HomeMy WebLinkAboutAgenda - 05-18-2004 - 9dORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: May 18, 2004
Action Agen a A
Item No. ql
SUBJECT: Acceptance of Recommendation of Justice Facilities Architect Selection Group;
and Contract Approval with Consultant
DEPARTMENT: Purchasing and Central PUBLIC HEARING: (Y/N) No
Services
ATTACHMENT(S):
GRZ Cost Proposal
INFORMATION CONTACT:
Pam Jones, (919) 245-2652
TELEPHONE NUMBERS:
Hillsborough 732-8181
Chapel Hill 968-4501
Durham 688-7331
Mebane 336-227-2031
PURPOSE: To consider accepting the recommendation of the .Justice Facilities Architect
Selection Group; and approving a contract with Corley Redfoot Zack Inc, (CRZ) of Chapel Hill to
provide consultant services associated with the design of the Justice Facilities Expansion -
Phase I, the Farmers' Market and the design of trail system in River Park,
BACKGROUND: The Board is aware of the near decade-long planning process from which the
Justice Facilities Expansion project has evolved, The Phase I program will include an
expansion of the existing New Courthouse that approximately doubles its size, The
approximately 27,000 square foot addition will house existing occupants including the District
Court, the Clerk of Court, the District Attorney and various areas that will be shared among a
variety of partners (the County, attorney-client conference office, visiting offices for court-related
agencies, etc.). The Sheriffs Department will relocate their operations from the existing
building at 144 Margaret Lane to the New Courthouse expansion as well.
Other components of the project will include the construction of a Farmers' Market and
development of the River Park area behind the Courthouse,
• The Farmers' Market was fianded through a $90,000 grant facilitated through
Congressman David Price's office and is planned for completion prior to the completion
of the Expansion project.
A preliminary park design was formulated by a task force several years ago and includes
low impact recreation areas with trails and picnic tables, grills, etc, The services
contained in the contract with CRZ would refine the design such that it may be bid in
tandem with the Expansion and the Farmers' Market.
The Architect Selection Team included:
• Judge Wade Barber
• Judge .)oe Buckner
• James Stanford, Clerk of Court
• Lindy Pendergrass, Sheriff
• Moses Carey, County Commissioner
• Barry Jacobs, Chair, County Commissioners
• John Link, County Manager
• Cathleen Turner, Alliance for Historic Hillsborough
• Todd Dickinson, Restoration Specialist
• David Stancil, Environment and Resource Conservation Department Director
• Pam .)ones, Purchasing and Central Services Director
This group reviewed all seven proposals that were submitted and selected four firms far
interview. Interviews were held on Monday, April 19, with Corley Redfoot Zack (CRZ) being
recommended for the work,
CRZ has assembled a team of qualified professionals to supplement their own experience with
projects such as the proposed expansion project. The full design team will include:
• CRZ
• Carter Goble, Inc, -Justice facility programming and planning
• Donald R, Truelove -Security Consultant
• Swanson and Associates, PA -Landscape Architect
• Reece, Noland & McElrath, Inc, -Mechanical/Electrical/Plumbing/Technology
• Lasater-Hopkins-Change, PC -Structural Engineering
• Cost Plus -Cast Estimating
CRZ has quoted a lump sum fee for the project of $669,800 as summarized below:
• Basic Services for Courthouse, Park and Farmers' Market Project - $520,800
• Additional Services - $119,000
o Master Planning the Campus
o Programming/Space Planning for existing Courthouse
o Approval process
o Coordination with County's Construction Manager
• Reimbursables - $30,000
o Direct bill for such items as printing, copying, postage, shipping, etc,
o Property survey (allowance of $10,000)
Detailed information regarding each of the elements is included in the attached proposal.
Upon the Board's acceptance of the Selection Team's recommendation, acontract that
incorporates these elements will be drafted for review by the County Attorney and signature by
the Chair to the Board.
CRZ is prepared to begin work with the interior and exterior design groups soon after execution
of the contract, Pursuant to a preliminary schedule submitted by CRZ, the construction of the
projected is slated for completion around July 2007,
FINANCIAL IMPACT: Funds totaling $294,375 are currently available for architectural services
related to construction of the Justice Facility Capital Project Qrdinance. The additional funding
of $226,425 needed for the Corley Redfoot Zack contract for architectural services would be
included in the upcoming 2004-14 County Capital Investment Plan. The Debt Issuance
Schedule that the Board endorsed on May 5, 2004 included alternative financing in the amount
of $6 million for construction of the Justice Facility
RECOMMENDATION(S): The Manager recommends that the Board accept the
recommendation of the Architect Selection Group and authorize a contract with Corley Redfoot
Zack (CRZ), consistent with the cost proposal elements cited herein; and authorize the Chair to
sign a contract, contingent upon Attorney and staff review,
~ ~ CORLEY REDFOOT ZACK .C
n a c l-{ i~ e c rs e~ c i~ c e a s r i_ A v N E a s
April .30, 2004
creNN D.. corsrev,AO, County of Orange
Pmadrnr. ceo Department of Purchasing and Central Services
KENNEra E. Reoroo-r„+r,~ Post Office Box 8181
w~,• p,«;dc~'r Hillsborough, NC 27278
mARKZACK,AO, ATTN: Ms. Pamela K. Jones, Director
Via• Presidcirt
hvaiAEU. r,Amh,enst.EV re RE: Orange County Justice Facilities Courthouse Expansion
+'""°F'°+ Hillsborough, North Carolina
LAUIiENC[ W. DUNCH,AIA PROPOSAL FOR PROFESSIONAL DESIGN SERVICES
ASSncinte
.W DREW R. CRUICKSt1AMC, AIA Dear Ms. Jones:
.~hsocinh•
DAVID ht. TAYLOR, ,,~., Corley Redfoot Zack, Inc., is pleased to submit to you our fee proposal to
a;,odn+~' provide design services for the above-referenced project. We are excited about
HARRY hi. IENSEN Orange County's challenge to our team to design a sustainable facility usuzg
~~`°~"'+~' High Performance Building Standards, while remaining sensitive to the historic
KENNETH E. shnni fabric of downtown Hillsborough. Toward that end, we submit the following
,~><ednrc proposah
The proposal is based on our understanding of the project from information
gathered from the Request for Proposal packet, the interview and designer
selection process, and subsequent telephone conversations with you.
PO hoc 2368
Chapel Hill, NC 27515-2368
222 Cloister court
Chapel I-lilt. NC 2751 d-2212
Corley Redfoot Zack's consultants for the project are as follows;
1, Carter Goble, Inc.:
Columbia South Carolina
2. Donald R. Truelove:
Hillsborough,NC
3. Swanson and Associates, PA:
Chapel Hill, NC
4. Reece, Noland & McElrath, Inc
Waynesville, NC
5. Lasater•Hopkins•Chang, PC:
Raleigh, NC
6. Cost Plus:
Clemson, SC
Justice facility prograznming and
planning
Security Consultant
Landscape Architect
Mechanical/Electrical/Plumbing - -
Teclmology
Structural Engineering
Cost Estimating
The proposal has been broken down into distinct components of work to clrarl~
(919) 9d2-s~86 Telephone respond to the variety of services needed for this project:
(919) 9?9-1302 Fac
5
Ms. Pamela K. Jones, Director April .30, 2004
RE: Courthouse Expansion Projects page 2
MASTER PLANNING PHASE:
1, Information Gathering: One of the first steps in developing a conceptual Master Plan and
further detailed development plans is to assemble all relevant information pertinent to
making future design decisions. We will work with you and other user groups to gather as
much information as possible. The development program, site constraints, significant
features, the context of the area, the impact the project may have on the adjoining
neighborhoods, and the character of downtown Hillsborough will be studied during the
information gathering phase, We will review any existing site plans you have, and we will
have a survey completed of the project area.
2. Compilation of miscellaneous existing Courthouse floor plans (provided by Owner) into a
comprehensive floor plan showing the New Courthouse in its present condition.
3. Kick-off meeting with the Interior and Exterior Committees to review the project and to
receive input regarding the overall project and its individual components.
4, Based on input received at the kick-off meeting, the design team will present Master Plan
options to the joint committee at subsequent meetings with various iterations studied and
presented, we can produce a final Master Plan for the Court campus..
5. The final Master Plan will be used to communicate to all concerned parties the objectives for
developing various portions of the site. This process will allow us to develop a consensus
for further presentations as we move into subsequent phases of the design.
The design fee for the Master Planning phase of the project will be $30,000.
COURTHOUSE EXPANSION PROTECT:
An approximately 27,000-square-foot addition to the New Courthouse Building located at the
corner of Churton Street and East Margaret Lane to house the Sheriff's Department, office
space, additional courtroom space, and "flex" space.
The programming and design of a new entrance to serve the new facility and the existing
courthouse are important elements in the design work.
The budget for this portion of the overall project has been set at $6,000,000, including design
fees; the anticipated occupancy date for the project is the first quarter of 2007. The actual
construction budget for building and sitework only, as well as the actual project schedule
will be determined as soon as possible during the design phase.
PROGRAMMING/SPACE PLANNING PHASE FOR
THE COURTHOUSE EXPANSION PROTECT:
Corley Redfoot Zack, Inc., and Carter Goble will perform these design services in a joint
effort. Carter Goble's services include the following:
CORLEY REDFOOT ZACKi~a'.
G
Ms, Pamela K. Jones, Director April 30, 2004
RE: Courthouse Expansion Projects page 3
1. Review existing Master Plan/M-P update and other available data.
2. Attend kick-off meeting
3, Conduct interviews, collect data and assess site..
4, Assemble standards and research identified teclulologies
5. Assess court operational program needs,
6. Prepare Security Concept Plan (in conjunction with the security consultant)
7. Develop draft Architectural Program (including adjacencies, movement flows and
separations)
8. Revise draft Architectural Program as required
9. Prepare final Program
10. Includes six trips to Hillsborough
11. Three field trips to various locations in North and South Carolina,
Corley Redfoot Zack will work jointly with Carter Goble to provide space planning diagrams
at various intervals in the Programming Phase. Space planning studies will be used to
enhance the user groups' understanding of the programmatic information.
The fee for this portion of the work is $70,000.
Upon your review and approval of the Programming/Space Planning phase and the Master
Planning phase of the project, the Design Team can begin work on the Schematic Design Phase of
the project, The Schematic Design Phase is the initial phase of the Basic Services portion of our
services.
SCOPE OF BASIC SERVICES FOR THE COURTHOUSE EXPANSION PROTECT:
The Basic Services include the following:
- Architectural design
- Civil Engineering design
- Security design
- Stnrctural Engineering design
- HVAC/Electrical/Plumbing/Fire Protection Systems/Technology design
- Landscape design
- Cost Estimating
- Construction Administration (Basic Services provides one visit per week to the project
during the construction period (anticipated 18-month construction period). Additional site
visits aze considered Additional Services.
Basic Services consist of the following phases and are broken down by percentages for your
information:
~ ~ ~ CORLEY REDEOOT ZACK ~.r.
7
Ms, Pamela K. Jones, Director
RE: Courthouse Expansion Projects
Schematic Design Phase: 15%
Design Development Phase: 20%
Construction Document Phase: 35%
Bidding or Negotiation Phase: 5%
Construction Administration Phase: 25%
100%
The fee for Basic Services on this project is $480,000.
PARK PROTECT:
Apri130, 2004
page 4
The development of a park on approximately five acres of land within the County
Government Campus (working title will be "River Park").
The budget and anticipated completion date for this project have not been determined at this
time.
The Master Planning phase of the project will address the Park Plan and its components in a
general way. Comprehensive planning and detailing will be handled under Basic Services,
similar to those outlined under the Courthouse Expansion project.. The Landscape Architect
will take the lead role in the development of the Park, with the support of the Design Team.
The fee for Basic Services for the Park Project is $28,800.
FARMERS' MARKET PROTECT
The design of a shelter to provide a covered area suitable for use as a Farmers' Market. This
shelter will be located within the Government Campus to serve the needs of the market
while addressing traffic patterns during market operations,
The project budget is $90,000, including design fees, and the anticipated completion date is
the second quarter of 2006,
The Master Planning phase of the project will address the Farmers' Market project and its
components in a general way. Comprehensive planning and detailing will be handled under
Basic Services, similar to those outlined under the Courthouse Expansion project.
The fee for Basic Services for the Farmers' Market Project is $12,000.
The following breakdown summarizes the fee schedule for each component of the work and outlines
Basic Services, Additional Services and reimbursable costs.
CORLEY REDFOOi ZACK me.
Ms. Pamela K. Jones, Director April 30, 2004
RE: Courthouse Expansion Projects page 5
BASIC SERVICES FEES:
1. Basic Services fee for the Courthouse expansion project only: $480,000
2. Basic Services fee for the Park project only: 28,800
3. Basic Services fee for the Farmers' Market shelter only: 12,000
Total Basic Services Fee: $520,800
ADDITIONAL SERVICES:
1, Master planning the Hillsborough Court campus: $ :30,000
2, Programming/Space Planning for the Courthouse
expansion portion of the project: 70,000
3. Town of Hillsborough approval process (assume 8 meetings (total) i.e., 4,000
5 Historic District Commission
2 Board of Adjustment
1 Mayor and Board of Commissioners)
4, Coordination with Construction Manager: 15,000
Total Additional Services Fee: $119,000
REIMBURSABLES:
Estimated reimbursable expenses will be billed at direct cost on
the monthly statement and include the cost of such items as the following:
1, Printing and copying costs/postage/shipping for overall project: $ 20,000
2. Property survey at an anticipated cost of (allowance): 10,000
Total estimated Reimbursables: $ 30,000
TOTAL FEE:
Total overall fee, including Basic Services for all three components of the project,
Additional Services and Reimbursables: $669,800
SERVICES NOT INCLUDED:
- Legal fees
- Geotechnical investigation
- Town pernutting or approval process fees
- Renderings or models
- Construction Administration beyond Basic Services
- Interiors and furniture selection
- Traffic Consultant
- Meetings with Historic District Commission, Board of Adjustment or Town Cornrnission
beyond those scheduled under Additional Services.
- Wetlands delineation
CORLEY REDFOOT ZACK i..x.
Ms. Pamela K. Jones, Director April 30, 2004
RE: Courthouse Expansion Projects page 6
- Flood Plain mapping
- NCDOT permitting
- Extensive renovations to the existing Courthouse building, including Mechanical, Electrical,
Plumbing and Fire Protection systems
- Testing of materials during construction period
- Asbestos survey or lead paint removal from existing building
- Travel expenses for site visits to similar court facilities
SCHEDULE
We have included for your information a preliminary project schedule showing
approximated completion dates for the various phases of the project, A final Project
Schedule will be determined early in the design process.
We will be prepared to execute the AIA Standard Form of Agreement Between Owner and Architect
as our formal agreement with the County at your request..
Please call me if you have any questions or comments on the above proposal. We are looking
forward to this challenging project and will dedicate our expertise to meet the expectations of
Orange County and its citizenry.
Sincere y, r
eth E. Redfoot, AIA
Vice President
KER:esw/0417-pro
Enclosures
cc Glenn D Corley. A[A
1 1 1 CORLEY REDFOOT ZACK..c.