HomeMy WebLinkAboutAgenda 04-02-24; 8-j - Orange County FY 2025 Annual Work Program 1
ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: April 2, 2024
Action Agenda
Item No. 8-j
SUBJECT: Orange County FY 2025 Annual Work Program
DEPARTMENT: Orange County Transportation Services (OCTS)
ATTACHMENT(S): INFORMATION CONTACT:
1. Final FY 2025 Annual Work Program Darlene Weaver, Transportation Planning
Manager, 919-245-2002
PURPOSE: To approve the Orange County FY 2025 Annual Transit Work Program (AWP).
BACKGROUND: In 2011, the Orange County Board of Commissioners (BOCC) authorized a
referendum for a half-cent sales tax to expand public transit in Orange County. The funding is
limited to public transit improvements identified in the Orange County Transit Plan approved by
the County, the GoTriangle Board, and the Durham-Chapel Hill-Carrboro Metropolitan Planning
Organization (DCHC MPO) Board. All three boards must approve any material changes and
amendments to the plan.
An Interlocal Implementation Agreement (ILA) approved by the three boards in 2013 outlines the
roles and responsibilities of each agency for the administration of the funding. The Orange County
Board of Commissioners approved a new ILA in February 2023. It specifies the process for
developing the Annual Work Program, including approval by the BOCC ahead of approval by the
GoTriangle Board. Section 3.04 of the new Comprehensive Participation Agreement also outlines
this process.
The FY 2025 AWP (Attachment 1) is the implementation of the Transit Plan for FY 2025. Orange
County has no new transit projects programmed or funded. The County's Mobility-on-Demand
increased to 6 days starting May 1, 2023, and now serves as a continuous operational project.
Any new County specific transit projects would require an amendment to the Orange County
Transit Plan. If the Transit Plan and Work Program approvals take place concurrently, no
additional amendment approval will be necessary. If not, a Transit Plan amendment would need
to be approved by the BOCC, DCHC MPO and GoTriangle for more County specific transit
improvements.
To date:
• January 19, 2024 — Staff Work Group (SWG) reviewed the Draft FY 2025 AWP
• February 19, 2024 — SWG released for 30 day public review period
• February 20, 2024 — BOCC conducted Public Hearing
• March 20, 2024 — SWG recommended BOCC approve the FY 2025 Annual Work Program
2
Public Comment:
• Why is Chapel Hill receiving the $7.1 million and Orange County only the $1 .5 million for
Transportation?
o Answer: Since Chapel Hill Transit and GoTriangle offer more service hours than
Orange County Transportation Services, those agencies do receive more funding
for transit operations from the Transit Plan. Those allocations were determined in
the financial assumptions for the Transit Plan.
• Why would Northern Orange County not be included in Bus Rapid Transit (BRT)?
o Answer: The Bus Rapid Transit projected funded through the Transit Plan is
currently programmed for within Chapel Hill town limits. These types of services are
used in high traffic, high density areas where transit vehicles can more easily and
quickly get through or bypass car traffic.
Next Step:
The Annual Work Program will go to the Durham Chapel Hill Carrboro Metropolitan Planning
Organization and GoTriangle Board for their approval.
FINANCIAL IMPACT: Orange County receives quarterly reimbursements from GoTriangle for all
Orange County specific projects approved in the AWG. Project sponsors (e.g. Hillsborough,
Chapel Hill, Carrboro and Mebane) receive their transit tax reimbursements as outlined in the
Annual Work Program.
SOCIAL JUSTICE IMPACT: The following Orange County Social Justice Goals are applicable
to this item:
• GOAL: FOSTER A COMMUNITY CULTURE THAT REJECTS OPPRESSION AND
INEQUITY
The fair treatment and meaningful involvement of all people regardless of race or color;
religious or philosophical beliefs; sex, gender, or sexual orientation; national origin or ethnic
background; age; military service; disability; and familial, residential, or economic status.
• GOAL: ENSURE ECONOMIC SELF-SUFFICIENCY
The creation and preservation of infrastructure, policies, programs, and funding necessary
for residents to provide shelter, food, clothing and medical care for themselves and their
dependents.
ENVIRONMENTAL IMPACT: The following Orange County Environmental Goal impact is
applicable to this item:
• CLEAN OR AVOIDED TRANSPORTATION
Implement programs that monitor and improve local and regional air quality by: 1)
promoting public transportation options; 2) decreasing dependence on single-occupancy
vehicles, and 3) otherwise minimizing the need for travel.
RECOMMENDATION(S): The Manager recommends the Board approve the Orange County FY
2025 Annual Work Program.
Attachment 1
I
y OUCTR
919.245.20
it
earlFACE 4
MM
NC 14
w X99
-REQ H
ADOPTED BY
Orange County Board of County Commissioners,November 1,2022 Durham-Chapel
Hill-Carrboro MPO Board,December 14,2022
GoTdangle Board of Trustees,January 25,2023
Orange County
Transit Plan FY25 Annual Work Program
Draft
1
'P"Mt i'—EL HIL{, {6ga13GRG- }, l
ORANGE1
cau-rY D C H C GO
11,a f I!1-11 fuh >x.nacanRwmon- TV"►aflC]le
4
SUMMARY
The Orange County FY25 Annual Work Program (AWP) balances the careful use of taxpayer dollars with planned transit
investments. The FY25 continues operating improvements for Orange County transit users:
• Improvements to Orange County Fixed Routes, Demand Response and Mobility-on-Demand
• Additional service on Chapel Hill Transit routes A,CM,CW, D, F, HS,J,and NS
• Additional service on GoTriangle routes 400,405,800,CRX and ODX
• Expansion of GoTriangle Paratransit service
The primary capital improvement in the FY25 Work Program remains the Chapel Hill Transit North-South Bus Rapid Transit
(N-S BRT) project. Funding is available in FY25 and beyond to continue the planning, design, and construction for this
project. In addition to the N-S BRT,the following capital projects are funded:
• The Hillsborough Amtrak Train Station and co-located bus stop
• An annual installment for replacement bus purchases
• Vehicle acquisition and replacement
FY 2025 expenditures balance with revenues, primarily due to significant sales tax revenue growth.
4
5
RECOMMENDED CAPITAL EXPENDITUREJ= [RECOMMENDED OPERATING EXPENDITURES
Transit Infrastructure $665,000 Transit Plan Administration $826,751
Vehicle Acquisition $426,351 Transit Operations $5,241,825
Capital Planning $175,000 Tax District Administration $329,284
Bus Rapid Transit $4,000,000 TOTAL $6,397,860
TOTAL $5,266,351
ORANGE CAPITAL FUND BALANCE PROJECTED - • -
Fund Balance projected at end of '/2 Cent Sales Tax $11,500,00
FY 2024 $11,000,000
Proposed FY 25 Fund Balance $1,068,031 $3 Registration Fee $363,596
Transfer
TOTAL —$12,068,031 $7 Registration Fee $843,646
TOTAL $12,707,242
This proposed work plan designates funding to five (4) agencies in FY25: Orange County/OPT, Chapel Hill/CHT.
Hillsborough, and GoTriangle. Programmed expenditures by agency:
RECOMMENDEDor
Orange County/OPT $1,345,989
Chapel Hill/CHT $7,069,936
GoTriangle $3,207,484
Durham-Chapel Hill-Carrboro MPO $40,801
TOTAL $11,664,211
5
6
BACKGROUND
The governing boards of GoTriangle, DCHC MPO, and the Orange County Board of Commissioners adopted the first Bus
and Rail Investment Plan in 2012, prior to the referendum on the transit sales tax. Following adoption of the transit sales
tax referendum and passage of the Orange County transit sales tax referendum in 2012,an Interlocal Agreement(ILA)was
adopted by the three parties in 2013.The ILA guides the overall implementation of the three transit tax revenues and the
expanded transit network they are used to fund.The governing bodies of the ILA are:
• Research Triangle Regional Public Transportation Authority(Go Triangle)
• Durham-Chapel Hill-Carrboro Metropolitan (DCHC MPO)
• Orange County
In 2023, The Comprehensive Participation Agreement (CPA) was approved by all project sponsors and updated the Staff
Working Group (SWG), comprised of staff from all CPA parties.
Orange
County
Hillsborough • . Chapel Hill
Per the ILA and CPA, the SWG is charged with producing a recommended Orange Annual Transit Work Plan (AWP) to the
governing boards.The AWP is comprised of annual operating and capital budgets, including future assumptions of revenue
and spending on those operating and capital projects. This Draft FY25 work program operates under the current 2022
Orange Transit Plan.
6
7
FY 2025 ORANGE TRANSIT WORK PROGRAM
A total of$12.7 million in expected local revenues is budgeted in the FY25 Work Program from the three funding sources
available to the transit tax district, as provided in NC law.The largest source of funds is the half-cent local option sales tax.
Administered by GoTriangle, the local sales tax went into effect in 2013. The total amount of expected revenue in FY25
from the half-cent sales tax for Orange County is $11.5 million. In addition to the half-cent sales tax, the FY25
Work Program has two other revenue sources. A portion of the $7 registration fee that is apportioned to Orange
County is projected to generate$843,646 for FY25, ad the $3 county vehicle registration fee is expected to total,$363,596
in FY25.
FY 2025 EXPENDITURES
The expenditures described below are divided between operations(including administration),and capital.
• Operating
o FY 24 Adopted:$6,027,716
o FY 25 Submission:$6,632,798
• Capital
o FY 24 Adopted:$9,850,421
o FY25 Submission:$5,091,351
The FY25 Work Program continues all service enhancements from the 2022 Orange Transit Plan that have been funded in
previous work programs, with no cuts to existing operations. These operations projects include additional service (above
2013 levels) on the following Orange Public Transit, Chapel Hill Transit, and GoTriangle routes:
Demand Response Orange-Chapel Hill Connector
Orange-Alamance Hillsborough Circulator
Mobility-On-Demand
CHT A CHT CM
CHT CW CHT D
CHT F CHT HS
CHTJ CHT JS
Route 400 Route 405
Route 800 ODX
CRX
7
8
urham
P.
® Regional Transit Facility -
O Hillsborough Train Station
-CHT Improved Routes
CHT NS BRT
OPT Improved Route
GoTriangle Improved Routes
Esri,HERE,Gannin.Ec)4pen 9traetMap wnlribulors,and the GIS user communlry
Figure 1:Transit Fixed Routes
In addition to these route-specific improvements,
• Chapel Hill Transit expanded services throughout its system on Saturdays and Sundays,including expansion of the
on-demand EZ Rider service.
• Orange County Mobility-on-Demand expanded to six days a week on May 1,2023,and updated its ADA
Paratransit Plan in 2022.
• Rural transit services were improved through Orange County Demand Response in partnership with Department
of Aging and Department of Social Services.
More information on each of the operations improvements is available in the project sheets later in this document.
Included as part of the operations budget, administrative services for the transit plan and the transit tax district are
provided by Orange County, the MPO, and Go Triangle. The total programmed budget for administrative services
in FY25 is$1,006,036. Ongoing administrative services increased by 2.5 percent from FY24, which is the standard cost of
living increase for all projects year over year.Administrative costs are broken out into three distinct functions:transit plan
administration, staff working group administration, and transit tax district administration.
GoTriangle provides transit planning, public outreach, and legal and administrative support services, as well as necessary
oversight and administration of GoTriangle's capital and operating projects are handled through transit plan
administration. Orange County hosts the Staff Working Group (SWG) administrator, who is responsible for
coordination of the SWG,which
8
9
includes staff representatives from each of the parties to the ILA as well as staff representatives from each municipality
in Orange County. The Staff Working Group makes recommendations on budget issues, oversees implementation of the
transit plan and annual work program, and prepares the draft annual work program for adoption.The SWG administrator
also drafts the work program and other supporting documents for the SWG. The proposed budget includes $573,323 to
Go Triangle, $40,801 to the MPO, and $62,628 to Orange County respectively for Transit plan administration.
GoTriangle staff manage the financial aspects of the Orange Transit Tax District. In addition to managing the budgets and
reimbursements as called for in the annual work programs, Orange Transit Tax District staff handle all fiduciary
responsibilities for the Orange Transit Plan as a whole, including financial modelling for the development of the
new Orange Transit Plan. The total budgeted for transit tax district administration is$329,284.
The capital projects budgeted in FY25 are in three categories: bus rapid transit(BRT),transit infrastructure,and
vehicle acquisition. More detail on each project can be found in the project sheets at the end of this document.
Funding continues for development of Chapel Hill Transit's North-South Bus Rapid Transit (N-S BRT) project, which will
provide service from the Eubanks park-and-ride lot to Southern Village, also serving downtown Chapel Hill and the UNC
campus and hospital. In FY25, $4,000,000 is designated for N-S BRT. A total of$4,000,000 million is budgeted for the N-S
BRT project over the course of the next 2 years.
The remaining capital funds for FY25, $4,000,000, is an annual contribution to future purchases of replacement
vehicles for service supported by the transit tax. The useful life of a bus ranges from 10-15 years, and bus purchases for
operations that are funded by the Orange Transit Tax are an eligible expense.GoTriangle is introducing a new methodology
for vehicle acquisition planning in FY25. Rather than setting aside a large amount of funds in the year in which the vehicles
are to be ordered, making it difficult to make any other capital improvements in that year, GoTriangle is instead
beginning a "level buying" program, in which a set amount of money is set aside each year and allowed and allowed
to accumulate future purchases.
9
10
FY25 Triangle Transit Tax District: Orange County
Recommended Projects FY25 Triangle Tax District-,
Revenues
Tax District Revenues
Article 43 Half-Cent Sales and Use Tax $ 11,500,000
Article 51 Three-Dollar Increase to Regional Vehicle Registration Fee $ 363,596
Article 52 Seven-Dollar County Vehicle Registration Fee $ 843,646
Total Revenues $ 12,707,242
Expenditures
Tax District Administration
Staff Costs $ 196,800
Support Services $ 132,484
Transit Plan Administration
Chapel Hill/CHT $ 150,000
DCHC MPO $ 40,801
GoTriangle $ 573,323
Orange County/OPT $ 62,628
Transit Operations
Chapel Hill/CHT $ 2,560,252
GoTriangle $ 1,398,211
Orange County/OPT $ 1,283,362
Total FY25 Operating Allocation $ 6,397,860
Capital Planning
Chapel Hill/CHT $ 150,000
GoTriangle $ 25,000
BRT
Chapel Hill/CHT $ 4,000,000
Transit Infrastructure
GoTriangle $ 665,000
Vehicle Acquisition
Chapel Hill/CHT $ 209,684
GoTriangle $ 216,667
Total FY25 Capital Allocation $ 5,266,351
Allocation To Fund balance $ 1,043,031
Total Programmed Expenditures* $ 12,707,242
Revenues over Expenditures $ -
*NOTE:Prior year carryover to be calculated in May 2024
9
11
FY25 Orange County Transit Plan:Operating
Orange County Orange County/ Total Orange County
Transit Tax District Chapel Hill CHT DCHC MPO GoTriangle OPT Transit Plan:Operating
Operating
Revenues
Tax District Revenues
Article 43 Half-Cent Sales and Use Tax $ 5,190,618 $ 5,190,618
Article 51 Three-Dollar Increase to Regional Vehicle Registration Fee $ 363,596 $ 363,596
Article 52 Seven-Dollar County Vehicle Registration Fee $ 843,646 $ 843,646
Allocations from Tax District Revenues to Agencies
Transit Plan Administration $ 150,000 $ 40,801 $ 573,323 $ 62,628
Transit Operations $ 2,560,252 $ - $ 1,398,211 $ 1,283,362
Total Revenues $ 6,397,860 $ 2,710,252 $ 40,801 $ 1,971,534 $ 1,345,989 $ 6,397,860
Expenditures
Tax District Administration
Tax District Administration-Financial Oversight Staff $ 196,800 $ - $ - $ - $ - $ 196,800
Tax District Administration-Financial Oversight-Support Services(0) $ 79,322 $ $ - $ $ $ 79,322
Tax District Administration-AuditServices $ 8,405 $ $ $ $ $ 8,405
Tax District Administration-Financial Services $ 44,757 $ $ $ $ $ 44,757
Transit Plan Administration
Transit Plan Administration-Program Management Staff $ - $ $ $ 26,266 $ $ 26,266
Transit Plan Administration-Project Implementation Staff $ $ $ $ 177,871 $ $ 177,871
TPA-Transit Planning -Support Services $ $ $ $ 64,975 $ $ 64,975
TPA-Legal and Real Estate-Support Staff $ $ $ $ 123,714 $ $ 123,714
TPA-Marketing,Communication and PE-Support Staff $ $ $ $ 54,843 $ $ 54,843
TPA-Marketing,Communication and PE-Support Services $ $ $ $ 33,200 $ $ 33,200
TPA-Regional Technology and Administration-SupportStaff $ $ $ $ 80,268 $ $ 80,268
Customer Surveys $ $ $ $ 12,187 $ $ 12,187
Orange County Staff Working Group Participation $ $ $ 40,801 $ - $ $ 40,801
Transit Plan Administration(SWG Administrator) $ $ $ - $ $ 62,628 $ 62,628
Planner I(Transit Planning Support Staff) $ $ 90,000 $ $ $ - $ 90,000
Bus Stop Amenities Technician(Project Implementation Staff) $ $ 60,000 $ $ $ $ 60,000
Transit Operations
Route 800 Improvements $ $ - $ $ 552,997 $ $ 552,997
Route 400 Improvements $ $ $ $ 439,253 $ $ 439,253
Route ODX $ $ $ $ 225,795 $ $ 225,795
Route CRX Improvements $ $ $ $ 77,732 $ $ 77,732
Paratransit expansion $ $ $ $ 24,528 $ $ 24,528
Youth Gopass $ $ $ $ 18,596 $ $ 18,596
Fare Collection Improvements(0) $ $ $ $ 19,962 $ $ 19,962
Low Income Fare Pass $ $ $ $ 39,348 $ $ 39,348
Service Expansion $ $ 1,784,916 $ $ - $ $ 1,784,916
Increased Cost of Existing Services $ $ 775,336 $ $ $ $ 775,336
Continuation of Transit Services Fixed Route $ $ - $ $ $ 155,981 $ 155,981
Continuation of Transit Services Rural Route $ $ $ $ $ 364,672 $ 364,672
Increase Cost of Existing Services(ICES) $ $ $ $ $ 39,772 $ 39,772
Hillsborough Circulator Expansion $ $ $ $ $ 370,240 $ 370,240
OPT Mobility on Demand $ $ $ $ $ 352,696 $ 352,696
Allocations from Tax District Revenues to Agencies
Transit Plan Administration $ 826,751
Transit Operations $ 5,241,825
Total Expenditures $ 6,397,860 $ 2,710,252 $ 40,801 $ 1,683,069 $ 1,345,989 $ 6,397,860
Revenues over Expenditures $ $ - $ - $ - $ $
10
12
FY25 Orange County Transit Plan: Capital
Orange County Transit Chapel Hill/CHT GoTriangle Town of Hillsborough Total Orange County
Tax District Capital Transit Plan:Capital
Revenues
Tax District Revenues
Article 43 1/2 Cent Local Option Sales Tax $ 6,309,382 $ 6,309,382
Allocations from Tax District Revenues to Agencies
Capital Planning $ 150,000 $ 25,000 $
Bus Rapid Transit(BRT) $ 4,000,000 $ - $
Transit Infrastructure $ - $ 665,000 $
Vehicle Acquisitions $ 209,684 $ 216,667 $
Total Revenues $ 6,309,382 $ 4,359,684 $ 906,667 $ $ 6,309,382
Expenditures
Capital Planning
Chapel Hill Transit Short Range Transit Plan Update $ - $ 150,000 $ - $ $ 150,000
TPA-Regional Technology Plan Update $ $ 25,000 $ 25,000
Bus Rapid Transit(BRT)
North South BRT Supplemental $ $ 4,000,000 $ - $ $ 4,000,000
Transit Infrastructure
New Regional Transit Facility(Orange County share) $ $ - $ 140,000 $ $ 140,000
Regional Fleet and Facilties Study Implementation-Nelson Road $ $ $ 525,000 $ $ 525,000
Vehicle Acquisitions
Vehicle acquisition and replacement $ $ $ 216,667 $ $ 216,667
Midlife Repower for FY18 and FY20 Vehicle Purchases $ $ 209,684 $ - $ $ 209,684
Allocations from Tax District Revenues to Agencies
Capital Planning $ 175,000
Bus Rapid Transit(BRT) $ 4,000,000
Transit Infrastructure $ 665,000
Vehicle Acquisitions $ 426,351
Allocation To Fund balance $ 1,043,031 $ 11043,031
Total Expenditures $ 6,309,382 $ 4,359,684 $ 906,667 $ $ 6,309,382
Revenues over Expenditures $ - $ - $ - $ $ -
11
13
Orange Transit Work Plan-FY25 Workplan 5ummary
Orange Workplan-Operating
Affen-a FV 2024 Adopted' FY 2025 Submission
Chapel Hill/CHT $2,827,168 $2,710,252
DCHCMPO $39,806 $40,801
GoTriangle $1,978,322 $2,300,818
Orange County/OPT $761,278 1,345,989.465
Total Operating(Agency) $5,606,574 $6,397,860
en FV 2024 Adopted' FY 2025 Submission
Tax District Administration $321,253 $329,284
Transit Plan Administration $929,245 $826,751
Transit Operations $4,356,076 $5,241,825
Total Operating(Appropriation Category) $5,606,574 $6,397,860
Total Operating $5,606,574 $6,397,860
Total Capital $10,450,421 $5,266,351
TOTALOrange Workplan1
Agency Workplan Project ID Prolect Description Cateeory FV 2024 Adopted* FY 2025 Submission
Chapel Hill/CHT 24CHTTSI HS Route-Weekend service Transit Operations 9,414 -
Chapel Hill/CHT 19CHTTS2 Increased Cost of Existing Services(ICES) Transit Operations 775,336 775,336
Chapel Hill/CHT 22CHT-FSI Chapel Hill Transit Service Expansion FY13-21 Transit Operations 1,742,418 1,784,916
Chapel Hill/CHT 23CHTTSI CW Route-Improve mid-day service Transit Operations - -
Chapel Hill/CHT 24CHT-FS13 Planner I(Transit Planning Support Staff) Transit Plan Administration 90,000 90,000
Chapel Hill/CHT 24CHT-FS14 Bus Stop Amenities Technician(Project Implementation Staff) Transit Plan Administration 60,000 60,000
Chapel Hill/CHT 24CHTTS15 Chapel Hill Transit Short Range Transit Plan Update Transit Plan Administration 150,000 -
DCHC MPO 241APOADI Orange County Staff Working Group Participation Transit Plan Administration 39,806 40,801
GoTriangle 21GOTADI Tax District Administration-Financial Oversight Staff Tax District Administration 192,000 196,800
GoTriangle 21GOTAD11 Tax District Administration-Financial Oversight-Support Services(0) Tax District Administration 77,388 79,322
GoTriangle 21GOTAD22 Tax District Administration-Audit Services Tax District Administration 8,200 8,405
GoTriangle 21GOTAD21 Tax District Administration-Financial Services Tax District Administration 43,665 44,757
GoTriangle 20GOTAD2 Transit Plan Administration-Program Management Staff Transit Plan Administration 25,625 26,266
GoTriangle 21GOTAD3 Transit Plan Administration-Project Implementation Staff Transit Plan Administration 173,533 177,871
GoTriangle 20GOTAD13 TPA-Transit Planning-Support Services Transit Plan Administration 32,390 64,975
GoTriangle 21GOTAD4 TPA-Legal and Real Estate-Support Staff Transit Plan Administration 120,697 123,714
GoTriangle 21GOTADS TPA-Marketing,Communication and PE-Support Staff Transit Plan Administration 53,505 54,843
GoTriangle 21GOTAD12 TPA-Marketing,Communication and PE-Support Services Transit Plan Administration 32,390 33,200
GoTriangle 21GOTAD6 TPA-Regional Technology and Administration-Support Staff Transit Plan Administration 78,310 80,268
GoTriangle 19GOT002 Customer Surveys Transit Plan Administration 11,890 12,187
GoTriangle 20GOTTS2 Route 800 Improvements Transit Operations 430,262 552,997
GoTriangle 20GOTTS3 Route 400 Improvements Transit Operations 368,812 439,253
GoTriangle 20GOTTSS Route ODX Transit Operations 201,530 225,795
GoTriangle 20GOTTS6 Route CRX Improvements Transit Operations 69,379 77,732
GoTriangle 2000TTS9 Route 405 Improvements Transit Operations 23,237 -
GoThangle 19GOTTS8 Paratransit expansion Transit Operations 23,893 24,528
GoTriangle 21GOT001 Youth Gopass Transit Operations 6,143 18,596
GoTriangle 21GOT002 Fare Collection Improvements(0) Transit Operations 5,475 19,962
GoTriangle 25GOTTS21 Low Income Fare Pass Transit Operations - 39,348
Orange County/OPT 240PTTS1 Transit Plan Administration(SWG Administrator) Transit Plan Administration 61,100 62,628
Orange County/OPT 190PTTS1 Continuation of Transit Services Fixed Route Transit Operations 365,686 155,981
Orange County/OPT 25OPTT512 Continuation of Transit Services Rural Route Transit Operations - 364,672
Orange County OPT 190PTTS2 Increase Cost of Existing Services(ICES) Transit Operations 39,772 39,772
Orange County/OPT 20OPTT54 Hillsborough Circulator 2.0(Combined) Transit Operations 161,920 370,240
Orange County/OPT 20OPTTS6 OPT Mobility on Demand Transit Operations 132,800 352,696
Total Operating By Project 5,606,574 6,397,860
*FY24 Adopted Amount includes YTD Amendments
12
14
Orange Transit Work Plan-FY25Workplan Summary
Orange Workplan-Capital
en FY 2024 Adopted* FY 2025 Submission
Chapel Hill/CHT $4,736,704 $4,359,684
GoTriangle $2,430,373 $906,667
Orange County/OPT $1,553,870 $0
Town of Carrboro $1,247,805 $0
Town of Hillsborough $481,668 $0.
Total Capital(Agency) $10,450,421 $5,266,351
Agen_qf FY 2024 Adopted* FY 2025 Submission
BRT $4,000,000 $4,000,000
Capital Planning $761,725 $175,000
LRT $141,777 $0
Transit Infrastructure $4,530,753 $665,000
Vehicle Acquisition $1,016,166 $426,351
Total Capital JAppropriation Category) $10,450,421 $5,266,351
Agency Workplan Project ID Project Description Category FY 2024 Adopted* FY 2025 Submission
Chapel Hill/CHT 20 CHTCD1 North South BRT Supplemental BRT 4,000,000 4,000,000
Chapel Hill/CHT 24CHTCD14 CHT Short Range Transit Plan Update Capital Planning 100,000 150,000
Chapel Hill/CHT 24CHTCD15 Safe Streets for All(SS4A)Supplemental Grant Capital Planning 50,000 -
Chapel Hill/CHT 19CHTCD2 CHT ADA Bus Stop Upgrades Transit Infrastructure 448,815
Chapel Hill/CHT 20CHTCDI Lighting in Bus Shelters Transit Infrastructure 53,148 -
Chapel Hill/CHT 20CHTCD2 Bus Stop Sign and Design Replacement Transit Infrastructure 84,741 -
Chapel Hill/CHT 25CHTCD15 Midlife Repower for FY18 and FY20 Vehicle Purchases Vehicle Acquisition - 209,684
GoTriangle 19GOTCOI ERP System-Transit Plan Capital Planning 69,971 -
GoTriangle 21GOT C01 Origin Destination Survey Capital Planning 245,000 -
GoTriangle 21GOT CO2 GoTriangle Short Range Transit Plan Capital Planning 4,802
GoTriangle 21GOT CO3 Transit Facilities Study Capital Planning 21,434 -
GoTriangle 25GOTCD18 TPA-Regional Technology Plan Update Capital Planning - 25,000
GoTriangle 20GOTCD2 Light Rail Transit LRT 141,777 -
GoTriangle 18GOTCD8 Hillsborough Park and Ride Transit Infrastructure 50,394 -
GoTriangle 18GOTCD11 Mebane Bus Stop Improvement Transit Infrastructure 233 -
GoTriangle 18GOTCDI2 Bus Stop Improvements(Orange County) Transit Infrastructure 247,222 -
GoTriangle 20GOTCD3 Mobile Ticket Validators-Orange share(includes Route 420) Transit Infrastructure 43,372 -
GoTriangle 22GOTCD2 Priority Transit Access Improvements Transit Infrastructure 100,000 -
GoTriangle 23GOTCD4 New Regional Transit Facility(Orange County share) Transit Infrastructure 240,000 140,000
GoTriangle 23GOTCD2 Regional Fleet and Facilties Study Implementation-Nelson Road Transit Infrastructure 500,000 525,000
GoTriangle 21GOT_VP1 Vehicle acquisition and replacement Vehicle Acquisition 766,166 216,667
Orange County OPT 20OPT_AD2 Planning for new Transit Plan Capital Planning 122,444 -
Orange County/OPT 190PTAD1 OPTAVL Capital Planning 43,073
Orange County/OPT 240PTAD06 FAST 2 Study Capital Planning 105,000 -
OrangeCounty/OPT 20OPTCD1 OPT Bus Stop Signs Transit Infrastructure 1,594 -
Orange County/OPT 20OPTCD2 Hillsborough Park and Ride Transit Infrastructure 800,000 -
Orange County/OPT 190PTCD1 OPT Bus Stop Improvements(five stops) Transit Infrastructure 31,759 -
Orange County/OPT 240PTTS12 Trapeze Transit Infrastructure 200,000 -
Orange County/OPT 24OPTCD21 Vehicle Acquistion&Replacement(5 new MOD minivans) Vehicle Acquisition 250,000 -
Town of Carrboro 18TOCCDI Estes Drive Bike-Ped Improvements Transit Infrastructure 252,373
Town of Carrboro ISTOCCD2 Estes Drive Transit Access Corridor Study Transit Infrastructure 106,296 -
Town of Carrboro 18TOCCD4 Morgan Creek Greenway Transit Infrastructure 260,216 -
Town of Carrboro 18TOCCD5 South Greensboro Street Sidewalk Transit Infrastructure 478,921 -
Town of Carrboro 20TOCCD01 Carrboro HAWK Signal Transit Infrastructure 150,000 -
Town of Hillsborough 18TOHCDI Hillsborough Train Station Transit Infrastructure 481,668 -
Total Capital By Project 10,450,421 5,266,351
13
FY25 WORK PLAN SUMMARY
16
Operating Cost Requests
Summary of Project Requests • •
.
21GOTADI Tax District Administration - Financial Oversight Staff $196,800 $201,720
21GOTAD11 Tax District Administration - Financial Oversight -Support Services(0) $79,322 $81,305
21GOTAD22 Tax District Administration -Audit Services $8,405 $8,615
21GOTAD21 Tax District Administration -Financial Services $44,757 $45,876
20GOTAD2 Transit Plan Administration - Program Management Staff $26,266 $26,922
21GOTAD3 Transit Plan Administration - Project Implementation Staff $177,871 $182,318
20GOTAD13 TPA-Transit Planning -Support Services $64,975 $47,057
21GOTAD4 TPA- Legal and Real Estate -Support Staff $123,714 $126,807
21GOTADS TPA- Marketing,Communication and PE-Support Staff $54,843 $56,214
21GOTAD12 TPA- Marketing,Communication and PE-Support Services $33,200 $34,030
21GOTAD6 TPA- Regional Technology and Administration -Support Staff $80,268 $82,274
19GOT002 Customer Surveys $12,187 $12,492
20GOTTS2 Route 800 Improvements $552,997 $641,648
20GOTTS3 Route 400 Improvements $439,253 $1,560,541
20GOTTS5 Route ODX $225,795 $231,439
20GOTTS6 Route CRX Improvements $77,732 $79,676
19GOTTS8 Paratransit expansion $24,528 $25,178
21GOT001 Youth Gopass $18,596 $19,061
21GOT002 Fare Collection Improvements(0) $19,962 $20,461
25GOTTS21 Low Income Fare Pass $39,348 $40,332
24MPOADI Orange County Staff Working Group Participation $40,801 $41,821
24CHTTSI3 Transit Planner 1 $90,000 $-
24CHTTSI4 Bus Stop Amenities Technician $60,000 $-
22CHTTSI Service Expansion $1,784,916 $1,827,414
23CHTTSI CW Route - Improve mid-day service $- $205,300
24CHTTSI HS Route -Weekend service $- $172,360
19CHTTS2 Increased Cost of Existing Services $775,336 $794,719
190PTTS1 Continuation of Transit Services Fixed Route $155,981 $159,881
250PTTS12 Continuation of Transit Services Rural Route $364,672 $373,789
190PTTS2 Increase Cost of Existing Services(ICES) $39,772 $40,766
20OPTTS4 Hillsborough Circulator 2.0 $370,240 $379,496
20OPTTS6 OPT Mobility on Demand $352,696 $361,514
240PTTS1 Transit Plan Administration (SWG Administrator) $62,628 $64,193
Total Operating Requests $6,397,860 $7,945,219
17
17
Capital Cost Requests
Summary of Project Requests •
22GOTVPI Vehicle acquisition and replacement $216,667 $225,333
23GOTCD4 New Regional Transit Facility(Orange County share) $140,000 $140,000
23GOTCD2 Regional Fleet and Facilties Study Implementation-Nelson Road $525,000 $750,000
25GOTCDIB TPA-Regional Technology Plan Update $25,000 $-
24CHTCDI4 Chapel Hill Transit Short Range Transit Plan Update $150,000 $-
20 CHTCDI North South BRT Supplemental $4,000,000 $-
25CHTCDI5 Midlife Repower for FY18 and FY20 Vehicle Purchases $209,684 $-
Total Capital Requests $5,266,351 $1,115,333
Revised Request New Request
18
FY25 PROJECT SHEETS
ADMINISTRATION
Orange County FY25 Annual Work Program 19
Administration
REQUEST# Project Name Requesting Agency
21GOTADI Tax District Administration Finance Team GoTriangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
July 1, 2018 Ongoing FY2025 (Current) $ 196,800
FY 2026 (Subsequent) $ 201,720
Project Description/Scope Enter below a summary of the project that may later be used as the project
The project request is a continuation of on-going operating and consolidation of 19GOT_AD1 and 20GOT_AD1
submissions approved in previous work plans with a revised project name of Tax District Administration Finance Team.
Financial oversight staff to the Orange Transit Plan for a total of 1.0 FTE. In FY25 the roles will continue improve financial
policies, provide financial analysis for the new Transit plan development including the commuter rail project,and process
quarterly reimbursements and reporting. The 1.0 FTEs will also be responsible for producing annual operating and capital
budgets and ordinances(and amendments thereto), updating the Orange Transit financial plan/model, annual financial
reports, coordinating integration of proposed plans into the budget, monitoring spending to ensure the Orange Transit
budget stays balanced.The team will also navigate and lead the process of debt issuance,transit fund revenue investing
and the yearend financial audit for the Orange Transit Plan.
Project Goal
Position filled 100%
Project Matrics
Position status
20
Orange County FY25 Annual Work Program 20
Administration
REQUEST# Project Name Requesting Agency
21GOTAD11 Tax District Administration-Financial Staff-Support GoTriangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
July 1, 2018 Ongoing FY2025 (Current) 1 $ 79,322
FY 2026(Subsequent) I $ 81,305
Project Description/Scope Enter below a summary of the project that may later be used as the project
NOTE:The project request splits 21GOT_AD11 into more specific detail.This project incorporates the equivalent of
0.6FTE's from the finance and administration support staff functions.These functions include transit plan accounting,
audit/ACFR process and supervision,fund investments, revenue and recollection, project sponsor payments and
receivables and other additional miscellaneous financial support services to the Orange Transit Plan.
Project Goal
Position filled 100%
Implementation Matrics
Position status
21
Orange County FY25 Annual Work Program 21
Administration
REQUEST# Project Name Requesting Agency
21GOTAD12 Tax District Administration-Audit Services GoTriangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
July 1, 2018 Ongoing FY2025 (Current) $ 8,405
FY 2026(Subsequent) $ 8,615
Project Description/Scope Enter below a summary of the project that may later be used as the project
NOTE:The project request splits 21GOT_AD11 into more specific detail.This project incorporates the funds allocated for
the Orange County Transit Plan audit fees.
Project Goal
Position filled 100%
Implementation Matrics
Position status
22
Orange County FY25 Annual Work Program 22
Administration
REQUEST# Project Name Requesting Agency
21GOTAD21 Tax District Administration-Financial Services GoTriangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
July 1, 2018 Ongoing FY2025 (Current) $ 44,757
FY 2026(Subsequent) $ 45,876
Project Description/Scope Enter below a summary of the project that may later be used as the project
NOTE:The project request splits 21GOT_AD11 into more specific detail.This project incorporates the funds allocated for
financial consulting and bank service charges.
Project Goal
Position filled 100%
Implementation Matrics
Position status
23
Orange County FY25 Annual Work Program 23
Administration
REQUEST# Project Name Requesting Agency
20GOTAD2 Transit Plan Administration-Program Management Staff GoTriangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
July 1, 2018 Ongoing FY2025 (Current) $ 26,266
FY 2026(Subsequent) 26,922
Project Description/Scope Enter below a summary of the project that may later be used as the project
NOTE:The project request is a continuation of on-going operating:Specifically,consolidation Program Management
functions from 20GOT_AD2 support services submissions approved in the FY20 Workplan.
GoTriangle will continue to allocate 0.1 FTE of GoTriangle program management staff to the Orange Transit Plan. In FY25,
this staffing will provide oversight and program management support for GoTriangle's bus facilities and bus stop amenities
planning and development programs and oversight and program management support for GoTriangle's efforts in support
of the Orange Transit Plan update. Specific tasks includes oversight of project planning; oversight of project scope,
schedule, and budget development and monitoring; oversight of quarterly reporting; and supervision of GoTriangle's
planning and project delivery teams.
Project Goal
Position filled 100%
Implementation Matrics
Position status
24
Orange County FY25 Annual Work Program 24
Administration
REQUEST# Project Name Requesting Agency
21GOTAD3 Transit Plan Administration-Project Implementation Staff GoTriangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
July 1, 2018 Ongoing FY2025 (Current) $ 177,871
FY 2026(Subsequent) $ 182,318
Project Description/Scope Enter below a summary of the project that may later be used as the project
NOTE:The project request is a continuation of on-going operating: Specifically, consolidation Project Implementation
functions from 20GOT_AD2 support services submissions approved in the FY20 Workplan. GoTriangle will continue to
allocate 0.8 FTE for project implementation activities for the Orange Transit Plan. In FY25,this team will manage and
execute planning, design, and construction management activities for GoTriangle's bus facilities and bus stop amenities
programs and participate in capital planning, coordination, and support activities for the Orange Transit Plan update.
Specific tasks include but are not limited to project scope, schedule, and budget development and monitoring;
quarterly reporting; and management of consultants and contractors. Planning tasks: planning/prioritization for bus
stop and park-and-ride improvements; management and technical consultant oversight; environmental planning and
coordination with regulatory agencies for federally funded projects; and coordination to support CHT's N-S BRT project.
Design/Engineering/Architecture tasks: field investigations, feasibility analysis, consultant oversight, and technical
support for bus stop and park-and-ride improvements; design management, project coordination, and technical
support for major facilities projects; and feasibility analysis and implementation oversight for BOSS. Construction
Management tasks: project management, contractor oversight, and construction inspection. Project Coordination
tasks: managing coordination with GoTriangle's partners; facilitating productive partnering; promoting schedule and
budget adherence and fostering timely conflict resolution. Project Controls Support tasks: eBuilder administration;
document management; contract administration; project controls support including budget and schedule monitoring,
risk management support, and reporting.
Project Goal
Position filled 100%
Implementation Matrics
Position status
25
Orange County FY25 Annual Work Program 25
Administration
REQUEST# Project Name Requesting Agency
21GOTAD4 TPA-Legal and Real Estate-Support Staff GoTriangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
July 1, 2018 Ongoing FY2025 (Current) $ 123,714
FY 2026(Subsequent) $ 126,807
Project Description/Scope Enter below a summary of the project that may later be used as the project
The project request is a continuation of on-going operating:Specifically,consolidation legal and real estate functions from
20GOT_AD2 support services submissions approved in the FY20 Workplan
Funds will be allocated for GoTriangle to continue to allocate 0.5 FTE of Legal and Real Estate -support staff and
miscellaneous administrative and related expense to the Orange Transit Plan.
• Legal and Real Estate services related to Hillsborough Park-and-Ride
• Interlocal Agreements related to Transit Plan administration
• General counsel needs related to Public Records,Open Meetings, Ethics,Contracts and Procurement
• Other property issues requiring real estate acquisition and management
• Property appraisals,Property Maintenance, Repairs, Paratransit lease
• Legal Consulting expenses to include but not limited to debt issuance,capital, and operating project support
Project Goal
Position filled 100%
Implementation Matrics
Position status
26
Orange County FY25 Annual Work Program 26
Administration
REQUEST# Project Name Requesting Agency
21GOTAD5 TPA-Marketing,Communication and PE-Support Staff GoTriangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
July 1, 2018 Ongoing FY2025 (Current) $ 54,843
FY 2026(Subsequent) $ 56,214
Project Description/Scope Enter below a summary of the project that may later be used as the project
NOTE:The project request is a continuation of on-going operating: Specifically, consolidation Marketing, Communication
and Public Engagement functions from 20GOT_AD2 support services submissions approved in the FY20 Workplan
GoTriangle is requesting funding for.5 FTEs that will be dedicated to public engagement.The Public Engagement Specialist
will work under the Community Engagement Manager, in the Communications& Public Affairs department at GoTriangle,
directly collaborating with project teams to plan and execute public involvement activities related to the development and
implementation of the Orange County Transit Plan.They will support the establishment and maintenance of relationships
with community stakeholders that include public officials,strategic partners, community groups, property owners and
businesses.
Project Goal
Position filled 100%
Implementation Matrics
Position status
27
Orange County FY25 Annual Work Program 27
Administration
REQUEST# Project Name Requesting Agency
21GOTAD12 TPA- Marketing,Communication and PE-Support GoTriangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
July 1, 2018 Ongoing FY2025 (Current) 1 $ 33,200
FY 2026(Subsequent) I $ 34,030
Project Description/Scope Enter below a summary of the project that may later be used as the project
NOTE:The project request is a continuation of on-going operating: Specifically,consolidation Marketing, Communication
and Public Engagement functions from 20GOT_AD2 support services submissions approved in the FY20 Workplan
GoTriangle is requesting funding for support services that will be dedicated to engaging equitably with the community.
This project will support ongoing community engagement efforts, marketing and communications activities related to the
Orange Transit Plan. Funding will also support our capacity to utilize creative consultant services, or expand the scope of
service through current consultants,to support materials for community outreach, public meetings, marketing campaigns,
information kits,web elements,translation, and interpretation,etc.
Project Goal
Position filled 100%
Implementation Matrics
Position status
28
Orange County FY25 Annual Work Program 28
Administration
REQUEST# Project Name Requesting Agency
21GOTAD6 TPA-Regional Technology and Administration-Support GoTriangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
July 1, 2018 Ongoing FY2025 (Current) $ 80,268
FY 2026(Subsequent) $ 82,274
Project Description/Scope Enter below a summary of the project that may later be used as the project
NOTE:The project request is a continuation of on-going operating:Specifically,consolidation technology and contract
administration functions from 20GOT_AD2 support services submissions approved in the FY20 Workplan
GoTriangle will continue to allocate 0.2 FTE of Regional Technology and Administration -support staff to the Orange
Transit Plan.Staffing includes budgeted time for the Regional Technology Manager,Contract and Grants Coordinator and
Contract Administrator. In FY25 the Technology and Administration functions will continue :
• Proposed continuation of the outcomes of the Regional Technology study that assess existing technology within all
participating transit agencies, in order to design a coordinated technology integration plan. One such outcome is the
mobile-ticketing transition that will be in the process of implementation.
• Assist with the strategic capital improvement of regional park and ride program, proposed RTC relocation, and other
infrastructure projects
Project Goal
Position filled 100%
Implementation Matrics
Position status
29
Orange County FY25 Annual Work Program 29
Administration
REQUEST# Project Name Requesting Agency
19GOT002 Customer Surveys GoTriangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
July 1, 2018 Ongoing FY2025 (Current) $ 12,187
FY 2026(Subsequent) $ 12,492
Project Description/Scope Enter below a summary of the project that may later be used as the project
GoTriangle will use these funds to continue the development and implementation of annual transit customer surveys that
help to continually evaluate user experiences as additional services are implemented. Routes surveyed include the 400,
405,800,805, CRX, and the ODX, all of which provide service to Orange County.
Project Goal
Survey all customers on designated fixed routes
Implementation Matrics
Receive 100%survey completion
30
Orange County FY25 Annual Work Program 30
Administration
REQUEST# Project Name Requesting Agency
21GOT001 Youth GoPass GoTriangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
July 1, 2018 Ongoing FY2025 (Current) $ 18,596
FY 2026(Subsequent) $ 19,061
Project Description/Scope Enter below a summary of the project that may later be used as the project
For youth ages 13-18,transit agencies across Orange,Wake and Durham County will continue to offer a 'Youth GoPass'
program.These fare passes are issued by GoTriangle,GoDurham,GoRaleigh,or GoCary with valid K-12 School ID Cards, or
with transit agency issued identification cards. GoTriangle, GoDurham GoRaleigh,GoCary,and , in partnership with the
respective County's,will continue to work with schools along triangle County's bus network to issue the passes. Passes
will also continue to be available to those with a valid ID at GoDurham Station,GoRaleigh Station,the Town of Cary
Finance Department,the GoTriangle Regional Transportation Center, public libraries,and regional centers.This project
covers the cost of offsetting fares that would have been collected by GoTriangle in the county share of routes, in addition
to purchasing the supplies needed for this program.The estimated cost is allocation of GoTriangle-Orange share of Youth
GoPass boardings in Orange County.
Project Goal
Implementation Matrics
31
Orange County FY25 Annual Work Program 31
Administration
REQUEST# Project Name Requesting Agency
21GOT002 Fare Collection Improvements GoTriangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
July 1, 2018 Ongoing FY2025 (Current) $ 19,962
FY 2026(Subsequent) $ 20,461
Project Description/Scope Enter below a summary of the project that may later be used as the project
This project will cover the annual costs associated with updated mobile ticketing technology for GoTriangle buses.Share
of cost based on FY19 boardings reported in Orange County.
This project request also allocates a portion of hold harmless against any reduction of fare revenue as a result of
implementing this uniform fare strategy. The regional fare-working groups priorities include (1) Improving Pass
Distribution and Sales; (2) Balance Revenue and Ridership Goals; (3) Improve the Passenger Experience; (4) Improve
Regional Coordination; (5) Make Transit an Affordable Option; and (6) Explore New Fare Technologies.These earmarked
funds will be estimated and will be dependent on the final methodology developed by a Fare Working Group.
Project Goal
Implementation Matrics
32
Orange County FY25 Annual Work Program 32
Administration
REQUEST# Project Name Requesting Agency
240PTTS1 Orange County Staff Working Group Participation DCHC MPO
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
July 1, 2018 Ongoing FY2025 (Current) $ 40,801
FY 2026(Subsequent) $ 41,821
Project Description/Scope Enter below a summary of the project that may later be used as the project
The Staff Working Group Participation request provides resources for MPO participation on the body, including meeting
preparation,attendance,and follow-up. MPO staff will also complete necessary research,support,and reporting for full
engagement with SWG activities.
Project Goal
MPO Staff participation in SWG
Implementation Matrics
100%Participation Rate
33
Orange County FY25 Annual Work Program 33
Administration
REQUEST# Project Name Requesting Agency
24MPOADI Orange County Staff Working Group Administration Orange County
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
July 1, 2018 Ongoing FY2025 (Current) $ 62,628
FY 2026(Subsequent) $ 64,193
Project Description/Scope Enter below a summary of the project that may later be used as the project
The Staff Working Group Administration supports the Staff Working Group comprised of Orange County,GoTriangle, Local
Parties, and the DCHCMPO. Meeting duties include preparation,coordination,and record keeping.Additional duties
include completing mutually agreed upon Staff Working Group requests like website maintenance and
information archives.
Project Goal
Orange County Staff participation in SWG
Implementation Matrics
100%Participation Rate
34
Orange County FY25 Annual Work Program 34
Administration
REQUEST# Project Name Requesting Agency
20GOTAD13 TPA-Transit Planning -Support Services Go Triangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
FY2025 (Current) $ 64,975
July 1, 2018 Ongoing FY 2026(Subsequent) $ 66,599
Project Description/Scope Enter below a summary of the project that may later be used as the project
NOTE:The project request is a continuation of on-going operating: Consolidation regional transit planning functions from
20GOT_AD3 (support consultants) submissions approved in FY20 Workplan.GoTriangle is requesting reimbursement for
on-going support costs(including indirect costs)that benefit the Orange County Tax District.The Support Consultant
costs are split 50% Durham and 50%Orange which include regional contracts. FY25 Update: GoTriangle is requesting
reimbursement for on-going support costs (including indirect costs)that benefit the Wake County Tax District. This
includes the Orange County share of the$31,775 (base year of FY25) of the Triangle Regional Model Service Bureau
contract.The revised split for this contract is split as follows:70-20-10 Wake- Durham-Orange.This split reflects the ratio
of population and employment that benefits from this support service among the counties.
Project Goal
Position filled 100%
Implementation Matrics
Position status
35
FY25 PROJECT SHEETS
OPERATING
Orange County FY25 Annual Work Program 36
Operating
REQUEST# Project Name Requesting Agency
22CHTTSI Service Expansion I Chapel Hill Transit
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
Jul-23 N/A FY2025 (Current) $ 1,784,916
FY 2026 (Subsequent) $ 1,827,414
Project Description/Scope Enter below a summary of the project that may later be used as the project
This project culminates service improvements to Chapel Hill Transit operations using Orange Transit Tax funds from its
inception in 2013.These funds provide additional hours of operation at times that were most demanded by the public:
evenings and weekends. This project funds evening and weekend service on the following routes: A, CM, CW, D, F, HS,J,
and NS.This project allowed Chapel Hill Transit to operate Sunday service for the first time. In addition,this project funds
expansion of the on-demand EZ Rider service.
a) Target Start Date
b) Assets Used(Vehicles,etc.) Vehicles
c)Geographic Termini Chapel Hill Transit Service Area
d) Major Destinations Served Towns of Chapel Hill and Carrboro; UNC campus and hospital
e) Annualized Revenue Hours 14,166
f) Span of Service Weekday Saturday Sunday
TIME PERIOD Weekday Saturday Sunday
u
v AM Peak
Cr Midday
LJ_ PM Peak
°p Evening
Project Goal
Implementation Matrics
37
Orange County FY25 Annual Work Program 37
Operating
REQUEST# Project Name Requesting Agency
24CHTTSI HS Route-Weekend Service I Chapel Hill Transit
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
Aug-23 N/A FY2025 (Current) 1 $ 168,190
FY 2026 (Subsequent) 1 $ 172,360
Project Description/Scope Enter below a summary of the project that may later be used as the project
Improvements to the HS route add weekend transit services and provides connections to higher-density neighborhoods
and multifamily housing. The HS route covers a large area of Chapel Hill, and this project improves transit access to key
destinations along Martin Luther King Jr. Boulevard. The service improvement benefits lower-income communities and
fulfills a stated public need for weekend service in transit reliant neighborhoods.
a) Target Start Date
b) Assets Used(Vehicles,etc.) None
c)Geographic Termini Morris Grove Elementary School; Smith Level Road
Morris Grove Elementary School; Rogers Road neighborhood, Homestead Road; Chapel
d) Major Destinations Served Hill High; MLK,Jr. corridor; Franklin Street/downtown Chapel; Hill; UNC campus and
hospitals; Smith Level Road
e) Annualized Revenue Hours 1,390
f) Span of Service Weekday Saturday Sunday
8 AM -6:30 PM
>. TIME PERIOD Weekday Saturday Sunday
v AM Peak N/A 70 minutes N/A
Cr Midday N/A 70 minutes N/A
U_ PM Peak N/A 70 minutes N/A
°A Evening N/A N/A N/A
Project Goal
Implementation Matrics
38
Orange County FY25 Annual Work Program 38
Operating
REQUEST# Project Name Requesting Agency
20GOTTS2 Route 800 Improvements I Go Triangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
Jul-23 N/A FY2025(Current) $ 552,997
FY 2026 (Subsequent) $ 641,648
Project Description/Scope Enter below a summary of the project that may later be used as the project
UPDATE 231213:This sheet includes FY25 and future year costs for SUP Route 800-this project is revenue-hour neutral
compared to FY21 Transit Plan work program (service reduction took effect midyear FY21 in route 800 that reduced
revenue hours in FY22 work program and forward, this request is to restore the FY21 hours and support SUP
implementation.)
This project consolidates all off-peak span and frequency improvements to GoTriangle Route 800(Chapel Hill-Southpoint-
RTC)since the Tax District began providing funding for it. On Route 800:
-Weekday midday frequency was increased from 60 to 30 minutes.
-Saturday daytime frequency was increased from 60 to 30 minutes.
-Saturday evening service was extended from 7:15 PM to 11:20 PM.
-Sunday service was added from 6:45 AM to 7:20 PM.- It also includes former 19GOT_TS1 extending service to 9:20 PM
(the 800 component) and 18GOT_TS4 adding additional trips (8005)
Costs are allocated 50%to Durham County and 50%to Orange.
a) Target Start Date
b) Assets Used(Vehicles,etc.)
c)Geographic Termini
d) Major Destinations Served
e) Annualized Revenue Hours
f) Span of Service Weekday Saturday Sunday
>, TIME PERIOD Weekday Saturday Sunday
AM Peak
Midday
U_ PM Peak
°p Evening
Project Goal
Implementation Matrics
39
Orange County FY25 Annual Work Program 39
Operating
REQUEST# Project Name Requesting Agency
20GOTTS3 Route 400 Improvements I Go Triangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
Jul-23 N/A FY2025(Current) $ 413,218
FY 2026 (Subsequent) $ 1,560,541
Project Description/Scope Enter below a summary of the project that may later be used as the project
UPDATE 231213:This sheet includes FY26 and future year costs for Orange Transit Plan Route 400/405 improvements
This project consolidates all off-peak span and frequency improvements to GoTriangle Route 400(Durham-Chapel Hill)
since the Tax District began providing funding for it. On Route 400:
-Weekday midday frequency was increased from 60 to 30 minutes.
-Saturday daytime frequency was increased from 60 to 30 minutes.
-Saturday evening service was extended from 6:55 PM to 10:55 PM.
-Sunday service was added from 7:00 AM to 6:55 PM. It also includes former 19GOT_TS1 extending service to 8:55 PM
(the 400 component).
Costs are allocated 50%to Durham County and 50%to Orange.
a) Target Start Date
b) Assets Used(Vehicles,etc.)
c)Geographic Termini
d) Major Destinations Served
e) Annualized Revenue Hours
f) Span of Service Weekday Saturday Sunday
>. TIME PERIOD Weekday Saturday Sunday
U
AM Peak
Cr Midday
LL PM Peak
°D Evening
Project Goal
Implementation Matrics
40
Orange County FY25 Annual Work Program 40
Operating
REQUEST# Project Name Requesting Agency
20GOTTS5 Route ODX I Go Triangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
Jul-23 N/A FY2025 (Current) $ 225,795
FY 2026 (Subsequent) $ 231,439
Project Description/Scope Enter below a summary of the project that may later be used as the project
UPDATE 231213: Updated to reflect future year service to transit-plan funded new Hillsborough Park and Ride lot (FY27).
A new Orange-Durham Express route was implemented, linking Mebane, Efland,and Hillsborough in Orange County to the
Duke &VA Medical Centers and downtown Durham during weekday peak hours.
Costs are allocated 50%to Durham County and 50%to Orange.
a) Target Start Date
b) Assets Used(Vehicles,etc.)
c)Geographic Termini
d) Major Destinations Served
e) Annualized Revenue Hours
f) Span of Service Weekday Saturday Sunday
>, TIME PERIOD Weekday Saturday Sunday
Q
v AM Peak
Cr Midday
PM Peak
°p Evening
Project Goal
Implementation Matrics
41
Orange County FY25 Annual Work Program 41
Operating
REQUEST# Project Name Requesting Agency
20GOTTS6 Route CRX I Go Triangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
Jul-23 N/A FY2025(Current) $ 77,732
FY 2026 (Subsequent) $ 79,676
Project Description/Scope Enter below a summary of the project that may later be used as the project
Due to high demand for express service between Chapel Hill and Raleigh, additional trips were added to Route CRX
(Chapel Hill - Raleigh Express).This project was originally charged 100%to Orange County, but proportionate additional
investment from Wake County started in Wake's FY 2019 work plan.
a) Target Start Date
b) Assets Used(Vehicles,etc.)
c)Geographic Termini
d) Major Destinations Served
e) Annualized Revenue Hours
f) Span of Service Weekday Saturday Sunday
>, TIME PERIOD Weekday Saturday Sunday
U
AM Peak
Cr Midday
v
LL PM Peak
Evening
Project Goal
Implementation Matrics
42
Orange County FY25 Annual Work Program 42
Operating
REQUEST# Project Name Requesting Agency
19GOTTS8 Paratransit Expansion I Go Triangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
Already Implemented N/A FY2025 (Current) $ 24,528
FY 2026 (Subsequent) $ 25,178
Project Description/Scope Enter below a summary of the project that may later be used as the project
Due to span increases on Saturday, Sundays, and holidays for Routes 400, 700, and 800,there are additional ADA
paratransit costs incurred. These costs are split 64%to Durham County and 36%to Orange County.
a) Target Start Date Already implemented w/exception of Sunday span increase from 7-9pm and new
b) Assets Used(Vehicles,etc.) Vehicles
c)Geographic Termini 3/4 mile of Routes 400, 700, 800
d) Major Destinations Served Durham and Orange Counties
e) Annualized Revenue Hours N/A
f) Span of Service Weekday Saturday Sunday/Holiday
N/A N/A N/A
>, TIME PERIOD Weekday Saturday Sunday/Holiday
v AM Peak N/A N/A 60 Minutes
Cr Midday N/A N/A 60 Minutes
Li PM Peak N/A N/A 60 Minutes
°p Evening N/A 60 Minutes 60 Minutes
Project Goal
Implementation Matrics
43
Orange County FY25 Annual Work Program 43
Operating
REQUEST# Project Name Requesting Agency
23CHTTSI CW Route-Improve Mid-Day Service I Chapel Hill Transit
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
Aug-24 N/A FY2025 (Current) $ 200,300
FY 2026 (Subsequent) $ 205,305
Project Description/Scope Enter below a summary of the project that may later be used as the project
The CW provides service between Carrboro and UNC via W. Main,Weaver St., and W. Franklin St. Based on customer
request and need for service, this project increases midday service frequency to 30 minutes (weekdays).
a) Target Start Date Aug-24
b) Assets Used(Vehicles,etc.) Vehicles
c)Geographic Termini Carrboro,Chapel Hill
d) Major Destinations Served Carrboro, UNC Campus, Downtown Chapel Hill,
e) Annualized Revenue Hours 1,500
f) Span of Service Weekday Saturday Sunday/Holiday
7:00 am -9:00 pm 8:30 am -6:30 pm 8:30 am -6:30 pm
>, TIME PERIOD Weekday Saturday Sunday/Holiday
U
c AM Peak 20/30 Minutes 60 Minutes 60 Minutes
v
Cr Midday 30 Minutes 60 Minutes 60 Minutes
LL PM Peak 20/30 Minutes 60 Minutes 60 Minutes
bD Evening 60 Minutes 60 Minutes 60 Minutes
Project Goal
Implementation Matrics
44
Orange County FY25 Annual Work Program 44
Operating
REQUEST# Project Name Requesting Agency
19CHTTS2 Increase Cost of Existing Services(ICES) Chapel Hill
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
Jul-23 N/A I FY2025 (Current) $775,336
FY 2026 (Subsequent) $783,258
Project Description/Scope Enter below a summary of the project that may later be used as the project
The original Orange County Bus and Rail Investment Plan based operating cost on $103 per hour. Since then,
operating costs have risen to $113. In order to continue to fund these services, Chapel Hill Transit utilizes funds
from the Orange County Transit Plan to offset some of these costs.
Project Gaal
lmplementard on Matrics
45
Orange County FY25 Annual Work Program 45
Operating
REQUEST# Project Name Requesting Agency
190PTTS1 Continuation of Transit Services Demand Response and Orange County
Paratransit
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
Jul-23 N/A FY2025(Current) $ 155,981
FY 2026(Subsequent) $ 159,881
Project Description/Scope Enter below a summary of the project that may later be used as the project
All rural transit services including ADA Paratransit and Demand Response in accordance with the 2015 Paratransit Plan,
this includes transit service improvements implemented following approval of transit tax in 2013.The plan and related
services were advanced in 2022 through a new Orange County ADA Paratransit Plan and Demand Response service
improvements with other County Departments like Department of Ageing, Social Services, Library and Criminal Justice
Resource Department.This project advances "Continuation of Transit Services" (190PTS1)as previously approved in each
annual work program and in accordance with the new 2022 Orange County Transit Plan.
a) Target Start Date Already Implemented
b) Assets Used(Vehicles,etc.) All ADA OCTS vehicles except those dedicated to Mobility-on-Demand and Fixed Routes
c)Geographic Termini 3/4-mile buffer around fixed route and all unincorporated portions of Orange County
d) Major Destinations Served Rural to urban,rural to rural,urban to rural,urban to urban (within 3/4-mile buffer)
e) Annualized Revenue Hours 1,500
f) Span of Service Weekday Saturday Sunday/Holiday
7:00 am -6:00 pm N/A N/A
>, TIME PERIOD Weekday Saturday Sunday/Holiday
AM Peak 7:00 am -9:00 am N/A N/A
a Midday 20/30 Minutes N/A N/A
i PM Peak 4:00 pm -6:00 pm N/A N/A
°p Evening N/A N/A N/A
Project Goal
Increase service hours, ridership, and bus stop frequency
Implementation Matrics
100%Service hours completed
Ridership increase
Increase stops
46
Orange County FY25 Annual Work Program 46
Operating
REQUEST# Project Name Requesting Agency
190PTTS1 Continuation of Transit Services Fixed Routes Orange County
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
Jul-23 N/A FY2025 (Current)'- 364,672
FY 2026 (Subsequent) $ 373,789
Project Description/Scope Enter below a summary of the project that may later be used as the project
This project advances "Continuation of Transit Services" (190PTS1) as previously approved in each annual work
program and in accordance with the new 2022 Orange County Transit Plan. Focus is primarily on fixed routes
implemented since the approval of the transit tax in 2013. Orange County Transit service area boundary was
updated 2 times prior to its most recent expansion on January 16, 2024. FY25 Fixed Routes include and not
limited to:
* Orange - Alamance Connector
* Orange - Chapel Hill connector (referred to Hill-to- Hill).
a)Target Start Date Already Implemented
b)Assets Used (Vehicles, etc.) All ADA OCTS vehicles except those dedicated to Mobility-on-Demand and Fixed Routes
c) Geographic Termini 3/4-mile buffer around fixed route and all unincorporated portions of Orange County
d) Major Destinations Served Rural to urban, rural to rural, urban to rural, urban to urban (within 3/4-mile buffer)
e)Annualized Revenue Hours 1,500
f) Span of Service Weekday Saturday Sunday/Holiday
7:00 am - 6:00 pm N/A N/A
TIME PERIOD Weekday Saturday Sunday/Holiday
T AM Peak 7:00 am - 9:00 am N/A N/A
c
3 Midday 20/30 Minutes N/A N/A
a'
L PM Peak 4:00 pm - 6:00 pm N/A N/A
Evening N/A N/A N/A
Project Goal
Increase service hours, ridership, and bus stop frequency
Implementation Matrics
100%Service hours completed
Ridership increase
Increase stops
47
Orange County FY25 Annual Work Program 47
Operating
REQUEST# Project Name Requesting Agency
190CTTS2 Increase Cost of Existing Services(ICES) Orange County
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
Jul-23 N/A FY2025 (Current) $39,772
FY 2026 (Subsequent) $39,772
Project Description/Scope Enter below a summary of the project that may later be used as the project
ICES offsets the cost of existing services.
Project Gaal
Implementation Matrics
49
Orange County FY25 Annual Work Program 48
Operating
REQUEST# Project Name Requesting Agency
20OPTTS4 Hillsborough Circulator 2.0 1 Orange County
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
Jul-23 N/A FY2025 (Current) $ 370,240
FY 2026 (Subsequent) $ 379,496
Project Description/Scope Enter below a summary of the project that may later be used as the project
Consolidation of 3 previously approved projects-continuation of existing services(Hillsborough circulator), Hillsborough
Expansion and Hillsborough Circulator II - including and not limited to:
* Extended service hours 6:30 am to 6:00 pm or later
* Reduce headway from 1 hour to 45 minutes and eventually from 45 minutes to 30 minutes
* Additional reverse route ran concurrently
a) Target Start Date Already Implemented
b) Assets Used(Vehicles,etc.) All ADA OCTS fixed route vehicles current and new, including potential EV
c)Geographic Termini Urbanized area in and around Hillsborough, including ETJ and EJ Community of Concern
d) Major Destinations Served Town and County government facilities, UNC and Duke clinics and urgent care, Durham
e) Annualized Revenue Hours 1,500
f) Span of Service Weekday Saturday Sunday/Holiday
7:00 am -6:00 pm N/A N/A
>, TIME PERIOD Weekday Saturday Sunday/Holiday
U
a,
AM Peak 7:00 am -9:00 am N/A N/A
Cr Midday 20/30 Minutes N/A N/A
LL PM Peak 4:00 pm -6:00 pm N/A N/A
Evening N/A N/A N/A
Project Goal
Increase service hours, ridership, and bus stop frequency
Implementation Matrics
100%Service hours completed
Ridership increase
Increase stops
50
Orange County FY25 Annual Work Program 49
Operating
REQUEST# Project Name Requesting Agency
20OPTTS6 Mobility-on-Demand I Orange County
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
Jul-23 N/A FY2025 (Current) $ 352,696
FY 2026 (Subsequent) $ 361,514
Project Description/Scope Enter below a summary of the project that may later be used as the project
Mobility on Demand is a micro-transit service with same day reservation, using ADA accessible vehicles to service rural
and urban areas. Project focuses specifically on underserved and Environmental Justice Community of Concern areas for
access to urban areas 6-days a week (Monday thru Saturday) from 9 am - 5 pm. Full implementation to six days a week
started May 1, 2023 as demand continues to increase. Orange County Transportation Services has Memorandums of
Understandings with different departments in the County, like Department on Aging (DOA), Criminal Justice Resources
Department (CJRD), Department of Social Services (DSS) and others. All are seeking to meet the increasing needs of rural
public transportation.
a) Target Start Date Already Implemented
b) Assets Used(Vehicles,etc.) All ADA OCTS vehicles except those dedicated to Mobility-on-Demand
c)Geographic Termini All unincorporated portions of Orange County, urbanized areas and connections other
d) Major Destinations Served Rural to urban, rural to rural, urban to rural,urban to urban
e) Annualized Revenue Hours
f) Span of Service Weekday Saturday Sunday/Holiday
7:00 am -6:00 pm N/A N/A
>, TIME PERIOD Weekday Saturday Sunday/Holiday
u
= AM Peak 7:00 am -9:00 am 7:00 am -9:00 am N/A
v
Cr Midday 20/30 Minutes 20/30 Minutes N/A
LL PM Peak 4:00 pm -6:00 pm 4:00 pm -6:00 pm N/A
°p Evening N/A N/A N/A
Project Goal
Increase service hours and ridership
Implementation Matrics
100%Service hours completed
51
Orange County FY25 Annual Work Program 50
Operating
REQUEST# Project Name Requesting Agency
24GOTTP21 Low Cost Fare Pass Go Triangle
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
Jul-24 N/A FY2025(Current) $ 39,348
FY 2026(Subsequent) $ 40,332
Project Description/Scope Enter below a summary of the project that may later be used as the project
UPDATE 231213:revised project cost per Fare Work Group Conversation
Due to the onset on the COVID pandemic in 2020, GoTriangle has remained fare free. According to the FY23 onboard
surveys completed, more riders have opted to use GoTriangle bus than prior to the pandemic.The surveys also indicate
32%of riders reported household incomes of less than $15,000 a year, increasing from 18% reported in 2019. As
GoTriangle prepares to return to fares in FY25, a Title VI equity analysis was completed to evaluate the effects of the fare
change on minority and low-income populations and to identify mitigation strategies if necessary.The analysis concluded
no disparate impacts or disproportionate burden were founded, mitigation strategies were proposed to maximize access
to discount fare programs for minority and low-income customers. GoTriangle is requesting funding allocation from
Orange County to provide zero fare passes for low-income qualifying individuals beginning in FY25. GoTriangle will work
with the Orange County Staff Working Group to identify qualifying measures and ensure necessary policies and
procedures are in place prior to July 1, 2024. GoTriangle is currently completing a study that will provide a framework for a
low-income fare program.This framework will be presented to the Orange County Staff Working Group and can be used to
assist in further developing of policies and procedures for the low-income fare program.The total amount funded from
the Orange Tax Revenues,will offset fares that would have been collected by GoTriangle, in addition to purchasing the
supplies needed for this program. The funding allocation will be monitored and evaluated as other providers make
decisions regarding fares.This allocation should be available to all Orange County transit providers who return to fares in
the future. This financial information included in this sheet is an estimate to be used for budget purposes. GoTriangle and
the Orange County Staff Working Group will work on developing administrative needs for the project and adjust financials
as needed.
a) Target Start Date
b) Assets Used(Vehicles,etc.)
c)Geographic Termini
d) Major Destinations Served
e) Annualized Revenue Hours
f) Span of Service Weekday Saturday Sunday/Holiday
TIME PERIOD Weekday Saturday Sunday/Holiday
AM Peak
a Midday
Li PM Peak
°p Evening
Project Goal
Implementation Matrics
52
FY25 PROJECT SHEETS
CAPITAL
Orange County FY25 Annual Work Program 52
Capital
REQUEST# Project Name Requesting Agency
23GOTCD4 New Regional Transit Facility(Orange GoTriangle
County share
Estimated Start Date Estimated Completion Estimated Capital Cost
FY20 FY28 FY2025 (Current) $ 140,000
FY 2026(Subsequent) $ 140,000
Project Description/Scope Enter below a summary of the project that may later be used as the project
The FY25 request includes phase II of the project,which consists of land acquisition,design,and construction of a new
regional transit center(RTC).
The Triangle Mobility Hub(aka regional Transit Center relocation)will provide travel time savings to riders of route 800
which serves Chapel Hill and UNC.The Triangle Mobility Hub and bus network improvements it enables will provide
faster, more frequent connections for longer periods of the day to Orange County residents wishing to travel to
destinations in/around RTP, including Hub RTP and Boxyard, as well as in Southern Durham County and Wake County.
Additionally,through improved travel times/ reduced operational costs,the relocation will also enable GoTriangle to
realign the 800 and 805 in order to provide all day service,for the first time,on route 805 which also serves Chapel Hill
and UNC.This concept was identified in the Draft GoTriangle SUP and viewed favorably by riders on the 800 and 805.
The completed feasibility study includes an evaluation of the current facility and identification of necessary passenger
amenities and infrastructure improvements, and a feasibility study to evaluate the potential new locations for the RTC,
taking into consideration current and future planned routes, land use, supply, and price.This study will be used to
inform the location and design of phase II.The feasibility study was funded by county transit plans in Wake, Durham,and
Orange counties.
Please detail project justification
The GoTriangle Regional Transit Center (RTC) is the primary hub for GoTriangle regional bus services connecting Wake,
Durham, and Orange Counties. This study includes an evaluation of the current facility and identification of necessary
passenger amenities and infrastructure improvements,and a feasibility study to evaluate the potential new locations for
the RTC,taking into consideration current and future planned routes, land use,supply,and price.The current location of
the RTC on Slater Road in Durham creates overlapping routes leading to inefficiency and is not proximate to 1-40 which
causes delays and reduced reliability during peak commuting times.The feasibility study is evaluating location options
that improve operating efficiency and reliability, connections to planned BRT and CRT, as well as potential for transit-
oriented development.
Phase Fiscal Quarter and Fiscal Year Fiscal Quarter and
Planning
Design Q1 FY24 Q2 FY25
Construction Q3 FY25 Q2 FY28
Equipment
Land-Right of Way FY25 FY25
Other
Project Goal
Implementation Matrics
54
Orange County FY25 Annual Work Program 53
Capital
REQUEST# Project Name Requesting Agency
23GOTCD2 Regional Fleet and Facilties Study GoTriangle
Implementation - Nelson Road
Estimated Start Date Estimated Completion Estimated Capital Cost
FY20 FY28 FY2025 (Current) $ 525,000
FY 2026(Subsequent) $750,000
Project Description/Scope Enter below a summary of the project that may later be used as the project
The project sheet requests funding for phases of Design and construction required to operate services identified in the
Transit Plan.The fleet and facilities study evaluated constraints and needs for maintenance, storage, fueling and
servicing capacity as well as work-flow efficiency at the GoTriangle Nelson Road bus operations and maintenance facility.
The outcome of this study will include site selection, schematic design, and cost estimates for a new and/or expanded
facility.The study included a regional coordination element to identify opportunities for shared facilities for vehicle
storage, servicing and/or repairs.The study has identified onsite expansion and renovation of the current Nelson Road
facility as the most cost-effective option to address current needs and provide opportunity to address future fleet needs
over the course of the useful life of the renovated facility: 40+years.The completed study will include phases and
associated costs of handling the fleet required to operate the services identified in the Bus Plan.
Please detail project justification
The GoTriangle Operations and Maintenance Facility at 5201 Nelson Rd. Morrisville, NC was originally constructed in
1998. In 2006,the facility was updated to add
space for administrative functions. GoTriangle is currently operating near capacity of the existing facility. GoTriangle's
Regional Fleet and Facilities Study recommends the design, renovation, and expansion of their Nelson Road Operations
and Maintenance Facility.This capital improvement will add the needed capacity required to accommodate GoTriangle's
projected fixed-route fleet of 120 buses,including vehicles needed for operations in Wake,Orange,and Durham Counties,
through 2050.The renovation and expansion will also include updates to better accommodate the facility's
administrative functionality. The Regional Fleet and Facilities study has also projected the need to relocate GoTriangle's
paratransit maintenance and servicing to a new facility to reach full build-out,the funding for which is not included in this
project's design and construction allocation. Facility costs to update the Nelson Road facility will be shared across
GoTriangle's service areas.
Phase Fiscal Quarter and Fiscal Year Fiscal Quarter and
Planning
Design FY23 Q4 FY25 Q4
Construction FY26 Q1 FY28Q4
Equipment
Land-Right of Way
Other
Project Goal
Implementation Matrics
55
Orange County FY25 Annual Work Program 54
Capital
REQUEST# Project Name Requesting Agency
22GOTVPI Vehicle acquisition and replacement GoTriangle
Estimated Start Date Estimated Completion Estimated Capital Cost
FY20 FY28 FY2025 (Current) $ 216,667
FY 2026(Subsequent) $ 225,333
Project Description/Scope Enter below a summary of the project that may later be used as the project
Orange Transit share of the GoTriangle level buying bus strategy. GoTriangle will serve as project sponsor as these new
buses will replace existing buses that have reached its useful life.There has been an increase of maintenance cost by
maintaining high mileage vehicles and a reduction in reliability.Vehicle purchase requests correspond to the fleet
replacement plan.
Please detail project justification
Project allocation was included in the project sheet submission for FY24.Vehicle acquisition is a critical part of the
passenger experience, meeting bus schedule timelines and accomplishing the goals of the Orange County Transit Plan
Update.
Phase Fiscal Quarter and Fiscal Year Fiscal Quarter and
Planning
Design
Construction
Equipment
Land-Right of Way
Other
Project Goal
Implementation Matrics
56
Orange County FY25 Annual Work Program 55
Capital
REQUEST# Project Name Requesting Agency
25CHTCD15 North-South BRT Supplemental Chapel Hill Transit
Estimated Start Date Estimated Completion Estimated Capital Cost
FY20 FY28 FY2025 (Current) 4,000,000
FY 2026(Subsequent) -
Project Description/Scope Enter below a summary of the project that may later be used as the project
The North-South Bus Rapid Transit(BRT) Project will provide frequent,fixed-guideway bus service along NC 86, known
locally as Martin Luther King,Jr. Boulevard and South Columbia Street, and the US Highway 15-501 corridor in Chapel
Hill.The project will benefit Chapel Hill and the University of North Carolina students,visitors,
and employees.
Please detail project justification
Project adopted in previous work program
Phase Fiscal Quarter and Fiscal Year Fiscal Quarter and
Planning FY25
Design FY25
Construction
Equipment
Land-Right of Way
Other
Project Goal
Implementation Matrics
57
Orange County FY25 Annual Work Program 56
Capital
REQUEST# Project Name Requesting Agency
25CHTCD15 Midlife Repower for FY18 and FY20 Chapel Hill Transit
Vehicle Purchases
Estimated Start Date Estimated Completion Estimated Capital Cost
FY20 FY28 FY2025 (Current) $ 209,684
FY 2026(Subsequent) $ -
Project Description/Scope Enter below a summary of the project that may later be used as the project
Midlife repower for FY18 and FY20 vehicle purchases
Please detail project justification
Project adopted in previous work program
Phase Fiscal Quarter and Fiscal Year Fiscal Quarter and
Planning
Design
Construction
Equipment
Land-Right of Way
Other
Project Goal
Implementation Matrics
58
Orange County FY25 Annual Work Program 57
Capital
REQUEST# Project Name Requesting Agency
24OPTTS12 Trapeze Orange County
Estimated Start Date Estimated Completion Estimated Capital Cost
FY24 FY25 FY2024(Current) $ 200,000
FY 2025 (Subsequent) $ -
Project Description/Scope Enter below a summary of the project that may later be used as the project
Converting Ecol-ane to Trapeze to improve data quality, service, and coordination with other transit providers in the
County and region.
Please detail project justification
59
Orange County FY25 Annual Work Program 58
Capital
REQUEST# Project Name Requesting Agency
24CHTCD14 Transit Short Range Transit Plan Update Chapel Hill
Estimated Start Date Estimated Completion Orange Transit Estimated Operating Cost
Jul-23 N/A FY2024 (Current) $ 100,000
FY 2025 (Subsequent) $ 150,000
Project Description/Scope I Enter below a summary of the project that may later be used as the project
Amend project appropriation category from Operating to Capital.
60
Orange County FY25 Annual Work Program 59
Capital
REQUEST# Project Name Requesting Agency
18TOCCD4 Carrboro
Morgan Creek Greenway
Estimated Start Date Estimated Completion Estimated Capital Cost
FY22 FY25 FY2023(Current) $ 357,862
$ -
Project Description/Scope Enter below a summary of the project that may later be used as the project
The Morgan Creek Greenway (EL-4828A) will connect the neighborhoods southwest of the Smith Level Road/NC 54
Bypass that are otherwise cut-off from the Town's bike-ped network,with eventual connections under Smith Level Road
to the Chapel Hill portions of the Morgan Creek Greenway and to University Lake. Completion of the Carrboro segment
will also facilitate access to Frank Porter Graham Elementary School. The bike-ped project is programmed in the
FY2020-2029 STIP. The updated bid documents are nearing completion,with construction anticipated for spring 2024.
Please detail project justification
Phase Fiscal Quarter and Fiscal Year Fiscal Quarter and
Planning
Design
Construction
Equipment
Land- Right of Way
Other
Project Goal
Implementation Matrics
61
Orange County FY25 Annual Work Program 60
Capital
REQUEST# Project Name Requesting Agency
18TOCCD5 Carrboro
South Greensboro Street Sidewalk
Estimated Start Date Estimated Completion Estimated Capital Cost
FY20 FY25 FY2023(Current) $ 478,921
$ -
Project Description/Scope Enter below a summary of the project that may later be used as the project
The design and installation of a sidewalk along one side on South Greensboro Street(TIP#C-5650)from the north end of Old
Pittsboro Road to Public Works Drive,appropriately 0.9 miles. In addition to establishing a continuous pedestrian facility along the
major north-south axis to Carrboro,the improvement would provide pedestrian access to bus stops for 8 Chapel Hill Transit routes
and one GoTriangle Route within the 1/2 mile(the walking service area). The project connects the recently completed improvements
to Smith Level Road (U-2803) and the future Morgan Creek Greenway(EL-4828)to downtown Carrboro.
Please detail project justification
Phase Fiscal Quarter and Fiscal Year Fiscal Quarter and
Planning
Design
Construction
Equipment
Land-Right of Way
Other
Project Goal
Implementation Matrics
62