HomeMy WebLinkAboutAgenda - 06-06-2023; 5-a - Public Hearing Regarding Proposed Performance Agreement Between Orange County, North Carolina and Terra Equity, Inc., and Approval of Budget Amendment #10-A 1
ORD-2023-025
ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: June 6, 2023
Action Agenda
Item No. 5-a
SUBJECT: Public Hearing Regarding Proposed Performance Agreement Between Orange
County, North Carolina and Terra Equity, Inc., and Approval of Budget
Amendment #10-A
DEPARTMENT: Manager's Office
Attorney's Office
Planning & Inspections Department
Economic Development Department
ATTACHMENT(S): INFORMATION CONTACT:
1. Public Hearing Media Notice Travis Myren, Deputy County Manager,
2. Year-to-Date Budget Summary (919) 245-2308
John Roberts, County Attorney, (919)
245-2318
Steve Brantley, Economic Development
Director, (919) 245-2326
Cy Stober, Planning & Inspections
Director, (919) 245-2585
Christopher Sandt, County Engineer,
(919) 245-2583
PURPOSE: To:
(1) Receive information and hold a public hearing on the issuance of a performance-based
agreement by the County to a private development company;
(2) Consider approval of the proposed performance-based agreement, with claw-back
provisions, for the extension of public utilities (water and sewer) into the Hillsborough
Economic Development District; and
(3) Consider approval of Budget Amendment #10-A.
BACKGROUND: Beginning in FY 2014-15 and extending through FY 2017-18, the County
budgeted a total of $2,590,000 (funded through the County's Economic Development Portion of
the Article 46 Sales and Use Tax) to extend public water and sewer infrastructure to the
Hillsborough Economic Development District (EDD). The Hillsborough EDD is an Economic
Development Transition Zone containing approximately 160 acres of land served by Diversity
Drive and located near the intersection of Old NC 86 and Interstate 40 in Hillsborough, North
Carolina. The general footprint of the Hillsborough EDD is identified on the following map.
2
Hillsborough Area EDD CIP Project Area
a —
n
0
4W
2
F
d
PRaPos�o
RTLP PRC}JECT
A
Streams Future Land Use City Limits
-Water Bodies 10 Year Transition ETJ
a: Water Supply Watersheds 20 Year Transition Activity Nodes !in=1.40leer
9R.NJGE � �Feet
Q CCICHICAJoint Planning Area Rural Residential Economic Development Transition courrrr a 1,2W
Rural Buffer ]range C.—ty Pl--,q end M.P—fi—
BC 6116f2D23
The County completed the design, permitting, and easement acquisition activities for the
Hillsborough Area EDD Phase 1 Water and Sewer Extensions project in late 2018, which would
have extended Town of Hillsborough public water and sewer service under Interstate 40 and south
of Interstate 40 to the eastern and western boundaries of the Hillsborough EDD. The County
would have served as the project owner and manager. The primary purpose of the County's
original project was to provide "backbone infrastructure" to service the Hillsborough EDD and
facilitate development within the EDD. Public utility installation within the County's Economic
Development Districts is a primary use of the Article 46 One-Quarter-Cent Sales and Use Tax.
Revenues from the additional Article 46 tax, approved by voters on November 8, 2011, are split
equally between Education and Economic Development. The funding allocation originally
evidenced by a Resolution approved by the Board of County Commissioners on June 21, 2011
was renewed for an additional 10-year period on September 6, 2022.
The County received construction bids for the Hillsborough Area EDD Phase 1 Water and Sewer
Extensions project in early 2019, and the lowest qualified bid was $4,527,383, or approximately
$1.9 million over the budgeted amount. The County paused the original project as staff evaluated
alternatives to decrease the construction cost. All regulatory permits for the Hillsborough Area
EDD Phase 1 Water and Sewer Extensions subsequently expired in 2021/2022.
At its October 20, 2020 Business meeting, the Board of County Commissioners approved a
Master Plan Development Conditional Zoning District (MPD-CZ) for the proposed "Research
3
Triangle Logistics Park" (RTLP) project to develop property in the Hillsborough EDD that would
be served by the public water and sewer extensions very similar to those originally proposed by
the County. The approval allows for up to 2.4 million square feet of light industrial development
to occur on the RTLP site, shown in red outline on the map above.
The developer (Terra Equity, Inc.) has coordinated with County staff, Town of Hillsborough staff,
and applicable State and Federal agencies to reacquire all regulatory permits specific to the offsite
public water and sewer infrastructure within the Hillsborough EDD that would be required to
adequately serve the proposed RTLP development. On March 13, 2023, the Town of Hillsborough
Board of Commissioners approved a Water/Sewer Extension Contract with the developer,
allocating 108,000 gallons per day of public water/sewer capacity. The Water/Sewer Extension
Contract has now been signed by both the Town and the developer.
As currently designed, the offsite public utility project is located within public rights-of-way and/or
recorded public utility easements and includes approximately:
• 4,150 linear feet of 12-inch diameter water main,
• 3,520 linear feet of 8-inch diameter water main,
• 1,520 linear feet of 12-inch gravity sewer main, and
• 1,190 linear feet of 8-inch gravity sewer main.
The proposed public water lines will help improve public water service to the project vicinity by
providing a "looping" of the existing public water mains from Old NC 86 to New Grady Brown
School Road. The proposed water line loop will allow for:
• Redundancy in the event of an isolated water main break/repair,
• Improved residual chlorine content for better long-term water disinfection,
• Improved available water pressure and volume, and
• Better fire suppression needs for the local area.
The proposed public gravity sewer mains will extend the existing public sewer system from the
north side of 1-40 to the south side of 1-40 via a proposed bore and jack underneath 1-40. Terra
Equity, Inc. will serve as the project owner and project manager for the installation of the offsite
public water and sewer extensions associated with the RTLP development.
Economic Development Approach: Local and state governments in North Carolina have the goal
to promote economic development by encouraging the location of new businesses and the
expansion of existing businesses. This activity serves to diversify the local tax base, increase
employment opportunities and introduce desired job skills and related benefits to a community,
and for the benefit of its residents. The Local Government Act, North Carolina General Statute
(NCGS) 158-7.1, outlines the requirements of public hearings, and NCGS 158-7.1(a) specifically
addresses the requirement that economic development appropriations "must be determined by
the governing body of the city or county to increase the population, taxable property, agriculture
industries, employment, industrial output, or business prospects of the city or county". The
proposed public hearing as presented here has been scheduled in compliance.
The proposed Performance Agreement between the County and Terra Equity, Inc. outlines the
offsite public sewer and water infrastructure project in two phases, as follows.
Phase 1 — This phase includes the public water and sewer main extensions that are required to
reach and serve the proposed RTLP development. The County will reimburse Terra Equity, Inc.
fifty percent (50%) of actual costs incurred for Phase 1, up to $2.2 million, assuming a total cost
4
for Phase 1 to be $4.4 million. However, if the total costs for Phase 1 are less than $4.4 million,
the County's contribution will be less than $2.2 million. If the total costs are more than $4.4 million,
the County's contribution is capped at $2.2 million regardless of the actual costs incurred by Terra
Equity, Inc.
Phase 2 — This phase is specific to the offsite public water line loop that will connect the public
water mains located within the EDD to the existing dead-end public water main located at the end
of New Grady Brown School Road. For this phase, the County will reimburse Terra Equity, Inc.
the actual costs of Phase 2, up to $950,000. If the actual costs for Phase 2 are lower than
$950,000, then the County will pay the lower amount. If the actual costs for Phase 2 exceed
$950,000, then Terra Equity, Inc. will be responsible for those additional costs.
The total potential County commitment under the proposed Performance Agreement is $3.15
million. The County will retain ten percent (10%) of the total potential County commitment
($315,000) until fifty percent (50%) of Phase 2 is completed. Thereafter, the amount retained will
decrease to five percent (5%) of the total County commitment ($157,500) for both phases. An
engineer will verify these milestones, and final completion is dependent on the Town of
Hillsborough accepting the new infrastructure into the Town's public water and sewer systems.
FINANCIAL IMPACT:
Performance Agreement: The attached Performance Agreement contract between Orange
County and Terra Equity, Inc. outlines a total financial impact of: a) TWO MILLION TWO
HUNDRED THOUSAND DOLLARS ($2,200,000), plus, b) 100% of the Qualifying Expenditures
for Phase 2 of the project up to and not to exceed NINE HUNDRED FIFTY THOUSAND
DOLLARS ($950,000) for a total not to exceed amount and total County commitment of up to
THREE MILLION ONE HUNDRED FIFTY THOUSAND DOLLARS ($3,150,000). Not more
frequently than monthly, Terra Equity, Inc. shall submit to the County a draw request (a "Draw
Request") which shall include a certification of Qualifying Expenditures, the percentage of
completion of the Project and each Phase thereof, and a description of the work performed. The
County shall remit payment to Terra Equity, Inc. within thirty (30) days following the receipt of
each Draw Request in an amount equal to the County's share of the Qualifying Expenditures
summarized in each such Draw Request, provided, however County's remittance of funds for any
draw (or portion thereof) pertaining to Phase 1 of the Project shall be fifty percent (50%) of the
amount specified in the Draw Request (or portion thereof pertaining to Phase 1), it being the intent
that (i) the County and Terra Equity, Inc. each bear responsibility for fifty percent (50%) of the
Qualifying Expenditures for Phase 1 of the Project, until such time that the County has advanced
a maximum of $2,200,000 for Phase 1 of the Project; and (ii) the County bear responsibility for
the Qualifying Expenditures for Phase 2 of the Project, up to but not exceeding $950,000.
Expenditures are recommended to be funded with $2,345,857 unspent, available funds in the
Hillsborough EDD project and $804,143 in the Eno EDD project. Budget Amendment #10-A
repurposes funds from these two EDD projects and amends those ordinances, and will create the
following RTLP EDD Capital Project Ordinance in the County Capital Fund:
5
Hillsborough EDD (-$2,345,857) - Project# 30048
Revenues for this project:
Current FY 2022-23 FY 2022-23
FY 2022-23 Amendment Revised
Alternative Financing -Article 46 Repayment $2,350,000 ($2,105,857) $244,143
Article 46 Sales Tax Proceeds $240,000 ($240,000) $0
Total Project Funding $2,590,000 ($2,345,857) $244,143
Appropriated for this project:
Current FY 2022-23 FY 2022-23
FY 2022-23 Amendment Revised
County Capital Fund Expenditures $2,350,000 ($2,105,857) $244,143
Article 46 Expenditures $240,000 ($240,000) $0
Total Costs $2,590,000 ($2,345,857) $244,143
Eno EDD (-$804,143) - Project# 30045
Revenues for this project:
Current FY 2022-23 FY 2022-23
FY 2022-23 Amendment Revised
Alternative Financing -Article 46 Repayment $1,605,000 ($684,707) $920,293
Article 46 Sales Tax Proceeds $120,000 ($119,436) $564
Total Project Funding $1,725,000 ($804,143) $920,857
Appropriated for this project:
Current FY 2022-23 FY 2022-23
FY 2022-23 Amendment Revised
County Capital Fund Expenditures $1,605,000 ($684,707) $920,293
Article 46 Expenditures $120,000 ($119,436) $564
Total Costs $1,725,000 ($804,143) $920,857
RTLP EDD Project($3,150,000) - Project# 30055
Revenues for this project:
Current FY 2022-23 FY 2022-23
FY 2022-23 Amendment Revised
Alternative Financing -Article 46 Repayment $0 $2,790,564 $2,790,564
Transfer from Article 46 $0 $359,436 $359,436
Total Project Funding $0 $3,150,000 $3,150,000
Appropriated for this project:
Current FY 2022-23 FY 2022-23
FY 2022-23 Amendment Revised
Project Expenditures $0 $3,150,000 $3,150,000
Total Costs $0 $3,150,000 $3,150,000
The amendment provides funding from the Hillsborough and Eno EDD projects with a combination
of Article 46 proceeds and Article 46 funded debt financing. The cash proceeds will be transferred
6
into the County Capital Fund for ease of tracking and will increase the authorization in the County
Capital Fund by $359,436.
SOCIAL JUSTICE IMPACT: The following Orange County Social Justice Goal is applicable to
this item:
• GOAL: ENSURE ECONOMIC SELF-SUFFICIENCY
The creation and preservation of infrastructure, policies, programs and funding necessary
for residents to provide shelter, food, clothing and medical care for themselves and their
dependents.
ENVIRONMENTAL IMPACT: The following Orange County Environmental Responsibility Goal
impact is applicable to this item:
• RESULTANT IMPACT ON NATURAL RESOURCES AND AIR QUALITY
Assess and where possible mitigate adverse impacts created to the natural resources of
the site and adjoining area. Minimize production of greenhouse gases.
RECOMMENDATION(S): The Manager recommends that the Board:
(1) Receive the proposal to consider entering a Performance Agreement for the purpose of
incentivizing Terra Equity, Inc.'s public utility investment in the Hillsborough Economic
Development District of Orange County;
(2) Conduct the Public Hearing and receive public comments;
(3) Close the Public Hearing;
(4) Approve the performance-based incentive agreement between Orange County and Terra
Equity, Inc., subject to final review by the County Attorney, and authorize the Chair to sign
the Performance Agreement on behalf of the County; and
(5) Approve Budget Amendment #10-A as detailed above.
Attachment 1 7
�r�rr�Sr C",�l�lf
44
r�J
1� P-N
PUBLIC HEARING
Tuesday, June 6, 2023 — 7:00 PM
Whitted Building
300 W. Tryon Street
Hillsborough, NC 27278
NOTICE OF PUBLIC HEARING REGARDING PROPOSED ECONOMIC
DEVELOPMENT INCENTIVE AGREEMENT
Notice is hereby given that in accordance with North Carolina General Statute 158-7.1 the
Board of Commissioners of Orange County (the "Board") will hold a public hearing on
Tuesday, June 6, 2023 at 7:00 PM at the Whitted Building 300 W. Tyron St., Hillsborough,
N.C. 27278. This public hearing concerns Orange County entering into an agreement with
Terra Equity, Inc., for the purpose of incentivizing the Company's investment in Orange
County.
PERFORMANCE AGREEMENT
The Board will consider the appropriation of County Article 46 Sales and Use Tax funds to
offset the water/sewer utility project construction costs for the south side of Interstate 40 in
the Hillsborough Economic Development District by entering into a Performance Agreement
with Terra Equity, Inc., a Texas Corporation. The work is proposed to occur in two phases
with the total County commitment for both project phases not to exceed Three Million One
Hundred Fifty Thousand Dollars ($3,150,000). According to the proposed agreement the
County will cover 50% of qualifying expenditures, or up to Two Million Two Hundred
Thousand Dollars ($2,200,000) for Phase 1, proposed public gravity sewer mains that will
extend the existing public sewer system from the north side of 1-40 to the south side of 1-40
via a proposed bore and jack underneath 1-40. Phase 2 of the project would cover 100% of
qualifying expenditures or up to Nine Hundred Fifty Thousand Dollars ($950,000) for public
water lines that will help improve public water service to the project vicinity by providing a
"looping" of the existing public water mains from Old NC 86 to New Grady Brown School
Road.
Anyone interested in the Performance Agreement or the nature of the agreement between
Orange County and Terra Equity, Inc. may appear and be heard at the public hearing.
Anyone who wishes to make comments in writing prior to the public hearing may do so via
email to ocbocc orangecountync.gov. Interested persons may contact the Orange County
Economic Development office at 919-245-2325 with any questions.
8
Year-To-Date Budget Summary
Fiscal Year 2022-23
Fund Budget Summary County
Capital
Original Budget Revenue $10,612,009
Interfund Transfer Revenue
Fund Balance Appropriation
Total Original Budget $10,612,009
Additional Revenue Received Through
Budget Amendment#10-A (June 6, 2023)
Grant Funds $436,177
Non Grant Funds $542,540
Additional Interfund Transfer Revenue $1,327,466
Additional Fund Balance Appropriation
Total Amended Budget $12,918,192
Dollar Change in 2022-23 Approved Budget $2,306,183
% Change in 2022-23 Approved Budget 21.73%
Authorized Full Time Equivalent Positions
Original Approved Full Time Equivalent Positions (includes
Permanent and Time Limited) 0.000
Changes to Full Time Equivalent Positions
Amended Approved General Fund Full Time Equivalent
Positions 0.000
Total Approved Full-Time-Equivalent Positions for Fiscal
Year 2022-23 1 0.000