,these will be in green areas. Justice Harris Test wells at 4 locations is fine.#2/0 is fine.Tier 8 boxes are okay. Please confirm wire sizing for grounding loop.The drawing shows#2/0 but the detail calls for 250kcmil which is unusual. 081 A601 Will exposed ceilings be painted?RCP/Finish plan does not indicate.Spec section 099123 Brooke Ross No,exposed ceilings will not be painted. 2.3E Dry Fall indicates exposed ceiling to be painted. Interior paint specifications 099123 call for wet areas to receive 2 component water based catalyzed epoxy while the high-performance specifications 099600 call for single component Intent is to use 2-component water based catalyzed epoxy found in the interior 082 precatalyzed epoxy which is significantly less costly and less durable.Is it the intent to use the Brooke Ross specifications. 2-component water based catalyzed epoxy found in the interior specifications or the single component precatalyzed epoxy? 083 Structural Please confirm that no HSS diaphragm collectors are required at the roof Brian Cooney Provide HSS3x2 1/2x1/4 diaphragm collectors between K-Series joist seats on Girder Lines 2,3,4,5,6,7,7.1,8,9,11,and 12. 4 of The GMP includes insurance requirements from Gilbane to the J10327.000-0032-000 Owner per the Prime Contract. Insurance Requirements from . • Gilbane to its subcontractors are included in the GMP per the attached Trade Contractor Insurance Requirements Exhibit. EXHIBIT A—DEFINITIONS hi the event of a conflict between any of the definitions in this Exhibit A and any of the definitions contained within the Contract Documents,the definitions in the Contract Documents shall control: "Applicable Laws" Shall mean all applicable laws,statutes,ordinances,codes,rules and regulations,and lawful orders of public authorities applicable to the Trade Contractor's performance under this Agreement and other programs as may be required by governmental and quasi-governmental authorities including but not limited to OSHA standards as well the Construction Manager's site-specific Accident Prevention Plan;all applicable Fair Employment Practices,provisions and regulations of Federal,State or other Governmental authority having jurisdiction including the provisions of Executive Order No. 11246,and Title VII of the Civil Rights Act of 1964,including amendments or revisions thereof,relating to nondiscrimination in employment,and any affirmative action provisions(including small business,minority-owned business,locally-owned business or similar requirements and/or local hiring requirements)contained in the Contract Documents or required by applicable law and all wage and workplace standards and all prevailing wage requirements;all applicable federal,state,municipal and local employment and immigration laws including all rules,regulations and procedures required to ensure full compliance with all such laws; "Approval" Shall mean where required for an item,shall be obtained from the Architect or the Owner through the Construction Manager in writing; "As hidicated" Shall mean a reference to example details,notes,or schedules on the drawings,other paragraphs or schedules in the Specifications,and similar requirements in the Contract Documents to define the Work and is not meant to limit the scope. Where terms such as"Shown","Noted","Scheduled",and"Specified"are used instead of"Indicated", it is for purpose of helping the reader accomplish the reference,and no limitation of location is intended except as specifically noted; "At no additional cost" The term"at no additional cost"shall mean at no additional cost to the Owner,the Architect,or the Construction Manager,and that all such costs are the Trade Contractor's responsibility; "Benchmarks" Shall mean portions of the actual Work in place used to establish a standard of measurement,evaluation or quality and in compliance with the Construction Manager's Quality Plan included within the Project Manual; "Construction Manager" Shall have the meaning given to such term in the Preamble of this Agreement; "Construction Manager's Schedule" The schedule shall contain detail appropriate for the Project,including(1)the date of commencement of the Work,interim schedule milestone dates,and the date of Substantial Completion;(2)an apportionment of the Work by construction activity; and(3)the time required for completion of each portion of the Work; "Contract Sum" The Contract Sum is the total amount payable by the Construction Manager to the Trade Contractor for timely and proper performance of the Work under the Contract Documents; "Contract Time" Unless otherwise provided,the Contract Time is the period of time,including authorized adjustments,allotted in the Contract Documents for the Trade Contractor to complete the Work; "Drawings" Shall mean drawings,diagrams,schedules and other data categorized as the following: (i) "Design Drawing"means drawings,diagrams,schedules and other data specifically prepared by a discipline of the design team,stamped and sealed by the Designer of Record,as representing the design intent(ii)"Coordination Drawing" means drawings showing work with horizontal and vertical dimensions required to avoid interference with structural,framing MEP rough-ins,fire protection,elevators, adjacent trade contactors'scope of work,and other thru floor and wall penetrations; -32- J10327.000-0032-000 and(iii)"Shop Drawing"means drawings,diagrams,schedules and other data specifically prepared for the Work by the Trade Contractor or any Lower Tier Trade Contractor,manufacturer,supplier or distributor to illustrate some portion of the Work.This includes drawings developed in the process of coordination with other trade contractors'scopes of work; "Electronic Data" Shall mean information or elements of measurable,extractable,and/or sortable value. This information will typically be delivered in spreadsheets,database tables,or,in less typical cases,tables within word processing documents; "Electronic Documentation" Shall mean software-based originals of hard copy documents resident in formats such as word processing,spreadsheet,graphic,or read-only applications; "Exposed" Shall mean any item or surface,exterior or interior,which can be seen by a person outside the building or seen by a person inside any accessible space within the building during normal activity; "Final Completion" Shall be as defined within the Prime Agreement and to the extent not inconsistent with the Prime Agreement,shall require: (i)the Work has been fully completed in accordance with the Contract Documents;(ii)all filings required to be made by the Trade Contractor,including,without limitation,those required for the Owner to obtain a permanent certificate of occupancy(if applicable),have been completed;(iii)all required documents and other items have been delivered to the Owner;and(iv)all Punchlist Work has been completed; "Furnish only","famish"or"supply" Shall mean to purchase,procure,acquire and deliver complete with all related accessories to the site or other designated location and transfer to others for installation; "Including","Such as" The terms"including"and"such as"shall be taken in most inclusive sense,namely, "including,but not limited to",and"such as,but not limited to; "Install" Shall mean to receive,unload,distribute,construct,erect,mount,and connect complete with related accessories; "Instruments of Service" Creative work performed by the Trade Contractor and/or its,and Consultant(s). Instruments of Service may include,without limitation,studies,surveys,models, sketches,drawings,specifications,digital models and other similar materials; "Maintained Assets" Shall mean items on drawings or specification documents that require the submittal of electronic data. Such asset data include but are not limited to doors,escalators, elevators,plumbing fixtures,air handling units,fans,pumps,heat exchangers,boilers, chillers,compressors,exhaust hoods,kitchen equipment,sub-stations,switchgear, transformers,panels,motor control centers,emergency generators,fire alarm p systems,fire pumps,biomedical equipment,laboratory equipment,hospital gas ° systems,roofing system,security systems,cameras,badge readers,computers,and vehicles. Bulk and general construction items such as concrete,structural steel, siding,casework,and wall,floor or ceiling materials will not be included with the exception of roofing,or any other element requiring routine or scheduled periodic maintenance in accordance with the manufacturer's written recommendations; "Mock-ups" Shall mean full-size,unless noted otherwise,models of a structure,component or assembly used for demonstration,study,or testing prior to commencing full production.Mock-ups are not incorporated into the actual Work and must be in ' compliance with Construction Manager's Quality Plan; U "OEM Shall mean Original Equipment Manufacturer; "Option" Shall mean a choice from the specified products or procedures,which shall be made by the Trade Contractor. The choice is not"whether"the work is to be performed, but"which"product or"which"procedure is to be used; V -33 - J10327.000-0032-000 m "Overhead" Unless specifically noted otherwise in the Contract Documents,the term"overhead" as used in Article 13.1 of the Trade Contract and elsewhere with similar meaning shall be understood to include but not necessarily be limited to the following(i)Salaries, fringes and other compensation of the Trade Contractor's personnel stationed at the Trade Contractor's principal office or offices other that the project site office;(ii) salaries,fringes and other compensation of the Trade Contractor's personnel stationed at the project in"non-working"supervisory and/or administrative roles(iii) expenses of the Trade Contractor's principal office and offices including the project site office(these expenses include,without limitation,heat,light,power,stationery& supplies,postage&shipping,office equipment(telephone,copiers,computers, printers,software,furniture,radios,telephones,parking,all company vehicles,etc.), lease line cost,drinking water,coffee,first aid,shop drawings,submittals,samples, as-built drawings,blueprinting,photocopying,record storage,trailers);(iv)Trade Contractor's capital expenses including interest on the Trade Contractor's capital employed for the Work(v)penalties,fines,and costs imposed by governmental authorities in connection with or resulting from any violation of,or noncompliance with laws,regulations,codes,ordinances or directives;(vi)the cost of small tools(valued at$250 or less per unit purchase price)and associated consumables;and(vii) incidentals; "Owner" Shall have the meaning given thereto in the Preamble to this Agreement; "Project" Shall have the meaning given thereto in the Preamble of this Agreement; "Project Criteria" All performance and design and/or performance criteria that such delegated design services must satisfy; "Punchlist(s)" Shall mean lists of incomplete or unsatisfactory items of Work prepared as part of the Substantial Completion process; "Punchlist Work" Shall mean Work shown on any Punchlist; "Product" The term"product"shall include materials,equipment and systems; "Product Data" Shall mean illustrations,standard schedules,performance charts,instructions, brochures,diagrams and other information furnished by the Trade Contractor to illustrate a material,product or system for some portion of the Work; "Provide",or"Perform" Shall mean to supply,install and connect,complete and ready for safe and regular operation of particular work referred to unless specifically noted otherwise; "RFI" Shall mean a written request to obtain information not contained,or inferable from, the Contract Documents.An RFI form will be used to obtain clarifications of the content or intent of drawings or specifications issued by the Architect; "Samples" Shall mean physical examples,which illustrate materials,equipment or workmanship and establish standards by which the Work will be judged,but not used in the actual Work; "Site Safety Officer" Shall mean the person designated by the Construction Manager who has been designated as the person responsible for implementing the field activities and ensuring that activities are conducted in strict accordance with the approved Safety Plan; "Site Supervisor" Shall be the person designated by the Construction Manager to supervise the construction activites on site.; "Specifications" Shall mean the portion of the Contract Documents consisting of the written requirements for materials,equipment,systems,standards and workmanship for the Work,and performance of related services; "Submittals" Shall include,but are not limited to,Shop Drawings,Product Data,Samples,Mock- ups,Benchmarks,Warranty,Maintenance Manuals,Waivers,and Releases; "Subcontractor Change Directive" Shall mean the written instrument signed by the Construction Manager directing the -34- J10327.000-0032-000 r Trade Contractor to proceed with a change in the Work prior to agreement on any adjustment of the Contract Sum and/or Contract Time; "Subcontractor Change Order" Shall mean the written instrument signed by the Construction Manager and the Trade Contractor stating their agreement on a change in the Work and any adjustment of the Contract Sum and/or Contract Time; "Substantial Completion" Unless defined otherwise within the Prime Agreement,Substantial Completion shall mean,with respect to the Work or designated portions thereof,the Work is sufficiently complete in accordance with the Contract Documents so that the Owner can use the Work for its intended purposes; "Substantial Completion Date" Shall be identified on the Construction Schedule attached hereto; "Suitable","reasonable","proper","correct"and Shall mean as suitable,reasonable,proper,correct,or necessary for the purpose "necessary' intended as required by the Contract Documents,subject to the judgment of the Architect,Owner or the Construction Manager; "Testing Laboratory" Shall mean an independent entity engaged to perform specific inspections or tests of the Work,either at the project site or elsewhere,and to report and interpret the results of those inspections or tests; "Trade Contractor's Lower Tier Contractor(s)" Shall mean any subcontractor,materialman or supplier entering into a written subcontract with the Trade Contractor;and "Work" Shall mean the construction and completion of the Project and performance of all other obligations of the Trade Contractor together with all items reasonably inferable from the Contract Documents whether or not such items are fully detailed or specified in the Contract Documents. IIl -35- J10327.000-0032-000 • EXHIBIT B—INSURANCE The following supplements Article 5 of the Agreement: 1. TRADE CONTRACTOR'S INSURANCE OBLIGATIONS. Prior to the commencement of the Work,Trade Contractor shall obtain and maintain insurance,in a form and amount satisfactory to the Construction Manager,according to the limits(denominated in US Dollars)and terms identified below for the duration of the Project and as required after completion,covering Worker's Compensation and Employer's Liability,Automobile Liability,Comprehensive General Liability, Excess Liability and Professional Liability/Errors and Omissions,and Pollution Liability,Contractor's Equipment,Riggers Liability,Cyber Liability,and Aviation Insurance(only as applicable as set forth below). The liability limits required by Trade Contractor under this Agreement for the primary Commercial General Liability insurance,Business Automobile Liability insurance and Umbrella/Excess Liability insurance may be satisfied through any combination of limits contained on either the primary or excess liability or combined policies of insurance. Except for Professional Liability coverages,all insurance must be provided on an occurrence basis.Except as otherwise set forth below,Trade Contractor shall maintain all required insurance under this Agreement during the term of this Agreement and through the Statue of Repose period in the State in which the Project is located,or if no Statute of Repose applies,for a period of ten(10)years following Trade Contractor's fulfillment of all obligations hereunder.No work shall be commenced by Trade Contractor,and no payment due,until satisfactory evidence has been provided that the insurance required by this Agreement is in force.Insurance shall be provided by a company with an A.M.BEST,rating of"A-"or better and financial ratings not lower than"VII"in the Best's Insurance Guide,latest edition in effect as of the date of this Subcontract,and which is licensed to do business in the state in which the Project is located. Should the Trade Contractor engage a subcontractor or consultant,the Trade Contractor shall ensure that such entity(ies)maintain insurance in the same forms and amounts as would apply if such entity was the"Trade Contractor"under this Agreement. 1.1 Controlled Insurance Programs: If the Project is insured by a Contractor Controlled Insurance Program(CLIP),and/or Owner Controlled Insurance Program(OCIP),the Trade Contractor shall refer to both the Project Manual and any insurance- related addendum to the Prime Contract(incorporated herein as a Contract Document)for any additional or alternate insurance obligations. If the CCIP or OCIP requires additional coverage or higher limits from the Trade Contractor than outlined in this Exhibit,Trade Contractor shall provide such additional coverage and/or limits as applicable. Unless specifically listed as an excluded party,Trade Contractor and its lower-tier Trade Contractors must follow the enrollment procedures set forth and comply with the amounts and terms of coverage as defined in the Project Manual. Trade Contractor and any lower-tier Trade Contractors are not allowed on site until enrollment has been completed. For Enrolled Trade Contractors and as applicable per the terms of the Controlled Insurance Program,the General Liability,Umbrella Liability,and Worker's Compensation requirements(if provided by the CIP)of this Exhibit will apply to off-site activities only. In the event any provision of this Agreement or any other Contract Document conflicts with the Controlled Insurance Program Insurance Policy,the provisions of the Policy shall govern. 2. COVERAGE LIMITS AND REQUIREMENTS 2.1 Worker's Compensation/Employers Liability: Trade Contractor shall provide Workers Compensation and Employer's Liability insurance in any jurisdiction(s)where the work is being performed or where benefits maybe applied. The Workers'Compensation insurance shall include a Voluntary Compensation Coverage Endorsement. When performing work in any monopolistic state or territory the Trade Contractor shall provide evidence of"stop gap"insurance in addition to workers'compensation. • Limits: • Worker's Compensation:Statutory • Employers Liability: • $1,000,000 each employee—by accident • $1,000,000 policy limit—by disease • $1,000,000 each employee—by disease • Waiver of Subrogation in favor of the Construction Manager,the Owner and any other parties as required by the Prime Contract,and Waiver of the rights to any statutory Worker's Compensation liens(in each case to the full extent permitted by law). • If Trade Contractor's employees are provided or managed by an employee-leasing firm,or Trade Contractor uses temporary employees -36- J10327.000-0032-000 r and/or uses other labor services,an Alternate Employer Endorsement naming the Trade Contractor is to be included as part of the policy and evidenced with the Certificate of Insurance,or Trade Contractor must provide Construction Manager with a Minimum Premium Policy(a.k.a."If Any"policy)from the employee leasing firm.Trade Contractor agrees to comply with any requests by the Construction Manager to verify coverage is being provided for leased or temporary employces.If Trade Contractor is leasing labor to Construction Manager,then Trade Contractor shall attach the alternate employer endorsement to its workers'compensation policy,and shall schedule the Construction Manager and the Agreement on the form. • If the work will involve,in whole or in part,work or operations on or near navigable waters of the United States,or on a flagged vessel, then Trade Contractor shall obtain coverage pursuant to the Jones Act and/or the Longshoremen's and Harbor Worker's Compensation Act as applicable. • Trade Contractor warrants that it has and shall maintain WC/EL insurance to cover any compensable or other legally viable employee claim arising under the laws of the state in which the Project is located.Trade Contractor expressly agrees that it will defend,indemnify and hold Construction Manager harmless from any uninsured claims as defined herein. 2.2 Commercial General Liability:Trade Contractor shall provide Commercial General Liability insurance for Bodily Injury,Personal and Advertising Injury,and Property Damage. Coverage must be provided on the most recent edition of the ISO CG 00 01 form on an Occurrence basis. The general aggregate must apply per Project,or per Work Order as applicable. • Limits: • $1,000,000 Each Occurrence(except for Projects within the State of New York must be$2,000,000 each occurrence) • $1,000,000 Personal and Advertising Limit • $2,000,000 General Aggregate Limit,applicable Per Project(except for Projects within the State of New York must be $4,000,000 General Aggregate Limit) • $2,000,000 Products Completed Operations Aggregate Limit(except for Projects within the State of New York must be $4,000,000 Products Completed Operations Aggregate Limit) • $5,000 Medical Expense • Coverage for explosion,collapse,and underground hazards(XCU)and subsidence • Blanket Contractual Liability,with no modification to or deletion of the"insured contract"exception to the contractual liability exclusion • No exclusions for Independent Contractors or Damage to Work Performed by Trade Contractors on Your Behalf • No modification to the standard Employers Liability exclusion,which gives back coverage for an"insured contract" • Policy shall not contain any exclusions directed toward any types of projects,materials or processes involved in the Work, including,but not limited to: • Work within fifty(50)feet of any railroad property,or affecting any railroad bridge or trestle,tracks,roadbeds,tunnel, underpass or crossing. If applicable,ISO endorsement CG 24 17 shall be attached to the policy • Defense costs must be in addition to,and not deplete,policy limits; • Must not contain any exclusions or limitations of coverage because of Wrap-up exclusions or project specific exclusions. • Must not contain any exclusion for or limitation applicable to residential work,or any prior work exclusion. • Must not contain any exclusions for or limitation applicable to heights,or any similar exclusion limitation. • Must not contain any exclusions for or limitations applicable to labor law,or any similar exclusion/limitation. • Must not contain any exclusions for or limitations applicable to 3rd party over action claims,or any similar exclusion/limitation. • Must not contain any exclusions for or limitations applicable to Exterior Insulation Finish Systems,Synthetic Stucco,Direct Applied Finish Systems,or any similar system. 2.3 Business Automobile Liability:Trade Contractor shall provide Business Automobile Liability insurance on the most recent ISO form for claims for damages due to bodily injury or property damage arising out of the ownership,maintenance,or use of any land motor vehicle (including trailer or semitrailer)used in connection with the Work,including,without limitation,loading and unloading. • Limits: -37- J10327.000-0032-000 • $1,000,000 Combined Single Limit—each accident • $1,000,000 Hired&Non-owned Auto Liability limit • Coverage shall be provided for all Owned,Non-Owned,Leased and Hired vehicles • This insurance shall also include contractual liability coverage. • Any statutorily required"No-Fault"benefits and uninsured/underinsured motorist coverage shall be included. • If Trade Contractor's Work includes hauling or transporting of hazardous or regulated materials,substances,or waste,as defined in Section 2.6 below,then the required limit shall be$5,000,000,and the policy shall include the most current version of the ISO CA 99 48 Broadened Pollution Liability and MCS 90 endorsements Coverage can be provided through a Pollution Liability policy in lieu of the above. • If Trade Contractor's work is to be performed within fifty(50)feet of any railroad property or affecting any bridge or trestle, tracks,roadbeds tunnels,underpass or crossing,then the most current version of ISO CA 20 70(or its equivalent)shall be attached to the auto policy. 2.4 Umbrella/Excess Liability: Trade Contractor shall provide occurrence-based Umbrella/Excess Liability insurance providing coverage in excess of the required Employer's Liability,Commercial General Liability and Business Automobile Liability policies.The policy shall be follow-form to the underlying policies and have no exclusions broader than the underlying coverage. Umbrella/Excess policy shall provide a priority of coverage endorsement or its equivalent and shall"drop down"for defense and indemnity in the event of exhausting of the underlying policies. • Limits: • $5,000,000 Each Occurrence • $5,000,000 Aggregate • If the Trade Contractor's Work requires it to provide a crane used to hoist,lower and horizontally move a suspended load then: • $25,000,000 Each Occurrence/$25,000,000 Aggregate for tower cranes(If New York,then limit shall be$80,000,000 Each Occurrence/$80,000,000 Aggregate,or as required by the local authority,whichever is greater) • $10,000,000 Each Occurrence/$10,000,000 Aggregate of other cranes 2.5 Professional Liability: If the Trade Contractor's scope of work(including the scope of any of its subcontractors or subconsultants) includes providing professional services that include,but are not limited to, preparing or approving maps,opinions,reports,surveys,field orders, engineered shop drawings,and/or drawings and specs;and also supervisory,inspection,quality control,architectural and engineering activities by the Trade Contractor or by Trade Contractor Lower-Tier Contractors on behalf of the Trade Contractor,the Trade Contractor shall provide Professional Liability insurance. • Limits: • $2,000,000 per claim/$2,000,000 aggregate for Design Assist Work,where Trade Contractor is not providing any calculations, ■ engineering,surveying,signing or stamping of documents. n • $2,000,000 per claim/$2,000,000 aggregate for Delegated Design OR Design Builder work where the Contract Sum is less than $10,000,000. However,if the scope of work involves curtainwall,then the required limit shall instead be$5,000,000 per claim/ $5,000,000 aggregate. • $5,000,000 per claim/$5,000,000 aggregate for Delegated Design OR Design Build work where the Contract Sum is greater than$10,000,000 but less than$25,000,000. However,if the scope of work involves curtainwall,then the required limit shall i instead be$10,000,000 per claim/$10,000,000 aggregate. ■ • $10,000,000 per claim/$10,000,000 aggregate for Delegated Design OR Design Build work where the Contract Sum is greater than$25,000,000 but less than$50,000,000. However,if the scope of work involves curtainwall,then the required limit shall instead be$15,000,000 per claim/$15,000,000 aggregate. -38- J10327.000-0032-000 • For Delegated Design OR Design Build work where the Contract Sum is greater than$50,000,000,then the insurance limit shall instead be defined in Article 13 of this Agreement. 2.6 Pollution Liability: If the Trade Contractor's scope of work(including the scope of any of its subcontractors or subconsultants) includes providing pollution services that include,but are not limited to,work involving water or wastewater,(including without limitation fire suppression,pool installation,HVAC,plumbing,underground utilizes and sewers)as defined in applicable law,regulation,ordinance or code,or performing:testing,investigation and characterization of contamination of land,groundwater or structures,demolition of structures,abatement, replacement,repair,enclosure,encapsulation of hazardous or regulated materials(Hazardous or regulated materials shall include,but are not limited to,asbestos,petroleum products,lead,mold,mercury or polychlorinated biphenyls("PCBs")),remediation of contaminated soil or groundwater including transportation and disposal of contaminated media,installation or removal of underground storage tanks,or any storage, transportation or disposal of materials that are hazardous or regulated under environmental laws by the Trade Contractor or by subcontractors on behalf of the Trade Contractor,the Trade Contractor shall provide Contractor's Pollution Liability Insurance • Limits: • $5,000,000 Each Occurrence • $5,000,000 Aggregate • The policy shall include coverage for bodily injury and property damage liability,remediation,defense costs,and clean-up costs arising from pollution events or conditions on,at,under or migrating from the Work site,and from transportation and disposal of pollutants and/or contaminated by pollution and shall provide non-owned off-site disposal coverage if hazardous or regulated materials will be transported to a disposal site. • If Trade Contractor's scope of work includes mold/fiangus remediation or the Project involves any residential,health care,custodial care or educational occupancy,then the contractor's pollution liability insurance shall include mold/fungus liability coverage for the full amount of the limits required herein. • If Trade Contractor is subcontracting out its entire scope of pollution services,Construction Manager may accept proof of the pollution liability insurance required in this Article from each person or entity who is performing the pollution services on behalf of F Trade Contractor. • The retroactive date on all pollution liability policies provided by Trade Contractor or any of its subcontractors shall precede the start of any work. L 2.7 Contractor's Equipment/Property Coverage II Trade Contractor shall procure and maintain all-risk property insurance necessary for protection against loss of owned,borrowed,or rented equipment or tools(including mechanical heavy equipment)including any tools owned by employees,and any tools,equipment,staging towers, and forms and other property,the capital value of which is not intended to be incorporated into the Work. The Trade Contractor shall be responsible to provide insurance for any purchased material while in off-site storage and/or in transit. If Trade Contractor's Work includes move management services such that it is responsible for: moving of personal property from one location to another(or within a single location),storage of personal property at one or more locations and/or installation of personal property then it shall provide an installation floater covering such exposures for the full replacement cost of such property. Failure of the Trade Contractor to secure such insurance or to maintain adequate levels of insurance shall not obligate Construction Manager or the Owner or any other Additional I I I Insured/Indemnitee for any losses.Policy shall include a Waiver of Subrogation in favor of all Additional Insureds. P 2.8 Crane Utilization Requirements/Riggers Liability: All Trade Contractors operating,hiring or contracting others to use,operate or hire a crane will be required to supply Construction Manager with an updated crane certification and adhere to all current OSHA Standards, including OSHA Standard#1926.1427,and any subsequent revisions. The crane certification shall be kept on the job site at all times. • Trade Contractor will maintain or cause to be maintained property damage insurance sufficient for the value of the crane. -39- J10327.000-0032-000 • The policy must contain a Riggers Liability endorsement with minimum limits equal to the value of the most expensive hoist intended in the Trade Contractor's Scope of Work and provide coverage for loss or damage to all property,including not only property in operator's care,custody and control but also consequential damage to all other property arising from all Crane and/or Rigging operations. • The insurance coverages will be the broadest form available including,Boom Overload and Collapse,Over-the Road Liability,Debris Removal,Preservation of Property and if applicable,Property in Transit. The policy will name the Construction Manager,Owner and other entities as may be reasonably requested as Additional Insureds and Loss Payees. • All damages to the crane are the sole responsibility of the Trade Contractor and the Trade Contractor waives and shall cause all applicable insurance carriers providing physical damage insurance on the Crane to also waive all right of recovery against the Construction Manager,Owner,parties required of the Prime Contract and all other parties with interest in the Project for all damages to the crane. 2.9 Cyber Liability Insurance: If the Trade Contractor's scope of work for the Agreement involves working on Building Information ' Systems,Security/Access Control Systems or Tel/Data Systems,handling personally identifiable information of Construction Manager ori Owner,the Trade Contractor shall provide Cyber Liability Insurance. • Limits: • $2,000,000 Each Occurrence • $2,000,000 Aggregate • Coverage shall be sufficiently broad to respond to the duties and obligations as is undertaken by Vendor in this agreement and shall include,but not be limited to,claims involving:infringement of intellectual property(including but not limited to infringement of copyright, trademark,and trade dress),invasion of privacy violations,information theft,damage to or destruction of electronic information,release of private information,alteration of electronic information,extortion,and network security.The policy shall provide coverage for breach response costs as well as regulatory fines and penalties as well as credit monitoring expenses with limits sufficient to respond to these obligations. 2.10 Aviation Liability Insurance: In the event any fixed aircraft,rotary aircraft,or Unmanned Aerial Vehicles("drones')are used in the execution of the Work,whether owned,leased,or borrowed,Aviation Insurance is required. • Limits: • $5,000,000 Each Occurrence for drones • $25,000,000 Each Occurrence for helicopters,plus Aircraft Hull Insurance for the full replacement value of the aircraft • Insurance shall provide coverage for all claims,suits,obligations,liabilities and damages(including attorneys'fees)arising out of actual or alleged Bodily hijury,Property Damage,and/or Personal and Advertising Injury 2.11 Other Coverages: To the extent that the Trade Contractor's work requires any additional insurance coverage,including but not limited to Marine Coverage,Construction Manager reserves the right to require the Trade Contractor to maintain such additional coverage as applicable. To the extent that the Prime Contract requires additional insurance or coverage with higher limits than required in this Exhibit B,then Trade Contractor shall provide additional coverage and/or higher limits. 3. GENERAL INSURANCE REQUIREMENTS 3.1 Additional Insureds: For purposes of this Article"Additional Insureds"shall mean(1)the Construction Manager(and its partners or members if Construction Manager is a joint venture or LLC),(2)Owner,(3)both Owner and Construction Manager's officers,directors and employees,(4)any person or entity requested by Construction Manager or Owner,and(5)any other person or entity required to be added as an additional insured by the Contract Documents or you have agreed to in writing. The Additional Insured parties shall be granted such status on the Trade Contractor's Commercial General Liability,Commercial Automobile Liability,Umbrella/Excess Liability,and Pollution policies. Each policy shall state that the insurance provided to the Additional Insured is Primary and Non-Contributory to any other insurance(including primary,excess,self-insurance,or on any other basis)available to the Additional Insured. The policies provided under this Exhibit shall not eliminate or restrict coverage for claims or suits between Named Insureds and Additional Insureds. To the fullest extent permitted by law,the -40- J10327.000-0032-000 • coverage provided to the Additional Insureds must be at least as broad as that provided to the first Named Insured on each policy. In the event that any policy provided in compliance with this Exhibit states that the coverage provided to an Additional Insured shall be no broader than that required by contract,or words of similar meaning,the parties agree that nothing in this Exhibit is intended to restrict or limit the breadth of such coverage. With respect to the Commercial General Liability policy,Additional Insured status must be provided on I.S.O.forms CG 20 10 11 85 (Additional Insured—Owners,Lessees or Contractors)OR CG 20 10 10 01 (Additional Insured—Owners,Lessees or Contractors—Sched. Person or Organization)AND CG 20 37 10 01 (Additional Insured—Owners,Lessees or Contractors—Completed Operations),or their collective equivalent that has been approved by Construction Manager prior to the Trade Contractor entering the site. The Additional Insured parties shall be granted such status on the Completed Operations endorsement through the Statute of Repose period. 3.2 Minimum Limits: The limits of insurance stated above for each type of insurance are minimum limits only;in the event Trade Contractor's policy provides greater limits,this Exhibit shall be deemed to require such limits,and the Additional Insureds shall be entitled to,or to share in,the full limits of such policy. 3.3 Waiver of Subrogation: Trade Contractor agrees to waive any right of action against Construction Manager(and its partners if Construction Manager is a joint venture or its members if an LLC),Owner,and any others required to be provided a waiver by the Contract Documents and/or the Prime Contract(collectively the"Waiver Parties")for recovery of loss and/or damages to the extent covered,or that should have been covered,by the insurance required of Trade Contractor in the Contract Documents or any other insurance provided by Trade Contractor which is applicable to the Project. Such waivers shall be provided by specific endorsement if the policy itself does not otherwise provide the required language.Trade Contractor will require its sub-Trade Contractors,agents and employees,by appropriate agreements, written where legally required for validity,to provide similar waivers in favor of the parties enumerated herein.A waiver of subrogation shall be effective as to a person or entity even though that person or entity would otherwise have a duty of indemnification,contractual or otherwise,did not pay the insurance premium directly or indirectly,and whether or not the person or entity had an insurable interest in the property damaged. 3.4 Deductibles and Self-Insured Retentions: Trade Contractor shall be responsible for payment of all deductibles and/or self-insured retentions for all insurance policies it provides in compliance with this Exhibit. The coverage afforded to the Additional Insureds shall not be conditioned on the Additional Insureds'payment of any deductible or self-insured retention. The policies Trade Contractor furnishes in compliance with this Section shall not be subject to any deductible or self-insured retention in excess of$250,000 unless approved in writing by Construction Manager. 3.5 Certificates of Insurance: Within five(5)days following the execution of this Contract,and prior to the commencement of the Work,and prior to any personnel coming onto the Site,and within three(3)days of any renewal,change in coverage,or replacement of coverage,Trade Contractor shall provide a Certificate of Liability Insurance(Acord form 25 2016/03). The Certificate shall: • State the Project name and number,list the Additional Insured,Primary and Non-Contributory and Waiver of Subrogation coverages as being provided in the Description of Operations section. • Any schedule required in such endorsements shall include all parties as Additional Insureds including any and all indemnities as specified in the Prime Contract. Acceptable language for an annual blanket certificate of insurance shall include"for whom you have agreed in a written contract,Agreement,or Work Order." • Include evidence of any self-insured retentions. • Include as an attachment hard copies of the Additional Insured(for both Ongoing and Completed Operations),Primary Non- Contributory,and Wavier of Subrogation endorsements. Trade Contractor shall continue to provide COIs to Construction Manager upon renewal,and at the time of any change in insurer,limits,or coverage,through the duration for which such insurance is required under this Exhibit. A Trade Contractor's failure to provide COIs shall not relieve it of its responsibility to carry and maintain the required insurance.Construction Manager's failure to demand or inspect a Trade Contractor's COI,and/or Construction Manager's failure to identify or object to any discrepancy therein,is not a waiver of any insurance requirement. If Trade Contractor fails to comply with its insurance obligations Construction Manager may be considered a material breach of this Agreement and Construction Manager may withhold monthly progress payments and exclude Trade Contractor from the Project site until -41 - J10327.000-0032-000 such time as it complies with its obligations. Upon request,Trade Contractor shall provide Construction Manager with any Certificate of Insurance,Endorsement,coverage provision,or certified copy of any insurance policy applicable to coverage required by this Exhibit. 3.6 Notice of Cancellation: All policies shall contain a provision that coverages afforded under the policies shall not be canceled, materially changed or not renewed unless at least thirty(30)days prior written notice has been given to Construction Manager 3.7 No Waiver: Any waiver or modification of the insurance requirements stated in this Section must be agreed to in writing by Construction Manager. 3.8 NO LEVHTATION: IN THE EVENT THAT THE LAW OF THE STATE IN WHICH THE PROJECT IS LOCATED(OR APPLICABLE LAW)LIMITS THE APPLICABILITY OF ANY OF THE INSURANCE COVERAGE THAT CONSTRUCTION MANAGER MAY REQUIRE FROM TRADE CONTRACTOR,THEN TRADE CONTRACTOR SHALL BE REQUIRED TO OBTAIN COVERAGE TO THE FULLEST EXTENT OF COVERAGE AND LIMITS ALLOWED BY APPLICABLE LAW AND THIS CONTRACT SHALL BE READ TO CONFORM TO SUCH LAW. -42- 33 Activity ID Activity Name Orig emaining Start Finish Dur Duration 2026 2027 2028 ar pr ay un u g p INOVI Dec[ an lFe ar r ay un It ug ep Nov Dec Jan I Febar Apr Orange MILESTONES lll� 379 379 13-Jul-26 13-Jan-28 MILS.1080 Building Permit Received 0 0 13-Jul-26 ♦Building Permit Received MILS 1090 Site Permit Received 0 27-Jul-26 ♦Site Permit Received MLS.1010 Site Mobilization 0 0 28Jui-26 ♦Site Mobilization MLSA020 Steel Structure Complete 0 0 25-Mar-27 ♦Steel Structure Complete MLS.1030 Building Dry-In 0 0 01-Jun-27 ♦Building Dry-In MLS.1040 Permanent Power 0 0 11Jun-27 ♦Permanent Power MLSA050 Conditioned Air 0 0 16-Jun-27 ♦Conditioned Air MILS 1080 Substantial Completion 0 0 12-1,11ov-27 ♦Substantial Completion _ MLS.1100 Change County Regulatory Reviewsllnspectli 0 D 14-Dec-27 ♦Orange County Regulatory MILS.1070 Rnal Completion 0 0 13-Jan-28 ♦Final Completion PRECONSTRUCTION NEW 365 352 17-Mar-26A 23-Aug-27 DESIGN 1 0 27-Mar-26A 30-Mar-26A DES.1000 100%CD Issuance 1 0 27-Mar-26A 30-Mar-26A 1 100%CD Issuance - PERMITTING 83 80 17-Mar-26A 27Jul-26 PER 1010 Building Permit tat Submission 40 40 03-Apr-26A 29-May-26 Building Permit let Submission PER.1020 Final Building Permit Approval Process 30 30 014un-26 13,1ul-26 D Final Building Permit Approval Process PER.1000 Site Plan&CDApproval 1 80 17-Mar-26A 27Ju1-26 Site Plan&CDApproval ESTIMATINGIGMP DEVELOPMENT 52 52 03-Apr-26A 1"un-26 - EST.1000 Bid Project 1 13 03-Apr-26A 28-Apr-26 Bid Project EST.1020 Compile PdcinglSmpe Review Trades/Build GMP 24 24 291 02-Jun-26 Compile Pncing/Scope Review TmdesrBuild GMP EST1030 Change County Board Approval 10 10 03-Jun-26 16-Jon-26 M Orange County Board Approval VDCICOORDINATION 65 65 26-Aug-26 30-Nov-26 COORD.1010 Underground VDC Coordination 20 20 26-Aug-26 23-Sep-26 D Underground VDC Coordination COORD.1020 Level VRoof VDC Coordination 45 45 24Sep-26 30-Nov-26 Level VRcof VDC Coordination - PROCUREMENT 300 300 17-Jun-26 23-Aug-27 r r rr rr I I I 31ASkamrk 130 130 17Jun-26 22-0eo-26 PRC1000 Award Sitework _ 20 20 17Jun-26 15-Jul-26 Award Sitework _ PRC1010 Submittals&Approval Storm Flier 20 20 16-Jul-26 12-Aug-26 O Submittals&Approval Storm Filter PRC1040 Submittals&Approval Storm Drain Structure T 25 25 16Jul-26 19-Aug-26 D Submittals&Approval Storm Drain Structure PRCID30 Fabrication/Delrvery Store Drain Structure 30 30 20-Aug-26 01-Oct-26 D FabricationlDelivery Storm Drain Structure PRC1020 Fabrication/Delrvery Storm Filler 90 90 13-Aug-26 22-Dec-26 -iial ,FabdgtionlDelivery Storm Filter 05A Structural Seel 165 165 17Jun-26 11-Feb-27 PRC1050 Award Structural Steel 20 20 17Jun-26 15Ju1-26 Award Structural Steel - PRC1060 Submittals&Apphaval SWrdual Steel 25 25 16Jul-26 19-Aug-26 Submittals&ApprovalSW uaI Steer PRC1090 FabricationlDelivery,Structural Steel 120 120 20-Aug-26 11-Feb-27 Fabrication/Delivery Structural Steel 08B Glass&Glazing 115 115 17-Jun-26 01-0eo-26 PRC1100 Award Storefront 20 20 17-Jun-26 15-Jul-26 D Award Storefront PRC1110 Submittals&Approval Storefront 25 25 16Ju1-26 19-Aug-26 O Submittals&Approval Storefront PRC1120 FabricationlDelivery Storefront 70 70 20-Aug-26 01-Dec-26 O Fabrication/Delivery Storefront 23A Mee lu nical T 90 90 17Jun-26 22-Oct-26 PRC1130 Award Mechanical 20 20 17Jun-26 15-Jul-26 O Award Mechanical PRC1140 Submittals&Approval Mechanical Units 20 20 16Ju1-26 12-Aug-26 D Submittals&Approval Mechanical Units _ PRC1150 FaltdcationlDelivery Mechanical Units 50 50 13-Aug-26 22-0ct-26 0 FabdcatioNp�liweryMechanical Units 26A Electrical 300 300 17-Jun-26 23-Aug-27 PRC1160 Award Electrical 20 20 17Jun-26 15-Jul26O Award Electrical PRC1171 Submittals&Approval Svritdt Gear 20 20 16-Jul-26 12-Aug-26 D Submittals&Approval Switch Gear PRC1250 Submittals&Approval Generator 20 20 16JuE26 12-Aug-26 D Submittals&Approval Generator PRC1180 Fabrication/Delivery Switch Gear 100 100 13-Aug-26 07-Jan-27 I FabricationlDelivery Switch Sear PRC1260 FabdcationlDelrvery Generator 260 260 13-Aug-26 23-Aug-27 Fabdwtion/Delivery Generator Finish Date: 13-J n-28 een '�°^'eFo' ♦ ♦c ar.�ne, Data Date: 03-Apr-26 Atla' °o'°' ♦ ♦"'� I*� Run Date 13-Apr-2610:56 aaawo Orange County Crisis Diversion Facility(4.3.26p Page 1 of 3 OC Crisis(4.3.26) ♦ ♦svmmarr�,.o 34 Activity I Activity Name Orig emaining Start Finish Dur Duration 2026 2027 2028 _ ar pr ay un u g p ov I Dec jan 1 Fe ar r ay un 1 JulAug bep I Ua NOV Use Jan e ar r 06A Mill—k 105 105 17-Jun-26 13-Nov-26 - PRC1190 Award Mtk fk 20 20 17.Jun-26 15-Juli Award Millwork PRC1200 Submittals&Approval MilMork 25 25 16-Jul-26 19-Aug-26 0 Submittals&Approval Milloork PRC1210 Fabri®tion/Delivery Millwork 60 60 21 13-Ncv-26 I FabrirationlDelivery Millwork 08A Doors,Frames,H ardware f 120 120 17Jun-26 08-0ec-26 PRC1220 Award DFH 20 20 17Jun-26 15-Jul-26 O Award DFH PRC1230 Submittals&Appmval D,FH 30 30 161 26-Aug-26 D Submittals&Approval D,F:H PRC1240 Fabncation/Delivery Doors and Frames 60 60 27-Aug-26 20-Nov-26 D Fabrication/Delivery Doors and Frames ..:...._... --- -- - ..--- PRC 280 Fabription(Delivery Hardware 70 70 27-Aug-26 08-0eo-26 O Fabrication/Delivery Hardware CONSTRUCTION 334 334 281 19-Nov-27 SITEWORK 307 307 281 12-00-27 SITE1000_ Mobilize&Survey 5 5 28-Jul-26 03-Aug-26 LlMobilize&Survey - SITE 1010 Clearfor Erosion Control&Install Sit Fence 51 5 04-Aug-26 10-Aug-26 ❑ Clear for Erosion Coni&Install Silt Fence SITE 1030 Clear and Grub Site 15 15 11-Aug-26 31-Aug-26 O Clear and Grub Site SITE.1020 Excavate and Prep BasinsforEC Compliance 15 15 01-Sep-26 22-Sep-26 D Excavate and Prep Basins for EC Compliance SI7E.1050 Builditg Pad to Subgrade 15 15 30-Sep-26 20-00-26 0 Building Pad to Subgrade SITE.1040 Mass Grading 40 40 23-Sep-26 18-Nov-26 O Mass Grading SITE,1060 Sanitary Sewer 20 20 21-00-26 18-Nov-26 0 Sanitary Sewer SITE.1070 Ste"Drain 20 20 04-Nov-26 01 ® Storm Drain SITE,1110 Retaining V1g 11 15 15 07-Dec-26 28-0eo-26 D Retaining Wall SITE.1080 Waterline 20 20 07-Deo-26 05-Jain27D Wa lame SITE,1120 Stonntech Chamber System 30 30 23-Dec-26 04-Feb-27 D Stormtech Chamber System SITE 1066 Curb&Gutter 20 20 05-Feb-27 04-Mar--27 D Curb&Gutter SITE,1100 Stone&Base Coat Asphalt 20 20 24-Feb-27 23-Mar-27_ O Stone&Base Coat Asphalt SITE.1140 Hardscape 25 25 10-Aug-27 14-Sep-27 D Hardscape SITEA130 Final Paving 10 10 15Sep-27 28-Sep-27 Fnal Paving SITE 1160 Striping 5 5 29Sep-27 05-0ct-27 ❑ Striping SITE,1150 Landscaping 20 20 15-Sep-27 12-00-27 D Landscaping FOUNDATIONS 66 66 21-01 27-Jan-27 FDN.1000 Mobilize Concrete Subcontractor 2 2 21-0ct-26 22-0ct-26 I Mobilize Concrete Subcontractor FDN.1010 SurveylLayoet 5 5 23-01 29-00-26 ❑ Survey/Layout FDN.1020 �dmeter Footings 20 20 30-00.26 01-Dec-26 0 Perimeter Footings FDN.1030 MEP Sleeves!Duct Bank 10 10 02-Deo-26 15-Dec-26O MEP Sleeves/Duct Bank FDN.1040 Spread Footings 20 20 02-Dec-26 30-D-26 _ O Spread Footings I I lstA360 Underground MEP work 20 20 02-Deo-26 K-Deo-26 O Underground MEP work FDN.1050 Stone,Vapor Barrier,Form and Piep&Pour Stab 15 15 31-Dec-26 21Jen-27 _ 1zr1 0 Stone,Vapor Bamer,Fbrm and Prep&Pour gab FDN.1080 Column isolation poufs 4 4 22-Jai27-Jan-270 Column isolation poufs STRUCTURE 35 35 12-Feb-27 01-Apr-27 STIR.1000 Steel Contractor Mobilization/Steel Shakeout 5 5 12-Feb-27 1B-Feb-27 ----' ---- -- -- ---- ■ Steel Contractor Mobilization l Steel Shakeout STR.1010 Erect Structural Steel 20 20 19-Feb-27 18-Mor-27 Erect Structural Steel STR.1030 Joist install 10 10 05-Mar-27 18-Aar-27 - M Joistinstall STR 1040 Install Metal Decking 5 5 19-Mar-27 25-Mar-27 ■ Install Metal Decking STIR 1050 Mise strutal metal install for penetrations 5 5 261 01-Apr-27 ❑ Misc strutal metal install for penetrations _ BUILDING ENCLOSURE 105 105 26-Mar-27 23-Aug-27 -- --- ----FAC 1000 Exterior Framing 30 30 26-Mar-27 06-May-27 EMedor Framing FAC 1010 Roofing Install 30 30 16-Apr-27 27-May-27 D Roofing Install FAC 1020 Sheathing 15 15 07-May-27 27-May-27 M Sheathing FAC.1030 Fluid Applied Waterproofing 10 10 16-May-27 01-Jun-27 _ -I Fluid Applied Waterproofing FAC.1040 Exterior Door Frame Installation 10 10 02Jun-27 15-Jun-27 M Extenor Door Fromelnstallation FAC.1060 Rigid Insulation Install 15 15 28-May-27 1"un•27 0 Rigid Insulation Install FAC.1060 ZStud install15 15 28-May-27 18-Jun-27 © ZStud install FAC.1130 Storefront antl Glazing _ 30 30 02Jun-27 14-Jul-27 D Storefront and Glazing FAC.1070 Stone Stacked Veneer 25 25 21-Jun-27 21 C= Stone Stacked Veneer Finish Date: 13-J n-28 Data Date: 03-Apr-26 Run Date 13-Apr-2610:56 aaawo Orange County Crisis Diversion Facility(4.3.26) Page 2 of 3 D a�s.aw OC Crisis(4.3.26) i• r'�R°" 1Nvk ♦ ♦svmmar ..o 35 Acivty ID Activity Name Orig emainingStart Finish Dur Duration 2026 20272028 ar pr ay unJulAug pNOVDec an 1-eFT - r ay un 1 JulAug[bep ov ec n ME I mar Apr FAC 1100 Fiber cement panel 30 30 21Jun-27 02-Aug-27 D Fiber cement panel FAC 1080 Thin Bride Wreer 25 25 06Ju1-27 09-Aug-27 Thin Brick Wneer FAC.1120 Coping install 10 10 10-Aug-27 23-Aug-27 O Coping install INTERIOR CONSTRUCTION 167 167 26-Mar-27 IMcv-27 1 St.1000 MEPFPI FA Ove rte ad Rwgh In 50 50 26-Mar-27 04-Jun 27 0 MEPFP I FA Overhead Rough In 1st.1380 Set Electrical Gear 5 5 28-May-27 04-Jun-27 ❑ Set Electrical Gear 1 st.1350 Electrical Gear l Equipment Startup 5 507Jun-27 11-Jun-27 U Electrical Gear l Equipment Startup 1st.1010 Interior Framing 40. 40 23-Apr-27 18-Jun-27 O Intedor Framing lsL1020 MEP In-ftll Rough In �_ 30! 30 07-May-27 18-Jun-27 0 MEP In-VrkII Rough In _ 20 02Jun-27 29-Jun-27 - Hang Drywall -- - - -- 1st.1030 Hang Drywall 20� � ' 1at.1320 HVAC Controls-Point to Point I Checkout 151 15 21-Jun-27 12-Jul-27 0 HVAC Controls-Pcintle Point)Checkout 1stAm Drywall Finishing 251 25 161 21-Jul-27 Drywall Finishing 1st1060 Prime and First Coat of Paint 15 15 OSJuI-27 2$-Jul-27 M Prime and First Coat of Paint 1st.1240 Swing Interior Doors&Install Hardware 15 15 22-Jul-27 11-Aug-27 : : O Swing Interior Doors&Install Hardware I at.1090 Install Tile Flooring 20 20 16-Jul-27 12-Aug-27 O Install Tie Flooring 1 L167 Ceiling Qid Install 15 15 29-Jul2718 Aug-27 Ceiling Grid Install 1 st.1066 Instak Speaa@des 15 15 2"u1-27 18 ug-27 O Install Specialties 1st.1100 Instar LVr Flooring 25 25 29-Jul-27 01-Sep-27 Install LVr Flooring t at.1250 Interior Door Glatting 15 15 12-Aug-27 01-Sep-27 D Interior door Glazing 1st.1130 Install Light Fudures 20 20 1 01 Sep-27 ! O Install Lght FlMures 1st.1110 Ceiling Tile Installation 5 5 02-Sep-27 0-9-Sep-27 ❑ Ceiling Tile Installation 1 St.1120 Install Millwork&Countertops 25 25 12-Aug-27 16Sep-27 Install Milvvorik&Countertops 1 st.1290 FA Device Trim Out&Testing 10 10 10-Sep-27 23-Sep-27 O FA Device Tran Out&Testing 1 st 1140 Final Point Up 10 10 17Sep-27 30-Sep-27 Final Point Up 1st.1180 Bathroom Rxtures_Accessones 10 10 17Sep-27 30-Sep-27 : 0 Bathroom FiAuresAceessores 1st-1300 MEP Ceiling Trim Out 20 20 10Sep-27 07-0Ct-27 MEP Ceiling Tom Cul lst1330 Sprinkler Tom Out 20 20 10Sep-27 07-W-27 Sprinkler Trim Out 1 St.1150 Final Paint 15 15 01-Oct-27 21-Oct-27 M Final Paint 1 st.1160 MEP Nall Trip Out 10 10 15-Oct-27 28-0ct-27 = MEP Mall Trim Out 1st.1190 Install We IFC aredrgs 5 5 22-0c1-27 28-0ct-27 _ - - ❑ Install ft llCove rims '. 1 st.1270 Access Control Tiimout 5, 5 22-0c1-27 2B-Oct-27 ❑ Access Control Trimout 1st1370 Door Hardvare and Card Readers 51 5 22-0et-27 21 ❑ Door Hardware and Card Readers 1at.1340 'Test and Balance 5 5 22-0ct-27 28-0ct-27 ❑ Test and Balance lstA170 Appliance install _ 51 5 29-0ct-27 04-Nov-27 _ ■ Appliance install 1 sL 1200 Instal Carpet/Rubber Flooring 10 10 22-0d-27 04-Nov-27 M Install CarpeVRubber Flooring 1 st.1220Gilbane Punch 10 10 29-0d-27 12-Nov-27 O Gllbane Punch 1 at.1396— Final Inspections 5 5 05-Nov-27 12-Nov-27 ■ Final Inspections 1sL1230 Final dean 5 5 151 1"ov-27 0 Fnaldean ROODEXITRIOR WORK r A1000 Set Rooftop Equipment 5 5 28-May-27 04Jun-27 : ❑ Set Rooftop Equipment A1010 Install screen V4eh 10 10 07Jun 2718Jun-27 Install screen Nhl A1050 RTU Startup Q 5 5 14-Juni 18-Jun-27 D RTU Startup A1060 Set Generator)Tie in 9 15 15 24-Aug-27 14-Sep-27D Set Generator Tie in SYSTEMS TESTING/COMMISS_IONINGICLOSEOUT 35 35 22-0d-27 14-Dec-27 SYS,1 coo HVAC Commissioning � 5 5 22-0d-27 28-Oct 27 ❑ HVAC Commissioning SYS,1010 Orange County Regulatory Reviekv&Inspections-By Owner II 20 20 15-Nov-27 14-Dec-27 - O Orange County Regulatory Finish Date: 13-Jan-28 Data Date: 03-Apr-26 Run Date: 13-Apr-2610:56 rcwwcm Orange County Crisis Diversion Facility(4.3.26) Page 3 of 3 OC Crisis(4.3.26) ♦ ♦s maw 36 Printed on Thu May 21, 2026 at 10:45 am EDT Job#:)10801.000 Orange County Crisis Diversion Facility 901 Waterstone Drive Hillsborough, North Carolina 27278 Gilbane Building Company Current Drawings Drawing No. Drawing Title Revision Drawing Date Received Date Set Architectural A201 LEVEL 1 DIMENSION FLOOR PLAN 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) A211 LEVEL 1 ANNOTATION FLOOR PLAN 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) A221 LEVEL 1 EQUIPMENT FLOOR PLAN 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) A231 ROOF PLAN-OVERALL 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) A300 BUILDING ELEVATIONS 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) A301 BUILDING ELEVATIONS-FENCE AND ENLARGED ART PANELS 1 04/20/2026 04/20/2026 Addendum 01(04/20/26) A350 BUILDING SECTIONS 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) A400 PARTITION TYPES 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) A401 PARTITION DETAILS 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) A402 PARTITION DETAILS-BLOCKING 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) A450 WALL SECTIONS 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) A451 WALL SECTIONS 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) A452 WALL SECTIONS 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) A453 WALL SECTIONS 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) A454 WALL SECTIONS 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) A455 WALL SECTIONS 1 04/20/2026 04/20/2026 Addendum 01(04/20/26) A601 LEVEL 1 REFLECTED CEILING PLAN-OVERALL 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) A700 TYPICAL FIXTURE AND ACCESSESSORY LEGENDS 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) A701 ENLARGED FLOOR PLAN AND INTERIOR ELEVATIONS 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) A702 ENLARGED FLOOR PLAN AND INTERIOR ELEVATIONS 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) A703 ENLARGED FLOOR PLAN AND INTERIOR ELEVATIONS 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) A704 ENLARGED FLOOR PLAN AND INTERIOR ELEVATIONS 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) A705 ENLARGED FLOOR PLAN AND INTERIOR ELEVATIONS 1 04/20/2026 04/20/2026 Addendum 01(04/20/26) A800 TYPICAL CASEWORK TYPES 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) A801 TYPICAL CASEWORK DETAILS 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) A802 TYPICAL CASEWORK DETAILS 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) A810 EXTERIOR PLAN DETAILS 1 04/20/2026 04/20/2026 Addendum 01(04/20/26) A811 EXTERIOR PLAN DETAILS 1 04/20/2026 04/20/2026 Addendum 01(04/20/26) A820 INTERIOR PLAN DETAILS 0 03/25/2026 03/25/2026 100%CD Set(03/25/26) A830 TYPICAL CASEWORK TYPES 0 03/25/2026 03/25/2026 100%CD Set(03/25/26) A831 TYPICAL CASEWORK DETAILS 11 04/20/2026 1 04/20/2026 Addendum 01(04/20/26) A840 CEILING DETAILS 0 03/25/2026 03/25/2026 100%CD Set(03/25/26) A900 DOOR PANELS,FRAME TYPES,DETAILS&SCHEDULES 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) A901 GLAZING SYSTEMS-TYPES&SCHEDULES 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) C0.0 OVERALL SITE PLAN 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C0.1 AREA MAP 0 03/25/2026 03/25/2026 1 Civil 100%Pricing Set(03/25/26) Page 1 of 4 37 Printed on Thu May 21, 2026 at 10:45 am EDT Job#:)10801.000 Orange County Crisis Diversion Facility 901 Waterstone Drive Hillsborough, North Carolina 27278 Gilbane Building Company Drawing No. Drawing Title Revision Drawing Date Received Date Set C1.0 EXISTING CONDITIONS PLAN 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) Cl.l OVERALL DEMOLITION PLAN 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C2.0 EROSION CONTROL PLAN STAGE 1 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C2.1 EROSION CONTROL PLAN STAGE II 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C2.2 NPDES GROUND STABILIZATION PLAN 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C2.3 TREE PROTECTION PLAN 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C3.0 SITE PLAN 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C3.1 STAKING PLAN 0 03/252026 03/25/2026 Civil 100%Pricing Set(03/25/26) C3.2 MATERIALS PLAN 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C3.3 VEHICLE TRACKING PLAN 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C3.4 WATERSTONE DRIVE PLAN AND PROFILE 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C3.5 PROPOSED PUBLIC STREET PLAN AND PROFILE 01 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C3.6 OVERALL WATERSTONE DRIVE CROSS SECTION MAP 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/2526) C3.7 INTERSECTION SIGHT DISTANCE PROFILE-DRIVEWAY 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C3.8 INTERSECTION SIGHT DISTANCE PROFILE-DRIVEWAY 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C3.9 DRIVEWAY STEM PROFILE 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C4.0 OVERALL UTILITY PLAN 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C4.1 WATERLINE PROFILE 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C4.2 SANITARY SEWER PROFILE 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C5.0 OVERALL GRADING PLAN 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C5.1 OVERALL STORM DRAINAGE PLAN 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C5.2 STORM SEWER PROFILES 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C5.3 UG DETENTION SYSTEM AND STORMFILTER PLAN AND PROFILE 01 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C5.4 UG DETENTION SYSTEM AND STORMFILTER PLAN AND PROFILE 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C5.5 STORM DRAINAGE SCHEDULE 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C5.6 PRE-DEVELOPMENT HYDROLOGY PLAN 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C5.7 POST DEVELOPMENT HYDROLOGY PLAN 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C5.8 SPOT GRADING PLAN 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C6.0 EROSION CONTROL NOTES AND DETAILS 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C6.1 EROSION CONTROL NOTES&DETAILS 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C6.2 EROSION CONTROL NOTES&DETAILS 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C6.3 SITE NOTES&DETAILS 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C6.4 SITE NOTES&DETAILS 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C6.5 UTILITY NOTES&DETAILS 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/2526) C6.6 UTILITY NOTES&DETAILS 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C6.7 UTILITY NOTES&DETAILS 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C6.8 STORM DRAINAGE NOTES&DETAILS 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C6.9 UG DETENTION NOTES&DETAILS 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C6.10 UG DETENTION NOTES&DETAILS 0 1 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C6.11 UG DETENTION NOTES&DETAILS 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) C6.12 UG DETENTION NOTES&DETAILS 0 03/25/2026 03/25/2026 Civil 100%Pricing Set(03/25/26) Page 2 Of 6 38 Printed on Thu May 21, 2026 at 10:45 am EDT Job#:)10801.000 Orange County Crisis Diversion Facility 901 Waterstone Drive Hillsborough, North Carolina 27278 Gilbane Building Company Drawing No. Drawing Title Revision Drawing Date Received Date Set E000 LEGEND AND NOTES 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) E001 ONE LINE-DIAGRAM 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) E050 OVERALL SITE PLAN 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) E051 SITE PLAN-NORTH 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) E052 SITE PLAN-SOUTH 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) E060 GROUNDING PLAN 0 04/20/2026 04/20/2026 Addendum 01(04/20/26) E061 LIGHTNING PROTECTION PLAN 0 04/20/2026 04/20/2026 Addendum 01(04/20/26) E200 POWER FLOOR PLAN 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) E201 POWER ROOF PLAN 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) E300 LIGHTING FLOOR PLAN 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) E400 SYSTEMS FLOOR PLAN 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) E500 FIRE ALARM FLOOR PLAN 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) E501 BDA SYSTEMS PLAN 1 04/20/2026 04/20/2026 Addendum 01(04/20/26) E600 EQUIPMENT CONNECTION FLOOR PLAN 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) E601 EQUIPMENT CONNECTION ROOF PLAN 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) E700 PV SYSTEM ROOF PLAN 1 04/20/2026 04/20/2026 Addendum 01(04/20/26) E701 PV SYSTEM ONE-LINE AND DETAILS 1 04/20/2026 04/20/2026 Addendum 01(04/20/26) E800 SITE DETAILS 1 04/20/2026 04/20/2026 Addendum 01(04/20/26) E801 GROUNDING DETAILS 1 04/20/2026 04/20/2026 Addendum 01(04/20/26) E802 ELECTRICAL DETAILS 1 04/20/2026 04/20/2026 Addendum 01(04/20/26) E805 FIRE ALARM MATRIX AND DETAILS 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) E900 SCHEDULES 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) E901 SCHEDULES 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) E902 SCHEDULES 2 04/20/2026 04/20/2026 Addendum 01(04/20/26) Fire Protection FP000 FIRE PROTECTION LEGEND,NOTES,&SYSTEM DIAGRAMS 1 0325/2026 03/25/2026 100%CD Set(0325/26) FP200 FIRE FLOOR FIRE PROTECTION PLAN 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) G000 COVER 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) G001 DRAWING LIST&ABBREVIATIONS 2 04/20/2026 04/20/2026 Addendum Ol(04/20/26) G002 NORTH CAROLINA-2018 APPENDIX B-BUILDING CODE SUMMARY 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) G101 LEVEL 1 LIFE SAFETY PLAN-OVERALL 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) G201 I LEVEL 1 RISK ASSESSMENT PLAN 1 21 04/20/2026 1 04/20/2026 jAddendim Ol(04/2026) Interior 1000 INTERIORS GENERAL 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) 1200 FLOOR FINISH PLAN 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) 1300 FLOOR PATTERNING PLAN 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) 1400 WALL PROTECTION PLAN 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) 1500 FURNITURE PLAN 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) Landscape L1.0 OVERALL PLANTING PLAN 01 03/25/2026 1 03/25/2026 1 Civil 100%Pricing Set(03/25/26) Ll.l PLANTING NOTES&DETAILS 101 03/25/2026 1 03/25/2026 1 Civil 100%Pricing Set(03/25/26) Page 3 Of 6 39 Printed on Thu May 21, 2026 at 10:45 am EDT Job#:)10801.000 Orange County Crisis Diversion Facility 901 Waterstone Drive Hillsborough, North Carolina 27278 Gilbane Building Company Drawing No. Drawing Title Revision Drawing Date Received Date Set L3.0 ENHANCED PLANTING PLAN 01 03/25/2026 1 03/25/2026 Civil 100%Pricing Set(03/25/26) Mechanical H000 HVAC SYMBOLS LEGEND AND CONTRACTOR NOTES 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) H2O0 FIRST FLOOR HVAC PLAN 2 03/25/2026 03/25/2026 100%CD Set(03/25/26) H2O1 ROOF HVAC PLAN 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) H500 HVAC CONTROLS 0 03/25/2026 03/25/2026 100%CD Set(03/25/26) H800 HVAC DETAILS 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) H900 SCHEDULES 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) Plumbing P000 PLUMBING LEGEND,NOTES,&SYSTEM DIAGRAMS 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) P200 FIRST FLOOR WASTE PIPING PLAN 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) P201 ROOF STORM AND WASTE PIPING PLAN 0 03/25/2026 03/25/2026 100%CD Set(03/25/26) P300 FIRST FLOOR DOMESTIC PIPING PLAN 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) P301 ROOF DOMESTIC WATER PIPING NEW WORK PLAN 0 03/25/2026 03/25/2026 100%CD Set(03/25/26) P700 WASTE AND VENT RISER DIAGRAM 01 03/25/2026 1 03/25/2026 1100%CD Set(03/25/26) P701 DOMESTIC WATER RISER DIAGRAM 0 03/25/2026 1 03/25/2026 100%CD Set(03/25/26) P800 DETAILS 01 03/25/2026 1 03/25/2026 100%CD Set(03/25/26) P801 DETAILS 01 03/25/2026 1 03/25/2026 1100%CD Set(03/25/26) Structural 5200 FOUNDATION PLAN 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) S201 CANOPY FRAMING PLAN 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) S202 ROOF FRAMING PLAN 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) 5300 COLUMN SCHEDULE 1 03/25/2026 03/25/2026 100%CD Set(03/25/26) 5401 SECTIONS AND DETAILS 0 03/25/2026 03/25/2026 100%CD Set(03/25/26) 5800 TYPICAL DETAILS 111 03/25/2026 1 03/25/2026 1100%CD Set(03/25/26) 5900 I STRUCTURAL NOTES 111 03/25/2026 1 03/25/2026 100%CD Set(03/25/26) Page 4 Of 4 40 Printed on Thu May 21, 2026 at 10:46 am EDT job#:)10801.000 Orange County Crisis Diversion Facility 901 Waterstone Drive Hillsborough, North Carolina 27278 Gilbane Building Company Current Specifications Number Description Revision Issued Date Received Date Set 00-Procurement and Contracting Requirements 00 31 00 Available Project Information 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 00 50 00 Contracting Forms and Supplements 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 0052 00 Agreement Form 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 0061 13 Contractor's Affidavit and Partial Release of Claims and Liens for Progress Payment 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 0061 16 Contractor's General Warranty 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 0061 19 Asbestos-Free Warranty 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 00 63 25 Substitution Form-During Construction for Cause 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 0072 00 General Conditions 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 000110 Table of Contents 1 04/20/26 04/20/26 Addendum 01 01-General Requirements 0102 00 General Sitework Requirements 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 1000 Summary 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 20 00 Price and Payment Procedures 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 0121 00 Allowances 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 21 10 Sitework Allowances 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 22 00 Unit Prices 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 2300 Alternates 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 25 00 Substitution Procedures 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 2657 Pricing of Construction Contract Change Orders 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 3000 Administrative Requirements 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 3100 Project Management Coordination 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 3200 Construction Progress Documentation 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 40 00 Quality Requirements 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 45 33 Code Required Special Inspections 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 5000 Temporary Facilities and Controls 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 5639 Temporary Tree and Plant Protection 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 60 00 Product Requirements 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 7300 Execution 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 7419 Construction Waste Management and Disposal 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 7700 Closeout Procedures 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 7800 Closeout Submittals 10 03/25/26 03/25/26 Orange County Crisis Diversion Center 01 7900 Demonstration and Training 10 03/25/26 03/25/26 Orange County Crisis Diversion Center 03-Concrete 03 05 16 Underslab Vapor Barrier 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 03 3000 Cast-in-Place Concrete 1 04/20/26 04/20/26 Addendum 01 04-Masonry Page 1 of 5 41 Printed on Thu May 21, 2026 at 10:46 am EDT Job#:)10801.000 Orange County Crisis Diversion Facility 901 Waterstone Drive Hillsborough, North Carolina 27278 Gilbane Building Company Number Description Revision Issued Date Received Date Set 04 26 16 Adhered Masonry Veneer 10 03/25/26 03/25/26 Orange County Crisis Diversion Center 04 73 00 1 Manufactured Stone Masonry 10 03/25/26 03/25/26 1 Orange County Crisis Diversion Center 05-Metals 05 12 00 Structural Steel Framing 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 0512 13 Architecturally-Exposed Structural Steel Framing 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 05 21 00 Steel Joist Framing 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 0531 00 Steel Decking 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 05 40 00 Cold-Formed Metal Framing 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 05 50 00 Metal Fabrications 10 03/25/26 03/25/26 Orange County Crisis Diversion Center 0551 33 1 Metal Ladders 10 03/25/26 03/25/26 1 Orange County Crisis Diversion Center 06-Wood,Plastics,and Composites 06 10 00 Rough Carpentry 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 06 16 43 Exterior Gypsum Sheathing 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 06 41 00 Architectural Wood Casework 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 07-Thermal and Moisture Protection 0705 53 Fire and Smoke Assembly Identification 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 0721 00 Thermal Insulation 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 0721 10 Mineral Wool Insulation 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 0721 19 Foamed-in-Place Insulation 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 07 25 00 Weather Barriers 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 07 42 00 Art Panels 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 07 42 43 Fire Cement Panels 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 07 46 16 Aluminum Soffits 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 07 5400 Thermoplastic Membrane Roofing 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 07 6200 Sheet Metal Flashing and Trim 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 07 71 00 Roof Specialties 0 04/20/26 04/20/26 Addendum 01 07 7200 Roof Accessories 0 04/20/26 04/20/26 Addendum 01 07 8400 Firestopping 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 07 91 00 Preformed Joint Seals 0 04/20/26 04/20/26 Addendum 01 07 92 00 Joint Sealants 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 08-Openings 08 11 13 Hollow Metal Doors and Frames 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 08 14 16 Flush Wood Doors 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 08 31 00 Access Doors and Panels 1 04/20/26 04/20/26 Addendum 01 08 33 13 Coiling Counter Doors 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 08 43 13 Aluminum-Framed Storefronts 1 04/20/26 04/20/26 Addendum 01 08 44 39 Behavioral Health Storefront 0 04/20/26 04/20/26 Addendum 01 08 7100 Door Hardware 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 08 80 00 Glazing 0 04/20/26 04/20/26 Addendum 01 0888 13 Fire Rated Glazing 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 1088854 Security Glazing-Behavioral Health 0 03/25/26 03/25/26 Orange County Crisis Diversion Center Page 2 of 5 42 Printed on Thu May 21, 2026 at 10:46 am EDT Job#:)10801.000 Orange County Crisis Diversion Facility 901 Waterstone Drive Hillsborough, North Carolina 27278 Gilbane Building Company Number Description Revision Issued Date Received Date Set 09-Finishes 0905 61 Common Work Results for Flooring Preparation 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 0921 16 Gypsum Board Assemblies 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 09 30 00 Tiling 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 09 51 00 Acoustical Ceilings 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 09 54 26 Suspended Wood Ceilings 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 0965 00 Resilient Flooring 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 0967 00 Fluid-Applied Flooring 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 0968 13 Tile Carpeting 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 0972 00 Wall Coverings 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 0991 13 Exterior Painting 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 0991 23 1 Interior Painting 10 03/25/26 03/25/26 Orange County Crisis Diversion Center 09 96 00 High Performance Coatings 10 03/25/26 03/25/26 1 Orange County Crisis Diversion Center 10-Specialties 10 14 00 Signage 0 04/20/26 04/20/26 Addendum 01 1021 23 Cubicle Curtains and Track 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 10 26 00 Wall,Corner and Door Protection 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 10 44 00 Fire Protection Specialties 1 04/20/26 04/20/26 Addendum 01 1051 29 Phenolic Lockers 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 1082 13 Rooftop Equipment Screens 10 04/20/26 04/20/26 Addendum 01 11-Equipment 11 40 00 1 Foodservice Equipment 10 04/20/26 04/20/26 jAddendurn 01 12-Furnishings 12 2400 Window Shades 10 03/25/26 03/25/26 Orange County Crisis Diversion Center 12 3600 Countertops 10 03/25/26 03/25/26 1 Orange County Crisis Diversion Center 21-Fire Suppression 21 0500 Common Work Results for Fire Suppression 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 21 0523 General-Duty Valves for Water-Based Fire Suppression Piping 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 21 0548 Vibration and Seismic Controls for Fire Suppression Piping and Equipment 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 21 0553 Identification for Fire Suppression Piping and Equipment 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 21 1300 Fire-Suppression Sprinkler Systems 1 04/20/26 04/20/26 Addendum 01 22-Plumbing 22 05 17 Sleeves and Sleeve Seals for Plumbing Piping 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 22 0523 General-Duty Valves for Plumbing Piping 1 04/20/26 04/20/26 Addendum 01 22 05 29 Hangers and Supports for Plumbing Piping and Equipment 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 22 05 48 Vibration and Seismic Controls for Plumbing Piping and Equipment 0 04/20/26 04/20/26 Addendum 01 22 05 53 Identification for Plumbing Piping and Equipment 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 2207 19 Plumbing Piping Insulation 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 22 1005 Plumbing Piping 1 04/20/26 04/20/26 Addendum 01 22 1006 Plumbing Piping Specialties 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 1223000 Plumbing Equipment 0 03/25/26 03/25/26 Orange County Crisis Diversion Center Page 3 of 5 43 Printed on Thu May 21, 2026 at 10:46 am EDT job#:)10801.000 Orange County Crisis Diversion Facility 901 Waterstone Drive Hillsborough, North Carolina 27278 Gilbane Building Company Number Description Revision Issued Date Received Date Set 22 40 00 Plumbing Fixtures 10 03/25/26 03/25/26 Orange County Crisis Diversion Center 22 46 00 1 security Plumbing Fixtures 11 04/20/26 04/20/26 jAddenclum 01 23-Heating,Ventilating,and Air Conditioning(HVAC) 23 00 00 General Provisions for Mechanical Work 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 23 00 02 Mechanical and Electrical Coordination 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 2305 13 Common Motor Requirements for HVAC Equipment 1 04/20/26 04/20/26 Addendum 01 2305 17 Sleeves and Sleeve Seals for HVAC Piping 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 2305 29 Hangers and Supports for HVAC Piping and Equipment 1 04/20/26 04/20/26 Addendum 01 23 05 48 Vibration and Seismic Controls for HVAC 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 2305 50 Wind Restraint for HVAC Systems 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 2305 53 Identification for HVAC Piping and Equipment 1 04/20/26 04/20/26 Addendum 01 2305 93 Testing,Adjusting and Balancing for HVAC 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 2307 13 Duct Insulation 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 2307 16 HVAC Equipment Insulation 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 2307 19 Piping Insulation 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 23 09 00 Building Automation System 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 23 09 34 Variable-Frequency Motor Controllers 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 23 23 00 Refrigerant Piping 1 04/20/26 04/20/26 Addendum 01 23 31 00 HVAC Ducts and Casings 1 04/20/26 04/20/26 Addendum 01 23 33 00 Air Duct Accessories 1 04/20/26 04/20/26 Addendum 01 23 34 23 HVAC Power Ventilators 1 04/20/26 04/20/26 Addendum 01 23 36 00 Air Terminal Units 1 04/20/26 04/20/26 Addendum 01 23 3700 Air Outlets and Inlets 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 23 7413 Packaged Outdoor Central-Station Air-Handling Units 1 04/20/26 04/20/26 lAddendum 01 23 8126.13 1 Small-Capacity Split-System Air Conditioners 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 23 82 00 Convection Heating and Cooling Units 0 032526 03/25/26 Orange County Crisis Diversion Center 26-Electrical 26 05 00 Common Work Results for Electrical 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 2605 19 Low-Voltage Electrical Power Conductors and Cables 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 26 05 26 Grounding and Bonding for Electrical Systems 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 26 05 29 Hangers and Supports for Electrical Systems 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 26 05 33.13 Conduit for Electrical Systems 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 26 05 33.16 IBoxes for Electrical Systems 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 26 05 53 Identification for Electrical Systems 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 26 05 73 Power System Studies 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 26 09 23 Lighting Control Devices 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 26 24 13 Switchboards 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 26 24 16 Panelboards 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 2627 13 Electricity Meeting 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 26 27 26 1wiring Devices 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 2628 13 IFuses 0 03/25/26 03/25/26 Orange County Crisis Diversion Center Page 4 of 5 44 Printed on Thu May 21, 2026 at 10:46 am EDT Job#:J10801.000 Orange County Crisis Diversion Facility 901 Waterstone Drive Hillsborough, North Carolina 27278 Gilbane Building Company Number Description Revision Issued Date Received Date Set 2628 16 Enclosed Switches and Circuit Breakers 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 2629 13 Enclosed Controllers 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 2631 00 Photovoltaic Collectors 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 2632 13 Engine Generators 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 26 36 00 Transfer Switches 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 26 43 00 Surge Protective Devices 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 2651 00 Interior Lighting 0 03/25/26 03/25/26 1 Orange County Crisis Diversion Center 27-Communications 27 1000 Structured Cabling 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 27 1100 Communications Equipment Room Fittings 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 2751 29.17 Two-Way Radio Communication Enhancement Systems-Fiplex by Honeywell 10 03/25/26 03/25/26 1 Orange County Crisis Diversion Center 28-Electronic Safety and Security 28 1000 Access Control 0 03/25/26 03/25/26 Orange County Crisis Diversion Center 28 20 00 Video Surveillance 1 04/20/26 04/20/26 Addendum 01 28 46 00 Fire Detection and Alarm 1 04/20/26 04/20/26 Addendum 01 31-Earthwork 31 1000 Site Clearing 0 03/25/26 03/25/26 Civil Specifications 31 2000 Earthwork 0 03/25/26 03/25/26 Civil Specifications 3125 00 Erosion Control 0 03/25/26 03/25/26 Civil Specifications 31 31 16 Termite Control 0 03/25/26 03/25/26 Civil Specifications 32-Exterior Improvements 32 12 16 Asphalt Paving 0 03/25/26 03/25/26 Civil Specifications 32 13 13 Site Concrete 0 03/25/26 03/25/26 Civil Specifications 32 17 00 Pavement Markings,Signs and Specialties 0 03/25/26 03/25/26 Civil Specifications 32 9200 Lawns and Grasses 0 03/25/26 03/25/26 Civil Specifications 32 93 00 Exterior Plants 0 03/25/26 03/25/26 Civil Specifications 33-Utilities 33 1000 Exterior Water System 0 03/25/26 03/25/26 Civil Specifications 33 30 00 Sanitary Sewerage Utilities 0 03/25/26 03/25/26 Civil Specifications 33 41 00 Storm Utility Drainage Piping 10 03/25/26 03/25/26 ICivil Specifications Page 5 of 5 45 co sLLpIMNpIox=AFTp1ApEpFpene°poE.11Arv�M—.I.NpwAL1F FR NEW LEFT TURN LANE ---------- ITH TAPER PER TIA PBOF£RTAUNE.E,L. ED..0 ANI, Const _ — — �pAxFpMxrvreprvEpFaoMFAEOFp FrvprFrarEp.xplpMExso„s,' owwGECOI Ilbane Job site RECOMMENDATIONS rv[Ere or nrvv oiscvEva+ciEs rereioa To cpMUExcmc nrvv rvrnrx<wmvmA .. CpN,R,Croap�w�,FF.pvFaF�A„pMFxsprvp�rLrESM,pp„ApEpPPprerp ppNp,nupTpry rvoTF.Exp fence ce: a exif ,. ---- NNEDBLC 1 SEurm corvsmucron. ING WATERO s..rw*m nx scEVEnnr goon xccorv+s*ocrou nnp oaoe*Avx�eitnxn ue,E _____ nEnMns Foa oEEsrcE siouvnm ANoroawAsre ABEAs. TIMMONS GROUP NEW HiGNTINRN_ANE WITH TAP ER _ __—_----- s, corvrrencrore isxERIIAT.srorvsis,E voxury UNumxp cars Uu U.arvosrvwL�. TA RECOMMENDATI ixuciwx cnv2non rxE corvmAcron sxAu prRYA I.— L,la„IpnnR�„-0oo�,oAETpxAVE IpiNo l� xER�,AcmPmxxm E Tp .I _IN_ p OWNTR _-_____z� - ,s,,,x1Iw .x. .11E.PWAsxn..r.srpx.,�N—snAI oA;;GICGxn LIMIT CAUIS OIVFASION CANTS, wx sou nccorep�cE wrtn TnE owNERS ONGoI irvTEnnu xp x 1 E PEA ry n .. orvs sono eE cooxoiNnrmmrx rnE OwNEre ATLEAsr xs xouxsxxlox Ta TRE I - 1 TMI SLOPoRTfELENGIH OFiHE rE.coN6muc.P.... . FAMSmONft55 BEEN IN- ro „I 1 1 I _ FI, H ory rxeP.wcm 1. 1 Ew aILE Es IBE H usn ntuaa I m�Ao vcnxxpv l1 1vFT p0 cN O71 sem' i °a uxrrs wx rzn rxE xosEoxrvsxo I ALL Em Exox xor No corm aEMcoS AN s,\Y El A 1 y PN, 98736 3]1 a %ico nml, \ `\ C ZONING:WATERSTONESOUiHPDO M� o 1 USE,VACANT TABLE ster �-t .atI1,01 a,a stretP,od fle A a � � L IN:98735-8 (/ Z NNG wix.�Hm�ia a.. VA CAN ANL � `kip fc T\ 1 REfNW LL f 5 , /- DESIGN BY OTHERS _ I EDPROPERTY NE 5 I I � z,a..rsx„o l Restrooms 4M E — — — c O SIBUCTICI-TS — �� pEre mFpp SFE �\ PROPo9IGHTF�PY8LCE. RD Park, Pedes , Tpwxo,nrLEpoprepppn,MlTs 1 I DRv w FUNCTION Nqs Construction lay alkways ore EW x. o L,a LnA.xoTEOE L down area I j { TURNARONNOFo, PIN 987 2713 DEAD ENG P_C ONING:RI / I STREET.p4Y USE FBESIDE— FUTURE STREET 1 Ilmm eoxaxsTEsmxwAu CONNECTION MABONRY DUMP TER 0 S 'yi / I ENCLOSURE TO MATCH BU LO u ( DES GN BY ARCHITECT corvcxsTs xnvEMwr \v'' O z � N PIN 98731117” s I” Y AL A zoN N . � oa.�. F E;1 I= USE SF HEs oENL AL NOt I ®I \ OPEN SPACE ow Ac r—z xExME*En se nEAw oNrv..9xnA.rxAVEMExr I xe oozl � r � o —,., N9xTppirA=nnEHT ----_-- Al --- _------�- -- lsuva px AssxowN SITE PLAN g o arc en _ s C3.0 46 Orange County Crisis Diversion JINC= Incomplete INR = Not Required BID TABULATION I =Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 01A Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Site Services Bid Time: 1:OOPM Estimate Amount: $1,161,910.00 2 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 NEXT150 WC Construction NBS Bidder Name Base Bid Amount $ 448,004.00 $ 556,000.00 $ - Estimate $ 1,161,910.00 $ 1,161,910.00 $ 1,161,910.00 Variance $ (713,906.00) $ (605,910.00) $ (1,161,910.00) Allocations: 1 Exterior Cleaning $ 50,000.00 $ 50,000.00 2 Street Sweeper $ 50,000.00 $ 50,000.00 3 Rough Cleaning $ 50,000.00 $ 50,000.00 4 Temp Cooling/Heating for 3 Months $ 30,655.00 $ 12,000.00 5 ITruck Wheel Wash $ 46,903.00 $ 9,000.00 Total Bid with Trade Allocations $ 675,562.00 $ 727,000.00 $ - Bid Inclusion Items: Addendum#1 (Yes/No) Y Y Y Supplement#1 (Yes/No) Y Y Y Supplement#2(Yes/No) Y Y Y Supplement#3(Yes/No) Y Y Y Supplement#4(Yes/No) Y Y Y Supplement#5(Yes/No) Y CI&E Y HUB Affidavits Provided (Yes/No/INC) NR NR NR Bid Bond Provided (Yes/No) NR NR NR Signed (Yes/No) Y Y Y 47 Orange County Crisis Diversion INC = Incomplete JNR = Not Required BID TABULATION .=Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 01B Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Final Cleaning Bid Time: 1:OOPM Estimate Amount: $21,146.00 4 Number of Bidders Bids Received: Bidder#1 B Bidder#3 Bidd' :#4 Sparkle&Shine Protege Next150 Classic Contracting Bidder Name Base Bid Amount $ 18,435.28 $ 14,280.00 $ 51,985.00 $ 18,777.77 Estimate $ 21,146.00 $ 21,146.00 $ 21,146.00 $ 21,146.00 Variance $ (2,710.72) $ (6,866.00) $ 30,839.00 $ (2,368.23) Allocations: 1 Additional Cleaning $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 Total Bid with Trade Allocations $ 23,435.28 $ 19,280.00 $ 56,985.00 $ 23,777.77 Bid Inclusion Items: Addendum#1 (Yes/No) Y Y Y Supplement#1 (Yes/No) Y Y Y Y Supplement#2 (Yes/No) Y Y Y Y Supplement#3 (Yes/No) INC Y Y Y Supplement#4 (Yes/No) INC Y Y Y Supplement#5 (Yes/No) INC Y Y Y CE&I Form (Yes/No/INC) INC Y Y Y Bid Bond Provided (Yes/No) NR NR NR NR Signed (Yes/No) Y Y Y Y 48 Orange County Crisis Diversion INC= Incomplete INR = Not Required BID TABULATION = Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 03A Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Concrete Bid Time: 1:OOPM Estimate Amount: $405,514.00 4 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 Bidder#4 IQ Contracting Advance Concrete Donleys Raleigh East Concrete Bidder Name Base Bid Amount $ 548,900.00 $ 510,612.00 $ 497,524.00 $ 464,000.00 Estimate $ 405,514.00 $ 405,514.00 $ 405,514.00 $ 405,514.00 Variance $ 143,386.00 $ 105,098.00 $ 92,010.00 $ 58,486.00 Allocations: 1 Dewatering $ 20,000.00 $ 20,000.00 $ 20,000.00 $ 20,000.00 2 ITrade Leaveouts/Coord i nation I $ 15,000.00 $ 15,000.00 $ 15,000.00 $ 15,000.00 Total Bid with Trade Allocations $ 583,900.00 $ 545,612.00 $ 532,524.00 $ 499,000.00 Bid Inclusion Items: Addendum#1 (Yes/No) Y Y Y Supplement#1 (Yes/No) Y Y Y Y Supplement#2 (Yes/No) Y Y Y Y Supplement#3 (Yes/No) Y Y Y Y Supplement#4 (Yes/No) Y Y Y Y Supplement#5(Yes/No) Y Y Y CE&I Form (Yes/No/ INC) Y Y Y Y Bid Bond Provided (Yes/No) NR NR NR NR Signed (Yes/No) Y Y Y Y 49 Orange County Crisis Diversion INC= Incomplete INR = Not Required BID TABULATION *=Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 04A Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Masonry Bid Time: 1:OOPM Estimate Amount: $500,348.00 4 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 Bidder#4 Joyner Masonry Pyramid Masonry Whitman Masonry WC Construction Bidder Name Base Bid Amount $ 874,000.00 $ 480,000.00 $ 639,500.00 $ 429,000.00 Estimate $ 500,348.00 $ 500,348.00 $ 500,348.00 $ 500,348.00 Variance $ 373,652.00 $ (20,348.00) $ 139,152.00 $ (71,348.00) Allocations: $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 1 Miscellaneous Trade Coordination 2 Jamb/Sill/Head Flashing $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 Caulking and Waterproofing $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 3 1 Unforeseen Conditions Total Bid with Allocations $ 904,000.00 $ 510,000.00 $ 669,500.00 $ 459,000.00 Bid Inclusion Items: Addendum#1 (Yes/No) Y Y Y Y Supplement#1 (Yes/No) Y Y Y Y Supplement#2(Yes/No) Y Y Y Y Supplement#3(Yes/No) Y Y Y Y Supplement#4(Yes/No) Y Y Y Y Supplement#5 (Yes/No) Y Y Y CI&E Y Y HUB Affidavits Provided (Yes/No/INC) NR NR NR NR Bid Bond Provided (Yes/No) NR NR NR NR Signed (Yes/No) Y Y Y Y 50 Orange County Crisis Diversion INC = Incomplete INR = Not Required BID TABULATION *=Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 05A Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Structural Steel Bid Time: 1:OOPM Estimate Amount: $915,020.00 4 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 Bidder#4 North State Steel 3 Sons Steel SteelFab Weldon Steel Bidder Name Base Bid Amount $ 984,893.00 $ 722,645.00 $ 2,272,600.00 $ 928,900.00 Estimate $ 915,020.00 $ 915,020.00 $ 915,020.00 $ 915,020.00 Variance $ 69,873.00 $ (192,375.00) $ 1,357,580.00 $ 13,880.00 Allocations: Miscellaneous Metals and Support $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 1 Steel 2 Miscellaneous Detailing $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 Total Bid with Trade Allocations $ 1,044,893.00 $ 782,645.00 $ 2,332,600.00 $ 988,900.00 Bid Inclusion Items: Addendum#1 (Yes/No) Y Y Y Y Supplement#1 (Yes/No) Y Y Y Y Supplement#2 (Yes/No) Y Y Y Y Supplement#3 (Yes/No) Y Y Y Y Supplement#4 (Yes/No) Y Y Y Y Supplement#5 (Yes/No) Y Y Y Y CI&E Y Y Y HUB Affidavits Provided (Yes/No/INC) NR Y Y Bid Bond Provided (Yes/No) NR NR Y NR Signed (Yes/No) Y Y Y Y 51 Orange County Crisis Diversion INC= Incomplete INR = Not Required BID TABULATION *=Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 06A Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Millwork Am Bid Time: 1:OOPM Estimate Amount: $506,215.00 3 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 Xylem Inc Numa Northside Bidder Name Base Bid Amount $ 467,527.00 $ 608,640.00 $ 309,300.00 Estimate $ 506,215.00 $ 506,215.00 $ 506,215.00 Variance $ (38,688.00)1 $ 102,425.00 $ (196,915.00) Allocations: 1 Multiple Trade Coordination $ 10,000.00 $ 10,000.00 $ 10,000.00 2 1 Miscellaneous Detailing $ 10,000.00 $ 10,000.00 $ 10,000.00 Total Bid with Accepted Allocations $ 487,527.00 $ 628,640.00 $ 329;300.00 Bid Inclusion Items: Addendum#1 (Yes/No) Y Y Y Supplement#1 (Yes/No) Y Y Y Supplement#2 (Yes/No) Y Y Y Supplement#3(Yes/No) Y Y Y Supplement#4(Yes/No) Y Y Y Supplement#5(Yes/No) Y Y Y CE&I Form (Yes/No/INC) Y Y Y Bid Bond Provided (Yes/No) NR NR NR Signed (Yes/No) Y Y Y 52 Orange County Crisis Diversion JINC=Incomplete INR=Not Required BID TABULATION =Signed under Contract execution. INBS=No Bid Submitted BID PACKAGE NUMBER: 07A Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Roofing Bid Time: 1:00PM Estimate Amount: $736,155.00 6 Number of Bidders Bids Received: Bidder#1 --Widder#2 Bidder#3 Bidder#4 Bidder#5 Bidder#6 Roofwerx Allied Roofing JT Murphy Tecta Hamlin Highland Roofing Bidder Name Base Bid Amount $ 498,126.00 $ 294,845. $ 624,672.00 $ 466,126.00 $ 622,208.00 $ 397,516.00 Estimate $ 736,155.00 $ 736,155.00 $ 736,155.00 $ 736,155.00 $ 736,155.00 $ 736,155.00 Variance $ (238,029.00) $ (441,310.00) $ (111,483.00) $ (270,029.00) $ (113,947.00) $ (338,639.00) 1 Stair Tower $ 150,000.00 $ 150,000.00 $ 150,000.00 $ 150,000.00 $ 150,001.00 $ 150,002.00 2 PV S stem Roof Warranty $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 3 Coordination&Additional Penetrations $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 4 Building Envelope Review $ 25,000.00 $ 25,000.00 $ 25,000.00 $ 25,000.00 $ 25,000.00 $ 25,000.00 Total Bid with Trade Allocations $ 688,126.00 $ 814,672.00 $ 656,126.00 $ 812,209.00 $ 587,518.00 Bid Inclusion Items: Addendum#1 Yes/No Y Y Y Y Y Y Supplement#1(Yes/No Y Y Y Y Y Y Supplement#2(Yes/No) Y Y Y Y Y Y Supplement#3(Yes/No) Y Y Y Y Y Y Supplement#4(Yes/No) Y Y Y Y Y Y Supplement#5 Yes/No Y Y Y Y Y Y CE&I Form Yes/No/INC Y Y Bid Bond Provided(Yes/No NR NR NR NR NR NR Signed Yes/No Y Y Y Y Y Y 53 Orange County Crisis Diversion INC= Incomplete INR = Not Required BID TABULATION *=Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 07B Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Caulking &Sealants Bid Time: 1:OOPM Estimate Amount: $216,122.00 3 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 JT Murphy Strickland Alpha Bidder Name Base Bid Amount $ 248,156.00 $ 300,000.00 $ 189,738.00 Estimate $ 216,122.00 $ 216,122.00 $ 216,122.00 Variance $ 32,034.00 $ 83,878.00 $ (26,384.00) Allocations: 1 Waterproofing Detailing $ 10,000.00 $ 10,000.00 $ 10,000.00 2 1 Miscellaneous Caulking $ 10,000.00 $ 10,000.00 $ 10,000.00 Total Bid with Trade Allocations $ 268,156.00 $ 320,000.00 $ 209,738.00 Bid Inclusion Items: Addendum#1 (Yes/No) Y Y Y Supplement#1 (Yes/No) Y Y Y Supplement#2(Yes/No) Y Y Y Supplement#3(Yes/No) Y Y Y Supplement#4(Yes/No) Y Y Y Supplement#5(Yes/No) Y Y Y CE&I Form (Yes/No/INC) Emu] Y Y Bid Bond Provided (Yes/No) NR NR NR Signed (Yes/No) Y Y Y 54 Orange County Crisis Diversion INC= Incomplete INR = Not Required BID TABULATION =Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 07D Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Fiber Cement Panels Bid Time: 1:OOPM Estimate Amount: $500,110.00 4 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 Bidder#4 Steel Clad Sears Ecclessia Advance Exterior Bidder Name Systems Base Bid Amount $ 510,000.00 $ 669,610.00 $ 352,000.00 $ 775,000.00 Estimate $ 500,110.00 $ 500,110.00 $ 500,110.00 $ 500,110.00 Variance $ 9,890.00 $ 169,500.00 $ (148,110.00) $ 274,890.00 Allocations: 1 Art Panel Coordination $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 2 Miscellaneous Trim Out $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 3 Trade Coordination $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 Total Bid with Trade Allocations $ 580,000.00 $ 739,610.00 $ 422,000.00 $ 845,000.00 Bid Inclusion Items: Addendum#1 (Yes/No) Y Y Y Y Supplement#1 (Yes/No) Y Y Y Y Supplement#2 (Yes/No) Y Y Y Y Supplement#3 (Yes/No) Y Y Y Y Supplement#4 (Yes/No) Y Y Y Y Supplement#5(Yes/No) Y Y Y HUB Affidavits Provided (Yes/No/ INC) Y Y Y Y Bid Bond Provided (Yes/No) NR NR NR NR Signed (Yes/No) Y Y Y Y 55 Orange County Crisis Diversion JINC= Incomplete INR = Not Required BID TABULATION I *=Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 08A Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Doors, Frames,&Hardware Bid Time: 1:OOPM Estimate Amount: $449,750.00 2 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 Martin Architectural Hardware Distributors NBS Bidder Name Base Bid Amount $ 346,122.00 $ 363,759.13 $ - Estimate $ 449,750.00 1 $ 449,750.00 1 $ 449,750.00 Variance $ (103,628.00) $ (85,990.87) $ (449,750.00) Allocations: 1 Expediting Allocation $ 10,000.00 $ 10,000.00 $ - 2 1 Door Hardware Coordination $ 5,000.00 $ 5,000.00 $ - Total Bid with Trade Allocations $ 361,122.00 $ 378,759.13 $ - Bid Inclusion Items: Addendum#1 (Yes/No) Y Y - Supplement#1 (Yes/No) Y Y - Supplement#2 (Yes/No) Y Y - Supplement#3(Yes/No) Y Y - Supplement#4(Yes/No) Y Y - Supplement#5(Yes/No) Y Y - CI&E Y Y - HUB Affidavits Provided (Yes/No/INC) NR NR - Bid Bond Provided (Yes/No) NR NR - Signed (Yes/No) Y Y - 56 Orange County Crisis Diversion INC= Incomplete INR = Not Required BID TABULATION '=Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 08B Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Glass&Glazing Bid Time: 1:OOPM Estimate Amount: $1,105,750.00 3 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 MSJ Glass 1 st Choice Novelle Tree Bidder Name Base Bid Amount $ 927,109.00 $ 853,820.00 Estimate $ 1,105,750.00 $ 1,105,750.00 1 $ 1,105,750.00 Variance $ (178,641.00) $ (251,930.00) $ (543,750.00) Allocations: 1 1 Miscellaneous Jamb Flashing $ 10,000.00 $ 10,000.00 $ 10,000.00 2 lGlazing Support $ 10,000.00 $ 10,000.00 $ 10,000.00 Total Bid with Trade Allocations $ 947,109.00 $ 873,820.00 $ 582,000.00 Bid Inclusion Items: Addendum#1 (Yes/No) Y Y Y Supplement#1 (Yes/No) Y Y Y Supplement#2 (Yes/No) Y Y Y Supplement#3 (Yes/No) Y Y Y Supplement#4 (Yes/No) Y Y Y Supplement#5 (Yes/No) Y Y Y HUB Affidavits Provided (Yes/No/INC) Y Y Y Bid Bond Provided (Yes/No) NR NR NR Signed (Yes/No) Y Y Y 57 Orange County Crisis Diversion INC = Incomplete JNR = Not Required BID TABULATION *=Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 09A Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Drywall &Framing Bid Time: 1:OOPM Estimate Amount: $1,101,103.00 3 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 NJR Northedge Gerloff Bidder Name Base Bid Amount $ 830,000.00 $ 906,600.00 $ 789,824.00 Estimate $ 1,101,103.00 $ 1,101,103.00 $ 1,101,103.00 Variance $ (271,103.00) $ (194,503.00) $ (311,279.00) Allocations: 1 Rough Carpentry $ 50,000.00 $ 50,000.00 $ 50,000.00 2 Additional Patching $ 50,000.00 $ 50,000.00 $ 50,000.00 3 Framing &Layout Adjustments $ 5,000.00 $ 5,000.00 $ 5,000.00 4 Additional Level 5 Finishing $ 10,000.00 $ 10,000.00 $ 10,000.00 Total Bid with Trade Allocations $ 945,000.00 $ 1,021,600.00 $ 904,824.00 Bid Inclusion Items: Addendum#1 (Yes/No) Y Y Y Supplement#1 (Yes/No) Y Y Y Supplement#2 (Yes/No) Y Y Y Supplement#3 (Yes/No) Y Y Y Supplement#4 (Yes/No) Y Y Y Supplement#5 (Yes/No) Y Y Y HUB Affidavits Provided (Yes/No/ INC) Y Y Y Bid Bond Provided (Yes/No) NR NR NR Signed (Yes/No) Y Y Y 58 Orange County Crisis Diversion INC= Incomplete JNR = Not Required BID TABULATION = Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 09B Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Tiling Bid Time: 1:OOPM Estimate Amount: $97,850.00 3 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 CB Flooring Concordia Lomax Tile Bidder Name Base Bid Amount $ 56,700.00 $ 84,421.00 $ 53,022.00 Estimate $ 97,850.00 $ 97,850.00 $ 97,850.00 Variance $ (41,150.00) $ (13,429.00) $ (44,828.00) Allocations: Misc. Tile Patching and Trade $ 5,000.00 $ 5,000.00 $ 5,000.00 1 Coordination 2 Unforeseen Transition Conditions $ 5,000.00 $ 5,000.00 $ 5,000.00 Total Bid with Trade Allocations $ 66,700.00 $ 94,421.00 $ 63,022.00 Bid Inclusion Items: Addendum#1 (Yes/No) Y Y Y Supplement#1 (Yes/No) Y Y Y Supplement#2 (Yes/No) Y Y Y Supplement#3(Yes/No) Y Y Y Supplement#4(Yes/No) Y Y Y Supplement#5(Yes/No) Y Y Y HUB Affidavits Provided (Yes/No/INC) Y Y Bid Bond Provided (Yes/No) NR NR NR Signed (Yes/No) Y Y Y 59 Orange County Crisis Diversion INC= Incomplete NR = Not Required BID TABULATION = Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 09C Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Ceilings Bid Time: 1:OOPM Estimate Amount: $250,061.00 3 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 Gerloff NJR Numa Bidder Name Base Bid Amount $ 260,000.00 $ 246,000.00 $ 207,317.00 Estimate $ 250,061.00 $ 250,061.00 $ 250,061.00 Variance $ 9,939.00 $ (4,061.00) $ (42,744.00) Allocations: 1 MEP Penetration Coordination $ 10,000.00 $ 10,000.00 $ 10,000.00 2 ICeiling Grid &Tile Replacement $ 10,000.00 $ 10,000.00 $ 10,000.00 Total Bid with Trade Allocations $ 280,000.00 $ 266,000.00 $ 227,317.00 Bid Inclusion Items: Addendum#1 (Yes/No) Y Y Y Supplement#1 (Yes/No) Y Y Y Supplement#2 (Yes/No) Y Y Y Supplement#3 (Yes/No) Y Y Y Supplement#4 (Yes/No) Y Y Y Supplement#5 (Yes/No) Y Y Y HUB Affidavits Provided (Yes/No/INC) Y Y Bid Bond Provided (Yes/No) NR NR NR Signed (Yes/No) Y Y Y 60 Orange County Crisis Diversion JINC=Incomplete INR= Not Required BID TABULATION I "=Signed under Contract execution. INBS= No Bid Submitted BID PACKAGE NUMBER: 09D Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Painting Bid Time: 1:OOPM Estimate Amount: $114,095.00 5 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 Bidder#4 Bidder#5 DCH Enterprises National Coatings Tri City NJR E Caligari Bidder Name Base Bid Amount $ 78,500.00 $ 84,840.00 $ 110,250.00 $ 95,000.00 $ 48,815.00 Estimate $ 114,095.00 $ 114,095.00 $ 114,095.00 $ 114,095.00 $ 114,095. $ 00 Variance $ (35,595.00) (29,255.00) $ (3,845.00) $ (19,095.00) $ (65,280.00) Allocations: 1 Wall Covering Allowance $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 2 Touch Ups $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 3 Surface Prep $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 $ 5,000.00 Total Bid with Trade Allocations $ 98,500.00 $ 104,840.00 $ 130,250.00 $ 115,000.00 $ 68,815.00 Bid Inclusion Items: Addendum#1 (Yes/No) Y Y Y Y Y Supplement#1 (Yes/No) Y Y Y Y Y Supplement#2(Yes/No) Y Y Y Y Y Supplement#3(Yes/No) Y Y Y Y Y Supplement#4(Yes/No) Y Y Y Y Y Supplement#5(Yes/No) Y Y Y Y Y HUB Affidavits Provided(Yes/No/INC) Y Y Bid Bond Provided(Yes/No) NR NR NR NR NR Signed(Yes/No) Y Y Y Y Y 61 Orange County Crisis Diversion INC= Incomplete INR = Not Required BID TABULATION =Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 09E Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Flooring Bid Time: 1:OOPM Estimate Amount: $255,588.00 3 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 Brock Flooring Storr CB Flooring Bidder Name Base Bid Amount $ 154,595.00 $ 267,329.79 $ 191,000.00 Estimate $ 255,588.00 $ 255,588.00 $ 255,588.00 Variance $ (100,993.00) $ 11,741.79 $ (64,588.00) Accepted Bid Alternates: 1 Additional Surface Prep $ 5,000.00 $ 5,000.00 $ 5,000.00 Trade Coordination&Unforeseen $ 5,000.00 $ 5,000.00 $ 5,000.00 2 Transitions Total Bid with Trade Allocations $ 164,595.00 $ 277,329.79 $ 201,000.00 Bid Inclusion Items: Addendum#1 (Yes/No) Y Y Y Supplement#1 (Yes/No) Y Y Y Supplement#2 (Yes/No) Y Y Y Supplement#3 (Yes/No) Y Y Y Supplement#4 (Yes/No) Y Y Y Supplement#5 (Yes/No) Y Y Y CI&E Y Y HUB Affidavits Provided (Yes/No/INC) NR Y NR Bid Bond Provided (Yes/No) NR NR NR Signed (Yes/No) Y Y Y 62 Orange County Crisis Diversion JINC=Incomplete NR= Not Required BID TABULATION I =Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 10A Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Specialties Bid Time: 1:OOPM Estimate Amount: $234,129.00 5 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 Bidder#4 Bidder#5 Warco Hardware Distributors Old Dominion Next150 Martin Arch Bidder Name Base Bid Amount $ 217,600.00 $ 169,990.00 $ 235,140.00 $ 256,997.00 $ 186,186.00 Estimate $ 234,129.00 1 $ 234,129.00 1 $ 234,129.00 1 $ 234,129.00 $ 234,129.00 Variance 1 $ (16,529.00) $ (64,139.00)1 $ 1,011.00 1 $ 22,868.00 1 $ (47,943.00) Allocations: 1 Miscellaneous Accessories $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 2 Trade Coordination $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 Total Bid with Trade Allocations $ 237,600.00 $ 189,990.00 $ 255,140.00 $ 276,997.00 $ 206,186.00 Bid Inclusion Items: Addendum#1 (Yes/No) No Yes Yes Yes No Supplement#1 (Yes/No) Yes Yes Yes Yes Yes Supplement#2(Yes/No) Yes Yes Yes Yes Yes Supplement#3(Yes/No) Yes Yes Yes Yes Yes Supplement#4(Yes/No) Yes Yes Yes Yes Yes Supplement#5(Yes/No) Yes Yes Yes Yes Yes HUB Affidavits Provided(Yes/No/INC) Yes Yes Yes Bid Bond Provided(Yes/No) NR NR NR NR NR Signed(Yes/No) Yes Yes Yes Yes Yes 63 Orange County Crisis Diversion INC=Incomplete INR= Not Required BID TABULATION -=Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 10B Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Signage Bid Time: 1:OOPM Estimate Amount: $55,287.00 3 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 KM Printing dba Carolina Sign Smith Mercury Signs Bidder Name Strategic Factory Base Bid Amount $ 32,549.10 $ 20,349.00 $ 26,515.42 Estimate $ 55,287.00 1 $ 55,287.00 1 $ 55,287.00 Variance 1 $ (22,737.90) $ (34,938.00) $ (28,771.58) Allocations: 1 ISig,Specification Coordination $ 20,000.00 $ 20,000.00 $ 20,000.00 Total Bid with Trade Allocations $ 52,549.10 $ 40,349.00 $ 46,515.42 Bid Inclusion Items: Addendum#1 (Yes/No) Yes No No Supplement#1 (Yes/No) Yes Yes No Supplement#2(Yes/No) Yes Yes No Supplement#3(Yes/No) Yes Yes No Supplement#4(Yes/No) Yes Yes No Supplement#5(Yes/No) Yes No No HUB Affidavits Provided (Yes/No/INC) Yes No No Bid Bond Provided(Yes/No) NR NR NR Signed(Yes/No) Yes Yes Yes 64 Orange County Crisis Diversion JINC= Incomplete NR= Not Required BID TABULATION I =Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 11A Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Equipment Bid Time: 1:OOPM Estimate Amount: $83,700.00 2 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 NEXT150 Stafford Smith NBS Bidder Name Base Bid Amount $ 78,470.00 $ 34,233.00 $ - Estimate $ 83,700.00 $ 83,700.00 1 $ - Variance $ (5,230.00) $ (49,467.00) $ - Accepted Bid Alternates: 1 INo Specification Coordination $ 20,000.00 $ 20,000.00 Total Bid with Trade Allocations 1 $ 98,470.00 1 $ 54,233.00 1 $ - Bid Inclusion Items: Addendum#1 (Yes/No) Y Y Supplement#1 (Yes/No) Y Y - Supplement#2(Yes/No) Y Y - Supplement#3(Yes/No) Y Y - Supplement#4(Yes/No) Y Y - Supplement#5(Yes/No) Y Y - CI&E Y Y - HUB Affidavits Provided (Yes/No/INC) NR NR - Bid Bond Provided(Yes/No) NR NR - Signed (Yes/No) Y Y - 65 Orange County Crisis Diversion JINC= Incomplete JNR= Not Required BID TABULATION I =Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 12A Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Window Treatments Bid Time: 1:OOPM Estimate Amount: $40,950.00 3 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 GB Shades Commonwealth Warco Bidder Name Base Bid Amount $ 8,450.00 $ 37,052.00 $ 39,620.00 Estimate $ 40,950.00 1 $ 40,950.00 $ 40,950.00 Variance $ (32,500.00) $ (3,898.00) $ (1,330.00) Allocations: 1 Window Shade Support $ 5,000.00 $ 5,000.00 $ 5,000.00 Total Bid with Trade Allocations $ 13,450.00 $ 42,052.00 $ 44,620.00 Bid Inclusion Items: Addendum#1 (Yes/No) Y Y Y Supplement#1 (Yes/No) Y Y Y Supplement#2(Yes/No) Y Y Y Supplement#3(Yes/No) Y Y Y Supplement#4(Yes/No) Y Y Y Supplement#5(Yes/No) Y Y Y CI&E Y Y HUB Affidavits Provided (Yes/No/INC) NR NR NR Bid Bond Provided (Yes/No) NR NR NR Signed(Yes/No) Y Y Y 66 Orange County Crisis Diversion JINC=Incomplete NR= Not Required BID TABULATION I =Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 21A Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Fire Protection Bid Time: 1:00PM Estimate Amount: $174,455.00 4 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 Bidder#4 ABL Strategic Connections VSC Wolverine Bidder Name Base Bid Amount $ 173,579.00 $ 1561,500.00 $ 208,600.00 $ 182,000.00 Estimate $ 174,455.00 $ 174,455.00 $ 174,455.00 $ 174,455.00 Variance I $ (876.00) $ (17,955.00)1 $ 34,145.00 1 $ 7,545.00 Allocations: 1 Fire Marshall Coordination $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 2 BIM Coordination $ 9,000.00 $ 9,000.00 $ 9,000.00 $ 9,000.00 3 Permitting Coordination and Sprinkler Head Relocations $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 10,000.00 Total Bid with Trade Allocations $ 202,579.00 $ 185,500.00 $ 237,600.00 $ 211,000.00 Bid Inclusion Items: Addendum#1 (Yes/No) Y Y Y Y Supplement#1 (Yes/No) Y Y Y Y Supplement#2(Yes/No) Y Y Y Y Supplement#3(Yes/No) Y Y Y Y Supplement#4(Yes/No) Y Y Y Y Supplement#5(Yes/No) Y Y Y Y CI&E Y Y HUB Affidavits Provided(Yes/No/INC) NR NR Y Y Bid Bond Provided(Yes/No) NR NR NR NR Signed(Yes/No) Y Y Y Y 67 Orange County Crisis Diversion JINC=Incomplete INR= Not Required BID TABULATION I =Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 22A Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Plumbing Bid Time: 1:OOPM Estimate Amount: $1,092,078.00 2 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 Gallo Precision Plumbing NBS Bidder Name Base Bid Amount $ 1,242,375.00 $ 1,145,000.00 $ Estimate $ 1,092,078.00 $ 1,092,078.00 $ Variance $ 150,297.00 $ 52,922.00 $ Allocations: 1 Underground MEP Coordination $ 25,000.00 $ 25,000.00 $ 2 Overhead Piping Coordination $ 10,000.00 $ 10,000.00 $ 3 BIM Coordination $ 9,000.00 $ 9,000.00 $ Total Bid with Trade Allocations $ 1,286,375.00 $ 1,189,000.00 $ Bid Inclusion Items: Addendum#1 (Yes/No) Y Y Supplement#1 (Yes/No) Y Y Supplement#2(Yes/No) Y Y Supplement#3(Yes/No) Y Y Supplement#4(Yes/No) Y Y Supplement#5(Yes/No) Y Y CAE Y HUB Affidavits Provided(Yes/No/INC) NR Y Bid Bond Provided(Yes/No) Y Y Signed(Yes/No) Y Y 68 Orange County Crisis Diversion JINC= Incomplete INR= Not Required BID TABULATION I =Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 23A Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: HVAC Bid Time: 1:OOPM Estimate Amount: $1,093,782.00 3 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 Associated Heating Gallo Comfort Mechanical Bidder Name &Air Base Bid Amount $ 1,472,000.00 $ 1,458,135.00 $ 1,244,000.00 Estimate $ 1,093,782.00 $ 1,093,782.00 $ 1,093,782.00 Variance $ 378,218.00 $ 364,353.00 $ 150,218.00 Allocations: 1 Comissioning Support $ 25,000.00 $ 25,000.00 $ 25,000.00 2 Temporary Cooling/Heating for 6 Months $ 90,000.00 $ 112,500.00 $ 250,000.00 3 BIM Coordination $ 9,000.00 $ 9,000.00 $ 9,000.00 Total Bid with Trade Allocations $ 1,596,000.00 $ 1,604,635.00 $ 1,528,000.00 Bid Inclusion Items: Addendum#1 (Yes/No) Yes Yes Yes Supplement#1 (Yes/No) Yes Yes Yes Supplement#2(Yes/No) Yes Yes Yes Supplement#3(Yes/No) Yes Yes Yes Supplement#4(Yes/No) Yes Yes Yes Supplement#5(Yes/No) Yes Yes Yes HUB Affidavits Provided (Yes/No/INC) Yes No Yes Bid Bond Provided (Yes/No) Yes Yes Yes Signed(Yes/No) Yes Yes Yes 69 Orange County Crisis Diversion JINC= Incomplete NR= Not Required BID TABULATION I =Signed under Contract execution. INBS= No Bid Submitted BID PACKAGE NUMBER: 26A Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Electrical Bid Time: 1:OOPM Estimate Amount: $2,728,703.00 4 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 Bidder#4 Bobby Wilson South Fair DW Evans Bryant Durham Bidder Name Base Bid Amount $ 2,597,944.00 $ 2,900,000.00 $ 2,650,000.00 $ 2,772,000.00 Estimate $ 2,728,703.00 1 $ 2,728,703.00 1 $ 2,728,703.00 1 $ 2,728,703.00 Variance I $ (130,759.00)1 $ 171,297.00 1 $ (78,703.00) $ 43,297.00 Allocations: 1 Fire Alarm Coordination $ 25,000.00 $ 25,000.00 $ 25,000.00 $ 25,001.00 2 Temporary Power $ 25,000.00 $ 25,000.00 $ 25,000.00 $ 25,000.00 3 EV Charging Stations $ 30,000.00 $ 30,000.00 $ 30,000.00 $ 30,000.00 4 BIM Coordination $ 9,000.00 $ 9,000.00 $ 9,000.00 $ 9,000.00 5 Solar PV System $ 243,951.00 $ 299,700.00 $ 288,750.00 $ 264,000.00 6 jArc Flash/Coordination Study $ 25,000.00 $ 25,000.00 $ 25,000.00 $ 25,000.00 Total Bid with Trade Allocations $ 2,955,895.00 $ 3,313,700.00 $ 3,052,750.00 $ 3,150,001.00 Bid Inclusion Items: Addendum#1 (Yes/No) Yes Yes No Yes Supplement#1 (Yes/No) Yes Yes Yes Yes Supplement#2(Yes/No) Yes Yes Yes Yes Supplement#3(Yes/No) Yes Yes Yes Yes Supplement#4(Yes/No) Yes Yes Yes Yes Supplement#5(Yes/No) Yes No No Yes HUB Affidavits Provided(Yes/No/INC) Yes Yes No Yes Bid Bond Provided(Yes/No) Yes Yes Yes Yes Signed (Yes/No) I Yes I Yes I Yes I Yes 70 Orange County Crisis Diversion JINC= Incomplete INR= Not Required BID TABULATION I =Signed under Contract execution. INBS= No Bid Submitted BID PACKAGE NUMBER: 31A Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Sitework Bid Time: 1:OOPM Estimate Amount: $5,021,971.00 3 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 Fred Smith Capital Grading Faulconer Bidder Name Base Bid Amount $ 4,579,500.00 $ 4,306,675.00 $ 5,908,000.00 Estimate $ 5,021,971.00 $ 5,021,971.00 $ 5,021,971.00 Variance $ (4421471.00) $ (715,296.00) $ 886,029.00 Allocations: 1 Sanitary Sewer Material Change $ 15,000.00 $ 15,000.00 $ 15,000.00 2 Storm Filter Changes $ 900,000.00 $ 900,000.00 $ 900,000.00 3 Unsuitable Soils $ 25,000.00 $ 25,000.00 $ 25,000.00 4 Street Sweeper $ 15,000.00 $ 15,000.00 $ 15,000.00 5 Miscellaneous Laydown Yard $ 10,000.00 $ 10,000.00 $ 10,000.00 6 Asphalt Binder Index Allowance $ 75,000.00 $ 75,000.00 $ 75,000.00 Total Bid with Trade Allocations $ 5,619,500.00 $ 5,346,675.00 $ 6,948,000.00 Bid Inclusion Items: Addendum#1 (Yes/No) Yes Yes Yes Supplement#1 (Yes/No) Yes Yes Yes Supplement#2(Yes/No) Yes Yes Yes Supplement#3(Yes/No) Yes Yes Yes Supplement#4(Yes/No) Yes Yes Yes Supplement#5(Yes/No) Yes Yes Yes CE&I Form(Yes/No/INC) Yes Yes Yes Bid Bond Provided(Yes/No) Yes Yes Yes Signed(Yes/No) Yes Yes Yes 71 Orange County Crisis Diversion INC=Incomplete INR= Not Required BID TABULATION =Signed under Contract execution. INBS= No Bid Submitted BID PACKAGE NUMBER: 32A Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Landscaping Bid Time: 1:OOPM Estimate Amount: $261,417.00 3 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 Yardnique Ideal Brightview Bidder Name Base Bid Amount $ 333,115.00 $ 343,300.00 $ 331,750.00 Estimate $ 261,417.00 $ 261,417.00 $ 261,417.00 Variance $ 71,698.00 $ 81,883.00 $ 70,333.00 Allocations: 1 Site Furnishings $ 50,000.00 $ 50,000.00 $ 50,000.00 2 Patient Courtyard Shade Structure-Vizor $ 140,500.00 $ 116,900.00 $ 118,766.00 3 Additional Soils,Seeding,&Plantings $ 15,000.00 $ 15,000.00 $ 15,000.00 4 Additional Watering $ 10,000.00 $ 10,000.00 $ 10,000.00 Total Bid with Trade Allocations $ 548,615.00 $ 535,200.00 $ 525,516.00 Bid Inclusion Items: Addendum#1 (Yes/No) Yes Yes Yes Supplement#1 (Yes/No) Yes Yes Yes Supplement#2(Yes/No) Yes Yes Yes Supplement#3(Yes/No) Yes Yes Yes Supplement#4(Yes/No) Yes Yes Yes Supplement#5(Yes/No) Yes Yes Yes CI&E Form(Yes/No/INC) Yes Yes Yes Bid Bond Provided(Yes/No) NR NR NR Signed(Yes/No) Yes Yes Yes 72 Orange County Crisis Diversion JINC=Incomplete INR= Not Required BID TABULATION I =Signed under Contract execution. INBS = No Bid Submitted BID PACKAGE NUMBER: 32B Bid Date: 5/6/2026 BID PACKAGE DESCRIPTION: Fences&Gates Bid Time: 1:OOPM Estimate Amount: $96,350.00 1 Number of Bidders Bids Received: Bidder#1 Bidder#2 Bidder#3 Frye Fencing NBS NBS Bidder Name Base Bid Amount $ 170,000.00 Estimate $ 96,350.00 $ 96,350.00 $ 96,350.00 Variance $ 73,650.00 $ (96,350.00) $ (96,350.00) Allocations: 1 Fence Gate&Hardware $ 10,000.00 $ - $ 2 Fencing Specification Coordination $ 20,000.00 $ $ Total Bid with Trade Allocations $ 200,000.00 $ $ Bid Inclusion Items: Addendum#1 (Yes/No) Y Supplement#1 (Yes/No) Y Supplement#2(Yes/No) Y Supplement#3(Yes/No) Y Supplement#4(Yes/No) Y Supplement#5(Yes/No) Y CI&E N HUB Affidavits Provided(Yes/No/INC) NR Bid Bond Provided(Yes/No) NR Signed(Yes/No) Y Tube www.gilbaneco.com 74 Year-To-Date Budget Summary Fiscal Year 2025-26 Fund Budget Summary County Capital Original Budget Revenue $36,635,068 Interfund Transfer Revenue $1,400,000 Fund Balance Appropiation $0 Total Original Budget $38,035,068 Additional Revenue Received Through Budget Amendment#12-A (June 16th) Grant Funds $684,938 Non Grant Funds $6,394,272 Additional Interfund Transfer Revenue $290,954 Additional Fund Balance Appropriation Total Amended Budget $45,405,232 Dollar Change in 2025-26 Approved Budget $7,370,164 Change in 2025-26 Approved Budget 19.38% 75 ORANGE COUNTY NORTH CAROLINA Approval of the Construction of the Crisis Diversion Facility 6-16-2026 76 PURPOSE • Review the final design of the Crisis Diversion Facility, including sustainability features. • Review the total project Budget, including the Guaranteed Maximum Price for the construction ORANGE COUNTY NORTH CAROLINA 77 FINAL DESIGN Site Plan WAYERSTONE DRIVE IISNl711'h 4 "I II NEW CENTER ' BUILDING 1 II I� I s = CPL II ARCHITECTURE ORANGE COUNTY ENGINEERING NORTH CAROLINA PLANNING CPLteam.com 78 FINAL DESIGN Floor Plan sm 14- �` p E CRISIS DIVERSION CENTER ""° .kdl-Ft..Fk" ORANGE COUNTY CPL c II ARCHITECTURE ORANGE COUNTY ENGINEERING NORTH CAROLINA PLANNING CPLteam.com 79 FINAL DESIGN North Elevation CPL ORANGE COUNTY ARCHITECTURE ENGWEERING NORTH CAROLINA PLANNING CPLteam.com 80 FINAL DESIGN Front Entrance s.: = CPL -'� CII ARCHITECTURE ORANGE COUNTY ENGINEERING NORTH CAROLINA PLANNING CPLteam.com 81 FINAL DESIGN Rear Entrance CPL CII ARCHITECTURE ORANGE COUNTY ENGINEERING NORTH CAROLINA PLANNING CPLteam.com 82 FINAL DESIGN Waiting Area 1 f` y ri I CPL Ct)ARCHITECTURE ORANGE COUNTY ENGINEERING NORTH CAROLINA PLANNING CPLteam,com 83 FINAL DESIGN Facility-Based Care Nurses Station s.: = CPL -'� CII ARCHITECTURE ORANGE COUNTY ENGINEERING NORTH CAROLINA PLANNING CPLteam.com 84 PROJECT COSTS Crisis Diversion Facility- Final Project Budget-June 6th Project Funding Request GMP(Construction and Indirect Costs) $22,906,906 Current Approved Project Funds $26,053,350 Land $1,353,266 Requested Projected Budget $29,412,035 Design/Other Professional Services $2,142,227 Additional Funds Needed $3,358,6851 Furniture $525,983 Environmental Impact and Related Fees $132,785 Commissioning/Special Inspections $175,868 Owner's Contingency $1,850,000 Offsite lighting $100,000 Audio Visual $25,000 IT Network Equipment and Cabling $75,000 Security Cameras and Badge Readers $125,000 Total: $29,412,035 ORANGE COUNTY NORTH CAROLINA 85 SUSTAINABILITY FEATURES • Solar - 274 solar panels capable of producing enough electricity to cover 72% of the building's energy usage during peak times. • LED Lights • Low water use features • Fully electrical HVAC system — No natural gas onsite. • Materials • Recycled Aluminum wood-look soffits • Low VOC paints, flooring, and wall coverings. ORANGE COUNTY NORTH CAROLINA 86 Questions? ORANGE COUNTY NORTH CAROLINA