HomeMy WebLinkAboutAgenda - November 15 2023 School Capital Needs Workgroup Agenda & Minutes ORANGE COUNTY BOARD OF COMMISSIONERS CHAPEL HILL-CARRBORO BOARD OF EDUCATION ORANGE COUNTY BOARD OF EDUCATION Capital Needs Work Group November 15, 2023 Meeting— 8:30-10am The Capital Needs Work Group is conducting a Virtual Meeting on November 15, 2023. Members of the Group will participate in the meeting remotely. Panelists: Jean Hamilton, Bonnie Hauser, Rhonda Rath, Jessica Goodell,Al Ciarochi, Alan Dorman,Andre Stewart, Catherine Mau, David Sturtz, Dwayne Foster, Gary Donaldson, Greg Wilder, Patrick Florence, Perdita Holz, Rani Dasi, Rob Olsen, Steven Arndt, Quamesha Whitted- Miller, Travis Myren, Kirk Vaughn, Christy Dodson, Cy Stober, Jim Merrill, Johnathan Scott, Riza Jenkins 1. Welcome—Commissioner Jean Hamilton, Chair of Work Group 2. Woolpert Inc. Update David Sturtz (Woolpert)presented updated slides with edits from last presentation (powerpoint presented with minutes). Option D is what has been recommended. Option C is Phase 1 of the recommendations and stretches the timeline from 5 years to 10 years. Focuses on priority rebuilds and one new capacity school for Orange County Elementary. For CHCCS: This is a shift since last time after talking to Al and his team. McDougle Elementary would serve as all of the district language program for the elementary schools in one location to consolidate their efforts and resources for those programs. This swaps out an elementary rebuild for a new middle school rebuild. The new middle school would be on an existing site near Morris Grove Elementary. This allows the language program to be in one location. The rest of the options remain the same where Frank Porter Graham serves as swing space for the major construction projects throughout phase 1 as that will reduce the sunk cost for swing space making it more efficient. For OC: Move Gravelly Middle School to phase 3 since that is a newer school. It had been identified for renovation due to undersized classrooms. Given the sum of all the needs, Orange Middle and Orange High are both slated for rebuild on the existing shared site as there is plenty of green space to do so. This prioritizes Orange Middle to phase I replacement and preliminary design for the Orange High in phase 2 as there could be some site efficiencies to be gained by looking at that as a joint project. This plan increases elementary school capacity, rebuilds Orange Middle and incorporates a new change of combining Hillsborough and Central Elementary. With the new investments in HVAC recently in Central, the discussion was to pare down the cost of that option by not fully rebuilding Central Elementary School but maintaining the majority of that building. Part of the building will be rebuilt into multi-story to gain capacity for a relatively small footprint and to provide some of the common spaces that are desired in larger elementary schools. The Central rebuild will be for the Hillsborough and Central elementary communities. With the new capacity, the existing Hillsborough existing program can move to Central or to a location that makes sense for the district at that time. The sum of Phase 1 major capital investments is $428.4m. Phase 2 moves to focus on one priority rebuild, which is Orange High School, and the rest is for capital renewals—renovations of existing capital infrastructure, windows, interiors, roofs, and other items on the replacement schedule. Phase 3 is continuing renovations and priority needs. This project has focused on separating out the major capital projects and the ongoing capital needs from a budgetary standpoint. This plan annualized capital renewals or priority repairs in buildings not being replaced to be approximately $5m/yr for the next 15 years. This is the bare minimum for ongoing capital needs. Inflation will need to be considered in outer years. Industry standard budget model, 2% of the present replacement value of the facilities for these priority repairs and capital renewals, suggest approximately $36m/yr to keep pace with ongoing facility needs. The midpoint is $27.5m/yr which considers the top 1-3 priorities for every building that is not being renovated or replaced in one of the 3 phases. Woolpert suggested aiming for the $27.5m on average and work down from there based on the priorities and what can be afforded on an ongoing basis outside of capital debt. A final report will be provided to look at funding needs over time, both in terms of ongoing capital renewals and what needs to be planned for on an annualized basis into the foreseeable future. The phases are set up in best practice model but should be evaluated every 5 years to see if they still meet the current needs. In consultation with the district teams,they feel confident in the recommendations made strategically should be move forward at this time. Hamilton thanked the Wolpert Team. Bonnie: If Orange County Schools have a partial rebuild of Central and close Hillsborough, does that increase capacity or is it a wash? David: It would essentially be a wash on capacity however adding a new school in the pipeline prior to the renewal of Central would have added capacity. Before this project, the new elementary school would be online to add new capacity and then reshuffle the boundaries accordingly. David: A relatively small budget has been included for consolidations to account for any site related removals of existing property to account for all costs. Bonnie: We are in middle of major renovations at Efland Cheeks Elementary School. They are putting in a new HVAC and there is a phased multi-year plan to upgrade the finishes in every part of the building. Wondering if it had been considered to move the Efland Cheeks improvement into this phase one. Jessica: If that money is already allocated,we would not want that included in a phase. We have not made any adjustments to the assessment data. David: We have not specifically called that out however this would be considered in the ongoing capital renewal budget. Woolpert identified deficiencies per the facility condition. Efland Cheeks does not get included in cost until year 6 and they have a total of $7.5m budgeted for those renovations right now. Jean:Asked for copy of slides and looks forward to Woolpert's presentation at the December 4th BOCC meeting. 3. County Staff Update: Discussion of Bond Plan Kirk Vaughn presented the Capital Planning Timeline (powerpoint provided with minutes) The County Facilities Masterplan was reviewed on November 91h The next two big items are: • Woolpert will present on December 4th • On December 12th, County staff will present the Financing Options for Woolpert's recommendations to the Board. In January, the Board will work toward a tentative plan for the bond referendum. Staff will then work with Local Government Commission (LGC). In February, the School Boards will adopt a resolution supporting the referendum. At certain board meetings, there are opportunities for the Board to change the bond referendum plan if they deem necessary. Then the bond purpose and "not to exceed" amount will be set on April 2"d. The purpose or"not to exceed" amount cannot be changed after that point. Next the Board will appoint a Bond Education Committee. Staff will work with the LGC to apply for the bond and set public meetings working toward a November 5th bond referendum. Bonnie: What assumption should School Districts be using for Capital Budget Planning? With Capital Budgets being due soon, what should they be planning in terms of shovel readiness for bond projects? What is the bond number? Heard $140M, is that correct? Are we to continue to capitalize maintenance? Are we going to be funded separately? Travis: The current capital investment plan represents a $130m bond but this timeline sets us up to determine what the final amount will be. Will have general scenarios at the December 12th meeting for the Board to consider. Those will have both tax rate and debt to revenue policy implications. Will create different scenarios between December 12th — January 16th as directed. Then we can set out tentative plans. There is room for refinement in March as we get more and improved information, including revenue projections. As we get closer to the introduction of the capital investment plan, the better information we will have. Kirk: We have not asked the school districts for their CIP submission at this time. We will be sending out CIP request and ask that they prioritize capital year 1 projects that need to get done before the bond kicks in. Rani —Are we looking at a total pool of funding consideration or are the county projects prioritized? Travis: The County Facility Master Plan was presented to the Board last week. Over the same 10-year period, that is $130m. We will layer the county,school,and school bond referendum plan to see the amount and then we can make changes. Jean: Asked for all of this to be presented at one time for ease of decision making with limited funds. Al: Is it safe to say that we will see a tentative amount for the school improvement category, at least for Article 46, so they can start planning as in the past. Same for deferred maintenance money so districts can do some items that need to continue regardless of timing on referendum approval. Kirk: yes, that information will be in the current CIP 4. County Staff Update: OREd Projection Update Kirk informed the workgroup that OREd has presented draft capacity tables for both districts to the district staff and Orange County Budget Office. A reminder of what OREd is and how it fits into this process: OREd—improves our projections for enrollment by looking at land use and projected developments that add students as they get built. That is helpful as we build out the projection while looking at future capacity and future capital needs. In draft report, neither district is showing out of capacity over the 10-year period. The capacity numbers that OREd use are from the projections we give them based on our new SAPFO projections. That information has assumptions and limitations that we have identified in the past. Since Woolpert has more recent review of the buildings and different space assumptions for different usage(ex: PreK and EC), OREd is going to build a capacity numbers using Woolpert data. We will see how the capacity tables are impacted by that. As the Board approves different phases of the Woolpert Model, we will get information on how each of those phases and projects affect capacity. That information can be overlaid as capital projects move forward and how they affect capacity in the next 10 yrs. Bonnie: What is the timetable for updating the SAPFO agreement? Travis: As part of the MOU,if we are going to change the projection model, we need to provide notice to parties by February. Between getting updated projections from ORED with adjusted PreK and EC assumptions and February, we will make the determination on which projections to use for the MOU moving forward. Bonnie: We are in the middle of a redistricting process. We added EC, PreK, and specials back into model and it threw the #'s off by 10%, which has created a semi-urgent problem. Dwayne can provide the updated numbers. It is creating a dilemma because if we move one school from 120% capacity, we end up with 2 others that are at 120% capacity. Jean: It is important to get the capacities to reflect what is actually going on in the classrooms. It is important to understand the assumptions the projections are based on such as items how many children in schools are generated from new developments and what is the impact of the older communities as residents turn over and bring in families with school age children. We need to check on assumptions to see how students are generated and confirm the accuracy. 5. Discussion and Group Next Steps Bonnie: Has there been any conversation in the facilities plan about operating improvements or efficiency improvements (ex: staffing, energy usage). Curious if there are any financial improvements based on these improvements. Hamiton: We don't know what's going to happen. This group was to focus on capital needs however operations is an important consideration for the Commissioners and others. 6. Next Meeting is TBD Jean: Do we need to meet in December? Future topics for next meetings? Rani: January would be good. Would like to learn more about SAPFO changes to take back to school district before February board meeting. Connect on Commissioner's discussion on funding. Cy: Perdita is working on Abstract for initial draft of the annual report for January BOCC Agenda. Jean: The BOCC business meeting is on January 16th. The next meeting for this Capital Needs Workgroup will be Jan 171h 8:30-10. Topics to include update on enrollment projections and what BOCC decided. Adjourn Capital Needs Work Group virtual meetings are open to the public to attend remotely. Should any member of the public wish to view this meeting,please click the following link to register: Capital Needs Workgroup Registration Link After registering, you will receive a follow-up email which will allow you to access and view the meeting. If you have any comments or questions, would like to submit any written comments to the group, or would like an emailed copy of the entire agenda package for this meeting,please email Kirk Vaughn at kvaughn(d),oran eg countync.gov