HomeMy WebLinkAboutMinutes 04-22-2025-Budget Work Session 1 APPROVED 6117/25 MINUTES ORANGE COUNTY BOARD OF COMMISSIONERS BUDGET WORK SESSION - CIP April 22, 2025 7:00 p.m. The Orange County Board of Commissioners met for a Budget Work Session on the CIP on Tuesday, April 22, 2025, at 7:00 p.m. at the Whitted Human Services Center in Hillsborough, NC. COUNTY COMMISSIONERS PRESENT: Chair Jamezetta Bedford and Commissioners Marilyn Carter, Amy Fowler, Sally Greene, and Earl McKee COUNTY COMMISSIONERS ABSENT: Vice-Chair Jean Hamilton and Commissioner Phyllis Portie-Ascott COUNTY ATTORNEYS PRESENT: John Roberts COUNTY STAFF PRESENT: County Manager Travis Myren, Deputy County Manager Caitlin Fenhagen, and Clerk to the Board Laura Jensen. (All other staff members will be identified appropriately below) Chair Bedford called the meeting to order at 7:00 p.m. All commissioners were present except Vice-Chair Hamilton and Commissioner Portie-Ascott. 1. Discussion of Manager's Recommended FY 2025-35 Capital Investment Plan (CIP) The Board discussed the Manager's Recommended FY 2025-35 Capital Investment Plan. BACKGROUND: Each year, the County produces a Capital Investment Plan (CIP) that establishes a budget planning guide related to capital needs for the County and Schools. The 10-Year CIP is evaluated annually to include year-to-year changes in priorities, needs, and available resources. Approval of the CIP commits the County to the first-year funding only of the capital projects; all other years are used as a planning tool and serves as a financial plan Capital Investment Plan — Overview The FY 2025-35 CIP includes County Projects, School Projects, and Proprietary Projects. The School Projects include Chapel Hill-Carrboro City Schools, Orange County Schools, and Durham Technical Community College — Orange County Campus projects. The Proprietary Projects include Water and Sewer, Solid Waste Enterprise Fund, and Sportsplex projects. The CIP has been prepared anticipating moderate economic growth of approximately 2% in property tax growth and 4% in sales tax growth annually over the next ten (10) years. The CIP will rely substantially on debt financing to fund the projects and these required debt amounts are fully integrated in the County's Long-Term Debt Model (page 40 in the CIP document provides a bar chart of the ten-year funding plan). The meeting discussion will focus on the specific projects in the County and Proprietary CIP. Note: Page numbers are referenced below as they appear in the CIP document. See Attachment A for the Overall CIP Summary (page 36), County CIP Projects Summary (page 48), the Proprietary CIP Summaries (page 119), and School CIP Summary (page 131). 2 Given voter approval of the Bond in November 2024, there will also be a discussion of the funding structure and new organization of the School CIP. Discussion of specific Schools CIP projects is scheduled for the May 15, 2025 Budget Work Session. Discussion at this meeting will also be directed to the Debt Service and Debt Capacity — General Fund (page 171), the Water and Sewer Debt Service requirements paid with Article 46 Quarter Cent Sales Tax proceeds (page 172), and Debt Service requirements for Solid Waste (page 173) and Sportsplex (page 174). Travis Myren made the following presentation: Slide #1 i ORANGE COUNTY NORTH CAROLINA ORANGE COUNTY CAPITAL INVESTMENT PLAN FY2025-35 Board of Commissioners'Work Session April22, 2025 1 Slide #2 3 Purpose • Purpose of the Capital Investment Plan — Board Approves Year 1 of the Plan as the FY2025 -26 Capital Budget — Ten Year Planning Horizon(FY2025-35) • Imposes Planning Discipline • No Surprises — Debt Service Requirements • Amount of Funds Required in the Operating Budget • Measures Debt Capacity—Debt Service Compared to Expected General Fund Revenue • Predicts Potential Tax Increases Required to Pay Debt Service ORANGE COUNTY 2 NOR-1-VI CAROLINA Slide #3 FY2025-35 Recommended Capital Investment Plan • Plan Alignment — Countywide Strategic Plan— Priorities — Responsive Projects • Environmental Protection and Climate Action Climate Action Plan Projects • Healthy Community Behavioral Health Crisis Diversion Facility • Housing for All Affordable Housing Funding • Multi-modal Transportation Mountains to Sea Trail • Public Education/Learning Community School Pay-go for Planning and Design • Diverse and Vibrant Economy PFPC HVAC Controls ORANGE COUNTY s R x cA A Slide #4 4 FY2025-35 Recommended Capital Investment Plan • Total Recommended FY2025-26 Capital Expenditures -$76.3 million — County Capital $38.5 million — Proprietary Funds $3.7 million — School Capital $34.1 million ORANGE COUNTY 4 NORTH C A-ROLINA 5 Slide#5 FY2025-35 Recommended Capital Investment Plan • Animal Services - $818,720 Environmental Protection and Climate Action (p 52) County Long Range Facilities Plan — Department of Agriculture Recommendations • Replace dog-hold enclosures-$404,460 j -- Y.. T • Resurface epoxy floor-$110,000 additional project cost to fund actual bid amount _ • $514,460 Total Dept.of Ag.Recommendations — Other Improvements • Add doors between rooms for improved cleaning • Tint glass • Improve signage • Replace exterior doors • $304,260 Total for Other Improvements ORANGE COUNTY $ NORTH CAROLINA Travis Myren said the Department of Agriculture recommendations listed in slide #7 are required to maintain accreditation for the Animal Services department. Slide #6 FY2025-35 Recommended Capital Investment Plan • Behavioral Health Crisis Diversion Healthy Community County Long Range Facilities Plan Facility (p. 53) ,rr.- ram_- - --r-_�v �,,,,���• per J - an••dA -- ____-_ c i• — $22.7 million Construction in FY2025-26 — $1,823,121 Revenue Applied from Cardinal Innovations One Time Transition Funds c=> — Staff amendment to reduce the construction budget by$285,000, consistent with Board action on the CMAR contract �l '' _ � • $179,928—Gllbane pre-construction services + • $35,000—Payment in lieu of taxes to Town of Fllllsborough to eventually connect stubbed out road • $70,072—Closing costs and permitting — s Commissioner Carter asked if there was any cost sharing in the infrastructure improvements for the behavioral health crisis diversion facility. 6 Travis Myren said there is no cost sharing, but the storm water retention facilities will be sized to accommodate both the county's development and future development. He said it must be done by the county, because the county is developing their parcel first. Commissioner Carter asked if it was part of closing costs. Travis Myren said it is part of site costs. Chair Bedford asked if there is a realtor commission cost. Travis Myren said no. Chair Bedford asked about the other closing and permitting costs. Travis Myren said the permitting fees are to the Town of Hillsborough and to the State of North Carolina. Alan Dorman, Asset Management Services Director, said some of those costs include contingency. Slide #7 FY2025-35 Recommended Capital Investment Plan • Behavioral Health Crisis Diversion Facility Timeline COMPLETE Board approves purchase and sale agreement and Construction Manager at Risk(CMAR)contract Spring 2025 Final site plan submitted to Town of Hillsborough staff for approval Summer 2025 Final construction documents prepared Fall 2025 Permitting completed Winter 2025 CMAR issues final Guaranteed Maximum Price(GMP) Winter 2025 Board considers acceptance of final GMP • Contract includes four(4)Board prior Board approvals at different stages of the project Winter 2025 Construction begins Early 2027 Owner acceptance of facility ORANGE COUNTY 7 NORTH CAROLINA Slide #8 FY2025-35 Recommended Capital Investment Plan mate Actin Mission Support Contai Storage • Board of Elections Storage - -A 4, $381,000 (p. 54) — $296,000 approved in FY2024-25 to "• n create climate-controlled storage for voting equipment 44` CD 0 Cn — Additional funds of$381,000 needed " a due to new cost estimates • Construction costs and small scale of project are contributing factors r nNINUL Commissioner Greene asked about the increased cost for the project. Chair Bedford asked if storage should be in a different location. Angel Barnes, Capital Projects Manager, said the small square footage resulted in a higher cost estimate and there are historic district requirements that must be included. Travis Myren said they can look at alternatives, but he is confident that the Board of Elections will strongly prefer to be collocated with their staff. Chair Bedford said it is also a security issue for elections. Commissioner Carter noted that the property is out of the flood plain and way out of the 500-year zone. Chair Bedford asked if the basement at Elections had been elevated. Alan Dorman said it is waterproof and there is nothing of value located on the lower level. Commissioner McKee asked if there is space that is climate controlled that could be used instead. Travis Myren said this is new construction and it is an expansion of an existing facility. He also said that the Board of Elections would insist that the voting equipment be co-located with staff. Commissioner McKee said the voting equipment is currently in storage units and he does not see that being any more secure there 100 feet away than it would be in an existing climate-controlled building and entry controlled. He said he is not sure how many square feet are needed for the machines. Alan Dorman said it would be an increase of 1,200 square feet. Commissioner McKee said it would be the Board of Commissioners' decision as to where they are located and even if the Board of Elections does not agree, he does not see that they need to spend funds to create existing space that can be used. Travis Myren said yes. 8 9 Slide #9 FY2025-35 Recommended Capital Investment Plan Environmental Protection and Climate Action • Climate Change Mitigation $267,750 All Climate Action Plan Focus Areas (p 56) Green Infrastructure Workforce Development Program — Climate mitigation grants to non-profit and V public agencies through a formal competitive grant process — Originally tied to cent of property tax rate ' — Manager recommends disconnecting future funding available for grants from tax rate — Future years assume 2% annual growth in amount available for grants Orange County students planting native plants to control stormwater erosion and runoff in a Carrboro neighborhood. ORANGE COUNTY NORTH C:AROLINA 9 Commissioner Greene said she had sent an email earlier in the day and discussed the history of the grants. She said she hoped that the county would get back to budgeting $400,000 for the grant program. Commissioner McKee noted that the county participates in other climate change mitigation strategies. He said he supported the County Manager's recommendation. Commissioner Greene said the community grant program allows the county to spread money into the community to address climate change. Commissioner McKee said he has concerns about raising property taxes to cover debt and the impact on residents. 10 Slide #10 FY2025-35 Recommended Capital Investment Plan • Climate Change Mitigation Project Status FY2023-24r Supplemental weatherization to Habitat for Humanity $55,000 In progress Shade for Schools Trees for the Triangle $50,000 In progress home repair projects Green infrastructure and Green Infrastructure Workforce Urban Sustainability $5g,700 In progress pprenticeship program for Urban Sustainability $69,156 Completed Development Program Solutions range County Schools Solutions Rooftop Solar on St.Joseph's Solar Equity $50,000 In progress Hillsborough United CME Church Rooftop solar Church of Christ $10,000 Completed Electrical Panel for Solar Project EMPOWERment $19,800 In progress Rooftop solar Binkley Baptist Church $49,036 Completed Prairie Restoration and Rooftop solar on Peach Reforestation Projects Eno River Association $22,600 In progress panments EMPOWERment $61,623 In progress Food Forest Jubilee Healing Farm $12,000 In progress Installation of gardens,terrace Club Nova $37,227 In progress and greenhouse Rooftop Solar on Habitat Homes Habitat for Humanity $50,000 In progress LED light campus changeover CHCCS $94,014 Completed 54-panel solar panel pedestal ith battery storage and EV Orange County Schools $188,029 In progress harging stations �1 ORANGE COUNTY NORTH CAROLINA 10 Chair Bedford said she wanted to discuss community resilience hubs. She said right now there are just schools being used but if people need to be housed for a longer period and schools need to start back would they need to house people in a different place. She asked if the $212,000 is intended to buy generators. Amy Eckberg, Sustainability Projects Manager, said there was some funding allocated to establish some resilience centers, and they are looking at having them serve as areas that can provide refuge during storms when the power is out. She said ideally, they would run off of solar power. She said that the value of these centers was evident during Helene. She said they are looking at the Senior Centers for the hubs. She said she was excited to announce that they just received a grant for solar installation on the Cedar Grove Community Center for almost $200,000 from the State Office of Energy. Chair Bedford said that is wonderful. She asked if it would come back and if some of the $212,000 could be used for some of the RENA expansion to create one of these hubs. Amy Eckberg said yes. Alan Dorman said all community centers and senior centers have whole building generators. Chair Bedford asked if the funds are needed then. Amy Eckberg said the funds would also be used for solar and battery backup storage along with other resilience features. 11 Slide #11 FY2025-35 Recommended Capital Investment Plan Environmental Protection and Climate Action Transportation Goals • Electric Vehicle & Infrastructure IL Study - $100,000 (p. 59) 0 — Climate Action Plan includes a goal to transition the County's fleet to electric by 2035 — Study will help develop a comprehensive implementation strategy for this transition f • Analyze the size of the fleet to right size • Review purchasing options oRw�c'` Y • Identify barriers to Fleet conversion • Create an EV charging infrastructure implementation plan—right number of chargers in the right places Commissioner Carter asked how the planning listed in slide #11 connects to future EV projects. Travis Myren said those future projects would be guided by this study. Commissioner McKee asked if there is anyone on staff who could perform this study. Travis Myren said he could not think of anyone on staff with the technical expertise. Commissioner McKee said locating charging stations would be based on vehicle numbers in the area and the space they would need. Travis Myren said there is a need for market knowledge and staff is at capacity so there is not a person available to do this work without taking from another project. Commissioner McKee said some of the worst decisions he has made over the last 15 years have involved studies and consultants. He said he understands that he may be walking past dollars to find pennies but at some point, they are going to have to start looking at pennies. Chair Bedford said locating EV charging stations is a small part of the study. She said reviewing purchasing options to compare strategies and figuring out what sets them up for the most value is an additional part of this study. Commissioner McKee said he would like a presentation for the current fleet of EVs and gasoline vehicles, so they can compare apples to apples. He said he would like to see cost of running the vehicles per mile and repair costs. Chair Bedford said climate change should also be included. She said they have reviewed elements of it, but they have not had a full presentation. She said it might be that they ask the consultant to do that. Travis Myren said that type of analysis is part of the scope for the consultant. Commissioner McKee said he understands the trend is toward electric and he has no issue with that, but he wants to make sure they follow their fiduciary duty to the public. Amy Eckberg said the county is still able to take advantage of direct pay rebates and that is 30%. She said they can get a huge chunk of money back for any electric vehicle purchases and those funds could be re-invested. She said staff does not have the capacity to figure out what their electrical capacity is and that is something that they need to study. 12 Chair Bedford said that this would be taken as a petition to include that in the study. Slide #12 FY2025-35 Recommended Capital Investment Plan Environmental Protection and Climate Action Built Environment and Energy Goals • Electrical Upgrades $175,787 (p. 60) — Robert& Pearl Seymour Center-$107,437 • Add additional lighting and reworklinstall outlets — Fuel Station- $14,850 • Full electrical system renovation — Emergency Services Station 1 -$3,500 • Update distribution panel — Energy Efficiency LED Upgrades - $50,000 ORANGE COUNTY NORTH CAROLINA 12 Chair Bedford said that in year 4, costs go up dramatically for electrical upgrades. She said there was also an upgrade for the Justice Center in the future, which does not seem to be necessary given discussions about other Justice Center improvements. Travis Myren said that any upgrades would be timed with other projects. Chair Bedford said there is $1.1 million in year six for a full electrical redo at the West Campus and for the Passmore Center in year seven. She asked what a full electrical redo includes. Angel Barnes said a full electrical redo looks at lighting fixtures, breaker panels, transformers, and automatic or manual switches. She said equipment wears out over time and this would look at anything from the transformer over. Chair Bedford said it is like a schedule for replacing roofs. She asked why that is not needed for residential. Angel Barnes said it is recommended for commercial buildings. Commissioner McKee asked if it is recommended maintenance. Angel Barnes said yes. Commissioner McKee asked if it is recommended from a safety perspective or safety audit. Angel Barnes said not from a safety audit. Commissioner McKee asked if they moved it back and verified that there are no safety issues if there is a requirement to hold to the recommendation. He said he did not believe it would be necessary. Chair Bedford said they pay about $55,000 every year for the inspection of roofs and asked if it is possible that they can adjust and get the electric inspected. Alan Dorman said if it were a safety issue they would have a different approach but that it is not at this time. 13 Commissioner McKee said he wants to make sure they are safe, but this is a private industry standard that was developed by people that sell this material. Commissioner Carter asked if there are insurance implications. Travis Myren said this is in the context of a 10-year plan. He said that as projects get closer, they can look to see if anything can be pushed out farther. He said a 10-year plan is meant to capture expected costs so the county can plan. Chair Bedford said if it can be moved two years, that could save $2-$3 million dollars and those could be saved for other emergency needs and it would make a difference in debt service, as well. Commissioner Fowler asked what the recommended frequency is for full electrical redoes. Angel Barnes said she would look into it. Commissioner McKee said you do not want to wait for things to get bad or for buildings to collapse because the county delayed necessary improvements. He said that he does not want to continue the mindset of everything is fine and we can keep doing as they have been doing. Commissioner Carter asked if there are any operational savings from the upgrades. Travis Myren said they are representing a general decline in the rate of increase based on the energy efficiency. Chair Bedford said that would have to do with LED lights but not necessary the transformers and wires. Commissioner Fowler said the lifespan is 20-30 years and she would like to know where they are in that. Chair Bedford said it would be good to have an inspection. Alan Dorman said West Campus was built in 2009 and he said they built a lot of buildings between 2007-2009. Commissioner Fowler said it looks like we are using the 20-year rather than the 20-30- year plan. Slide #13 14 FY2025-35 Recommended Capital Investment Plan Mission Support �■ • Evidence Storage Building- $3,708,500 (p. 63) — Current evidence storage is in the former detention center facility — New building to be located at the Northern Campus on US 70 West — Includes office space for staff members who manage the evidence — Size and scope of new facility under review as part of the Justice System Space Needs Work Group1 ORANGE COUNTY is NORTH CAROLINA Travis Myren said that if the Sheriff's Office is moved to the Link Building, there will also be capacity for "warm" evidence storage. He said that it would decrease the size of the evidence storage building listed in slide #13 and reduce the cost to about $2.4 million. He said the smaller storage building would still be needed for"cold" storage. Chair Bedford asked what the timeline is for deciding on the Link Building and amending the budget. Travis Myren said that staff will work with the Sheriff's Office to make a final determination and then they will bring that back to the Board as a budget amendment. Slide #14 15 FY2025-35 Recommended Capital Investment Plan Environmental Protection and Climate Action Built Environment and Energy Goals Facades $1,365,800 (p. 64) — Exterior doors, windows, sidewalks, retaining walls, loading docks - i • Richard E Whitted Complex(Buildings A&B) — Replacement of Exterior Windows- " $1,045,000 — Replacement of Exterior Doors&Retaining Walls-$302,450 �` ,y ryIOMWM4Y4nMiM®MiE. • Gateway Center-Awning over entrance door 11�� -$15,000 j • Eno Mountain Equipment Storage- SidewalklConcrete Repairs$3,350 1 ORANGE COUNTY 14 NORTH CAROLINA Chair Bedford asked when the last time the windows in the Whitted Building were updated. Alan Dorman said some were more recent, but many were from 2004. 16 Slide #15 FY2025-35 Recommended Capital Investment Plan Mission Support • Facility Accessibility, Safety, and Fire Alarm and Fire Suppression System Security Improvements - $25,000 Replacements - $511,740 (p. 68) (p. 66) — Whitted Human Services — Facility Wide Accessibility Improvements Fire Alarm System Upgrades-$305,745 • Emergency Exit Lighting -$7,920 — Future years include elevator and security _ Animal Services system upgrades. • Fire Alarm System Upgrades-$173,075 — Fire door replacements Countywide - $25,000 • New building code requires annual inspections leading to more replacements �1 ORANGE COUNTY 6 NORTH CAROLINA Slide #16 FY2025-35 Recommended Capital Investment Plan Lovirowll eillat P oteutioo ai)o l.,ilmale Acbu(i Resifier,f communifv Goals • Heating, Ventilation, and Cooling (HVAC) Projects - $427,224 (p. 74) Component Replacement -$50,000 • Proactively maintain system components to extend the life of the systems — Justice Facility Air and Heat-$373,824 • Phased replacement of 30 of the water source heat pumps across the Justice Facility • Remainder of the heat pumps are scheduled for replacement in FY2026-27 Eno Mountain Communication Equipment Storage- $3,400 — Stores fire/EMS paging repeaters,Sheriff's Office VHF repeater,and microwave link equipment that connects to the Emergency Services Headquarters Commissioner McKee asked the age of the heat pumps. Alan Dorman said they were done around 2007. Commissioner McKee asked if there are issues with the heat pumps or if this one a schedule. 17 Alan Dorman said he would not say there are problems, but that they do not want to be too conservative on replacing heat pumps. Chair Bedford said they have lasted almost 20 years. Commissioner Carter asked about the generator projects in the CIP. She asked for a list of all buildings with backup generators. Slide #17 FY2025-35 Recommended Capital Investment Plan Environmental Protection and Climate Action Built Environment and Energy Goals Interior Finish Replacements - $152,000 (p. 76) — Seymour Center Great Hall window coverings- $61,000 — Enclose administrative check-in area at Hillsborough Commons (DSS)-$91,000 X ORANGE COUNTY NORTH CAROLINA 17 Alan Dorman said the enclosure at Hillsborough Commons was to preserve client confidentiality. Commissioner Greene asked for more information about the improvements to the Seymour Center. Travis Myren said the Seymour Center could be deferred, but the Hillsborough Commons was a priority. Alan Dorman said the Seymour Center project would increase energy efficiency. 18 Slide #18 FY2025-35 Recommended Capital Investment Plan Environmental Protection and Climate Action Built Environment and Energy Goals • Lake Orange — Dam Rehabilitation - $970,000 (p. 79) — Accommodate cost increases of Intake Tower project originally authorized in prior years based on an updated engineering estimate — Future years will replace existing emergency spillway and concrete spillway channel — Staff will continue to seek federal and private infrastructure grants to reduce the cost ORANGE COUNTY NORTH CAROLINA 18 Commissioner McKee asked if federal grants could offset the cost of dam rehabilitation. Travis Myren said yes. Slide #19 FY2025-35 Recommended Capital Investment Plan Built Environment and Energy Goals Resilient Community Goals • Parking Lot Improvements - $191,029 — Repave Board of Elections Parking- $124,242 — Repave Emergency Services Parking Lot and Driveway -$36,787 — Other Repair, Patching, Striping, Sealing - $30,000 — Review to reduce unnecessary parking and create more green spaces ORANGE COUNTY NORTH CAROLINA 19 Commissioner Carter asked if the Elections parking lot is in the flood plain. Travis Myren said yes, a portion of it. 19 Slide #20 FY2025-35 Recommended Capital Investment Plan Environmental Protection and Climate Action Green Community Goals • Piedmont Food Processing Center- — FY2024-25 Budget included replacement of the HVAC system at PFPC — FY2025-26 project adds system controls for better system management and controlAll him MR — Funded from Article 46 Sales Tax Proceeds. ORANGE COUNTY 20 NORTH CAROLINA Commissioner Carter asked if the PFPC was included in an emergency preparedness plan. Travis Myren said he did not think so, but he would look into it. Commissioner McKee asked if all the participants in the facility are private enterprises. Travis Myren said yes. Commissioner McKee said that probably would affect their participation in an emergency preparedness plan. Chair Bedford said PFPC met with Emergency Services, and they do have large capacity refrigerators and commercial kitchens. 20 Slide #21 FY2025-35 Recommended Capital Investment Plan Environmental Protection and Climate Action Mission Support Resource Conservation Goals • Plumbing Repairs - $8,900 (p. 84) Register of Deeds Automation - $80,000 (p. 87) - Gateway Center water fountains • Including bottle filling functionality - Multiyear account to finance technology improvements in Register of Deeds Office - Collection of funds is mandated under General Statute ORANGE COUNTY 21 NORTH CAROLINA Chair Bedford said in year four, septic will be done at the Cedar Grove Community Center. She said there was a study on the septic when she first was on the Board, and it is something that needs to be looked at each year. Slide #22 FY2025-35 Recommended Capital Investment Plan ; tom Environmental Protection and Climate Action Built Environment and Energy Goals • Roofing - $221,710 (p. 89) - Annual inspections and repair program - i $55,000 - Roof Replacements& Repairs • Efland Cheeks Community Center-$145,410 • Eno Mountain Comm Tower-$2,500 • Fuel Station-$18,800 ORANGE COUNTY N(IR-1-ti CAROLINA zz Chair Bedford asked about a future project for the Rogers Road Community Center. She said the project seems to have grown. 21 Travis Myren said that to accommodate all of the programming needs, the project would need to be two stories. He said that the Board could review the scope of the project. He said all of the needs were addressed by the current occupants and the Board can take a closer look. He said that the impervious surface does not allow them to build out, so they have to build up and then they have to add elevators, and it certainly affects the costs. Chair Bedford asked for this to be brought back at a future work session. Slide #23 FY2025-35 Recommended Capital Investment Plan Environmental Protection and Climate Action County Fleet EV Stations • Electric Vehicle Charging Stations for County Vehicles - $362,448 (p. 94) i — 16 Charging Stations based on current and planned EV assignments -$276,488 • Asset Management Services(2) Y ' • Eno River Parking Deck(4) • Hillsborough Commons(2) ! • Bonnie B Davis Center(3) • Transportation Services(1) • Whitted Building (4) — Additional Funds needed to complete staff EV charges approved in FY2024-25 - $86,000 23 Chair Bedford asked about the solar photovoltaic systems in a future year project. She asked if they are already put in at new builds. Travis Myren said yes. Chair Bedford asked if they are in the EMS substations. Travis Myren said that the county looks at feasibility for solar on all new buildings. He said that he saw 1,000% tariff on solar panels, so it depends on costs right now on if any of it is affordable. Alan Dorman said they are working on a feasibility study now to see where they can get the most solar energy per dollar. Commissioner Fowler asked if the EV study would be done before the charging stations. Alan Dorman said that the study would be done before implementation of any charging stations. Chair Bedford asked if an expansion of Southern Human Services Center is necessary. She said it does not seem crowded when she visits. Travis Myren said that project renovates the current space and also looks at expansion. He said the exam rooms need to be upgraded. He said they could review the expansion aspect. Chair Bedford said she would like to see figures for the cost with and without the expansion. Commissioner Fowler asked if Medicaid funding would be lost if they are not spent in a certain timeframe. 22 Travis Myren said they roll from year to year. Chair Bedford said the focus of those funds are limited. Commissioner Carter asked if the EV study could be presented to the Board. Travis Myren said yes. Slide #24 FY2025-35 Recommended Vehicle Replacements Eovuowneotai Protection and Climate Acticr Transnorlation Goals • Vehicle Replacements - $3,567,530 total (p. 95) — Public Safety Priorities • Emergency Services $2,053,304 - Ambulances(3)-$1,744,539 - Administrative Vehicles(3)-$308,765 • Hillsborough Fire Marshall (reimbursed) $9,000 • Sheriff's Office vehicles $598,271 • Total Public Safety $2,660,575 �1 ORANGE COUNTY 24 NORTH CAROLINA Chair Bedford asked if all of the ambulances are new vehicles or replacements. Travis Myren said all are replacements. Commissioner McKee asked what administrative vehicles are and why are they so expensive. Travis Myren said they are primarily SUVs and trucks that must be outfitted with light bars and equipment. 23 Slide #25 FY2025-35 Recommended Vehicle Replacements Liiviroiimental Protection and Climate Action Transportation Goals — Administrative Vehicles Electric Vehicles in County Fleet • AMS Service Vehicles (2) $119,950 with FY26 Current• Cooperative Extension Van $71,906 Recommended • DEAPR Vehicle Replacements (2) $89,635 Total county Fleet 373 373 • DEAPR Truck Replacement $54,066 Less Public Safety 211 211 • DSS Vehicle Replacement (2) $80,319 Total Non-Public Safety 162 162 • Health Vehicle Replacement (2) $72,400 Total FV•s 22 38 • Housing Replacements (2) $141,306 ev i of County Fleet 14% 23% • Planning Replacements (3) $121,979 Strategic Plan performance measure to replace at least • Tax Admin Vehicle Replacement (1) $39,160 8 non-public safety vehicles per year with electric J(1) • Taxes,Tags, Registration $72,338 FY2025-26 CIP recommends a total of 16 electric vehicles • Total Administrative $906,956 ORANGE COUNTY zs NORTH CAROLINA Slide #26 FY2025-35 Recommended Emergency Services Projects Healthy Community Mission Support • Communication System Improvements — $300,000 (p. 97) — Multiyear plan to upgrade radios for Time Division Multiple Access(TDMA) compliance • Emergency Services • Sheriff's Office • Health Department — FY2025-26 authorization would replace 15 portable and 15 mobile radios for the Sheriff's Office �1 ORANGE COUNTY 26 NORTH CAROLINA 24 Slide#27 FY2025-35 Recommended Emergency Services Projects Mission Support • Emergency Services Replacement and Renewal — $598,955 (p. 99) oil — Replacement of Emergency Medical Services Equipment • Long range replacement schedules for mission critical EMS equipment — EKG monitors ' Radios — Automated External Defibrillators(AED) - a ks — Radios — Power Air Purifying Respirator(PAPR) ORANGE COUNTY N4DR- I C:AROLINA 27 Slide #28 FY2025-35 Recommended Information Technology Projects Mission Support • Laptop and Desktop Replacements - $438,000 (p. 103) — Desktop/Laptop replacement schedule implemented in FY 2021-22 — 219 Laptops are over five (5)years old Impact of Laptop Replacement Schedule Impact of Desktop Replacement Schedule 1400 Soo - 1200 400 l000 800 300 600 200 400 200 100 0 0 FY 2024-25 FY 2025-26 FY 2026-27 FY 2027-28 FY 2028-29 FY 2024-25 FY 2025-26 FY 2026-27 FY 2027-28 FY 2028-29 0 0-4 Yrs. 5-6Yrs. ■7-9Yrs. 010+Yrs. 0 0-4 Yrs. 5-7Yrs. 08-10Yrs. 011+Yrs. 25 Slide #29 FY2025-35 Recommended Information Technology Projects Mission Support • Information Technology Infrastructure - $988,000 (p. 103) — Install Standardized AN in Conf. Rooms $20,000 — Wireless Expansion & Replacements $20,000 — Cyber Security Initiatives $120,000 — Server and Network Upgrades $390,000 — Laptop/Desktop Replacement Schedule $438,000 from prior slide — Project Total $988,000 ORANGE COUNTY 29 NORTH CAROLINA Slide #30 FY2025-35 Recommended Information Technology Projects Mission Support • Information Technology Governance Council Initiatives - $145,000 (p. 104) — New technology for Departments- Up to$250,000 per year • Update the County's website to comply with the 2024 update to the Americans with Disabilities Act(ADA)final rules — Deadline for completing this work is April 24,2026 • Multilingual chat bot on County website • Contract management module for the County's financial system — Better track contract end dates and certificates of insurance — Automates the financial processes related to contract management — Operating costs of software maintenance included by year ORANGE COUNTY 30 NORTH CAROLINA 26 Slide#31 CIP ParkPr jectLnr.M— Long Range Parks Plan No projects recommended in FY2025-26 FY2026-27 Hollow Rock-$224,000 50%funded by Durham County .L FY2027-28 Blackwood Farm Park- !r . $100,000 FY2027-29 Soccencom Phase II-$3.96 • million • FY2028-29 Little River Park II-$100,000 • 50%funded by Durham County FY2029-30 Mountains to Sea-$693,000 • ® FY2030-32 Fairview Park Improvements- $1.9 million -@ e • °-"" FY2030-32 Upper Eno Nature Preserve- • $438,000 b FY2032-34 Millhouse Road-$3.45 million 50%funded by Town of Chapel Hill FY2034-35 Northeast Dist.Park Planning- $277,265 Proiects Outside of Ten-Year Planning Horizon �E o•� � 9 Prm,kN=M � Cedar Grove Park II Planning ORANGE COUNTY Bingham Park Planning ==.s— Twin Creeks Park Planning NORTH CAROLINA Commissioner Carter asked about conservation easements listed in the CIP. She recalled that there was about $4 million that was unspent. She asked how that gets applied. Travis Myren said that would show as "prior approved funding." Kirk Vaughn said the balance of all county and school capital projects are listed in the CIP as an appendix. Chair Bedford said that on page 167, between conservation easements and lands legacy, they are expecting to spend funds that will bring the balance down. David Stancil, DEAPR Director, said there are about $400,000 worth of projects that will be coming back to the Board that have been previously authorized but not finalized. He said that there is also about $300,000 of projects that have been approved but have not closed yet. Chair Bedford asked if that $700,000 total. David Stancil said yes and that he is always conscious of what is pending and encumbered. Chair Bedford said about $3.4 million between the two that are holding space in 10-year plan but not yet borrowed. Travis Myren said yes, it is included in the debt model, and they would borrow when those expenditures would occur. 27 Slide#32 FY2025-35 Recommended Parks, Open Space, and Trail Development Projects Environmental Protection and Climate Action Grer'n com',,,,;r,if • Neuse River Rules for Nutrient Management - $175,000 (p. 114) — Alternative Implementation Agreement for Falls Lake nutrient management — Each jurisdiction agrees to budget and implement projects to reduce nitrogen levels in reservoir — Gravely Hills Middle School Stormwater Wetland Retrofit d fS r• Slide #33 FY2025-35 Recommended Parks, Open Space, and Trail Development Projects Healthy Community n Commur ' Goal • Park and Recreation Facility Renovations, Repairs, and Safety Improvements - $210,000 (p. 116) — Annual request for ongoing capital improvements • Tree repair and management • Replacement soccer equipment I` • EV Tools for park maintenance (ex� Saws) • Cedar Grove basketball court resurfacing • River Park garden repair • Little River playground natural surface • Preventative maintenance • Fairview Park access improvements — Connection to Homemont Drive and accessibility improvements around Fairview CommunQy Center �°+s ORANGE COUNTY a3 NORTH CAROLINA Chair Bedford asked about Fairview Park projects on page 108 of the CIP. She asked if Phase II will be on the landfill part of the park. David Stancil said yes and that has been reflected in the CIP. He said that once the landfill issues are mitigated and the land is usable, this will be where the park is placed. 28 Chair Bedford said she does not think that $3 million will cover mitigation needs because it had a lot of really bad chemicals listed. She asked if the $1.9 million into year 11 because she does not think it will be workable. She said that she has been waiting on the state for six years. David Stancil said that the state has the consultant's mitigation findings and has identified a consultant to create a mitigation plan. He said that things have taken much longer than expected. He said it is all paid by the state. He said that he hopes by 2026 the plan is ready for the public. He said it will go through a 45-day public hearing and public comment process. Chair Bedford said the Board has tried to prioritize making improvements in neighborhoods that have not had parks. She said that they may need to rethink Millhouse Park. She said that parks are becoming more of wants instead of needs. She asked if they sold it if they can make it deed restricted. She said the former mayor of Chapel Hill, Pam Hemminger, had really pushed to make this a joint project and at this point, she is unsure if the Town of Chapel Hill has the funds for it. She said that Alderwoman Haven-O'Donnell is pushing that it could be an economic development project if it had been sold to a private developer for athletic use. Commissioner Greene said she would like more information and discussion on the Millhouse Park project and perhaps not put it in the CIP at all. Chair Bedford said she would like to have a budget work session on that. Commissioner Greene said she does not think she is even ready to have a work session on it because she may just recommend that it not be in the CIP until they have much more information. Travis Myren said it will be added to the rolling calendar to have the discussion, and it will not be before June 17th. Chair Bedford said there are funds that are not being spent on the Mountains to Sea Trail and asked if they can be used for something different. David Stancil said the $693,000 is for the very last section of the trail and in year three or four. He said the existing funds are going to be spent on a project he alluded to just earlier, trailheads, park trails, and a very expensive highway crossing. He said a lot of the money will get used. Commissioner Fowler asked if the trailhead on Hwy 54 is where Bingham Park might be. David Stancil said no and that they envision that Bingham Park would be along the route. He said the approved master plan for Parks and Recreation, is that the Mountains to Sea Trail would connect to Bingham Park. Chair Bedford said in relation to Soccer.com, she thinks that three fields for $5.4 million is high. David Stancil said the improvements in years seven through nine are improvements to existing infrastructure. He said the first part in years three and four are for the new expansion. Chair Bedford asked if it would be legal to use occupancy tax to fund some of this. Travis Myren indicated that it could be used. Travis Myren said the next slides are related to enterprise funds and do not impact the county's general fund. 29 Slide #34 d Solid Waste m Facilities Y A. Eubanks Road District Center f+Ecas reo B. Ferguson Neighborhood Center a C. Bradshaw Quarry • S 70 Neighborhood Center N ` a D. High Rock Neighborhood Center �a E. Walnut Grove District Center 69 d 54 ORANGE COUNTY Slide #35 FY2025-35 Recommended Solid Waste Projects Environmental Arotectior '1 Climate Action Operational Support • Solid Waste Operations Building-$286,000 (p. 120) - Replacement of Crew and Vehicle Maintenance ' Buildings which are 25+years old -- FY2025-26 includes professional services for building _— design and site work --_ -- -- - - - Construction in FY2027-28 �1 ORANGE COUNTY as NORTH CAROLINA 30 Slide #36 FY2025-35 Recommended Solid Waste Projects i 'I E10R°GF b I I I EXKiNC GiYE I , I .a...,o a �a �. �,��• I ��...,. I : ,_�� „ E.4_ � � • W .•,..- mrmms E]fLOOR FLAN-OPTION I •MAINTENANCE BUILDING ADDITION ORANGE COUNTY LANDFILL FLOOR PLAN SD-1 XSXE EUE 3RD 1-EL NU NE MIS ~ANEW CREW BUILDING OMNGE COUNTY LANDFILL ,� "'"""' �' ORANGE COUNTY 36 N012TI—I CARIi Slide #37 FY2025-35 Recommended Solid Waste Projects Environmental Protection and Climate Action Transportation Goals • Solid Waste Vehicle and Equipment Replacements-$2,988,294 (p. 121) • New AC Machine -$6,000 IS Replace Front Loader#1963 - $455,681 • Replace Wheel Loader#460 -$284,586 IS Replace Skidsteer#730 -$60,243 • Replace Hook Truck#1768 - $297,024 IS Replace Ford F250#852 - $49,694 • Replace 315 D Excavator#433 -$296,604 Replace Mower#229 -$7,290 • Replace Cat 32 Excavator#462 -$337,979 Replace Mower#226 -$8,500 • Replace Ford Pickup#853 -$87,565 • Replace Wheel Loader#7154 - $202,967 • Replace Automated Curbside Truck 1966 - $447,081 • Replace Automated Curbside Truck #1967 -$447,081 ORANGE COUNTY 37 NORTH C—:AR4i 31 Slide #38 FY2025-35 Recommended Sportsplex Projects Healthy Community • Sportsplex Projects - $470,000 — Backflow Preventer and HVAC Replacements-$150,000 (p.125) — Ice Rink Rental Skate Replacements- $35,000 (p.127) — Design of New Family Change Area and Roof Structure over Artificial Turf Field - $120,000 (p. 129) — Pool Vacuum and Plaster Replacement-$165,000 (p. 130) ORANGE COUNTY 38 NOR-rH CAROLINA Commissioner McKee asked if the ice surface issues at the Sportsplex were addressed. He said some hockey players had contacted him a year or two ago. Andrew Stock of the Sportsplex said those issues were addressed and they can manage it better now. Slide #39 FY2O25-35 Recommended Capital Investment Plan • Timing for County Long-Range Facility Plan Projects County Long Range Facility Plan Projects County Long Range Facilities Plan Recommended in FY2025-35 • Following O'Brien Atkins Recommendations Year of Construction Protect County Cost • Up to$90.1 million FY2027-28 Cedar Grove Conditioned $2,635,200 • Seven Major Projects Storage FY2027-28 Emergency Services $33,571,484 Cedar Grove Conditioned Storage Headquarters • Need to move storage out of EAC for FY2028-29 510 meadowlands Admin. $3,641,385 potential reuse of EAC FY2029-29 Justice system space Needs $16,914,576 FY2029-30 Recreation Facility $21,530,703 FY2030-31 Deconstruct Old Recreation Facility $1,095,784 FY2031-32 Southern Human Services $9,628,672 TOTAL $89,117,804 39 ORANGE COOUNA Y 32 Chair Bedford asked if the county did not build a new recreation facility, what would the needed repairs be. Alan Dorman said $7.5 million would still be needed for repairs. Chair Bedford asked what kind of programming takes place at the current gym. She said it is used for basketball in the evenings. David Stancil said it is used all day for preschool, afterschool, classes throughout the day, and at night there is basketball and volleyball, rentals from the community, and summer camps. Chair Bedford said that if one of the school systems builds an elementary school or middle school, there would be an option for their gym to be built with an outside door and separate bathrooms and offices. She said that kind of facility would only be available after 6 p.m. She said it is expensive, but it was ranked high. She asked if the $7.5 million in repairs would only help the county limp along with the existing facility without improvements. Alan Dorman the facility is in need of improvements and the figure includes renovations and they have also put off several large CIP projects. He said they can do it for less, but it would be far from idea. Chair Bedford asked where the new gym would be located. Travis Myren said there is space by the motor pool and also where it is currently located. He said the opportunity cost would be that they cannot expand programming and serve more children. David Stancil said the current facility is maxed out. Commissioner Fowler asked if the new one is built, would the existing facility be demolished. Chair Bedford said yes. She said there were options for other projects to be adjusted. She said she thought there should be contingency for escalating costs of capital projects. She asked if there was a capital reserve fund. Travis Myren said there is less than $60,000 in that fund. Chair Bedford asked if there should be a contingency fund that could be tracked so staff could see what specific expenditures were higher than expected. She asked if that is allowed. Travis Myren said the expenditure needs to be connected to a capital project. He said each project carries a contingency of about 8% of the cost of construction. Kirk Vaughn said the CIP is a plan. He said once funds are borrowed, it needs to be tied to a project. He said placeholders for future years do not result in borrowing until much later. He said it could be a project basis or tied to a contingency project as part of the plan. Commissioner Fowler confirmed that 8% contingency is included. Travis Myren said yes. Chair Bedford said the expenses increase each year and they have not been very accurate on the operating side. Kirk Vaughn said it has been an extraordinary period of expenditure and inflation. He said that it has operating impacts and those are reflected on page 47. Travis Myren said they cannot borrow for operating costs. Chair Bedford said it has an impact on whether they should do the project. She said that she learned that $23 million is county pay-go and she asked if there is a history of pay-go. She said if they are framing $6.4 million causing a tax increase, it really is all of the projects together. She said she did not know that they were doing prior year pay-go. Kirk Vaughn said not every CIP cost is "borrowable." He said the $23 million in pay-go is over 10 years. He said there is a summary of the county capital on page 49, which is an incremental increase over time. Travis Myren said that if it were not for the school projects there would not be a tax increase. 33 Chair Bedford said there is an option that they could use debt for that and there is flexibility. Slide #40 FY2025-35 Recommended Capital Investment Plan • Significant Long-Range Projects — Affordable Housing • Three Five(5)million installments throughout FY2025-35 Community Center Space Needs • Rogers Road Expansion-$2.9 million in FY2027-FY2029 • Chapel Hill and Carrboro Contributions-$1.7 million • County Share-$1.2 million — Emergency Radio System Buildout • Four New Towers+Equipment Enhancements on Five Existing-$32 million in FY2027-28 • Town Public Safety Agencies-$8 million • County Share-$24 million 40 ON ONGR'rH COOUNA Y Chair Bedford asked if the Link Building project is three years out. Travis Myren said it is four years out and they will bring back a recommendation on the timing of it all. Commissioner Fowler asked if the Chapel Hill and Carrboro contributions to the Rogers Road Community Center are in addition to the $2.9 million. Travis Myren said no, and that the county's portion is $1.2 million. Chair Bedford said it is not confirmed that they want to participate. Travis Myren said they would need an inter-local agreement and that it would need to be negotiated. Commissioner Fowler said that the county is including the share for the expansion. Chair Bedford said the revenue is offsetting. Travis Myren said they are assuming the projects will be cost shared on the same basis as the original community center project. Commissioner Greene said it looks like Article 46 is being used. She asked if half of Article 46 is still being reserved for the schools. Travis Myren said yes. Chair Bedford said $500,000 debt rolled off this year for sewer. She asked if that is built into Article 46 budget. Travis Myren said there is an Article 46 model and if the debt service is decreasing, that is getting consumed by the incentives that the county approves. He said that the thought is that Article 46 pays for the incentive projects. Commissioner Carter said there is no water and sewer infrastructure included in the CIP after that $500,000 rolls off. Travis Myren said they do not have anything firm enough to be put into a plan at this point. 34 35 Slide #41 FY2025-35 Recommended Capital Investment Plan • Significant Long-Range Projects — Justice System Space Needs Work Group Update Based on April 9 Meeting • Justice Stakeholders — All functions under one roof — Secure and modem courtrooms — Short Term Plan Under Development • Concept is to move Sheriff to renovated Link Building — Current Justice System Space Needs budget can accommodate — $16.9 million in Justice System Space Needs project — $13.5 million estimate to renovate Link Building • Backfill Sheriff's Office with District Attorney and Public Defender and perhaps others — Longterm plan • New Courtrooms, Parking, Remodel existing spaces • Add Adult Probation, Juvenile Justice _ • $90+million cannot be accommodated in current 10-year plan a1 ORANGE COUNTY NOR`FHCA Slide #42 FY2025-35 Recommended Capital Investment Plan • Significant Long-Range Projects — Emergency Services Substations • $3.6 million in FY2025-26 for colocation with Town of Chapel Hill—Site feasibility study underway • $4.4 million in FY 2029-30 for Emergency Services Hub — EMS substation plus Community Paramedicine,Post overdose Response Team,and Mobile Crisis Team — Lake Orange Dam—Phase 2 • $3.8 million in FY2029-30 to replace emergency spillway and spillway channel Parks Projects • Soccer.com expansion in FY2027-28-$4 million • Millhouse Road park development in FY2029-30-$3.4 million total cost — Additional School Capital Needs • Total School Capital Needs-$1 billion • Continued Planning and Vigilance ORANGE COUNTY 42 NORTH CAROLINA 36 Slide #43 FY2025-35 Recommended Capital Investment Plan FY2025-35 Recommended Expenditures by Year 1e0,00o.000 $161,975,514 $164,454,928 160,a00,000 $148,073,840 140,000,000 120,000ADD 1w,w0,000 ■School Bond Projects $85,154,959 ■School Capital Ba,0u0,0a0 $76,379,922 $68,778,385 ■Proprietary Funds $65,467,782 ■County Capital 60,D00,000 $47,829,387 $42,109,162 40,000,000 $35,579,104 20,000,000 D FY 2D25-26 FY 202E-27 FY 2027-28 FY 2028-29 FY 2029-30 FY 2030-31 FY 2031-32 FY 2032-33 FY 2033 34 FY 2034-35 43 ORoR l-�ECOUNATY Chair Bedford discussed the three tranches and if expenditure speed impact the tax needs. Kirk Vaughn said that there is a slide that covers that in detail coming up. Slide #44 FY2025-35 Recommended Capital Investment Plan Debt Service Schedule through 2025-35 $90,000,000 $80,632,7a5 576.636,345 580,000,00E $70,0,EOD 967,291,643 S68,862,899 $64,a38,44] $6D.00o,000 557,182,a19 $s0,a00,o00 $45,ae4,4 539,920,629 $4DO ,D00 $32,460,117 Borrow on $30,000,000 first Bond Projects 520,000,00E $10.aao,000 5 FY2025-26 FY2026-27 FV027-28 FY2028-29 FY2029-30 FY2030-31 FYZ031-32 FY2032-33 FY2033-34 FY2634-33 ORANGE COUNTY 44 NowrH CAROLINA 37 Slide#45 FY2025-35 Recommended Capital Investment Plan Annual Debt Service Payments on Existing and Proposed CIP Debt seo,000.oao s2n,o9o,om 96o,a9o,ovo sw.coo.ow $-0 W.000 ¢10,d6p,600 sm.o9o.oao 81ga9opm b •Er i Mug N bt Service •Props CIPCebtS.— 45 ORAN GE�COUNTY NIDSlide #46 FY2025-35 Recommended Capital Investment Plan Debt Service to General Fund Revenue Policy Compliance FY2025-35 2x% o% 19-13% 18.63% iB.13% le% 17.76% 17_efi% 1b.43% 16% 19.09 ld% u,96% 12% ID% FY2025�26 F12n26.27 FY2c27.28 FY2028.29 FY20293D FY203a FY20333 FY203z33 PY203334 FY2014-35 y�Pd ky T9r8H —Pr J—d �1 ORANGE COUNTY 46 NORTH CAROLINA Commissioner Carter asked what the statutory requirements are for debt. Travis Myren said there are no legal, statutory requirements, but it is considered a best practice according to government finance professional organizations. He said it also considers the comfort level of rating agencies. He said there is a law about the percentage of assessed valuation that can be dedicated. 38 Chair Bedford said they are nowhere close to that limit. Travis Myren said they are not close at all. Slide #47 FY2025-35 Recommended Capital Investment Plan Funding the Plan • Pay-Go—1.98 cent tax increase in FY2025-26 • Debt—No tax increase required in FY2025-26 • County has options for how to fund future debt service increases in the future Fiscal Year Incremental Tax Upfront Tax Tranche 2026 2027 1.78 7.68 4.0 2028 1.77 2029 2.91 2030 1.59 4.0 2031 0.19 2032 2033 1.04 1.4 2034 0.73 _ Total 10.01 7.68 9. o ORANGE COUNTY 47 NOR'I'1-I CAROI.INA The Board indicated that they were interested in an incremental tax strategy as listed in slide #47. Slide #48 FY2025-35 Recommended Capital Investment Plan • Schedule for Consideration — Work Session on Capital Investment Plan April 22 — Further Consideration through Budget Work Sessions May-June — Approval of the Operating and Capital Budget June 17 ORANGE COUNTY 48 NOR-rH CAROLINA 39 Slide #49 Questions? ORANGE COUNTY N4DR-r I CAMOLINA Kirk Vaughn made the following presentation: Slide #1 ORANGE COUNTY NORTH CAROLINA School Capital Investment Plan FY 2025-35 April 22, 2025 Board of Commissioners Work Session 40 Slide#2 What has changed from prior School CIPs • Adoption of the School Capital Funding Policy (Page 177) & Major Project Planning Addendum (Page 181). - School CIP has been reorganized into three sections (Major Projects, High Priority Needs, Other Capital Uses) • Inclusion of Major Project plans by both school districts, with county staff assisted sequencing. Phasing in of Pay-Go funds to assist Major Project funding - $6.4 M in FY 26, full $10MinFY27 • Project-based allocations for High Priority Needs Projects. • Questions about specific projects can be directed to School Staff at May 15th Education Budget Work session �1 z ORAN HE COUNTY NTOSlide #3 Major Projects — Projects and Sequencing • CHCCS — Pages 132-134 - FY 26 Carrboro Elementary, FY 27 Estes Hills Elementary and FY 31 Frank Porter Graham Elementary replacements • OCS — Pages 151-153 - Tentative plan of FY26 Elementary School Replacement, FY 30 Major Renovation Elementary School, FY 31 Major Renovation Middle School - District currently in public review of three options that differ from plan presented to the county. • County used the following rules to sequence these plans - Bonds must be borrowed within 7 years of referendum. May ask for 3-year extension with LGC. - Once borrowed, funds must be drawn down for actual expenses within 3 years. - Funds are allocated between the districts fairly and within the tax impact as presented to the public. ORANGE COUNTY 3 NORTH CAROLINA 41 Slide #4 Major Projects — Projects and Sequencing • Every year, the Bond funds will be able to fund less impactful investments. Staff wanted formula to quantify that loss in value. — Net Present Value Formula • If you divide the NPV by the total funding provided to that district, you get an estimate how much each district loses from being allocated in future years. Net Present Value/Total Funding Original Tranche Model 90.78% CHCCS Sequencing 90.70% OCS Sequencing 90.71% • Both bond plans lose about the same value from being allocated in future years and are within our original tanche model. • The $300 M Bond plan spread out over 7 years is worth the same as if we funded $272 M in projects all in FY 2025-26. 4 OP,ANG CA OLINA COUNTY TTOR'FHChair Bedford asked what interest rate is assumed. Kirk Vaughn said 3%. Slide #5 Major Projects — Projects and Sequencing Bond Funding By District $60.000.000 $70,000,000 $69.13 M $60.000.000 $51.28 M $62.68 M S50,000,000 $47.70 $40,000,000 35.84 M $80,000.000 $28.50 M S20.000.000 $10,000.000 $6.0 M. 0.42 M$3.68 M g ■ $.77 M FY 202a Fv 2027 F 2o2a FY 2029 FY 2030 FY 2031 FY 2032 ■CHCCS Funding ■OCS Funding *Planning Funds for 005 Elementary Replacement using Bond Funds, not Pay-Go ORANGE COUNTY 5 NowrH CAROLINA 42 43 Slide #6 Major Projects — Project Costs and Funding Source • Major Projects are funded using a combination of Pay-Go and Bond Funds. CHCCS Projects Bond Funds Pay-Go Funds Total Funds OCS Projects Bond Funds Pay-Go Funds Total Funds Carrboro Elementary $ 47,700,000 $ 5,300,000 $ 53,000,000 Elementary Replacement $ 57,283,000 $ 2,817,000 $ 60,100,000 iEstes Hills Elementary$ 51,547,000 $11,283,000 $ 62,830,000 Major Elementary Renovation $ 27,000,000 $ 3,000,000 $ 30,000,000 Frank Porter Graham $ 63,901,300 $ 6,240,000 $ 70,141,300 Major Middle School Renovation $ 37,340,000 $ 7,660,000 $ 45,000,000 Contingency+HPN $ 11,551,700 $31,050,999 $ 42,602,699 Contingency+HPN $ 3,677,000 $22,649,001 $ 26,326,001 Total $174,700,000 $53,873,999 $228,573,999 Total $125,300,000 $36,126,001 $161,426,001 • Pay-Go funds provide four major uses to support the Bond Program: - Absorb soft costs like Design, Project Management Project Management included in separate$1 M/year project not allocated to either district pending ILA negotiations. - Extend project budgets above what the Bond could support on its own. - Improve County debt metrics once county debt exceeds 15% of GF revenues - Once bond projects are done, support the districts'High Priority Needs �1 s ORAoR GE COUNrH ATY Slide #7 Major Projects — Pay-Go Phase-in To spread out tax burden, the Manager's Recommended CIP splits Pay-Go introduction into two steps. $6.4 M in FY 26, and an additional $3.6 M in FY 27, to reach $10 M target. - To maintain$100 M over 10-year commitment,the $3.6 M shortage in year 1 is added incrementally into the later years of the plan. Reaches $11.2 M in year 10. • $6.4 M is tied to specific project activities listed below. Amount Usage Convert to Bond Proceeds? Design funds for Carrboro Elementary $5.3 M (pg,132) Yes.Can borrow design with construction in FY 27. Not directly.Would need to be tied to specific Project Management Set Aside(pg. projects to be borrowed.Would increase project $1.0 M 164) budgets. Preliminary site selection and design forPossibly.Only if construction on project occurs by FY $100 K OCS Elementary School(pg.151) 27. �1 ORANGE COUNTY 7 NORTH C:AROLINA 44 Slide #8 Major Projects — Pay-Go Phase-in Staff can rework Pay-Go Phase-in to further delay tax increases. Though would need direction from Board in how to adjust overall plan. Four possible adjustment frameworks: 1. Reduce Pay-Go in early years, reallocate funds for additional Pay-Go in backend to maintain $100 M over 10 years. Impact: Less funding available to Major Projects, increased funding for later High Priority Needs. 2. Reduce Pay-Go in early years, do not reallocate funds to future years. Impact: Less funding available to Major Projects. 3. Delay district projects by a year, requiring later pay-go introduction. Impact: Increased Major Project costs due to inflation, less time to complete projects. 4. Reduce Pay-Go allocation across ten-year plan. No longer target $10 M/year. Impact: Less funding available total.Worse debt metrics. ORANGE COUNTY 8 NORTH CAROLINA Chair Bedford said she thought that they would be approving projects separately and considering how each one is going. Kirk Vaughn said a school CIP is similar to the county's CIP, where it is a plan, but only year one is approved at a time. Commissioner Fowler said she thought the county needed to see the entire budget before determining how to approach pay-go. She said she would like to keep as much of the pay-go as possible and if they were forced to choose, she would choose #1. She said it depends on the total bill and what that would mean. Commissioner Carter said she preferred to look at option 1, with option 3 possibly in tandem. She said there are federal cuts coming to major programs that will impact them operationally and those will not be known for some time. She said that Medicaid will be significantly cut so she would like to be flexible on pay-go because that may be hard for them. Chair Bedford said she was thinking of a form of option 1, where pay-go is reduced in the first year and borrowed. Kirk Vaughn said that is option 1. He said that bond funds would fill in where the pay-go was reduced. He said it would cut bond funds from a later project. Commissioner Greene said she hoped they could keep all of the pay-go. She said she did not support options 3 and 4. She said option 1 is her first alternative. Chair Bedford said she agreed with Commissioner Greene. Commissioner McKee said he is more inclined to option 2, because of concerns about costs of schools. He said that options 1 and 2 were his preference. Chair Bedford said that they will discuss project management in the schools in the fall. She said they will have to make decisions as a Board about how to move forward. She said they have agreed that the construction manager at risk has more value than the others and they may need to explain that to the schools. Kirk Vaughn said the current structure has the school having the contract with the construction manager. 45 Commissioner Carter said having the construction manager at risk will mitigate some of the costs. She asked if the county is still pursuing a program manager to manage all projects in both school systems. Travis Myren said those funds could be used for program management. He said this needs to be negotiated with the districts. He said that a county staff person can be brought on rather than a consultant and they can use the pay-go funds to fund salaries. Commissioner McKee said projects will get more and more expensive and the county will need to lock bids down to keep from escalating. Chair Bedford said they spoke a bit about this at the Durham Tech meeting, and they have a person working with them on resourcing and timing. Commissioner McKee said it will be key to not let costs get away from us. Chair Bedford said they may not get a third school, depending on expenditures. Commissioner McKee said the funds will not go as far as hoped. Slide #9 Major Projects — CIP Pages and Presentation Each of the districts three Major Projects are listed as separate project pages. The remaining funds are listed in a remainder project (Page 135,154), with a detail sheet that districts have provided to identify usages: ftErnnl � Yeul YYrl YMe3 Yv Ype5 Yvfi Y[+r) Yerj Yv9 YSRYIR C+nporo fkmenl+ Repl+[emml Xlaod a.101(IGa S !)nU 04 fsl[a Xrllt Ekmemary Replacemrn Xlml $ 6.383.00 $ 56,55).OW nR pprter Gunam 9arrgye XnpRl Reels[.•- MCDo�le fkmenury nIIMa - W1] Mc[brgle MMGk Sebol Ml[I..� W31 i6459J [ndpN Xal Xr nXnOd $ 6.tIW,OW Morns G(w[Ekm[nury - RatNnCkmerrtary 5 3.81.]1i Mary XrOgp CMmpmdry acMal - 5 3.ID5.WG xv YrR ENmem+ry 5[Mal .rwl Reearr:,i. S 9:?C: F p[iut Ekm[nlary nl IMdrrt Eurmrn5l W 31 :R 83] o[vawme ,nmeer :.ux,eea PFrldpt Mltltlk Xnwl snJaumlwPrm7llV:i 5 I,]+fi,IOa PInIL aMAtlk XFcol MIiM+mIlW 5to 3 9 Id+5.9a5 OntrFt Wife S 16).353 5 <.369.LW Remainder funds will be split into specific project pages for any projects in year 1 of a future CIP. � — ORANGE COUNTY 9 NOWIM CAROL INA 46 Slide #10 High Priority Needs — CIP Pages and Presentation CHCCS Pages 137-144 OCS Pages 156 - 160 $4,235,042 $2,091,178 • High Priority Needs projects funded by existing annual debt funding and lottery proceeds funds. • Project based allocation - Individual Project Pages for all projects with FY 2025- 26 funding, identifying the specific project and the Woolpert definition. Summary Project for all remaining years 2 - 10 funding. New Hope Elementary-Roof Replacement Project Category S,h- I Eu—ianal Sa MleArea: Education Department: Orange County Schools Strategic Allgnment: public Education/teaming Community Objective Project Number. OCSHPI Dim ate Action Plan: N/A $1,397.610 in FY 2025-26 and$594,690 in FY 202&27 is budgeted to complete a roof replacement at New Hope Elementary School.This project is identified as level 2-Essential in the Woolpert framework as adopted by the Board of County Commissioners, 10 ORANGE CA COUNTY Slide #11 Other Capital Uses — CIP Pages and Presentation CHCCS Pages 145 -148 OCS Pages 161 — 163 $3,826,002 $2,555,118 • Other Capital Uses projects funded by existing Article 46 and Recurring Capital funds. Both tax supported Pay-Go sources. • Purpose or Function based allocation — Project Pages based on type of expense, regardless of location. • Allocated to both districts' Technology replacements, Rental expenses and Recurring Capital allocations. ORANGE COUNTY 11 NORTH CAROLINA 47 Slide #12 Supplemental Deferred Maintenance CHCCS - Page 149 $9,000,000 Last tranche of $60 M, allocated between districts based on ADM at point of allocation. Funds predated current School Funding Policy, so allocated in one purpose or function project code. District provided detailed usages and alignment to Woolpert priorities on Page 150. 12 ORAN GE ACOUNATY Commissioner Carter asked what the last tranche of$60 million was for. Chair Bedford said that was for maintenance needs at the schools. Slide #13 Questions? ORANGE COUNTY NORTH CAROLINA Commissioner Fowler asked if staff could model how delaying pay-go as in option 3 on slide 8 would impact the tax rate. Travis Myren said they could provide that. 48 Kirk Vaughn said he could model different scenarios for the Board. Chair Bedford said that in a previous meeting, she asked about spending speed and the three tranches and was told that it does not make a difference. Kirk Vaughn said the way they paid for those projects happening more quickly is it took out from 29 and 30 so it was split out to remain neutral. He said if they take the first-year projects and slide them back, we could not slide the savings, and it would not really change the incremental tax rate. Adjournment A motion was made by Commissioner Greene, seconded by Commissioner Fowler, to adjourn the meeting at 9:27 p.m. VOTE: UNANIMOUS Jamezetta Bedford, Chair Recorded by Laura Jensen, Clerk to the Board Submitted for approval by Laura Jensen, Clerk to the Board