HomeMy WebLinkAboutOTHER-2023-056-Orange County Procurement and disbursement ploicy urgent repair and housing rehabilitation programs C� rim50
n ORANGECOUNTY
I& HOUSING DEPARTMENT
Orange County Procurement and Disbursement Policy
Urgent Repair and Housing Rehabilitation Programs
Procurement Policy
To the maximum extent practical , Orange County ( the " County" ) promotes a fair, open and competitive
procurement process as required under the North Carolina Housing Finance Agency ( " NCHFA" ) Urgent
Repair Program ( " URP " ) , NCHFA Essential Single4amily Rehabilitation Loan Pool ( " ESFRLP " ) and the
County' s local urgent repair and housing rehabilitation programs . Bids are invited from contractors on the
County ' s Contractor Registry . Any current contractor listed with and approved by the County and in good
standing ( i . e . , no unresolved past performance issues and not listed on the federal or state debarred list )
will receive automatic approval status on the Contractor Registry .
To be listed on the Contractor Registry, a contractor must complete an application , submit proof of
insurance and have their recent work inspected and approved by the Rehabilitation Specialist . All
contractors ' insurance renewals must be submitted to the County on an annual basis . In order to bid on a
pre4978 property, the contractor' s firm must be Renovate , Repair and Paint ( " RR & P" ) certified and have
their RR & P certificate on file with the County .
To the maximum extent practical , a minimum of three ( 3 ) eligible contractors on the Contractor Registry
should be invited to bid on each job and the lowest, most responsive and responsible bidder shall. be
selected for the contract . " Responsive and responsible " means the following : the contractor is deemed
able to complete the work in a timely fashion ; the bid is within 15 % in either direction of the County ' s cost
estimate ; the contractor has not been suspended or debarred ; and there is no real or perceived conflict of
interest . Because of the increasing difficulty of soliciting eligible bids for URP projects, the County can
solicit a bid from an eligible contractor on the Contractor Registry based on their rotating placement on
the Registry . If the selected contractor submits a responsive and responsible bid then it will be accepted
and after successful completion of the project that contractor' s name will rotate to the end of the Registry .
If the contractor does not submit a responsive and responsible bid or chooses not to submit a bid , then the
next contractor on the Registry will be eligible to submit a bid on the project . In addition , in emergency
situations, telephone or email bids or quotes will be accepted and documentation of such bids or quotes
will be maintained in the applicable file .
Although bid packages may be bundled for multiple job sites, these bids shall be considered separate and
apart when awarded and shall be awarded to the lowest responsive and responsible bidder ( s ) for each job
site . No contractor shall have more than three ( 3 ) open jobs at any one time . A job shall be considered
" open " once a contract is signed .
Bid packages shall consist of an invitation to bid , work write - up ( s ) and bid sheet ( s ) for each job , including
instructions for distribution and receipt of bids . For urgent repair activities, contractors will be given no
less than seven ( 7 ) days in which to inspect the property and prepare bid proposals . Each contractor will
need access to all parts of the house in order to prepare a bid . For minor and comprehensive housing
rehabilitation activities, contractors will be given no less than ten ( 10 ) days in which to inspect the
property and prepare bid proposals .
Orange County Urgent Repair and Housing Rehab Procurement and Disbursement Policy Page 1
n ORANGECOUNTY
4lol HOUSING DEPARTMENT
Bids must include a cost- per- item breakdown with line item totals equaling the submitted bid price . Any
discrepancies must be reconciled prior to a contract being awarded .
The County reserves the right to reject any or all bids at any time during the procurement process .
In the event of an emergency situation , the County reserves the right to waive normal procurement
procedures in favor of more expedient methods, which may include seeking quotes and bids by telephone ,
email , fax and the like . Should such methods ever become necessary the transaction , including the nature
of the emergency, will be fully documented and placed in the project file . In the event telephone bids are
used , the County will call the next eligible contractor on the Approved Contractor Registry who has
indicated a desire to be on the Emergency Call List . The County will track who has been called and been
responsive and will rotate through the Emergency Call List before beginning the rotation again .
All sealed bids will be opened publicly at a date , time , and venue specified in the bid invitation . All bidders
are invited and welcome to attend . Within 72 hours of the bid opening, after the review of bid breakdowns
and construction schedules, the winning bidder ( s ) will be selected . All bidders and the homeowner will be
notified in writing of the selection of the winning bid , the amount of the winning bid , and the specific
reasons for the selection if the lowest bidder was not selected .
The contractor is responsible for obtaining a building permit for the project before beginning work . The
permit must be posted at the project site during the entire period of construction . If applicable , the
contractor will obtain a permit for lead and /or asbestos hazard - related activities . The Rehabilitation
Specialist will closely monitor the construction to make sure that the work is being done according to the
work write - up ( which is made part of the contract by reference ) and in a timely fashion . Local code
enforcement officials will , if required , inspect the work for compliance with the NC State Building Code and
the local minimum housing code, when applicable . The homeowner will be responsible for working with
the contractor to clear their personal property from the work areas as needed , as much as practicable . The
contractor will be responsible for all clearing and cleaning activities necessary due to construction .
Any change to the original scope of work must be in writing in the form of a change order to be agreed
upon and signed by all parties to the original contract and two representatives of the County . The change
order must detail any changes to the original contract price .
No work may begin prior to a contract being awarded and executed and a written order to proceed
provided to the contractor . A pre - construction conference and a walk through of the project site must also
be held prior to the commencement of the project . At this time, the homeowner, contractor, and
Rehabilitation Specialist will discuss the details of the work to be completed . Project start and end dates
will be finalized , along with any special arrangements such as weekend or evening work hours and the
disposition of items to be removed from the home . Within 24 hours of the pre - construction conference,
the County will issue a " proceed order" formally instructing the contractor to commence work by the
agreed upon date .
Orange County is an equal opportunity employer, implements non - discriminatory practices in its
procurement and disbursement and will make special outreach efforts to include Minority/Women
Business Enterprise ( M /WBE ) businesses within its contractor and subcontractor pool . Contractors will be
chosen by the above criteria without regard to race, color, national origin , disability, religion , age ,
Orange County Urgent Repair and Housing Rehab Procurement and Disbursement Policy Page 2
r ORANGECOUNTY
,91, HOUS , NG DEPARTMENT
sex/gender, sexual orientation , gender identity and expression , marital status or veteran status .
Disbursement Policy
All repair work must be inspected by the Rehabilitation Specialist, the local Building or Minimum Housing
Code Inspector, when applicable, and the homeowner prior ;taiany payments to contractors . If all
construction work is deemed satisfactory and all other factors and, written agreements are in order,
payment shall be issued upon presentation of an original cost- per- item invoice from the contractor . The
contractor should allow up to fourteen ( 14 ) business days for processing of the invoice for payment .
The contractor is entitled to request two partial payments and aJinal payment . The first partial payment
may be requested when the work is 50 % complete . The second partial payment may be requested when
the work is 90 % complete . When a payment is requested , the Rehabilitation Specialist will inspect the
work within three ( 3 ) days, determine the percentage of job ' completion and calculate a payment based on
90 % of the total work completed . For projects that have a contract amount of less than $ 5 , 000, the second
payment will be the final payment for 100 % of the total work completed .
Following the completion of the construction , the contractor and the Rehabilitation Specialist will meet
with the homeowner in a post - construction conference . At this time , the contractor will provide to the
homeowner the owner ' s manuals and warranties on equipment and materials and be available to answer
any questions .
When the contractor declares the work complete , the Rehabilitation Specialist will thoroughly inspect the
work as part of the project closeout . If any of the work is deemed unsatisfactory, it must be corrected prior
to the authorization of final payment . If the contractor fails to correct the work to the satisfaction of the
Rehabilitation Specialist, payment may be withheld until such time as the work is deemed satisfactory . If a
dispute occurs, contractors may follow the procedure dealing with complaints, disputes, and appeals in
the applicable program ' s Assistance Policy . Contractors must abide by the final decision as stated in the
policy . The homeowner, Rehabilitation Specialist, and Housing and Community Development Manager
must sign off on the work . After the receipt of the contractor ' s final invoice, inspections, certificate of
completion and lien releases, the final payment will be processed . All material and workmanship will be
guaranteed by the contractor for a period of one ( 1 ) year from the date of completion of the work .
Orange County assures, through this policy, that adequate funds shall be available to pay the contractor
for satisfactory work .
All contractors , subcontractors and suppliers must sign a lien waiver prior to the disbursement of funds .
Orange County Urgent Repair and Housing Rehab Procurement and Disbursement Policy Page 3
n ORANGE COUNTY
4a, HOUSING DEPARTMENT
EN
f r
This Procurement and Disbursement Policy is adopted thisuday of SeO JANPX(e 20
1405 2
,•••'� NEWS
�,�•�;':) A J�;�� b� my Manager
• r
WIESE
s . pjjjjLj
Y
Notary Public �► : Wq s: : � :
Is
�AN .
Contractor' s Statement : '�'••• . . .. •••'�
00
I have read and understand the attached Procurement and Disbursement Policy .
SIGNED :
COMPANY NAME :
WITNESS .
Orange County Urgent Repair and Housing Rehab Procurement and Disbursement Policy Page 4