HomeMy WebLinkAboutAgenda 11-14-23; 8-e - Construction Bid Award for the Richard E. Whitted Complex Stormwater Improvement Project 1 ORANGE COUNTY BOARD OF COMMISSIONERS ACTION AGENDA ITEM ABSTRACT Meeting Date: November 14, 2023 Action Agenda Item No. 8-e SUBJECT: Construction Bid Award for the Richard E. Whitted Complex Stormwater Improvement Project DEPARTMENT: Asset Management Services (AMS) ATTACHMENT(S): INFORMATION CONTACT: Recommendation Letter and Certified Bid Angel Barnes, 919.245.2628 Tabulation Steven Arndt, 919.245.2658 Jovana Amaro, 919.245.2651 PURPOSE: To: 1) Approve a construction contract with Hamlett Associates for the construction of the Richard E. Whitted Complex Stormwater Improvement Project; and 2) Authorize the County Manager to execute the Agreement, subject to final review by the County Attorney, and any subsequent amendments for contingent and unforeseen requirements up to the approved budget amount on behalf of the Board. BACKGROUND: In 2019, the Board of Commissioners approved funding within the Capital Investment Plan for the Richard E. Whitted Complex stormwater management improvements in the northern/rear area of the Whitted Campus. The scope included a facility waste container corral, site drainage improvements, building waterproofing, site grading improvements, gravel parking lot improvements, back stair step/sidewalk improvements, and required signage. The project was advertised for bid on two occasions; however, due to the increases from the pandemic, the Project came in over budget with both bids. In FY 2022-2023, the Board approved additional funding in order to move this project forward. In September 2023, Orange County published an Advertisement for Bids. On October 26, 2023, the County received four (4) sealed bids from General Contractors. A Recommendation Letter and Certified Bid Tabulation are attached. FINANCIAL IMPACT: The construction contract to complete the work as designed for the Richard E. Whitted Complex Stormwater Improvements Project will be in the amount of$675,000. The Board previously approved funding for this purpose. SOCIAL JUSTICE IMPACT: The following Orange County Social Justice Goal is applicable to this item: 2 • GOAL: ESTABLISH SUSTAINABLE AND EQUITABLE LAND-USE AND ENVIRONMENTAL POLICIES The fair treatment and meaningful involvement of people of all races, cultures, incomes, and educational levels with respect to the development and enforcement of environmental laws, regulations, policies, and decisions. Fair treatment means that no group of people should bear a disproportionate share of the negative environmental consequences resulting from industrial, governmental, and commercial operations or policies. ENVIRONMENTAL IMPACT: The following Orange County Environmental Responsibility Goal impacts are applicable to this item: • ENERGY EFFICIENCY AND WASTE REDUCTION Initiate policies and programs that: 1) conserve energy; 2) reduce resource consumption; 3) increase the use of recycled and renewable resources, and 4) minimize waste stream impacts on the environment. • RESULTANT IMPACT ON NATURAL RESOURCES AND AIR QUALITY Assess and where possible mitigate adverse impacts created to the natural resources of the site and adjoining area. Minimize the production of greenhouse gases. RECOMMENDATION(S): The Manager recommends that the Board: 1) Approve a construction contract with Hamlett Associates for the construction of the Richard E. Whitted Complex Stormwater Improvement Project; and 2) Authorize the County Manager to execute the construction Agreement, subject to final review by the County Attorney, as well as any subsequent amendments for contingent and unforeseen requirements up to the approved budget amount on behalf of the Board. USUMMIT DESIGN AND ENGINEERING SERVICES October 27, 2023 Angel Barnes Orange County Asset Management Services a ba rnes@ora ngecou ntync.gov Re: Orange County Stormwater Services Richard E. Whitted Complex Stormwater Improvements Bid Tab Summary Dear Ms. Barnes: The County has received four bids for us to review for the project. The bids were received prior to October 26, 2023 at 2pm. All companies provided a bid bond and required paperwork. See summary tab attached. The bid breakdown is as follows: Contractor Bid Amount Hamlett Associates, Inc. $675,000.00 H.M. Kern Corporation $898,000.00 Harrod and Assoc Constructors, Inc $1,075,000 JM Thompson $1,101,000 Engineers Estimate $690,000 The apparent low bidder is Hamlett Associates, Inc. We have verified that the company is active with Secretary of State, and the company's contractors license has an unlimited value. It is our recommendation that the County accept the bid from Hamlett Associates Inc. and proceed with the next step. Please feel free to contact us with any questions. Sincerely, SUMMIT DESIGN AND ENGINEERING SERVICES l)aa Sew"T Donald A. Sever, PE Senior Project Manager Attachments (Bid Proposal) Kelli Wilcox (Atlas Engineering) Headquarters Office 320 Executive Court, Hillsborough, NC 27278 919.732.3883 // www.summitde.com 4 ORANGE COUNTY NORTH CAROLINA Bid No 367-005399-R: Richard E. Whitted Complex Stormwater Improvements DUE DATE: October 26, 2023 at 2:00 pm TABULATIONS VENDOR NAME TOTAL BASE BID Hamlett Associates, Inc. $ 675,000.00 H.M. Kern Corporation $ 898,000.00 Harrod &AssociatesnConstructors, Inc. $ 1,075,000.00 J.M. Thompson $ 1,101,000.00