Southern Community Park
This park, located off US 151501 adjacent to Dogwood Acres and south of Southern
Village in Chapel Hill is in the design stage with Special Use Permit drawings under way.
The approved master plan includes connection to the existing park and ride lot, a roller
hockey court, two basketball courts, two parking areas, future recycling site, future
community center, two picnic shelters, a playground with observation deck, a children's
splash play area, iestrooms with a maintenance building, three soccer fields, a youth
baseball field, meadow, dog park, greenway trail and three resource conservation
districts. Funding allocated for this park totals $2,842,441.
The master plan has undergone some minor revisions to accommodate improvements in
design of specific components and in the overall design. They include clustering of the
dog park,baseball field and meadow to the area immediately south of Dogwood Acres
Drive and the reorientation of the soccer fields to a north/south configuration.
This park is subject to the Town of Chapel Hill's "Percent for Art"project. The Orange
County Board of Commissioners has agreed to commit 1% of the county funding for this
project to an art component in the park, A Request for Qualifications for Public Artists
has recently been distributed and an artist or team of artists may be selected by June.
Submittal of a Special Use Permit is expected in late spring or early summer, The
Council has granted Expedited Processing for the project application. At the conclusion
of the Special Use Permit process, the design firm will prepare construction drawings and
specifications needed for a Zoning Compliance Permit and bidding. Construction of the
park is expected to begin by the fall of 2005 and the current time line indicates the park
will be ready to open by the spring of 2007,
Homestead Park Aquatic Center
This facility will be sited adjacent to the skate park in Homestead Park off Homestead
Road, A 25 meter by 25 yard pool will be included as well as a 25 meter by 15 yard
warm water, zero entry pool. All of the essential operating components of a public pool
facility are included in the design of the building. The budget for this project is
$5,513,106, A public hearing was held on January 14, at which many suggestions were
offered from two major groups within the swimming community. The comments
received at the meeting were all of a positive nature, and no one indicated dissatisfaction
with the project
This project is also a candidate for"Percent for Art" funding apportionment and the
committee has worked to distribute a call for artists and hopes to award the contract for
this project by August,
This project is also in the Special Use Permit application development phase although not
quite as far along as the Southern Community Park, The Council has granted Expedited
Processing for this project. The current timeline for the Aquatics Center indicates that a
Special Use Permit application will be submitted in 2004. This timing would allow the
project to be completed in the fall of 2006 or early in 2007.
Twin Creeks Park
Formerly CHTPEC, this 193 acre education/park "campus" located on old 86 south of
Eubanks Rd contains 96 acres designated for the park. Recently, the Board of County
Commissioners formally named the park as Twin Creeks (Moniese Nomp). The
proposed master plan has been reviewed by the Board of County Commissioners and
continues to be under consideration. Carrboro has received the proposed plan, but the
Special Use Permit process has not yet begun, pending submittal of phase I (to be
determined) drawings.