HomeMy WebLinkAboutAgenda - 09-13-2022; 2 - School Capital Needs Work Group Final Report 1 ORANGE COUNTY BOARD OF COMMISSIONERS ACTION AGENDA ITEM ABSTRACT Meeting Date: September 13, 2022 Action Agenda Item No. 2 SUBJECT: School Capital Needs Work Group Final Report DEPARTMENT: County Manager and Finance and Administrative Services ATTACHMENT(S): INFORMATION CONTACT: Capital Needs Work Group Final Report Jean Hamilton, Chair, Capital Needs Work Group, (919) 245-2130 Gary Donaldson, Chief Financial Officer, (919) 245-2453 PURPOSE: To receive the Final Report from the School Capital Needs Work Group and provide direction on next steps. BACKGROUND: The Capital Needs Work Group (the work group) was established in Fall 2021 as a result of a petition by Commissioner Jean Hamilton of the Orange County Board of County Commissioners (BOCC). The petition requested the work group address the capital needs of the two public school systems in Orange County — Orange County Schools (OCS) and Chapel Hill Carrboro City Schools (CHCCS)—especially the older schools, such that an actionable plan (over 10 years) would be developed that would dedicate funds and a process to address the needs. The work group sees value in collaboration and coordinating capital efforts across the BOCC, County staff and two school districts. The County is responsible for allocating capital funds amongst the schools and County capital needs. The school districts are responsible for managing their individual facilities to best meet local needs. In that context, the work group is interested in continuing to explore ways to improve efficiencies and transparency, and to better inform decision- making around the capital needs for all its schools. The work group agreed to present the three recommendations listed below (and as detailed in Appendix 1) to each of the three elected boards represented on the work group for consideration and approval: • Hire a consultant to evaluate the County's approach to school capital planning, design, contracting, and financing. • Research alternative funding sources for school capital improvements. • County and both school districts commit to continue working together on school capital planning through the existing work group. 2 If both school boards and the County agree, and the County moves forward with the consulting assessment, the work group should shift to an advisory role working with the consultant. School districts and the County should appoint board and staff leaders to continue. FINANCIAL IMPACT: There is no financial impact associated with receiving the Final Report from the School Capital Needs Work Group. There may be potential future impacts based on the next steps in the Board's consideration of this matter. SOCIAL JUSTICE IMPACT: There is no Orange County Social Justice Goal impact associated with receiving the Final Report from the School Capital Needs Work Group. There may be potential future impacts based on the next steps in the Board's consideration of this matter. ENVIRONMENTAL IMPACT: There is no Orange County Environmental Responsibility Goal impact associated with receiving the Final Report from the School Capital Needs Work Group. There may be potential future impacts based on the next steps in the Board's consideration of this matter. RECOMMENDATION(S): The Manager recommends the Board receive the report and provide feedback and comments as appropriate. School Capital Needs Work Group Report 3 Executive Summary In the fall of2021, in response to a petition from Commissioner Jean Hamilton, the Orange County Board of County Commissioners (BOCC) created the Capital Needs Work Group (the workgroup). The workgroup included elected officials and staff from the county and both school districts(Orange County Schools (OCS) and Chapel Hill-Carrboro City Schools (CHCCS) and was charged with focusing on school facilities. Orange County operates 32 school campuses and seven school administrative offices. Over half of the school buildings in both districts are over 50 years old and all are in need of updating and repair. Many of the newer schools are more than 20 years old and need maintenance and repair. Today more than 2,500 teachers and staff, and nearly 20,000 students work and learn in these school buildings every day. Orange County funds both school districts. The county's local contribution to per pupil funding ranks Orange County's schools first(CHCCS) and third(OCS) in the state for operating funding. On the other hand,school facilities, like in so many other districts, are chronically underfunded. By state law, Orange County is solely responsible for funding school capital(construction, repair and maintenance). The county's two school districts are responsible for developing facilities plans that are submitted to the county for funding. School capital is included in the county's 10 year capital planning process, where schools compete with county projects for scarce capital funds and access to debt financing. The workgroup reviewed current Orange County capital financing policies,planning and design practices and identified issues and obstacles to building and maintaining high quality schools. Current and projected funding sources are not adequate to address the backlog of unfunded school capital needs that are estimated at over$500 million. A significant issue is funding availability. The workgroup is aware that the current county funding model funds based on available funds and debt capacity rather than actual school needs. This restricts the county's ability to adequately fund school construction.Additionally, Orange County often does not qualify for state funded capital and grants that are available to other districts across the state. This is because Orange County is considered a high wealth county based on the formula that includes the median household income of its residents. Given the scale of school facility needs, we recommend that BOCC and county staff immediately begin to explore alternative funding sources to generate additional resources to support this work. The workgroup main recommendation is to engage an independent outside consultant that specializes in school facilities issues to assess the current situation and provide recommendations that will help Orange County and both school districts improve their approach to planning, priority management, design and construction and funding of school facilities. These improvements would be integrated into a 10- year plan to address school facility needs that both school districts have begun. In addition, the workgroup recommends that Orange County update SAPFO to more accurately reflect how school buildings are used. 1 4 Report and Recommendations BACKGROUND The Capital Needs Work Group (the work group) was established in Fall 2021 as a result of a petition by Commissioner Jean Hamilton of the Orange County Board of County Commissioners (BOCC). The petition requested that the work group address the capital needs of the two public school systems in Orange County: Orange County Schools (OCS) and Chapel Hill Carrboro City Schools (CHCCS), especially the older schools, such that an actionable plan (over 10 years) would be developed that would dedicate funds and a process to address the needs. The work group was designed to include representatives from the elected boards and staff of Orange County, Orange County Schools, and Chapel Hill Carrboro City Schools. Commissioner Jean Hamilton was designated as the chair and Orange County School Board member Bonnie Hauser was designated as vice-chair. (See table A for the list of participants and their titles.) Table A: Work Group Participants Entity Name Participant Name Participant Title Orange County Renee Price Board Chair Jean Hamilton Board Member,Work Group Chair Gary Donaldson Chief Financial Officer Steven Arndt Asset Management Director Greg Wilder Assistant to County Manager, Le islative Affairs Rebecca Crawford Deputy Director of Financial Services Kirk Vaughn Budget Analyst II Chapel Hill Carrboro City Deon Temne Board Chair Schools Dr. Jillian La Serna Board Member Rani Dasi Board Vice Chair Dr. N ah Hamlett Superintendent Andre' Stewart Chief Operations Officer Jonathan Scott Chief Financial Officer Eric Allen Former Director of Capital and School Facilities Al Ciarochi Deputy Superintendent of Operations Orange County Schools Carrie Doyle Board Member Bonnie Hauser Board Member,Work Group Vice Chair Brenda Stephens Former Board Member - served through June 30, 2022 Dr. Monique Felder Superintendent Patrick Abele Deputy Superintendent of Operations Rhonda Rath Chief Finance Officer 2 5 The work group had its first meeting on November 29, 2021. It generally meets on the third Wednesday of the month and is open to the public to attend remotely. It has met virtually seven times. (Meeting notes can be found in Appendix 1.) There are 32 K-12 school campuses in Orange County operated by two school districts. These campuses serve nearly 20,000 students and 2,500 employees every day. Over half of the campuses are over 50 years old. Some date back to the 1950s. (See Appendix 2 with lists of all school buildings and their age.) Funding for school capital needs is included in the Orange County Capital Investment Plan (CIP). Starting in fiscal year 2022, the CIP projects capital projects for 10 years (an increase from the 5 years in prior years). Each year the BOCC approves the capital funding for the current fiscal year providing flexibility for re- prioritization as necessary. School capital funding sources include the following: • General obligations bonds that require voter approval • Limited obligation bonds that are secured with assets • Lottery funds • Pay as you go funding (PAYGO). PAYGO funding is funding that comes from general fund revenues. • 50% of Article 46 quarter-cent sales tax revenue for capital/technology needs. Funding is allocated to the two school systems based on average daily membership (ADM) that is set by the North Carolina Department of Public Instruction. While state law requires school operating funds to be allocated by ADM, state law does not require capital expenditures to be allocated the same way. Over the past 5 years $154.6 million has been spent on school capital needs. (See table C for a breakdown by category). The last general obligation bond was in 2016 for$125 million while the school district capital needs were $232 million. The amount of unfunded school capital needs is estimated at over $500 million. Both school districts are currently developing updated 10-year plans. The CIP has $307.3 million planned for schools for the next ten years. The county's current capital plan and financing does not anticipate funding major improvements to schools through new bond funding before 2027. Table B: 5 Year Historical Capital Expenditures by Category Category Total Deferred Maintenance $3,122,950 Supplemental Deferred $1,808,999 Maintenance Vehicles $167,971 Rental S ace $663,705 Safety/Security Improvements $2,537,832 Construction $91,663,739 Chapel Hill HVAC $791 Athletic Facilities $713,786 3 Roofing $5,065,404 6 Equipment $15,621,950 General Renovations $1,473,743 Emergency/Security System $989,370 Door&Window Replacement $245,201 Energy Management $474,347 Technology $13,564,939 Abatement $688,333 Other (Recurring Capital) $15,832,253 Total $154,635,310 Orange County is not alone in dealing with aging school facilities. Wake, Guilford, and Durham Counties have undertaken substantial initiatives to comprehensively address the capital needs of schools. The work group sees value in collaboration and coordinating capital efforts across the BOCC, county staff and two school districts. The county is responsible for allocating capital funds amongst the schools and county capital needs. The school districts are responsible for managing their individual facilities to best meet local needs. In that context,the workgroup is interested in continuing to explore ways to improve efficiencies and transparency, and to better inform decision-making around the capital needs for all its schools. FINDINGS • Facility Planning/Standards o Updated facilities studies are needed for our public schools. OCS is planning to start a new study in the coming school year. CHCCS is currently undertaking an updated facility study to be completed in Spring 2023. o There are no county standards/guidelines for renovating or replacing aging school buildings. The work group discussed concerns about over-investing in buildings that should be replaced. The work group discussed how a facility condition index (FCI),which is a ratio of deferred maintenance to replacement cost, is one way to determine when a school needs to be replaced. o Orange County's School Construction Standards were last updated in 2007. These standards focus on new school construction and include traditional and non-traditional models. o School Adequate Public Facilities Ordinance (SAPFO) was adopted in 2003 between BOCC, school boards, and towns (except Mebane) as an attempt to ensure school capacity can meet the population growth. SAPFO has not been updated to meet the current conditions including taking into account Pre-K classrooms, space for special needs students, non-standard room sizes, model capacity assumptions, and growth in the western part of county. o Our aging school buildings do not reflect modern building standards and therefore provide sub-optimal learning environments for children with many of them 4 ■ lacking natural light, 7 ■ having air quality challenges, including mold ■ not having flexible spaces, e.g. for break-out rooms ■ having small classrooms ■ not meeting modern safety standards including having modular classrooms and open classrooms ■ having heating and cooling system failures, o Our aging school buildings are energy inefficient and expensive to maintain. • Facility Maintenance o OCS and CHCCS are challenged to recruit and retain facilities staff due to the high demand for those occupations and the relatively low salaries that are offered by the school systems. The pandemic has made these challenges worse. o Material costs and delays have increased due to the pandemic. o Cost and timing efficiencies may be possible by coordinating the capital and maintenance expenditures of OCS and CHCCS. o Major capital projects like new construction and major renovations require time commitments that school facility staff may not have and so these projects may benefit from contracted construction professionals that can be part of the capital budget. o There are no standards or funding for ongoing school maintenance. Policy/Funding o Capital school funding is impacted by BOCC guidelines that limit total (county and schools) debt capacity to about 15 percent of general revenues o The target to maintain total school funding (capital debt service, PAYGO, and operations) at 48.1% of the county's general revenue constrains school capital spending given other school needs. o Policies have not been developed for how much money needs to be allocated for on-going maintenance needs. Looking at other industries would be helpful to inform policy for school facilities. o There is no county-wide plan to land bank for future school needs. o State funding sources have not kept up with the school capital needs. Historically, from the late 1940s, North Carolina voters approved state obligation bonds on average every 10 years to help counties with school construction projects. They have not done so since 1996. RECOMMENDATIONS • Hire a consultant to evaluate the county's approach to school capital planning, design, contracting, and financing including: o Examine the planning, design/build, and maintenance process for both school districts and identify areas for improvement. o Work with school districts to evaluate every school campus and administrative building and highlight those that should be urgently replaced or renovated o Evaluate the county's school capital funding approach o Identify ways to plan and fund ongoing school maintenance. 5 o Provide insight about approaches, opportunities, and risks around $ emerging practices for contracting and program management, including projects that could cross campuses and districts. o Recommend how the county and two school districts can prioritize projects within a 10 year plan to address school facility needs in a transparent way. • Research alternative funding sources for school capital improvements: o Revisit county capital plans and financing to identify potential funding sources for school capital o Work with state and federal legislators and the public to advocate for funds for school capital. • County and both school districts commit to continue working together on school capital planning through the existing work group: o Review and update the county's policies governing school facilities planning and financing o Work with both school districts to develop a 10 year plan for school facilities -building upon the work that's already been done by both school districts. o In parallel, the county should work with the two school districts to update SAPFO to better reflect school capacity characteristics. NEXT STEPS If both school boards and the county agree, and the county moves forward with the consulting assessment,the work group should shift to an advisory role working with the consultant. School districts and the county should appoint board and staff leaders to continue. The work group should also work with the SAPFO Technical Advisory Committee (TAC) to review changes to SAPFO or other capacity planning standards. 6 9 Appendix 1: Work Group Meeting Notes ORANGE COUNTY BOARD OF COMMISSIONERS CHAPEL HILL-CARRBORO BOARD OF EDUCATION ORANGE COUNTY BOARD OF EDUCATION Capital Needs Work Group November 29, 2021 Meeting—8:00am Due to current public health concerns, the Capital Needs Work Group is conducting a Virtual Meeting on November 29, 2021. Members of the Group will be participating in the meeting remotely. 1. Welcome, Introductions, and Purpose 2. Designate Officers 3. FY 2022-32 Capital Budget Kickoff 4. Deferred Maintenance Planning 5. Schedule Next Meeting Adjourn Capital Needs Work Group virtual meetings are open to the public to attend remotely. Should any member of the public wish to view this meeting, please click the following link to register: https:Horan-e�ygc.zoom.us/webinar/register/WN_7QDnY E4RK-zV3vuAQxtPQ After registering, you will receive a follow-up email which will allow you to access and view the meeting. If you have any comments or questions, would like to submit any written comments to the group, or would like an emailed copy of the entire agenda package for this meeting, please email Rebecca Crawford at rcrawfordkoran ems. nic.gov before 3:00 pm on November 26, 2021. 10 ORANGE COUNTY BOARD OF COMMISSIONERS CHAPEL HILL-CARRBORO BOARD OF EDUCATION ORANGE COUNTY BOARD OF EDUCATION Capital Needs Work Group November 29, 2021 Meeting—8:00am Due to current public health concerns, the Capital Needs Work Group is conducting a Virtual Meeting on November 29, 2021. Members of the Group will be participating in the meeting remotely. 1. Welcome, Introductions, and Purpose 2. Designate Officers a. Commissioner Jean Hamilton—Chair b. OCS Board of Education member Bonnie Hauser—Vice Chair 3. FY 2022-32 Capital Budget Kickoff a. Gary Donaldson, Orange County Chief Financial Officer and Rebecca Crawford, Orange County Deputy Financial Services Director shared a powerpoint presentation for the FY 2022-32 Capital Budget process kick-off(attached to these notes). 4. Deferred Maintenance Planning a. Work Group members had the following comments: i. Bonnie Hauser — 30 aging buildings in system — missing from the conversation 1. Is there a way to move some of the costs to PAYGO? Debt is alarming. ii. Patrick Abele — would like to look at feasibility of funding going into old buildings vs building new schools and replacing old ones 1. Concerned with forecasting 6-10 years based on short time frame and existing facility study is older from 2012 — will need an updated facility study in order to ensure information is accurate — proposed a Phase I for 1-5 years of needs and Phase II 6-10 years of needs, which would be presented after the initial budget period. 2. Asked the status of land banking for new schools — inventory of sites is low and predicts tremendous growth is coming 11 a. SAPFO results will share timeline of when to build new schools b. Will have a need but no land — need to plan 20-30 years from now 3. Is there an opportunity for county CIP support to include planning for capital project staff and construction staff to move the projects forward? (now can only move projects ahead when have capacity) iii. Renee Price —how definitive is planning for 6-10 years actually? 1. Likes the idea of a plan 2. A lot of maintenance and repair issues, especially in OCS —can't put a bandaid on all of the issues — when do we construct something new? a. Maintenance costs on Chapel Hill High School will be huge — did we plan for those? i. Gary shared we do plan for that iv. Jean Hamilton — goal for this group is to look at long term without putting extra work on staff(20 years out) 1. Need to update facility studies — but cost effectively a. can schools piggy-back on county facility study? v. Rani Dasi - maintenance needs fresh eyes —what is the right level of maintenance to avoid between 3-6% of asset value 1. CHCCS=less than 1%, which causes big problems vi. Bonnie Hauser — how do other counties fund ongoing school maintenance? 1. In-house vs outsource? 2. Can we check with other jurisdictions such as Alamance, Durham, Chatham, Guilford, and Wake? 3. Find new ways to do it in OC 4. All campuses should be on regular, funded schedule vii. Renee Price — seeing increased costs for projects and supplies — could the purchases be done across both systems to find savings? 1. Patrick said this is possible 2. Align projects like roofs — did this during COVID on pre-bids and found great results 12 3. Can do the same with county projects such as tennis courts viii. Bonnie Hauser—debt service is in operation budget and rolled into 48% for school funding 1. Can we uncouple debt service from operating budget% 2. Wake Co. keeps it separate 3. Operating is distributed per pupil — capital doesn't have to be since some schools are in worse shape than others a. Can we revisit these policies? b. SAPFO was focused on rapid growth, which we don't have any more — should we focus more on maintenance now? ix. Renee Price — no stuck on 48%, just a guideline/target and can be adjusted 1. Gary Donaldson shared we have been above this in some years x. Eric Allen — meeting with architect about CHCCS facility study today and should have an estimated timeline 1. At a point where need to replace major systems, which will be a bandaid, when go in should replace full systems to make best investment xi. Patrick Abele — OCS would need to put out an RFP for facility study—will take 6-8 months 1. Can easily do years 1-5 now and 3rd week of January is ok for CIP submissions 2. Echoed Eric's comments — we need to do a better job communicating all of that to public and officials xii. Bonnie Hauser — Guilford's CIP increased in cost because focused on school modernization 1. Can we contract out maintenance so it's off of our financial books? xiii. Renee Price — have some unsafe campuses — especially elementary schools 1. "open" and need to be more safe 2. Keep seeing school shootings and need to secure our campuses 3. Would like to see maintenance need list even if don't know when or how much can plan better a. Eric Allen mentioned a roof management plan would help with that— are doing that now with consultants on facility maintenance plan 13 b. Rani Dasi mentioned it's reasonable to do with windows, HVAC, etc. 4. Can we share these slides with the BOCC? Would be really helpful xiv. Jean Hamilton—Recap of To Do List: 1. Need for updated facility study 2. Need for updated facility maintenance plan 3. Coordinated capital projects 4. Benchmark how other districts handle ongoing maintenance (share at next meeting) a. When fix vs when replace (County and districts will work on) 5. Long range capital plan 6. Complete normal budget cycle 7. Review state of individual schools and needs (use same format) a. % spent on maintenance right now (Finance can say impact on models — 2019 template?) 5. Schedule Next Meeting a. Renee Price and Rani Dasi — would like to see all projects and needs—schools bring requests for next 10 years b. Meet Monday mornings i. January I01h from 8am-9:30am Adjourn Capital Needs Work Group virtual meetings are open to the public to attend remotely. Should any member of the public wish to view this meeting, please click the following link to register: https:Horan eg countync.zoom.us/webinar/register/WN 7QDnY E4RK-zV3vuAQxtPQ After registering, you will receive a follow-up email which will allow you to access and view the meeting. If you have any comments or questions, would like to submit any written comments to the group, or would like an emailed copy of the entire agenda package for this meeting, please email Rebecca Crawford at rcrawfordAoran eg countync.gov before 3:00 pm on November 26, 2021. 14 ORANGE COUNTY BOARD OF COMMISSIONERS CHAPEL HILL-CARRBORO BOARD OF EDUCATION ORANGE COUNTY BOARD OF EDUCATION Capital Needs Work Group January 27, 2022 Meeting—8:30am Due to current public health concerns, the Capital Needs Work Group is conducting a Virtual Meeting on January 27, 2022. Members of the Group will be participating in the meeting remotely. 1. Welcome—Commissioner Jean Hamilton, Chair of Work Group 2. Review School Maintenance Needs Reports 3. Peer Jurisdiction School Maintenance Report Outs 4. Discussion and Next Steps 5. Schedule Next Meeting Adjourn Capital Needs Work Group virtual meetings are open to the public to attend remotely. Should any member of the public wish to view this meeting, please click the following link to register: Capital Needs Work_rgroup Registration Link After registering, you will receive a follow-up email which will allow you to access and view the meeting. If you have any comments or questions, would like to submit any written comments to the group, or would like an emailed copy of the entire agenda package for this meeting, please email Rebecca Crawford at rcrawford(d),oran eg countync.gov before 3:00 pm on January 25, 2022. 15 ORANGE COUNTY BOARD OF COMMISSIONERS CHAPEL HILL-CARRBORO BOARD OF EDUCATION ORANGE COUNTY BOARD OF EDUCATION Capital Needs Work Group January 27, 2022 Meeting—8:30am Due to current public health concerns, the Capital Needs Work Group is conducting a Virtual Meeting on January 27, 2022. Members of the Group will be participating in the meeting remotely. Joining are: Jean Hamilton, Bonnie Hauser, Andre Stewart, Brenda Stephens, Monique Felder, Nyah Hamlett, Eric Allen, Gary Donaldson, Rebecca Crawford, Kirk Vaughn, Greg Wilder, Jonathan Scott, Patrick Abele, Rani Dasi, Renee Price, Rhonda Rath, Steve Arndt, and resident Kari Hamel 1. Welcome—Commissioner Jean Hamilton, Chair of Work Group • Jean to provide opening remarks, introduce the panelists and topics ■ Group settles on first names for discussion ■ Staff will rotate note taking ■ Use GARE framework ■ Wants action items and final product to come from this group ■ Jean, Rani, Brenda, Renee, Monique, Gary, Patrick discuss frequency of meetings—Monthly, with ability to drop meetings ■ Jean, Rani, Bonnie discuss outcome of this process — Bond, or other aspects of the CIP process • Review School Maintenance Needs Reports o Patrick to present Orange County's School Maintenance ■ Breaking down bond projects— • Expanded Parking &Ag Building not complete at CRHS • Roof projects complete save one roof,under budget • Mechanical projects in process o See attached slides • School safety projects mostly complete • Purchased property OC Welcome Center ■ Break down major projects by school • Broken down by safety, new construction, Major Systems 10 year service life, Other Major Building Improvements • Total needs of$142 M over next ten years • Shows Grady Brown Major Projects Summary ■ Stresses cost increases and delays for supplies in pandemic. 16 • Suggests combining projects between county and school districts to mitigate this issue ■ Question: Renee asks if older schools are being bandaided, if they match the needs of the 21St century • Patrick discusses the increased costs for new schools — says $40 M for Elem $100 M for High School ■ Question: Bonnie asks if costs of schools are driven by being designed to last 50 years. Is there a model where we build schools for 20 years? ■ Renee and Bonnie point out the design of Grady Brown do not match the modern safety standards o Andre to present CHCCS report slideshow ■ 9 structures that are over 50 years, newer structures are 10 — 30 years old ■ Worked with external consultant to plan different structures determined 3 options ■ Eric to discuss difference between repair v new schools • New structures may cost more but can save costs in long run • Wake County high school building 2200 kids $176 M costs ■ Question: Jean asks about the cost of land, and how do you move kids from structure in repair? • Eric suggests different models, both moving into swing space - building temporary facility - vs keep students on site. Both add costs. ■ Question: Bonnie asked about charter school's cheaper construction costs. How can we use those efficiencies? • Eric discuss meeting with construction, generating efficiencies in constructions and operating costs. ■ Question: Bonnie wants group to review innovations in building standards and structures to make efficiencies • Patrick discussed getting best practices session from other entities. SOG, other schools. 2. Peer Jurisdiction School Maintenance Report Outs o Patrick to discuss OCS construction standards, notes other counties that use DPI standards. Orange County standards are out of date and drive up costs. Discuss how schools need to construct for growth, i.e. larger elementary schools. • Patrick discussed hiring and retention in trade staff, turnover drives costs, delays o Eric shows slide on CHCCS classified employee study, to determine proper salary ranges. • Discuss hiring construction professionals as project managers, can be costed in the project budgets. o Question: Bonnie asks about hiring versus contracting for this staff. 17 • Eric discussed how for major construction, school needs to have manager that represents the schools, not the construction company. o Question: Bonnie asks about maintenance, and how both are in the CIP process • Patrick talks about how construction and maintenance are two different skill sets, and we have same staff doing both. • Weakness in maintenance drives costs in CIP, parts not lasting full length. • Patrick includes conversation on sustainability possibly built into projects, and how that can drive up costs. o Question: Jean asks about maintenance costs, are they capital costs or operating costs o Patrick states that they are costs in both. Staff in operating, both school systems use recurring capital for projects 4. Discussion and Next Steps o Jean wants to get those costs in our meeting, both operating and capital costs o Bonnie ask about capital versus operating. County puts schools in tension of deciding between using per-pupil on instructional versus maintenance needs. Should we use separate funding sources o Jean wants to know total costs, then we can decide how to get there. Believes this group is the basis to determine the need. o Renee points out that we have a CIP budget, separate from operating budget. Should CIP budget be set up differently? Especially since Orange County Schools does not have extra funding source. o Rani states that the county has all these assets, between county and two school systems. o Renee wants to make sure maintenance costs in new construction are considered o Patrick wants to look at other counties that have county/city schools. How do they allocate in timing between systems? 5. Schedule Next Meeting &Next Topics o Jean wanted to ask about next meeting: timing and items. Suggests 3ra Wednesday of the month in mornings. 8:30 to loam • February 16th at 8:30am— l0am will be next meeting o Eric asks timing for construction. Takes 18 months to advertise,plan, get DPI approval. Wants to make sure that construction time is built in. • Gary stated that that is built into county CIP o Bonnie wants invite an outsider to upcoming meeting to learn about best practices. Wants to ask about different financing methods. 18 o Steve asked about facility condition index. Ratio of deferred maintenance to replacement cost. Can use that to rank the schools to make decisions on which can be replaced. • Eric states Mosley to update report to include that detail. • Patrick states that facility study can include that metric. o Bonnie asks if we have two different frameworks, how can we standardize reports? • Eric states we don't have design guideline for school systems, rely on firm. Next step can be merging guidelines. o Jean made closing statement and requested that CIP budget requests be shared at the next meeting to understand the impact on debt. • Gary stated both School District Finance Officers have received the necessary forms and timeline to provide their CIP requests to the county. Adjourn Capital Needs Work Group virtual meetings are open to the public to attend remotely. Should any member of the public wish to view this meeting, please click the following link to register: Capital Needs Workgroup Registration Link After registering, you will receive a follow-up email which will allow you to access and view the meeting. If you have any comments or questions, would like to submit any written comments to the group, or would like an emailed copy of the entire agenda package for this meeting, please email Rebecca Crawford at rcrawfordkoran epic.gov before 3:00 pm on January 25, 2022. 19 2106 EDUCATION BOND Project Budget Expenditures %Exp Balance Notes Classroom addition completed.Expanded parking and AG CRHS Classroom Addition $14,500,000.00 $12,984,021.00 89.54% $1,515,979.00 building not completed. Transportation Joint Facility $0.00 $0.00 0.00% $0.00 Removed from the projects by CHCCS/OCS Roof Replacements $4,038,889.00 $3,040,560.00 75.28% $998,329.00 See below Mechanical Systems $24,096,118.00 $14,264,360.92 59.20% $9,831,757.08 See below School Safety $2,156,993.00 $1,940,205.97 89.95% $216,787.03 Vesitbules installed all locations except HES. Purchase Real Property OC-Welcome Center $3,100,000.00 $3,100,000.00 100.00% $216,787.03 $47,892,000.00 $35,329,147.89 73.77% $12,562,852.11 Bond Sales by Orange County Dates Year 1 Funding FY'18(2017-2018) $15,964,000 Year 3 Funding FY'20(2019-2020) $15,964,000 Year Funding FY'22 (2021-2022) $15,964,000 $47,892,000 20 BOND PROJECTS 2016 Mechanical Projects Status Update River Park Elementary Phase II Ongoing 50% complete Central Elementary 100% design, rebid in Feb/Mar '22 Efland Cheeks 100% design, bid in Feb/Mar '22 AL Stanback 85% design, bid in Feb/Mar '22 New Hope Partial complete, working with DPI on replacement schedule Hillsborough Not started Grady A Brown Not started 21 BOND PROJECTS 2016 Roof Projects Status Update AL Stanback Middle Completed River Park Elementary Completed Efland-Cheeks Elementary Completed Grady A Brown Elementary Completed Hilsborough Elementary Not completed-TBC '2023 22 New Construction or Major Systems<10 Other MajorTotal Projected Safety Additions Years Service Life Building Cost School Name Improvements Central ES $140,000 $5,707,090 $5,269,961 $4,313,469 $15,430,520 Efand-Cheeks Global ES $140,000 $4,027,933 $3,780,204 $1,252,864 $9,201,001 / 1 Grady ABrown ES $140,000 $1,358,930 $2,792,961 $5,659,457 $9,951,348 Hillsborough ES $186,948 $26,848,000 $5,229,972 $6,078,122 $38,343,042 Orange New Hope ES $140,000 $0 $3,034,092 $1,300,000 $4,474,092 Pathways ES $140,000 $0 $2,567,101 $643,604 $3,350,705 County River Park ES $140,000 $18,276,225 $1,724,746 $778,632 $20,919,603 ALStanbackMS $140,000 $0 $1,781,607 $2,728,768 $4,650,375 Schools Gravelly Hill MS $222,701 $0 $2,533,034 $1,334,593 $4,090,328 Orange MS $184,827 $0 $1,908,865 $3,872,360 $5,966,052 NORTH CAROLINA Cedar Ridge HS $325,719 $0 $7,285,461 $523,650 $8,134,830 Orange HS $975,000 $5,491,775 $3,922,766 $5,336,208 $15,725,749 Partnership $47,479 $2,500,000 $45,449 $77,869 $2,670,797 DISTRICT TOTALS $2,922,674 $64,209,953 $41,876,219 $33,899,596 $142,908,442 23 AL STANBACK MIDDLE SCHOOL School Capacityl Major capital Projects Requiring Additional Funding SAPFO CAPACITY 740 MEMBERSHIP COUNT. 653 AGE OF SCHOOL/BUILDINGS 1995 PROJECT PRIORITY&CATEGORY ESTIMATED RANGE OF COST. CAPACITY IMPACT 2 Option SAFETY LOW HIGH 1 !IMPLEMENT SECURITY RECOMMENDATIONS $100,000 $140,000 N Subtotal $100,000 i $140,000 0 Option NEW CONSTRUCTION&BUILDING ADDITIONS LOW HIGH Subtotal $0 $0 0 :MAJOR SYSTEMS RECOMMENDED FOR REPLACEMENT WITH<10 Option LOW HIGH :YEARS OF USABLE LIFE I ;:NEW BOILER $242,396 1 $302,994 N 3 'ENERGY MANAGEMENT SYSTEM UPGRADE $515,091 $721,127 N 1 ::NEW CHILLER $605,989 $757,486 N Subtotal $1,363,475 i $1,781,607 0 Option ;MAJOR BUILDING IMPROVEMENTS LOW HIGH 3 RENOVATE 6TH GRADE CLASSROOM WING $136,348 $166,647 N 1 :FOOD SERVICE RENOVATIONS $9,090 $10,908 N 3 :INTERIOR FACILITIES UPGRADES AND REPAIRS: SCIENCE ROOM $252,495 1 $378,743 N 1 LIGHTING: ENERGY EFFICIENT LIGHTING UPGRADE $745,366 $975,642 1 N 1 :NEW EMERGENCY GENERATOR LIGHTING $309,054 $515,091 N I ::EXTERIOR RECOMMENDED REPAIRS $605,989 $681,738 N Subtotal $2,058,342 i $2,728,768 0 Grand Tota13(2024 cost estimate):: $3,521,818 $4,650,376 0 Number of classrooms below DPI minimums sf.• TBD Number of mobile units: 0 Note:The above cost estimates include major projects that were identified in the 2013-2014 Schools Comprehensive Facilities Assessment as well as projects that have been identified since that study,None of the projects listed have been fully funded. I School Capacity:Orange County NC Schools Adequate Public Facilities Ordinance(SAPFO).Annual membership count November 15,2019. Optionof Service(LOS)means the amount(level)of students that can be accommodated(serviced)at certain school system grade group.[i.e.,Elementary Option(K-5),Middle Option(6-8),High School Option(9-12)]Standards for LOS:Elementary 105%,Middle 107%,High School 110%.Source:Orange County NC SAPFO Annual Report. Class size reduction phase-in based on House Bill 90(SL 2017).Allotment and average class size in grades K-3 shall be at the following ratios for 2021-2022:Kindergarten(1:18), 1st Grade(1:16),2nd&3rd Grade(1:17). 12 Impact:YIN(number indicates number of potential seats gained or lost.) 3 Annual inflationary construction cost is calculated at 6%. Priori tv Rankin Ke Repair,replacement or renovation of items,components or systems that are important to the health and safety of the students and staff and to sustain the overall operation of the facility.General maintaince and system service life upgrades.(state building code violations,health department violations,handicapped accessibility issues,removal of hazardous material,security issues not Optionl being met by current systems) Repair and renovation of long-range items that also bring the class size square footage of elementary classrooms to 1,200 sf Option2 and/or meet future capacity needs and the Orange County School Building Standards of 585 students for elementary schools. Option Repair and renovation of long-range items that also bring the class size square footage of elementary classrooms to 1,200 sf REVISED DATE:2/20/20 24 CEDAR RIDGE HIGH SCHOOL School Capacity' Major capital Projects Requiring Additional Funding SAPFO CAPACITY; 1,500 MEMBERSHIP COUNT. 1,067 -AGE OF SCHOOL/BUILDINGS 2002 PROJECT PRIORITY&CATEGORY ESTIMATED RANGE OF COST! CAPACITY IMPACT 2 Option SAFETY LOW HIGH I IMPLEMENT SECURITY RECOMMENDATIONS $287,845 $325,719 N Subtotal $287,845 $325,719 0 Option NEW CONSTRUCTION&BUILDING ADDITIONS LOW HIGH Subtotal $0 $0 1 500 !MAJOR SYSTEMS RECOMMENDED FOR REPLACEMENT WITH<10 Option I LOW HIGH :YEARS OF USABLE LIFE 1 :MECHANICAL HVAC SYSTEM $1,856,750 $2,542,124 1 N I :ROOF COATING/SEALING(20 yr) $2,000,000 $3,500,000 1 1 :ENERGY MANAGEMENT SYSTEM UPGRADE $626,896 $940,343 1 N 1 :NEW BOILER $242,396 $302,994 N Subtotal $4,726,041 $7,285,461 0 Option MAJOR BUILDING IMPROVEMENTS LOW HIGH I ::FOOD SERVICE RENOVATIONS $42,419 $53,024 N 1 :INTERIOR FACILITIES UPGRADES AND REPAIRS: SCIENCE ROOM $183,312 $226,488 IN 1 :LIGHTING: ENERGY EFFICIENT LIGHTING UPGRADE $149,111 $244,138 IN Subtotal $374,842 $523,650 1 0 Grand Total(2024 Costs w1increased capacity): $5,388,728 1 $8,134,831 1 0 Number of mobile units currently on site 0 Note:The above cost estimates include major projects that were identified in the 2013-2014 Schools Comprehensive Facilities Assessment as well as projects that have been identified since that study.None of the projects listed have been fully funded. Service(LOS)means the amount(level)of students that can be accommodated(serviced)at certain school system grade group.[i.e.,Elementary level (K-5),Middle Level(6-8),High School Level(9-12)]Standards forLOS:Elementary 105%,Middle 107%,High School 110%.Source:Orange County NC SAPFO Annual Report. Class size reduction phase-in based on House Bill 90(SL 2017).Allotment and average class size in grades K-3 shall be at the following ratios for 2021-2022:Kindergarten(1:18), 1st Grade(1:16),2nd&3rd Grade(1:17). 12Capacity Impact:YIN(number indicates number of potential seats gained or lost.) Priority Ranking Key staff and to sustain the overall operation of the facility.General maintaince and system service life upgrades.(state building code violations,health department violations,handicapped accessibility issues,removal of hazardous material,security issues not Option I being met by current systems) Pt_'0nT Repair and renovation of long-range items that also bring the class sizes uare footage of elementary classrooms to 1,200 sf Up-tion3 Repair and long-range improvements that extend a minimum of twenty-five years of additional operation to a facility and meet REVISED DATE:1/8/2022 25 ti CENTRAL ELEMENTARY SCHOOL School Capacity' Major capital Projects Requiring Additional Funding SAPFO CAPACITY; 428 MEMBERSHIP COUNT. 286 AGE OF SCHOOUBUILDINGS 1953 PROJECT PRIORITY&CATEGORY ESTIMATED RANGE OF COST. CAPACITY IMPACT 2 Option SAFETY LOW HIGH 1 :IMPLEMENT SECURITY RECOMMENDATIONS $100,000 $140,000 N Subtotal $100,000 $140,000 0 Option :NEW CONSTRUCTION&BUILDING ADDITIONS LOW HIGH 2 ::CLASSROOM EXPANSION(UNIT PRICES INCLUDE PROJECT COSTS):: $3,306,427 1 $4,133,034 1 TBD :MEDIA CENTER EXPANSION(upgrades 3 $757,486 $946,858 N :completed without SF expansion in 2018) 3 ::OFFICE EXPANSION $545,390 $627,199 N Subtotal $4,609,303 i $5,707,090 i TBD ':MAJOR SYSTEMS RECOMMENDED FOR REPLACEMENT WITH<10 Option LOW HIGH .YEARS OF USABLE LIFE 1 NEW BOILER $121,198 $151,497 N 1 ::ENERGY MANAGEMENT SYSTEM UPGRADE $325,472 $418,464 N :MECHANICAL HVAC 1 $2,100,000 $4,700,000 N :EQUIPMENT/ELECTRICAL UPGRADES Subtotal $2,546,670 $5,269,961 0 Option :MAJOR BUILDING IMPROVEMENTS LOW HIGH I :FOOD SERVICE RENOVATIONS $151,497 $181,797 N ;INTERIOR FINISHINGS(VCT,CABINETS, I :SINKS, RESTROOM UPGRADES, PAINTING, $1,500,000 $3,000,000 1 ::GYM RENOVATIONS) 1 ::PRE-K PLAYGROUND SURFACE REPLACEMENT $348,444 $475,000 N 1 !PLAYGROUND FENCE INSTALLATION $121,198 $166,647 N 1 :LIGHTING: ENERGY EFFICIENT LIGHTING UPGRADE $212,096 1 $257,545 N 1 NEW EMERGENCY GENERATOR LIGHTING $139,488 1 $232,480 N Subtotal $2,472,723 i $4,313,469 0 Grand Total(2024 Costs w1increased capacity): $9,728,696 $15,430,521 TBD Number of mobile units currently on site 0 Note:The above cost estimates include major projects that were identified in the 2013-2014 Schools Comprehensive Facilities Assessment as well as projects that have been identified since that study.None of the projects listed have been fully funded. 7 Scnooi Capacity:Orange County NU Z5Crloois equate Pulwic Facluties urainance(SAFF-0)_Annual memijersnip count Novemijer 7b, ZV79.Levei or Service(LOS)means the amount(level)of students that can be accommodated(serviced)at certain school system grade group.[i.e.,Elementary level (K-5),Middle Level(6-8),High School Level(9-12)]Standards for LOS:Elementary 105%,Middle 107%,High School 110%.Source:Orange County NC SAPFO Annual Report. Class size reduction phase-in based on House Bill 90(SL 2017).Allotment and average class size in grades K-3 shall be at the Ifollowing ratios for 2021-2022:Kindergarten(118), 1st Grade(116),2nd&3rd Grade(1:17). 12capacity impact:YIN(number indicates number of potential seats gained or lost.) Priority Ranking Key Kepair,replacement or renovation of items,components or systems that are important to the health and safety of the students and staff and to sustain the overall operation of the facility.General maintaince and system service life upgrades.(state building code violations,health department violations,handicapped accessibility issues,removal of hazardous material,security issues not Option I being met by current systems) _70ption 2 Repair and renovation of long-range items that also bring the class sizes uare footage of elementary classrooms to 1,200 sf p ion Repair and long-range improvements that extend a minimum of twenty-five years of additional operation to a facility and meet REVISED DATE:1/8/20 26 EFLAND CHEEKS GLOBAL ELEMENTARY! School Capacity' Major capital Projects Requiring Additional Funding SAPFO CAPACITY; 455 MEMBERSHIP COUNT. 499 AGE OF SCHOOL/BUILDINGS 1952 PROJECT PRIORITY&CATEGORY ESTIMATED RANGE OF COST! CAPACITY IMPACT 2 Option SAFETY LOW HIGH .IMPLEMENT SECURITY RECOMMENDATIONS 1 $100,000 $140,000 N Subtotal i $140,000 0 Option NEW CONSTRUCTION&BUILDING ADDITIONS LOW HIGH 2 CLASSROOM EXPANSION $2,485,502 $2,982,602 126 2 PRE-K ADDITION $908,983 $1,045,331 1 TBD Subtotal $3,394,485 i $4,027,933 TBD MAJOR SYSTEMS RECOMMENDED FOR REPLACEMENT WITH<10 Option LOW HIGH .YEARS OF USABLE LIFE 3 ROOF REPLACEMENT $318,144 $363,593 N 1 :ENERGY MANAGEMENT SYSTEM UPGRADE $345,102 $443,702 N 1 :NEW BOILER $121,198 $151,497 1 N 1 NEW COOLING TOWER $48,479 $60,599 1 N 1 TOTAL HVAC REPLACEMENT $2,366,411 $2,760,813 N Subtotal $3,199,334 $3,780,204 0 Option ;:MAJOR BUILDING IMPROVEMENTS LOW HIGH 1 ;:FOOD SERVICE RENOVATIONS $278,906 $332,385 N 1 !EXTERIOR RECOMMENDED REPAIRS $181,797 $206,036 N 1 ;:LIGHTING: ENERGY EFFICIENT LIGHTING UPGRADE $357,221 $467,942 N I :NEW EMERGENCY GENERATOR LIGHTING $147,901 $246,501 N Subtotal $965,825 $1,252,864 0 Grand Total(2024 Costs w/increased capacity): #VALUE! $9,201,001 TBD Number of mobile units currently on site 0 Note:The above cost estimates include major projects that were identified in the 2013-2014 Schools Comprehensive Facilities Assessment as well as projects that have been identified since that study.None of the projects listed have been fully funded. Service(LOS)means the amount(level)of students that can be accommodated(serviced)at certain school system grade group.[i.e.,Elementary level (K-5),Middle Level(6-8),High School Level(9-12)]Standards for LOS:Elementary 105%,Middle 107%,High School 110%.Source:Orange County NC SAPFO Annual Report. Class size reduction phase-in based on House Bill 90(SL 2017).Allotment and average class size in grades K-3 shall be at the Ifollowing ratios for 2021-2022:Kindergarten(1:18), 1st Grade(1:16),2nd&3rd Grade(1:17). 12Capacity Impact:YIN(number indicates number of potential seats gained or lost.) Priority Ranking Key staff and to sustain the overall operation of the facility.General maintaince and system service life upgrades.(state building code violations,health department violations,handicapped accessibility issues,removal of hazardous material,security issues not Option I being met by current systems) 1)1_ion T Repair and renovation of long-range items that also bring the class sizes uare footage of elementary classrooms to 1,200 sf Up-tion3 Repair and long-range improvements that extend a minimum of twenty-five years of additional operation to a facility and meet REVISED DATE:1/8/2022 27 GRADY BROWN ELEMENTARY SCHOOL School Capacity' Major capital Projects Requiring Additional Funding SAPFO CAPACITY 490 MEMBERSHIP COUNT 442 AGE OF SCHOOL/BUILDINGS 1974 PROJECT PRIORITY&CATEGORY ESTIMATED RANGE OF COST. CAPACITY IMPACT 2 Option SAFETY LOW HIGH I IMPLEMENT SECURITY RECOMMENDATIONS $100,000 $140,000 N Subtotal $100,000 $140,000 0 Option NEW CONSTRUCTION&BUILDING ADDITIONS LOW HIGH 1 MAIN ENTRANCE ADDITION $1,181,678 $1,358,930 N Subtotal i $1,181,678 i $1,358,930 i 0 :MAJOR SYSTEMS RECOMMENDED FOR REPLACEMENT WITH<10 OptionLOW HIGH .YEARS OF USABLE LIFE I BOILER UPGRADES $166,647 $212,096 N 1 ::NEW COOLING TOWER $48,479 $60,599 N 1 :NEW ENERGY MANAGEMENT SYSTEM $397,765 1 $511,412 N I :MECHANICAL HVAC UPGRADE $1,702,829 $2,008,853 N Subtotal $2,315,720 $2,792,961 0 'MAJOR BUILDING IMPROVEMENTS —Option I LOW I HIGH I 3 :MEDIA CENTER/TEACHER SUPPORT RENOVATIONS $2,461,830 1 $2,954,196 1 N :PARKING LOT REPAVING AND CANOPY 1 $300,000 $600,000 1 AEPAIR 1 :HAZARDOUS MATERIALS REMOVAL $250,000 $600,000 N I :FOOD SERVICE RENOVATIONS $202,022 1 $251,561 N 3 :MOVE FRONT PLAYGROUNG/NEW PARKING/QUEUE LINE $681,738 1 $833,235 1 N I :LIGHTING: ENERGY EFFICIENT LIGHTING UPGRADE $106,048 1 $136,348 N 1 :NEW EMERGENCY GENERATOR LIGHTING $170,471 $284,118 N Subtotal $4,172,108 $5,659,457 0 Grand Total(2024 Costs w/increased capacity). $7,769,507 $9,951,348 0 Number of mobile units currently on site Note:The above cost estimates include major projects that were identified in the 2013-2014 Schools Comprehensive Facilities Assessment as well as projects that have been identified since that study.None of the projects listed have been fully funded. , ow,uu,�apawty. �'O"Vv�Uumy ��ou".—_­j atu�Uullu k­1 J J_­111UW 10,ZU I Z;F.LUVtl U1 Service(LOS)means the amount(level)of students that can be accommodated(serviced)at certain school system grade group.[i.e.,Elementary level (K-5),Middle Level(6-8),High School Level(9-12)]Standards for LOS:Elementary 105%,Middle 107%,High School 110%.Source:Orange County NC SAPFO Annual Report. Class size reduction phase-in based on House Bill 90(SIL 2017).Allotment and average class size in grades K-3 shall be at the Ifollowing ratios for 2021-2022:Kindergarten(118), 1st Grade(1:16),2nd&3rd Grade(1:17). 12c;apacity impact:YIN(number indicates number of potential seats gained or lost.) Priority Ranking Key staff and to sustain the overall operation of the facility.General maintaince and system service life upgrades.(state building code violations,health department violations,handicapped accessibility issues,removal of hazardous material,security issues not Option 1 being met by current systems) Option 2 Repair and renovation of long-range items that also bring the class sizes uare footage of elementary classrooms to 1,200 sf Option.3 Repair and long-range improvements that extend a minimum of twenty-five years of additional operation to a facility and meet REVISED DATE:1/8/2022 28 GRAVELLY HILL MIDDLE SCHOOL School Capacity'major capital Projects Requiring Additional Funding SAPFO CAPACITY 700 MEMBERSHIP COUNT 468 AGE OF SCHOOL/BUILDINGS 2006 PROJECT PRIORITY&CATEGORY ESTIMATED RANGE OF COST. CAPACITY IMPACT 2 Option SAFETY LOW HIGH .IMPLEMENT SECURITY RECOMMENDATIONS 1 $199,976 $222,701 N Subtotal $199,976 $222,701 0 Option NEW CONSTRUCTION&BUILDING ADDITIONS LOW HIGH Subtotal $0 $0 0 :MAJOR SYSTEMS RECOMMENDED FOR REPLACEMENT WITH<10 OptionLOW HIGH YEARS OF USABLE LIFE .NEW BOILER $242,396 $302,994 N 1 NEW CHILLER $605,989 $757,486 N 1 :NEW HVAC COMPONENTS(DOAS,AHU, FCU) $1,042,301 1 $1,472,553 N Subtotal $1,890,685 $2,533,034 0 Option :MAJOR BUILDING IMPROVEMENTS LOW HIGH .INTERIOR RENOVATIONS: UPGRADE SCIENCE CLASSROOMS TO 3 $90,000 $180,000 N :DPI STANDARDS I :NEW GENERATOR $60,599 $75,749 1 N ::PAVING/SIDEWALK REPAIR; PAVE REAR I 1 $502,994 $840,994 N :GRAVEL LOT 1 ISTORMDRAIN BMP REFURBISHING AND TOPSOIL/SEEDING $151,497 1 $196,946 N I :LIGHTING:AUDITORIUM ENERGY EFFICIENT LIGHTING UPGRADE $26,815 $40,904 N Subtotal i $831,905 $1,334,593 0 Grand Total(2024 Costs w/increased capacity): $2,922,567 $4,090,328 0 Number of mobile units currently on site 0 Note:The above cost estimates include major projects that were identified in the 2013-2014 Schools Comprehensive Facilities Assessment as well as projects that have been identified since that study.None of the projects listed have been fully funded. 1 School Gapace ty.,C)range County NC;Schools Adequate Public 1--acifitles Ordinance(SAPI-C)).Annual membership count November 15, 2019.Level oT— Service(LOS)means the amount(level)of students that can be accommodated(serviced)at certain school system grade group.[i.e.,Elementary level (K-5),Middle Level(6-8),High School Level(9-12)]Standards for LOS:Elementary 105%,Middle 107%,High School 110%.Source:Orange County NC SAPFO Annual Report. Class size reduction phase-in based on House Bill 90(SL 2017).Allotment and average class size in grades K-3 shall be at the following ratios for 2021-2022:Kindergarten(1:18), 1st Grade(1:16),2nd&3rd Grade(1:17). r2—capacity Impact:YIN(number indicates number of potential seats gained or lost.) Priority Ranking Key Hepair,replacement or renovation of items,components or systems that are important to the health and safety of the students and staff and to sustain the overall operation of the facility.General maintaince and system service life upgrades.(state building code violations,health department violations,handicapped accessibility issues,removal of hazardous material,security issues not Option 1 being met by current systems) Option 2 Repair and renovation of long-range items that also bring the class sizes uare footage of elementary classrooms to 1,200 sf Option.3 Repair and long-range improvements that extend a minimum of twenty-five years of additional operation to a facility and meet -REVISED DATE:1/8/2022 29 HILLSBOROUGH ELEMENTARY SCHOOL School Capacity' Major capital Projects Requiring Additional Funding SAPFO CAPACITY 420 MEMBERSHIP COUNT. 444 AGE OF SCHOOL/BUILDINGS 1952 PROJECT PRIORITY&CATEGORY ESTIMATED RANGE OF COST, CAPACITY IMPACT 2 Option :SAFETY LOW HIGH 1 IMPLEMENT SECURITY RECOMMENDATIONS $143,922 $186,948 N Subtotal $186,948$143,922 0 Option NEW CONSTRUCTION&BUILDING ADDITIONS LOW HIGH 2 REPLACE BUILDING 100 $22,500,000 $26,848,000 TBD Subtotal $22,500,000 $26,848,000 TBD MAJOR SYSTEMS RECOMMENDED FOR REPLACEMENT WITH<10 Option . LOW HIGH .YEARS OF USABLE LIFE I NEW HVAC SYSTEM $1,735,837 1 $2,433,176 1 N :ENERGY MANAGEMENT SYSTEM UPGRADE $386,397 $496,796 N 1 ROOF REPLACEMENT(BLDG 200/300/1 OO/LC) $1,800,000 $2,300,000 N Subtotal $3,922,234 i $5,229,972 1 0 —Option :MAJOR BUILDING IMPROVEMENTS LOW HIGH 1 BUILDING CONNECTORS $2,500,000 $3,500,000 N I ::OUTDOOR UPGRADE $545,390 $621,139 N I :SEWER LINE REPAIR $340,869 $393,893 N I ::HAZARDOUS MATERIAL REMOVAL $525,492 $618,987 N I FOOD SERVICE RENOVATIONS $209,596 $281,709 N I :LIGHTING: ENERGY EFFICIENT LIGHTING UPGRADE $331,197 1 $386,397 N I :NEW EMERGENCY GENERATOR LIGHTING $165,708 $275,998 N Subtotal $4,618,253 $6,078,122 0 Grand Total(2024 Costs w/increased capacity). $31,184,409 $38,343,042 TBD 2 OPTION: REMOVE 100,200 AND 300 BUILDINGS AND REPLACE WITH 1 I $28,000,000 $32,000,000 TBD NEW BUILDING BUILT TO NCDPI SPECIFICATIONS I Note:The above cost estimates include major projects that were identified in the 2013-2014 Schools Comprehensive Facilities Assessment as well as projects that have been identified since that study.None of the projects listed have been fully funded. I School Capacity:C)range County NC;Schools Adequate Public acifitles Ordinance(SAPI-U).Annual membership count November 15, 2019.Level ot Service(LOS)means the amount(level)of students that can be accommodated(serviced)at certain school system grade group.[i.e.,Elementary level (K-5),Middle Level(6-8),High School Level(9-12)]Standards for LOS:Elementary 105%,Middle 107%,High School 110%.Source:Orange County NC SAPFO Annual Report. Class size reduction phase-in based on House Bill 90(SL 2017).Allotment and average class size in grades K-3 shall be at the following ratios for 2021-2022:Kindergarten(1:18), 1st Grade(1:16),2nd&3rd Grade(1:17). 2Capacity Impact:YIN(number indicates number of potential seats gained or lost.) Priority Ranking Key Repair,replacement or renovation of items,components or systems that are important to the health and safety of the students and staff and to sustain the overall operation of the facility.General maintaince and system service life upgrades.(state building code violations,health department violations,handicapped accessibility issues,removal of hazardous material,security issues not Option 1 being met by current systems) Repair and renovation of long-range items that also bring the class size square footage of elementary classrooms to 1,200 sf Option 2 and/or meet future capacity needs and the Orange County School Building Standards of 585 students for elementary schools. Repair and long-range improvements that extend a minimum of twenty-five years of additional operation to a facility and meet Option 3 future capaicty needs or capacity standards of 637 students for elementary schools. REVISED DATE:1/8/2022 30 NEW HOPE ELEMENTARY SCHOOL School Capacity' Major capital Projects Requiring Additional Funding SAPFO CAPACITY 526 MEMBERSHIP COUNT 579 AGE OF SCHOOL/BUILDINGS 1991 CAPACITY PROJECT PRIORITY&CATEGORY ESTIMATED RANGE OF COST. IMPACT 2 Option SAFETY LOW HIGH 1 :IMPLEMENT SECURITY RECOMMENDATIONS $100,000.00 $140,000.00 N Subtotal $100,000.00 $140,000.00 0 Option NEW CONSTRUCTION&BUILDING ADDITIONS LOW HIGH _ Subtotal $0.00 $0.00 0 :MAJOR SYSTEMS RECOMMENDED FOR REPLACEMENT WITH<10 OptionLOW HIGH .YEARS OF USABLE LIFE 1 NEW HVAC SYSTEM $1,727,825.97 $2,351,237.09 N 1 ENERGY MANAGEMENT SYSTEM UPGRADE $531,109.92 $682,855.61 N Subtotal $2,258,935.88 1 $3,034,092.70 1 0 Option !MAJOR BUILDING IMPROVEMENTS LOW HIGH 1 ;:FOOD SERVICE RENOVATIONS $18,937.15 $26,057.52 N I IHAZARDOUS MATERIAL REMOVAL:CARPET AND MASTIC $340,868.78 $378,743.09 I N I :LIGHTING: ENERGY EFFICIENT LIGHTING UPGRADE $409,669.73 $515,835.97 N I ::NEW EMERGENCY GENERATOR LIGHTING $227,618.54 $379,364.23 N Subtotal $997,094.20 $1,300,000.81 0 Grand Total (2024 Costs w/increased capacity):: $3,356,030.09 $4,474,093.50 0 Number of mobile units currently on site 2 Note:The above cost estimates include major projects that were identified in the 2013-2014 Schools Comprehensive Facilities Assessment as well as projects that have been identified since that study.None of the projects listed have been fully funded. 7 Scnooi capacity:urange Counry coos equate Pubuc vacaitles uroinance nnual memDersnip coun ovember 7b, 2U79.Levei or Service(LOS)means the amount(level)of students that can be accommodated(serviced)at certain school system grade group.[i.e.,Elementary level (K-5),Middle Level(6-8),High School Level(9-12)]Standards for LOS:Elementary 105%,Middle 107%,High School I 10%.Source:Orange County NC SAPFO Annual Report. Class size reduction phase-in based on House Bill 90(SL 2017).Allotment and average class size in grades K-3 shall be at the Ifollowing ratios for 2021-2022:Kindergarten(1:18), 1st Grade(1:16),2nd&3rd Grade(1:17). 12Capacity Impact:YIN(number indicates number of potential seats gained or lost.) Priority Ranking Key Kepair,replacement or renovation of items,components or systems tnat are important to tne nealtn an satety of tne stuaens and staff and to sustain the overall operation of the facility.General maintaince and system service life upgrades.(state building code violations,health department violations,handicapped accessibility issues,removal of hazardous material,security issues not Option 1 being met by current systems) option 2 Repair and renovation of long-range items that also bring the class sizes uare footage of elementary classrooms to 1,200 sf Option 3 Repair and long-range improvements that extend a minimum of twenty-five years of additional operation to a facility and meet REVISED DATE:1/812022 31 ORANGE HIGH SCHOOL School Capacity' Major Capital Projects Requiring Additional Funding SAPFO CAPACITY 1,399 MEMBERSHIP COUNT 1,296 AGE OF SCHOOL/BUILDINGS 1962 PROJECT PRIORITY&CATEGORY ESTIMATED RANGE OF COST: CAPACITY IMPACT z Option :SAFETY LOW HIGH 1 IMPLEMENT SECURITY RECOMMENDATIONS $524,180 $975,000 N Subtotal $524,180 $975,000 0 Option SNEW CONSTRUCTION&BUILDING ADDITIONS LOW HIGH 3 REPLACE WORKFORCE DEVELOPMENT BUILDING $4,393,420 $5,491,775 TBD Subtotal $4,393,420 i $5,491,775 TBD Option ;MAJOR SYSTEMS RECOMMENDED FOR REPLACEMENT WITH<10 LOW HIGH :YEARS OF USABLE LIFE 1 :ROOF REPLACEMENTS(400/AUX GYM) $350,000 1 $525,000 1 N 1 :NEW BOILER-FIELD HOUSE $121,198 $151,497 N 1 :ENERGY MANAGEMENT SYSTEM UPGRADE $1,132,112 $1,455,572 : N 1 :ELECTRICAL SYSTEMS UGRADE $1,375,595 $1,790,697 : N Subtotal $2,978,904 $3,922,766 i 0 Option :MAJOR BUILDING IMPROVEMENTS LOW HIGH 1 FOOD SERVICE RENOVATIONS $266,938 $348,065 N 1 BACK DRIVEWAY REPAIR $1,363,475 $1,666,470 : N 1 INTERIOR RENOVATIONS: NON-ACCESSIBLE GROUP RESTROOMS : $699,917 1 $769,606 N 1 :INTERIOR RENOVATIONS:WOOD GYM FLOORS REFURBISH $143,922 $159,072 N 1 LIGHTING: ENERGY EFFICIENT LIGHTING UPGRADE $1,222,252 $1,584,344 : N 1 :NEW EMERGENCY GENERATOR LIGHTING $485,191 $808,651 N Subtotal $4,181,696 $5,336,208 1 0 Grand Total(2024 Costs w/increased capacity): $12,078,201 $15,725,749 TBD Number of mobile units currently on site 8 Note:The above cost estimates include major projects that were identified in the 2013-2014 Schools Comprehensive Facilities Assessment as well as projects that have been identified since that study.None of the projects listed have been fully funded. 1 School Capacity:Orange County NC Schools Adequate Public Facilities Ordinance(SAPFO).Annual membership count November 15,2019.Level of Service(LOS)means the amount(level)of students that can be accommodated(serviced)at certain school system grade group. i.e.,Elementary level (K-5),Middle Level(6-8),High School Level(9-12)]Standards for LOS:Elementary 105%,Middle 107%,High School 110%.Source:Orange County NC SAPFO Annual Report. Class size reduction phase-in based on House Bill 90(SL 2017).Allotment and average class size in grades K-3 shall be at the following ratios for 2021-2022:Kindergarten(1:18), 1st Grade(1:16),2nd&3rd Grade(1:17). 2Capacity Impact:YIN(number indicates number of potential seats gained or lost.) Priority Ranking Key staff and to sustain the overall operation of the facility.General maintaince and system service life upgrades.(state building code violations,health department violations,handicapped accessibility issues,removal of hazardous material,security issues not Option 1 being met by current systems) p ion 2 Repair and renovation of long-range items that also bring the class sizesquare footage of elementary classrooms to 1,200 sf p Ion Repair and long-range improvements that extend a minimum of twenty-five years of additional operation to a facility and meet REVISED DATE:1/8/2022 32 ORANGE MIDDLE SCHOOL School Capacity' Major capital Projects Requiring Additional Funding SAPFO CAPACITY; 726 MEMBERSHIP COUNT. 642 AGE OF SCHOOUBUILDINGS 1968 PROJECT PRIORITY&CATEGORY ESTIMATED RANGE OF COST! CAPACITY IMPACT 2 :Option SAFETY LOW HIGH I IMPLEMENT SECURITY RECOMMENDATIONS $162,102 $184,827 N Subtotal $162,102 $184,827 0 Option NEW CONSTRUCTION&BUILDING ADDITIONS LOW HIGH Subtotal $0 $0 0 MAJOR SYSTEMS RECOMMENDED FOR REPLACEMENT WITH<10 Option LOW HIGH .YEARS OF USABLE LIFE 1 NEW BOILER $242,396 $302,994 N 1 :NEW CHILLER $393,893 $454,492 N 1 :REPLACE ALL AIR HANDLERS $1,060,481 $1,151,379 N Subtotal $1,696,769 $1,908,865 1 0 Option :MAJOR BUILDING IMPROVEMENTS LOW HIGH I REPLACE CANOPIES CAMPUS-WIDE $1,724,039 $1,896,745 N I :FOOD SERVICE RENOVATIONS $268,908 $309,736 N :INTERIOR RENOVATIONS: UPGRADE SCIENCE CLASSROOMS TO $325,719 $356,019 N :DPI STANDARDS I :LIGHTING: ENERGY EFFICIENT LIGHTING UPGRADE $655,066 $859,542 N :NEW EMERGENCY GENERATOR LIGHTING $270,354 $450,318 IN Subtotal $3,244,086 $3,872,360 0 Grand Total(2024 Costs w/increased capacity). $5,102,957 $5,966,052 0 Number of Mobile units currently on site 0 Note:The above cost estimates include major projects that were identified in the 2073-2014 Schools Comprehensive Facilities Assessment as well as projects that have been identified since that study.None of the projects listed have been fully funded. I Owluul udlidully.Urallyu UUU111y Ivu oufluuls/iU&qudtU r-uola;rau/11II&S L.;1U111d11C;U(OMr-rU).MI/IlUdl III&MU&IS111IJ CUUM 1VUVU111k)&1 10, ZUIZ'.LUV&1-0T-- Service(LOS)means the amount(level)of students that can be accommodated(serviced)at certain school system grade group.[i.e.,Elementary level (K-5),Middle Level(6-8),High School Level(9-12)]Standards forLOS:Elementary 105%,Middle 107%,High School 110%.Source:Orange County NC SAPFO Annual Report. Class size reduction phase-in based on House Bill 90(SL 2017).Allotment and average class size in grades K-3 shall be at the Ifollowing ratios for 2021-2022:Kindergarten(1:18), 1st Grade(1:16),2nd&3rd Grade(1:17). 12Gapacity Impact:YIN(number indicates number of potential seats gained or lost.) Priority Ranking Key Repair,replacement or renovation ot items,components or systems that are important to the health and safety of the students and staff and to sustain the overall operation of the facility.General maintaince and system service life upgrades.(state building code violations,health department violations,handicapped accessibility issues,removal of hazardous material,security issues not Option I being met by current systems) Option 2 Repair and renovation of long-range items that also bring the class sizes uare footage of elementary classrooms to 1,200 sf p ion Repair and long-range improvements that extend a minimum of twenty-five years of additional operation to a facility and meet REVISED DATE:1/8/2022 33 PARTNERSHIP ACADEMY School Capacity' Major capital Projects Requiring Additional Funding SAPFO CAPACITY 40 MEMBERSHIP COUNT 34 AGE OF SCHOOL/BUILDINGS 2006 PROJECT PRIORITY&CATEGORY ESTIMATED RANGE OF COST CAPACITY IMPACT 2 Option SAFETY LOW HIGH I IMPLEMENT SECURITY RECOMMENDATIONS(CURRENT LOCATION):: $39,389.28 1 $48,479.12 1 N Subtotal $39,389.28 $48,479.12 0 Option NEW CONSTRUCTION&BUILDING ADDITIONS LOW HIGH I RELOCATION WELCOME CENTER WITH ADMIN AND CAFE ADDITION! $1,200,000.00 $2,500,000.00 Subtotal $1,200,000.00 1 $2,500,000.00 1 0 :MAJOR SYSTEMS RECOMMENDED FOR REPLACEMENT WITH<10 OptionLOW HIGH .YEARS OF USABLE LIFE 1 HVAC SYSTEM REPLACEMENTS(CURRENT LOCATION) $38,480.30 $45,449.17 N Subtotal $38,480.30 $45,449.17 0 Option :MAJOR BUILDING IMPROVEMENTS LOW HIGH .EXTERIOR DRAINAGE WORK(CURRENT 1 $45,449.17 $68,173.76 N LOCATION) I LIGHTING: EXTERIOR LIGHTING UPGRADE(CURRENT LOCATION) $4,847.91 $9,695.82 N Subtotal $50,297.08 i $77,869.58 1 0 Grand Total(2024 Costs w/increased capacity). $1,328,166.66 $2,671,797.86 1 0 Number of mobile units currently on site 0 Note:The above cost estimates include major projects that were identified in the 2013-2014 Schools Comprehensive Facilities Assessment as well as projects that have been identified since that study.None of the projects listed have been fully funded. 7 Scnool Capacity:urange County FIC Scoos equate Fulilic Faculties urainance Annual memijersnip count Novemijer 7b, 2079.Levei or Service(LOS)means the amount(level)of students that can be accommodated(serviced)at certain school system grade group.[i.e.,Elementary level (K-5),Middle Level(6-8),High School Level(9-12)]Standards for LOS:Elementary 105%,Middle 107%,High School 110%.Source:Orange County NC SAPFO Annual Report. Class size reduction phase-in based on House Bill 90(SL 2017).Allotment and average class size in grades K-3 shall be at the ifollowing ratios for 2021-2022:Kindergarten(1:18), 1st Grade(1:16),2nd&3rd Grade(1:17). 12capacity impact:YIN(number indicates number of potential seats gained or lost.) Priority Ranking Key Repair,replacement or renovation of items,components or systems that are important to the health and safety of the students and staff and to sustain the overall operation of the facility.General maintaince and system service life upgrades.(state building code violations,health department violations,handicapped accessibility issues,removal of hazardous material,security issues not Option I being met by current systems) [�Zp:tion 2 Repair and renovation of long-range items that also bring the class sizes uare footage of elementary classrooms to 1,200 sf Option J Repair and long-range improvements that extend a minimum of twenty-five years of additional operation to a facility and meet REVISED DATE:1/8/2022 34 PA TH WA YS ELEMENTARY SCHOOL School Capacity' Major capital Projects Requiring Additional Funding SAPFO CAPACITY 540 MEMBERSHIP COUNT. 381 AGE OF SCHOOL/BUILDINGS 2000 PROJECT PRIORITY&CATEGORY ESTIMATED RANGE OF COST! CAPACITY IMPACT 2 Option :SAFETY LOW HIGH 1 IMPLEMENT SECURITY RECOMMENDATIONS $100,000 $140,000 N Subtotal $100,000 $140,000 0 Option NEW CONSTRUCTION&BUILDING ADDITIONS LOW HIGH Subtotal $0 $0 0 IMAJOR SYSTEMS RECOMMENDED FOR REPLACEMENT WITH<10 Option LOW HIGH :YEARS OF USABLE LIFE 1 :NEW BOILER $242,396 $302,994 1 N 1 :NEW CHILLER $605,989 $757,486 1 N 1 :MECHANICAL HVAC EQUIPMENT $714,309 $1,054,421 N 1 ENERGY MANAGEMENT SYSTEM UPGRADE $323,000 $452,200 N Subtotal $1,885,694 i $2,567,101 i 0 Option ;MAJOR BUILDING IMPROVEMENTS LOW HIGH 1 FOOD SERVICE RENOVATIONS $7,120 $10,605 N 1 PARKING LOT EXPANSION $252,000 $310,000 N 1 NEW EMERGENCY GENERATOR LIGHTING $193,800 $323,000 N Subtotal $452,920 $643,604 0 Grand Total(2024 Costs w/increased capacity). $2,438,614 $3,350,705 0 Number of mobile units currently on site j 0 Note:The above cost estimates include major projects that were identified in the 2013-2014 Schools Comprehensive Facilities Assessment as well as projects that have been identified since that study.None of the projects listed have been fully funded. 1 School Capacity.,Orange County NG Schools Adequate Public Facilities Ordinance nnual membership count November 15,2019.Level oT— Service(LOS)means the amount(level)of students that can be accommodated(serviced)at certain school system grade group.[i.e.,Elementary level (K-5),Middle Level(6-8),High School Level(9-12)]Standards for LOS:Elementary 105%,Middle 107%,High School 110%.Source:Orange County NC SAPFO Annual Report. Class size reduction phase-in based on House Bill 90(SL 2017).Allotment and average class size in grades K-3 shall be at the 12Capacity Impact:YIN(number indicates number of potential seats gained or lost.) Priority Ranking Key Repa—ir,replacement or renovation of items,components or systems that are important to the health and safety of the students and staff and to sustain the overall operation of the facility.General maintaince and system service life upgrades.(state building code violations,health department violations,handicapped accessibility issues,removal of hazardous material,security issues not Option I being met by current systems) —70ption2 Repair and renovation of long-range items that also bring the class sizes uare footage of elementary classrooms to 1,200 sf p ion Repair and long-range improvements that extend a minimum of twenty-five years of additional operation to a facility and meet REVISED DATE:1/8/2022 River Park Elementary School School Capacity' 35 Major capital Projects Requiring Additional Funding SAPFO CAPACITY 502 MEMBERSHIP COUNT 601 AGE OF SCHOOL/BUILDINGS 1956 PROJECT PRIORITY&CATEGORY ESTIMATED RANGE OF COST. CAPACITY IMPACT 2 Option SAFETY LOW HIGH 1 IMPLEMENT SECURITY RECOMMENDATIONS $100,000 $140,000 N Subtotal $100,000 $140,000 0 Option NEW CONSTRUCTION&BUILDING ADDITIONS LOW HIGH 2 RENOVATE/EXPAND EXISTING 2-4 WING $4,999,409 $5,732,655 Y 2 1 DECONSTRUCT/EXPAND EXISTING 4-5 WING $6,665,878 $8,332,348 Y 3 :NEW CONNECTOR $587,052 $733,815 N 3 :RENOVATE EXISTING K-1 WING $2,670,139 $3,076,000 N 3 :RENOVATE EXISTING OFFICE SUITE $348,444 $401,407 IN Subtotal $15,270,921 $18,276,225 TBD ;MAJOR SYSTEMS RECOMMENDED FOR REPLACEMENT WITH<10 Option LOW HIGH .YEARS OF USABLE LIFE 1 NEW BOILER $242,396 $302,994 N ::HVAC MECHANICAL UPGRADES 1 $439,000 $939,000 I(CLASSROOM WINGS) 3 :ENERGY MANAGEMENT SYSTEM UPGRADE $375,474 $482,752 N Subtotal $1,056,869 i $1,724,746 0 Option MAJOR BUILDING IMPROVEMENTS LOW HIGH I LIGHTING: ENERGY EFFICIENT LIGHTING UPGRADE $370,326 $510,437 N 1 :NEW EMERGENCY GENERATOR LIGHTING $160,917 $268,196 N Subtotal i $531,243 i $778,632 150 Grand Tota13(2024 cost estimate):. $16,959,034 $20,919,604 TBD TBD Number of mobile 2 Note:The above cost estimates include major projects that were identified in the 2013-2014 Schools Comprehensive Facilities Assessment as well as projects that have been identified since that study.None of the projects listed have been fully funded. I School Capacity:Orange County NC Schools Adequate Public Facilities Ordinance(SAPFO).Annual membership count November 15,2019.Level of Service(LOS)means the amount(level)of students that can be accommodated(serviced)at certain school system grade group.[i.e.,Elementary level (K-5),Middle Level(6-8),High School Level(9-12)]Standards for LOS:Elementary 105%,Middle 107%,High School 110%.Source:Orange County NC SAPFO Annual Report. Class size reduction phase-in based on House Bill 90(SL 2017).Allotment and average class size in grades K-3 shall be at the following ratios for 2021-2022:Kindergarten(1:18), 1st Grade(1:16),2nd&3rd Grade(1:17). F2Capacity Impact:YIN(number indicates number of potential seats gained or lost.) 3Annual inflaitonary construction cost increased is calculated at 6% Priority Ranking Key Repair,replacement or renovation of items,components or systems that are important to the health and safety of the students and staff and to sustain the overall operation of the facility.General maintaince and system service life upgrades.(state building code violations,health department violations,handicapped accessibility issues,removal of hazardous material,security issues not Option 1 being met by current systems) Option 2 Repair and renovation of long-range items that also bring the class sizes uare footage of elementary classrooms to 1,200 sf Option 3 Repair and long-range improvements that extend a minimum of twenty-five years of additional operation to a facility and meet REVISED DATE:1/812022 36 HMEL HILL � ;Y ARRBORO Date Joint Taskforce Facilities Report Andre' Stewart and Eric Allen -N Aging Structures CHCCS has 9 structures that Our newer are 50 years or older. structures range between 10 and 30 Carrboro ES (1957) years old. Glenwood ES (195 Estes Hills ES (1958) McDougle MS Seawell ES (1969) McDougle ES Culbreth MS (1969) East CHHS Phillips MS (1962) Scroggs ES FP Graham ES (1963) ��' Smith MS Ephesus ES (1972) Rashkis ES Lincoln Center (1950) Carrboro HS Aging Infrastructure ADA Egress Issues Morris Grove ES Phoenix Academy Northside JNow d 2 . . . :O'• r SCHOOLS Campus Security Issues Lighting ITY Options for Structure Renovation or Replacem;%+_ Option One r Option Two Option 3 Repair, replacement or renovation Repair and renovation of long-range Repair and renovation of long-range of items, components or systems items that also bring the class size items that also bring the class size that are important to the health square footage of elementary square footage of elementary and safety of the students and classrooms to 1,200 sf and/or meet classrooms to 1,200 sf and/or meet staff and to sustain the overall future capacity needs and the future capacity needs and the operation of the facility. General Orange County School Building Orange County School Building maintenance and system service Standards of 585 students for Standards of 637 students for life upgrades. (state building code elementary schools. (OC standard at elementary schools. Utilize violations, health department 585 currently: New standard =517 sustainable approaches to extend violations, handicapped with class size changes) INTERIOR building life while reducing overall accessibility issues, removal of RENOVATIONS BUILDING maintenance and operation costs. hazardous material, security ADDITION AND SITE (DPI building size old standard= issues not being met by current IMPROVEMENT MECHANICAL 700 students/new standard with systems) SYSTEM UPGRADES MAJOR class size changes =637 students) BUILDING IMPROVEMENTS C-HMEL HILL- IWX11A %ISRI lll�\\�11���1►%/�\\\�1111� CIT�NOO 39 Estimated Renovation Cost Structures with O tion 1 & 3 Structures with Option 1 Option 1 (cost est. 2024) Option 1 (cost Option 3 (cost School Name cost range est. 2024) cost est. 2024) cost School Name range range Glenwood Elementary School $5 - $6.4 million Carrboro $12.3 - $15.7 $31.5 - $40.7 Frank Porter Graham Elementary School million million Elementary School $5 - $6.2 million Seawell Elementary School $6 - $7.5 million Estes Hills $34.9 - $45.1 Elementary School $5.2 - $6.9 million million Phillips Middle School $8.5 - $10.6 million Ephesus $35.6 - $44.4 Culbreth Middle School $10 - $12.9 million Elementary School $5.6 - $7.3 million million J Lincoln Center $44.5 - $46.9 million (-LAPEL HI - Ways in which other counties fund 40 Renovation/Reconstruction 41 ORANGE COUNTY BOARD OF COMMISSIONERS CHAPEL HILL-CARRBORO BOARD OF EDUCATION ORANGE COUNTY BOARD OF EDUCATION Capital Needs Work Group February 16, 2022 Meeting—8:30-10am Due to current public health concerns, the Capital Needs Work Group is conducting a Virtual Meeting on February 16, 2022. Members of the Group will be participating in the meeting remotely. 1. Welcome—Commissioner Jean Hamilton, Chair of Work Group 2. Review School Facilities Definitions (Orange County Finance staff) a. Capital Project b. Maintenance c. Deferred Maintenance d. Recurring Capital e. Operating Costs 3. Current (FY22-23) School Facilities Planning and Budgeting Process (OCS and CHCCS staff) a. Explain how facility needs are planned, and how they are submitted to the county in capital and operating budgets. b. Preview of 2022-23 Capital budgets that are currently under development. c. How are capital and maintenance projects prioritized? d. What needs are excluded from the capital budget request? e. For longer term planning, what if we had a CIP with details for 10 years? 4. Discussion and Next Steps 5. Next Meeting is Wednesday, March 16, 2022 Adjourn Capital Needs Work Group virtual meetings are open to the public to attend remotely. Should any member of the public wish to view this meeting, please click the following link to register: Capital Needs Workgroup Registration Link 42 After registering, you will receive a follow-up email which will allow you to access and view the meeting. If you have any comments or questions, would like to submit any written comments to the group, or would like an emailed copy of the entire agenda package for this meeting, please email Rebecca Crawford at rcrawford&oran_eg countync.gov before 3:00 pm on February 14, 2022 43 ORANGE COUNTY BOARD OF COMMISSIONERS CHAPEL HILL-CARRBORO BOARD OF EDUCATION ORANGE COUNTY BOARD OF EDUCATION Capital Needs Work Group February 16, 2022 Meeting—8:30-10am Due to current public health concerns, the Capital Needs Work Group is conducting a Virtual Meeting on February 16, 2022. Members of the Group will be participating in the meeting remotely. Panelist Attendees: Jean Hamilton, Bonnie Hauser, Andre' Stewart, Carrie Doyle, Dr. Nyah Hamlett, Eric Allen, Greg Wilder, Jonathan Scott, Patrick Abele, Rani Dasi, Renee Price, Rhonda Rath, Steve Arndt, Rebecca Crawford, Kirk Vaughn Public Attendee: Kari Hamel 1. Welcome—Commissioner Jean Hamilton, Chair of Work Group a. Jean asked if we needed to open the meeting with a motion but the group determined that wasn't necessary for a workgroup b. Jean reviewed the agenda and requested that the definition section last no longer than 20 minutes. c. Jean requested no introductions but that if you are presenting to share your name first for those viewing. d. Jean requested that you submit your slides from previous meetings to Rebecca to share with the group. 2. Review School Facilities Definitions (Orange County Finance staff) a. Capital Project b. Maintenance c. Deferred Maintenance d. Recurring Capital e. Operating Costs • Notes: Gary Donaldson shared that the Orange County Finance staff shared this presentation ahead of time for all to review and proceeded to define the items listed on the agenda through PowerPoint slides. • Gary clarified that some operating costs can be debt financed as approved by the Local Government Commission such as those related to architectural design, engineering, and project management related to capital expenditures 44 o LGC wants to prevent a change in scope such that we don't finance soft costs and then don't follow through with the related construction/capital project o Operating Cost Impacts are projected to understand the impact of capital projects to our operating budget ■ Ex: Southern Branch Library staff,utilities, etc. • Patrick shared that SAPFO frequently discusses how to fund future growth and renovations of schools • Bonnie requested that we review the Finance definitions from the school usage perspective o Are computers considered capital equipment? Gary shared that we have financed them in the past • Bonnie shared that she still has questions about deferred maintenance. District CFOs had no comments. Bonnie asked why are maintenance items deferred rather than being funded and pursued? Requested that we discuss further when we talk about specific priorities. • Jean commented that she wondered when we get caught-up? What are the actual costs to do everything and how do we do know the funding gap so we can catch up? • Jean asked about the definition of recurring capital vs capital asset—are they the same? o Gary clarified they are different and have different useful life ■ Recurring capital items that are debt financed always match the useful life of the assets with the bond principal amortization schedule. ■ The County delineates recurring capital items separate from longer term projects in its NC Local Government Commission application. ■ Ex: vertical building = capital asset but the furniture inside is recurring capital (shorter useful life) ■ The county would like to shift towards using more PAYGO funding for recurring capital rather than financing o Would like to have a better idea of school needs and then figure out how to finance • Bonnie asked if ongoing maintenance staff are considered operating or capital? o Gary shared they should be operating. If you hire a project manager for a specific capital project, that could be financed as a part of the construction cost o Bonnie shared that if we aren't making improvements that are needed, it will overinflate our operating budget causing more needs for handymen to fix ongoing 45 problems. Could that be a savings if we did the renovations in the capital budget? ■ Patrick responded that is an issue, especially when you're operating older buildings. More costly to keep older systems up and running. Harder to replace — have to bring other systems up to code at the same time. ■ Agrees with Gary that we should try to shift recurring capital off of debt financing so we have as much flexibility as possible about how to use those funds • The restrictions cause a burden on schools and parents, especially athletics for paint, grass seed, etc., which don't meet the definition for debt financing and have to be covered in school budgets ■ Eric shared that utility usage also contributes to higher operating costs — the longer you use a system, the more costly it is to run vs replace 3. Current(FY22-23) School Facilities Planning and Budgeting Process(OCS and CHCCS staff) a. Explain how facility needs are planned, and how they are submitted to the county in capital and operating budgets. i. OCS 1. Patrick shared there is no formal presentation but in the past planning is done through county CIP a. We are aligning to a new format for a 10 year plan so everyone looks at the same format and will be helpful for ongoing meetings with county staff and both systems b. Use reports to divide up categories and then analyze projects from there i. Roof systems, windows, etc. that impact operating costs (mechanical systems such as HVAC, boilers, chillers, fire alarm systems, etc.), sustainability projects, learning environments (need adequate furnishings, bathrooms, learning equipment) ii. Do assessments, then review available funding both from system and from county 46 ii. CHCCS 1. Andre' and Eric shared a PowerPoint presentation a. Partner with Mosley Architects for facility needs study i. Have 9 older buildings and continuously have to band aid systems ii. Eric echoed that failing older units are definitely an issue — there is a point where a system is costing more to fix than to replace 1. Andre' shared that is also true of roofing projects b. Preview of 2022-23 Capital budgets that are currently under development. i. CHCCS 1. Athletic field upgrades, abatement projects, building improvements, electrical/lighting and HVAC upgrades,roofing and pavement, security upgrades, technology upgrades ii. OCS 1. Completing HVAC renovation projects, Elfand Cheeks, River Park, Stanback, Grady Brown, Hillsborough (mechanical plus projects — upgrade classrooms and buildings when go in to replace HVAC such as flooring, lighting, ceiling tiles, bathrooms, etc. since they will be impacted by the mechanical system replacements) a. No swing space in OCS — renovations can't necessarily be completed over the summer any more (buildings are in use, not enough time) so have to bring in mobile units for swing space for students during times of renovations while school is in session c. How are capital and maintenance projects prioritized? i. CHCCS —Andre' 1. Use Facility Condition Assessment and FCI to determine the prioritization and order of projects to be taken on — structural safety and sustainability come first H. OCS - Patrick 1. Don't have a sustainability coordinator but will be looking into it 47 2. Would like to use FCI to prioritize and help with feasibility and planning d. What needs are excluded from the capital budget request? i. CHCCS —Andre' 1. New school construction, swing space needed during renovations not included in request ii. OCS -Patrick 1. School growth from west(Mebane)—difficult to project increases e. For longer term planning, what if we had a CIP with details for 10 years? i. CHCCS 1. Have shifted to 10 year framework and submitted request to county ii. Note from Orange County Manager and Finance: It is critical to have detail in years 6 through 10 of the 10 year CIP in order to best understand the implications on debt service and predict next bond issuance. 4. Discussion and Next Steps a. Jean: i. Example of template used for submitting CIP requests to county ii. If there were no funding limits what would that look like? 1. Patrick and Andre' shared that if funding wasn't a limit, would build new schools rather than renovate old schools (would still need swing space to house students while build and demolish older buildings) a. Eric shared that he would engage with Green Tract site to build a new elementary site, land next to Morris Grove for more swing space for Phillips Middle school to start renovate it, and start working on more renovations at other middle schools iii. Could we construct the"aspirational"CIP so we can talk about how could we make it work and look at the priorities countywide? 1. BOCC will hear the long term financial plan presentation and debt model this Thursday evening so this is good timing b. Bonnie: i. Loves the idea of an aspirational CIP. 48 ii. Would like to review the idea of standards. Are our useful life standards of buildings too long? How do we build schools cheaper like Eno River Academy and make that consistent across the school district? iii. Can we do maintenance across campuses? Is it currently done at the same time or should we do it that way for economies? c. Renee: Both school systems have told us previously what they need but the funding isn't there. Mandates coming from the state have been hard i. Schools and BOCC have had goals with the bonds, but then weather catastrophes and cost increases came up and we had to re-prioritize, The same with state mandated class sizes. 1. Definitely should look at needs but be prepared for things to derail that are unanticipated 2. How can we plan these together? Especially since the state won't give us our lottery money. d. Carrie: i. When we do delay replacing school buildings,we do lose ADM when kids go to charter schools and private schools and then lose funding e. Rani: i. It's important that we consider the elements of the plan and the funding elements. Renee is right that there are local funding limitations but maybe we can all advocate for more funding on the state level 1. State has a surplus of excess revenue receipts 2. Likes the idea of the aspirational plan to work towards while advocating for other funding from the state f. Renee: i. Do you still have your list of capital needs from the last bond? That might help as a starting point 1. Patrick: those are the mechanical projects that we're working on—larger parts are complete and additional funding from the county will be used against escalating costs from the pandemic a. The only project not funded,was the joint transportation facility. Everything else the district intended to fund will be funded with the bond$ 2. Eric: Have the 2013/2014 Facility Commission report—what could do/have to do/like to do a. Updated in 2018 and in the process now to update the last version 49 b. CHCCS will use that to create the aspirational list, especially for Lincoln Center and Transportation building (erosion problems) 3. Rani: a. Basic needs vs aspirational b. Walked through an older school yesterday and was very apparent how much better it would be to rebuild it vs renovating i. Still constrained by time and energy even if had money g. Bonnie i. Our building and construction standards are too outdated and don't match between the two districts 1. Eric asked if Bonnie was referring to joint design standards between both districts? Could draft them but would be up to boards to review and approve a. DPI standards vs Orange County building standards ii. It takes too long to get projects completed iii. Need to take weather conditions into account, too h. Jean—Next agenda: i. Discuss difference between OC standards and DPI design standards? 1. Implications on costs? ii. Joint bidding/shared contractors for projects across both districts 1. Implications on costs? iii. Outsourcing of maintenance for assets iv. Someone to present on best practices for construction, design, and maintenance standards i. Patrick i. Could they have longer than a month — lots of topics discussed ii. Eric said he could reach out to experts to come back and present about construction standards but would need longer than a month (the group agreed upon May as the target date for the subject matter expert to share information) 1. The group agreed this would be helpful j. Jean i. When could we get a spreadsheet with the"aspirational" CIP? To be kept in mind when making decisions about funding? 50 k. Bonnie — it's hard to imagine doing aspirational or the next round of bond funding before we have design standards 1. Rani isn't sure that it's going to change the scale of the needs and the first priorities may need to be to create the list and then break down how we confront each need i. The CHCCS needs assessment is underway and that will help determine needs. Will be completed in April and it may be June at the earliest before can put together the list. in. Jean—both districts may not want to have the same standards so we can't let that slow down the work that needs to be done i. Ok if we have to delay if we need the time to do it right and be prepared for the future n. Renee—reminded the group about SAPFO and the implications of Pre-K, which is not included in SAPFO numbers i. Providing universal Pre-K may need to be added and ask Planning staff to redo formula to anticipate that o. Carrie — agree with Renee, we really need to integrate Pre-K, was discussed pre-COVID i. At what time do we need to garner stakeholder input for this? ii. Jean responded that she see that coming from the boards —recommendations will go to the boards for their review then p. Bonnie — standards are important to her because they would change the urgency for replacing schools and accelerate renovations if we have a plan i. Not having standards is harming our efficiency and not working ii. Would like to see maintenance timelines standards that we should use q. Jean—Draft timeline i. March-talk about SAPFO—understand what is SAPFO, how it limits and impacts our decisions 1. Gary shared we could coordinate with Planning Office (Ashley Moncado) 2. How we move forward with funding advocacy ii. April—no meeting iii. May — plan to discuss standards and having a subject matter expert (Eric volunteered to contact a Subject Matter Expert) to share about industry standards, standards for design, efficiencies in contracting and maintenance iv. June/July—have aspirational CIP drafted for review 5. Next Meeting is Wednesday, March 16, 2022 51 Adjourn Capital Needs Work Group virtual meetings are open to the public to attend remotely. Should any member of the public wish to view this meeting, please click the following link to register: Capital Needs Work_rgroup Registration Link After registering, you will receive a follow-up email which will allow you to access and view the meeting. If you have any comments or questions, would like to submit any written comments to the group, or would like an emailed copy of the entire agenda package for this meeting, please email Rebecca Crawford at rcrawfordAoran eg countync.gov before 3:00 pm on February 14, 2022 52 GRANGE COUNTY NORTH CAROLINA School Capital Needs Work Group Terms and Definitions Prepared by Department of Finance February 16, 2022 53 Capital Asset and Capital Project Capital Asset - An item with a value exceeding $5,000 and a useful life of one year or greater; includes motor vehicles, furniture, fixtures and equipment. Capital Project - A project with an estimated cost exceeding $100,000 or more and useful life exceeding ten years or greater. Capital projects include the construction, purchase, or major renovation of buildings, parks, utility systems, or other structures and sites; and purchase of land and major landscaping projects. Source - Page 375 of the FY 21 -22 Commissioner Approved Budget — the preface to the CIP document. ORANGE COUNTY NORTH CAROLINA 54 Maintenance & Deferred Maintenance Maintenance — Regular repair to county and school assets, such as HVACs, Fire Alarm Systems, Roofs, and Electrical systems. To maintain and extend the useful lives of these assets. Deferred Maintenance — Supplemental Funding provided by the county to fund the backlog of school maintenance needs. In FY 2020-21 , the County funded $30 million over 3 years to the school systems to expedite the list of deferred maintenance projects. Extended to 4 years at school request. Source — School deferred maintenance projects are found on pages 462 and 479 of the FY 21 -22 Commissioner Approved Budget. Similar county maintenance projects can be found on page 389-391 for Facility Safety, 392-393 for HVACs, and 405-406 for Roofs. ORANGE COUNTY NORTH CAROLINA 55 Deferred Maintenance Deferred Maintenance Projects -CHCCS Project Category School Project Status: Active Project Type Functional ServlceArea; Education Proposed Bid Date: TBD New School System: CHCCS Starting Date: 711/2021 Expansion Completion Date: TBD Renovation X Project Number: 54022 Replacement X Project Description/Justification The FY 2020-21 CIP included a supplemental funding program for deferred maintenance and life/safety improvements. The program would involve a total of$30 million over the next three 13)years to expedite each School District's backlog of deferred maintenance projects. Based on the FY 2020-21 Average Daily Membership(ADM)percentage,CHCCS share will be$17,997,000 over the three(3)year period. The Supplemental Deferred Maintenance program described above would use debt financing to supplement an additional$3 million that is recommended to be funded using bond premiums that was earned when the County issued$85.4 million in General Obligation Bonds in FY 2017-18. The$3 million appropriation in FY2020- 21 will exhaust the bond premium earned in FY 2017-18. CHCCS share of this$3 million was$1,799,700 in FY2020-21. FINANCIAL SUMMARY Current Year 1 Year 2 Year 3 Year 4 Year 5 Five Year 5 Prior Years Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Year to Project Budget Funding 2020-21 2021.22 2022.23 2023-24 2024.25 2025-26 Total Year10 Appropriation Prolesslo>ralservices 1'3001000 constructlonlRe airs/Remwtions 1,804,21D0 2,299,701) 1o,n00,000 6,197,004 14,197,Dt10 49,207,493 Appropriation Total 1,804,21D0 3,599,704 10,000,000 6,197,004 16,197,000 49,207,493 Revenues/Funding Souree Debt Financing-School Improvements 11800,000 10,000,000 61197,000 16,197,000 49,207,493 From Capital Reserve Funds 1,804,200 1,799,70D Revenues/Funding Source Total 1,804,2W 3,599,70D 10,DDDAW 6,197,0W 16,197,000 49,207,493 A1111111111- ORANGE COUNTY NORTH CAROLINA 56 Deferred Maintenance Deferred Maintenance Projects - OCS Project Category School Project Status; Active Project Type Functional Service Area; Education Proposed Bid Date; T-RD New School System: ocs Starting Date: 7J112020 Expansion Completion Date: TSD Renovation x -Project Number: 51045 -Replacement X Project❑escriptionfJustification: The FY2020-21 CIP included a supplemental funding program for deferred maintenance and life/safety improvements. The program would involve a total of$30 million over the next three (3)year to expedite each School District's backlog of deferred maintenance projects. Based on the FY 2021-22 Average Daily Membership (ADM)percentage,OCS share will be$12,003,000 over the three (3)year period. The Supplemental Deferred Maintenance program described above would use debt financing to supplement an additional $3 million that is recommended to be funded using bond premiums that were earned when the County issued$8S.4 million in General Obligation Bonds in FY 2017-18, The$3 million appropriation in FY2020-21 will exhaust the bond premium earned in FY 2017-18. OCS share of this$3 million was $1,200,300 in FY2020-21. FINANCIAL SUMMARY Current Year 1 Year 2 Year 3 Year 4 Year 5 Five Year 6 Prior Years Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Year to Project Budget Funding 2ffi0-21 2021-22 2022-23 2023-24 2024-25 2025-26 Total Year10 Appropriation conftrudiwReppirsIftenovadans 1,195,800 5350,300 3,600,000 4,253,000 7,853,000 44,303,065 AppropriortJon TotGl 1,195,S00 5,350,200 3,600,000 4,253,000 7.853,000 44,303,065 RevenueslFund►nq Source Debt Financing-5chaor improvements 4,150,000 3,600,000 4,253,000 7,S53,000 44,303,065 From Ccr italReserve Funds 1,195,800 1,200,300 Revenues/Fun ding Source Total 1,195AW 5350300 1,600,000 4,253,000 7,853,000 44,303,065 ORANGE COUNTY NORTH CAROLINA 57 Recurring Capital Recurring Capital - Recurring capital outlay funding supports Category I (facility improvements), Category II (equipment and furnishings), and Category III (vehicles and bus purchases) expenditures. The equal per pupil allocations required by law for current expense appropriations are not applicable to this category of local school funding. However, Orange County splits $3 million between the school districts by current ADM. Source — Definition found on 332 of the FY 21 -22 Commissioner Approved Budget — the education section of the budget. Project pages found on 471 and 482. ORANGE COUNTY NORTH CAROLINA 58 RecurringCapital Recurring Capital Projects - CHCCS Project Category School Project Status: Active Project Type Functional Service Area; Education Proposed Bid Date: MD New School System: CHCCS Starting Date: 71112021 Expansion Completion Date: MD Renovation x Project Number. S4010 lReplacement x Project Description/Justification: To address recurring capital projects as identified by the school system each fiscal. The $1,810,800 each fiscal year represents CHCCS portion, based on the current ADM, of the $3,000,000 provided schools each year for recurring capital projects. The funding source for these annual projects used to be pay-as-you-go, but beginning in FY 2018-19, they changed to debt financing. Examples of FY 2021-22 projects include: furnishings and equipment at schools district-wide, drainage improvements, carpet/tile installation, roof repairs, and mechanical and plumbing repairs/renovations. FINANCIAL SUMMARY Current Year 1 Year 2 Year 3 Year 4 Year 5 Five Year 6 Prior Years Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Year to Pro ectBudget Funding 2020-21 2021-22 2022-23 2023.24 2024-25 2D25-26 Total Year 10 Appi*Dpriortion ConstructionfRe airsfRenovatians 1,626,100 1,799,7D0 1,810,800 1,910,300 1,810,80 1,910,800 1,810,800 9,054,000 9,as4,om _Appropriation Total 3,626,100 1,799,7D0 1,810,800 1,810,8011 1,810,80 1,810,800 1,810,800 9,054,000 9,as4,000 RetterluesJFunding Source Debt Firranon -School lm rovements 3,626,100 1,799,700 1,810,800 1,910,800 1,810,860 1,810,800 1,910,800 9,0P,000 9,054,400 RevenuesJFunding Source Total 3,626,100 1,799,700 1,810,800 1,910,800 1,810,800 1,810,800 1,810,8011) 9,054,000 9,054,400 r ORANGE COUNTY NORTH CAROLINA 59 RecurrinqCapital Recurring Capital Projects - QCS Project Category School Project Status: New Project Type Functional Service Area: Education Proposed BTd Date: MID New School System: oc5 Starting date: 7/1/2021 Expansion Completion Crate: TBD Renovation X ,Project Number: 51009 Replacement X Pf0jeLt aesLriptionflustifiLation: To address recurring capital projects as identified by the school system each fiscal. The $1,189,200 each fiscal year represents 005 portion, based on the current ADM,of the $3,000,000 provided schools each year for recurring capital projects. The funding source for these annual projects used to be pay-as-you-go, but beginning in FY 2018-19,they changed to debt financing. Examples of FY 2021-22 projects include: mobile units, HVAC replacements, roof repairs,new classroom set-up, computer equipment maintenance,and environmental maintenance. FINANCIAL SUMMARY Current Year 1 Year 2 Year 3 Year 4 Year 5 Five Year 6 Prior Years Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Year to PFojrct6udRet Funding 2020-21 2021.22 2022.23 2023 24 2024-2S 202S.26 Total Year10 dpproprio ti on Cons tructionfRe irsfRenouotions 2,373,900 1,200,300 111891200 11199,200 1,189,200 1,189,200 1,169,200 5,946,000 5,146,0o0 Appropriation Total ;,373,900 1,200,30ti 1,189,200 1,119,200 1,199,200 1,189,200 LIN,200 S,948,000 5,946,D00 Revenues/Funding Source Debt Financing-$chooffrn rovements 2,373,900 1,200,100 L,1$9,200 1,189,200 1,L89,200 L,1$9,200 1,1$9,200 5046,000 S,946,600 Revenues/Fun ding Source Total 2,373,900 1,200,100 L,189,200 1,189,200 1,189,200 1,189,200 1,189,200 5,946,000 5,946,om ORANGE COUNTY NORTH CAROLINA 60 Operating Cost Operating Cost — Per the NC Local Government Commission and U .S. Public Finance laws. A limited amount of operating costs tied to capital projects can be capitalized. These specific operating costs are generally restricted to architecture design, engineering and project management costs related to the capital expenditures being debt financed. The majority of County staff costs to manage the capital projects are funded with operating revenues. Education operating costs are provided by the County through the current expense appropriation. The current expense is funded through taxes and is the primary funding source for capital staff requirements. Source — The Education funding section of the FY 2021 -22 Commissioner Approved Budget begins at page 329. ORANGE COUNTY NORTH CAROLINA 61 Operating Cost Impact Operating Impact — The estimated impact of completing a project on the county's operating budget in upcoming years. Estimated operating impacts are included in the Long Term Financial Model to better anticipate upcoming budget costs. Source — Examples of operating impact in the FY 2021 -22 Commissioner Approved budget: Page 399 — The cost to staff and operate the Orange County Southern Branch Library. Page 412 — The annual subscription costs for IT software in the IT Governance Council Initiatives. Page 445 — the revenue generated by enclosing the field house for the Sportsplex. ORANGE COUNTY NORTH CAROLINA 62 County Example : Operating Cost Impact — Southern Branch Library FINANCIAL SUMMARY Current Year 1 Year 2 Year 3 Year4 Years Five Year 6 Prior Years Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Year to Project6udget Funding 2020.21 2021.22 2022.23 2023.24 2024-25 Z025.26 Total YearlO Appropriation PrafessionniSerWces 1,172,500 400,000 414,"3 414,993 C0r>'strUCtlon/Rep0k'$1RenMa00ns Poirking Consrrucrfon 1,fl00,000 950,000 2,125,335 2,125,335 corlsrructfon W/conringency 4,625,000 5,339,052 5,339r052 EquipmerptlFurnishinp 802,22S 802,225 Appropriation Total 6,797 LLW5 0Q 8,681,605 9.681.605 RevenuesJFundinff Source Debt Financing 6,533,500 1,350.M 803,606 8,68l,ws Available Project Balances 264,000 RevenuesJFunding Source Total 6,797,500 1,350,000 8,681,60S 9,691,605 Impact on Operating Budget Personnel 385,668 385,668 385,669 185,669 1.542.672 1,928,340 Operations 152,000 152,004 152,000 152,000 608.000 760,ODD impact on Operating Budget Total 537,668 537,668 537,668 537,668 2,150,G72 2.688,3C0 ORANGE COUNTY NORTH CAROLINA 63 QUESTIONS I-.-�-00-�- ORANGE COUNTY NORTH CAROLINA 164 HMEL HILL � ;Y ARRBORO Date CHCCS CIP for the Facilities Work Group February 16, 2022 Presented by: Andre' Stewart and Eric Allen -N Question One 65 Explain how facility needs Our process begins as a are planned , and how part of the budget they are submitted to the process in conjunction county in capital and with principal and operating budgets. operational department considerations. We analyze the facilities assessments and index to prioritize projects. Question Two 66 Preview of 2022-23 Capital budgets that are Athletic field upgrades at CHS currently under Abatement Projects development. Building Improvements • Electrical, lighting and HVAC upgrades • Roofing and pavement • Security upgrades • Technology upgrades Question Three 67 How are capital and After collaborating with maintenance projects our outside partners, the prioritized ? prioritization is made by the Facility Condition Assessment and FCI (facilities condition index) on the order of projects. Structural safety and sustainability are taken into account. Question Four 68 What needs are excluded New school construction from the capital budget request? Question Five 69 For longer term planning, Our plan has been what if we had a CIP with developed on the ten details for 10 years? year cycle. 70 ORANGE COUNTY BOARD OF COMMISSIONERS CHAPEL HILL-CARRBORO BOARD OF EDUCATION ORANGE COUNTY BOARD OF EDUCATION Capital Needs Work Group March 16, 2022 Meeting—8:30-10am Due to current public health concerns, the Capital Needs Work Group is conducting a Virtual Meeting on March 16, 2022. Members of the Group will be participating in the meeting remotely. 1. Welcome—Commissioner Jean Hamilton, Chair of Work Group 2. Orange County Schools Adequate Public Facilities Ordinance (SAPFO) Discussion—Craig Benedict, Orange County Planning and Inspections a. Delayed — Please send Rebecca any questions you have about SAPFO 3. School Funding Advocacy 4. Discussion and Next Steps 5. Next Meeting is Wednesday, May 18, 2022 Adjourn Capital Needs Work Group virtual meetings are open to the public to attend remotely. Should any member of the public wish to view this meeting, please click the following link to register: Capital Needs Workgroup Registration Link After registering, you will receive a follow-up email which will allow you to access and view the meeting. If you have any comments or questions, would like to submit any written comments to the group, or would like an emailed copy of the entire agenda package for this meeting, please email Rebecca Crawford at rcrawford&oran e�2c.gov before 3:00 pm on March 14, 2022 71 Mar 16, 2022 1 Capital Needs Work Group Attendees: OC: Renee Price, Jean Hamilton, Gary Donaldson, Rebecca Crawford, Kirk Vaughn, Alan Dorman, and Greg Wilder OCS: Carrie Doyle, Bonnie Hauser, Dr. Monique Felder, Rhonda Rath, Catherine Mau, and Nick Mincey CHCCS: Rani Dasi, Jilllian Laserna, Dr. Nyah Hamlett, Eric Allen, Andre Stewart, and Jonathan Scott Notes: 1. Welcome —Commissioner Jean Hamilton, Chair of Work Group 2. Orange County Schools Adequate Public Facilities Ordinance (SAPFO) Discussion — Craig Benedict, Orange County Planning and Inspections Skipped due to County staff scheduling conflict. 3. School Funding Advocacy Rani Dasi suggested a collaboration in advocacy between the County and School Districts with the State. Engaging the community in the form of a campaign. Engaging State organizations. Lobby the State for lottery funds and an additional State bond. Bonnie Hauser asked if the County raised taxes could they be earmarked for the schools capital needs exclusively? Schools need a recurring revenue stream for capital needs. What is happening with the light rail funds? Gary Donaldson advised they are for public transportation and administered by Go Triangle. Rani Dasi asked Gary Donaldson about the timing of the next school bond. Opportunity for $120 million in fiscal year 2027. There is another opportunity for limited obligation bonds prior to ($30 million 2024) Rene Price advised the County does not earmark funds on tax rate increases. Jean Hamilton suggested the possibility of increasing the Article 46 Sales Tax Revenue percentage to school districts. 72 Jean Hamilton asked about the status of the original$30 million limited obligation bonds. Covid Issues, supply chain, lack of central services, contractors would not bid on equipment replacement for materials they could not access. Dr. Hamlett asked for clarification on deferred maintenance vs. larger renovation projects. Bonnie Hauser suggested the need for a model or set of standards to dictate renovation timelines. 4. Discussion and Next Steps May meeting 18th: Presentation on building standards, June, when to reschedule the (SAPFO), IT allocations, What is the expectation of the Task Force's work? (Report to the Boards, Plan of Action— discuss at July meeting) 5. Next Meeting is Wednesday, May 18, 2022 73 Active Chapel Hill Carrboro City Schools Capital Projects as of 3110/22 Note:()=negative available balance Actual Available Project#and Name Expenditure Expenditures Balance Percent Budget 3/10/22 3/10/22 (including prior Complete year carry overs) 53001 -CHAPEL HILL HIGH SCHOOL $72,295,024.00 $73,562,288.10 ($1,267,264.10) 101.75% 53003-CHHS-MAJOR RENOVATIONS $598,478.00 $598,477.65 $0.35 100.00% 53018-TRANSPORTATION CENTER $300,508.00 $300,508.18 ($0.18) 100.00% 53019-CARRBORO HIGH SCHOOL $75,000.00 $75,000.15 ($0.15) 100.00% 53023-DOORS,HARWARE,CANOPIES $678,000.00 $493,963.27 $184,036.73 72.86% 53025-CLASSROOM/ACADEMIC IMPROVEMENTS $3,953,227.00 $3,342,122.81 $611,104.19 84.54% 53026-ELECTRICAL SYSTEMS $1,683,852.00 $1,331,398.73 $352,453.27 79.07% 53027-WINDOW REPLACEMENTS $508,691.00 $417,647.10 $91,043.90 82.10% 53040-LINCOLN CENTER CONVERSION $760,868.00 $796,868.19 ($36,000.19) 104.73% 53050-MORRIS GROVE ELEMENTARY $38,911.00 $38,911.36 ($0.36) 100.00% 53051 -NORTHSIDE ELEMENTARY $23,108,762.00 $23,119,562.29 ($10,800.29) 100.05% 53052-CARRBORO HIGH ARTS WING $4,048,028.00 $4,048,027.33 $0.67 100.00% 54000-ADAREQUIREMENTS $515,616.00 $248,765.43 $266,850.57 48.25% 54001 -ABATEMENT PROJECTS $1,390,080.00 $1,037,211.48 $352,868.52 74.62% 54002-ATH FACILITIES/PLAYGROUNDS $2,424,053.00 $1,888,297.44 $535,755.56 77.90% 54003-ENERGY EFFICIENCY RENOVS $1,125,088.00 $399,322.55 $725,765.45 35.49% 54004-FIRE/SAFETY/SECURITY $1,961,053.00 $1,869,307.73 $91,745.27 95.32% 54005-INDOOR AIR QUALITY $881,340.00 $775,246.16 $106,093.84 87.96% 54006-MECHANICAL SYSTEMS $4,879,359.00 $4,073,517.91 $805,841.09 83.48% 54007-MOBILE CLASSROOMS $883,696.00 $846,616.22 $37,079.78 95.80% 54008-PARKING LOT IMPROVEMENTS $980,000.00 $848,318.69 $131,681.31 86.56% 54009-PLANNING FOR FUTURE PROJECTS $1,200,000.00 $1,145,550.80 $54,449.20 95.46% 54010-RECURRING CAPITAL $7,236,600.00 $6,633,000.00 $603,600.00 91.66% 54012-ROOFING PROJECTS $6,709,001.00 $6,303,268.92 $405,732.08 93.95% 54013-TECHNOLOGY $17,935,839.00 $17,341,512.95 $594,326.05 96.69% 54017-BATHROOM RENOVATIONS $193,406.00 $193,406.00 $0.00 100.00% 54018-CULBRETH SCIENCE WING $4,971,676.00 $4,971,676.00 $0.00 100.00% 54019-RENTAL SPACE $840,000.00 $688,251.12 $151,748.88 81.93% 54020-STORMWATER MANAGEMENT $250,000.00 $160,555.85 $89,444.15 64.22% 54021 -SUSTAINABILITY INVESTMENT $250,000.00 $177,126.29 $72,873.71 70.85% 54022-DEFERRED MAINTENANCE* $6,369,224.00 $2,822,888.32 $3,546,335.68 44.32% Total $169,045,380.00 $160,548,615.02 $8,496,764.98 94.97% *Only includes funding approved for FY 20-21 and FY 21-22 of the supplemental deferred maintenance plus a prior year balance from previously Article 46 Sales Tax Projects Available Project#and Name Expenditure Expenditures Balance Percent Budget 3/10/22 3/10/22 (including prior Complete year carry overs) 53025-CLASSROOM/ACADEMIC IMPROVI 880000-CONSTRUCTION $ 380,000.00 $ 350,281.41 $ 29,718.59 92.18% 54006-MECHANICAL SYSTEMS 890000-EQUIPMENT $1,988,587.00 $1,614,135.80 $374,451.20 81.17% 54012-ROOFING PROJECTS 882000-ROOFING $135,966.00 $0.00 $135,966.00 0.00% 54013-TECHNOLOGY 897100-TECHNOLOGY $6,121,418.00 $6,097,400.56 $24,017.44 99.61% 54016-RENOVATIONS&SITE IMPROVEM 892000-GENERAL RENOVATIONS $2,020,922.00 $2,029,562.51 ($8,640.51) 100.43% 54021 -SUSTAINABILITY INVESTMENT 892021 -ENERGY MANAGEMENT $90,000.00 $0.00 $90,000.00 0.00% Total $10,736,893.00 $10,091,380.28 $645,512.72 93.99% 74 Active Orange County Schools Capital Projects as of 3/10/22 Note:()=negative available balance Expenditure Expenditures Available Balance Percent Project#and Name Budget 3/10/22 3/10/22 (including prior year Complete carry overs) 50000-A.L.STANBACK MIDDLE SCHOOL $5,795.00 $5,794.25 $0.75 99.99% 50001 -CAMERON PARK ELEMENTARY $525,468.00 $524,921.82 $546.18 99.90% 50003-EFLAND CHEEKS ELEMENTARY $448,423.00 $443,646.69 $4,776.31 98.93% 50004-GRADY BROWN ELEMENTARY $54,023.00 $54,022.65 $0.35 100.00% 50005-HILLSBOROUGH ELEMENTARY $362,899.00 $320,300.53 $42,598.47 88.26% 50006-ORANGE HIGH SCHOOL $558,481.00 $558,481.22 ($0.22) 100.00% 50008-STANFORD MIDDLE SCHOOL $686,939.00 $686,938.00 $1.00 100.00% 50009-ALTERNATIVE SCHOOL $361,653.00 $307,043.61 $54,609.39 84.90% 50010-NEW HOPE ELEMENTARY RENOVATIONS $264,917.00 $264,917.01 ($0.01) 100.00% 50011 -ELEMENTARY#8 $300,000.00 $0.00 $300,000.00 0.00% 51002-ELECTRIC SERVICE UPGRADES $83,000.00 $0.00 $83,000.00 0.00% 51005-HANDICAP ACCESSIBILITY $483,300.00 $168,234.02 $315,065.98 34.81% 51007-PLANNING FOR FUTURE PROJECTS $778,000.00 $744,269.60 $33,730.40 95.66% 51009-RECURRING CAPITAL $4,763,400.00 $4,367,000.00 $396,400.00 91.68% 51010-ROOFING PROJECTS $6,913,130.00 $4,678,217.05 $2,234,912.95 67.67% 51011 -TECHNOLOGY PLAN $4,619,893.00 $3,476,226.17 $1,143,666.83 75.24% 51013-HVAC UPGRADE/IMPROVEMENTS $1,614,361.00 $1,533,484.60 $80,876.40 94.99% 51016-CENTRAL ELEMENTARY AIR $118,584.00 $111,439.11 $7,144.89 93.97% 51019-INDOOR AIR QUALITY $4,807.00 $4,806.33 $0.67 99.99% 51021 -DISTRICT WIDE IMPROVEMENTS $247,487.00 $234,781.97 $12,705.03 94.87% 51022-ORANGE HIGH TRACK REPAIRS $495,634.00 $495,633.97 $0.03 100.00% 51023-BATHROOM RENOVATIONS $105,314.00 $105,313.05 $0.95 100.00% 51024-FIRE/SAFETY UPGRADES $1,224,918.00 $379,500.53 $845,417.47 30.98% 51025-CLASSROOM/BUIILDING IMPROVEMENTS $6,800,521.00 $3,860,419.61 $2,940,101.39 56.77% 51026-WINDOW REPLACEMENTS $575,348.00 $305,656.70 $269,691.30 53.13% 51027-ATHLETIC FACILITIES $1,089,931.00 $561,780.64 $528,150.36 51.54% 51028-ENERGY EFF/LIGHTING IMPROVEMENTS $259,918.00 $246,382.27 $13,535.73 94.79% 51029-MECHANICAL SYSTEMS $1,347,013.00 $348,934.28 $998,078.72 25.90% 51030-PAVING/PARKING LOT IMPROVEMENTS $818,000.00 $256,810.15 $561,189.85 31.39% 51031 -CEDAR RIDGE AUXILIARY GYM $2,846,949.00 $2,846,948.95 $0.05 100.00% 51032-VEHICLE REPLACEMENTS $255,000.00 $267,441.76 ($12,441.76) 104.88% 51033-FOOD SERVICES $1,047,704.00 $450,211.00 $597,493.00 42.97% 51034-SCHOOL SAFETY/SECURITY $2,075,602.00 $908,815.55 $1,166,786.45 43.79% 51035-PROPERTY ACQUISITION $3,100,000.00 $3,104,352.78 ($4,352.78) 100.14% 51036-ROOFING PROJECTS-2016 BONDS $4,363,579.00 $1,876,868.33 $2,486,710.67 43.01% 51038-MECHANICAL SYSTEMS-2016 BONDS $22,909,574.00 $11,783,759.08 $11,125,814.92 51.44% 51039-SCHOOL SAFETY/SECURITY-2016 BONDS $2,500,000.00 $1,508,192.34 $991,807.66 60.33% 51040-CEDAR RIDGE AGRICULTURE ADDITION $481,801.00 $45,904.58 $435,896.42 9.53% 51041 -CRHS CLASSROOM ADDITION-2016 BONDS $14,500,000.00 $13,419,916.56 $1,080,083.44 92.55% 51042-CLASSROOM/BLD IMPROV-2016 BONDS $1,284,250.00 $882,094.06 $402,155.94 68.69% 51045-DEFERRED MAINTENANCE* $10,712,699.00 $1,067,210.79 $9,645,488.21 9.96% Total $101,988,315.00 $63,206,671.61 $38,781,643.39 61.97% *Only includes funding approved for FY 20-21 and FY 21-22 of the supplemental deferred maintenance plus a prior year balance from Article 46 Sales Tax Projects 75 Expenditure Expenditures Available Balance Percent Project#and Name Budget 3/10/22 3/10122 (including prior year Complete carry overs) 51011 -TECHNOLOGY PLAN 897100-TECHNOLOGY $6,975,510.00 $5,996,115.68 $979,394.32 85.96% Total $6,975,510.00 $5,996,115.68 $979,394.32 85.96% 76 $30M Schools Deferred Maintenance Update Bonds Bonds %Split by ADM District Bonds Issued Authorized but Authorized (FY 2020-21) Un-Issued OCS 12,003,000 0 12,003,000 41.10% CHCCS 1 17,997,0001 631,7401 17,365,2601 58.90% Total 1 30,000,0001 631,7401 29,368,2601 100.00% BOCC Authorized $30M to both school systems on an ADM basis in FY 20-21. Bonds issued to date: $0 for OCS and $631,740 for CHCCS. Timing of Original Funding Tranches: District FY 2020-21 FY 2021-22 FY 2022-23 Total OCS 4,150,000 3,600,000 4,253,000 12,003,000 CHCCS* 1,800,000 10,000,000 6,197,000 17,997,000 Total 5,950,000 13,600,000 10,450,000 30,000,000 *Requested to delay Year 2 and Year 3 Tranches for 1 year due to pandemic K-12 Supplemental Deferred FY 2020-21 FY 2021-22 FY 2022-23 FY 2023-24 Total Maintenance Funding Initial Allocation $ 5,950,000 $ 3,600,000 $ 14,253,000 $ 6,197,000 $ 30,000,000 Proposed Additional Allocation $ 3,000,000 $ 27,000,000 $ 30,000,000 Total 1 $ 5,950,000 1 $ 3,600,000 $ 17,253,000 1 $ 33,197,000 $ 60,000,000 77 ORANGE COUNTY BOARD OF COMMISSIONERS CHAPEL HILL-CARRBORO BOARD OF EDUCATION ORANGE COUNTY BOARD OF EDUCATION Capital Needs Work Group May 18, 2022 Meeting—8:30-10am Due to current public health concerns, the Capital Needs Work Group is conducting a Virtual Meeting on May 18, 2022. Members of the Group will be participating in the meeting remotely. 1. Welcome—Commissioner Jean Hamilton, Chair of Work Group 2. Best Practices in School Building Standards 3. Discussion and Next Steps 4. Next Meeting is Wednesday, June 15, 2022 Adjourn Capital Needs Work Group virtual meetings are open to the public to attend remotely. Should any member of the public wish to view this meeting, please click the following link to register: Capital Needs Work_rgroup Registration Link After registering, you will receive a follow-up email which will allow you to access and view the meeting. If you have any comments or questions, would like to submit any written comments to the group, or would like an emailed copy of the entire agenda package for this meeting, please email Rebecca Crawford at rcrawfordAoran eg countync.gov before 3:00 pm on May 16, 2022 78 ORANGE COUNTY BOARD OF COMMISSIONERS CHAPEL HILL-CARRBORO BOARD OF EDUCATION ORANGE COUNTY BOARD OF EDUCATION Capital Needs Work Group May 18, 2022 Meeting—8:30-10am Due to current public health concerns, the Capital Needs Work Group is conducting a Virtual Meeting on May 18, 2022. Members of the Group will be participating in the meeting remotely. 1. Welcome—Commissioner Jean Hamilton, Chair of Work Group a. Steve Arndt, Bonnie Hauser, Greg Wilder, Jean Hamilton, Kirk Vaughn, Patrick Abele, Carrie Doyle, Gary Donaldson, Rani Dasi, Jonathan Scott, Rebecca Crawford, Eric Allen, Thomas Hughes, Nyah Hamlett, Andre Stewart, Renee Price, Jillian La Serna 2. Best Practices in School Building Standards (45 minutes) — Thomas Hughes - sfl@a principle architect a. Tom shared there are lots of state funding sources for school capital right now: i. ESSER, lottery, needs based school funding b. Subheadings i. Education 1. Sfl&A a. Strong schools create vibrant communities which create sustainable futures 2. Technology is an important advancement in schools a. Distance learning, etc. b. Computers are a mainstay in education now c. The jobs of architects are to put all of the pieces together (furniture is especially important — kids learn better when they move around and not just sitting at a desk) 3. Student-Centered collaborative learning environments, natural materials and controlled daylighting, environmental awareness and stewardship, sustainable approach to learning for future generations 79 ii. Environment 1. Natural light (absolute key to a creative environment) 2. Learning commons 3. Visual transparency (see what's going on in the world around you) 4. Controlled access 5. Appealing interior finishes 6. Flexible space for collaboration 7. Mechanical 8. Technology — wireless handware (including locks), cameras, lighting controls, etc. 9. Spaces are designed in advance for expansion when necessary 10. Horry County a. Used a lot of pre-manufactured mechanical systems assembled offsite — construction time is minimized as a result b. Net-positive energy (geothermal and solar panels) c. This is the future of school design d. 1,100 students in this middle school e. Sfl&a operates the schools for first 5 years to make sure work to design-build standards iii. Process l. Have had to tear down a lot of buildings built in the `80's that aren't sustainable but also have worked on a lot of really well built schools 2. Need to invest and build sustainable facilities 3. $ not used on facilities can be put back on education 4. The #1 cost savings is on energy efficiency (air- tight, operationally sensitive to the environment they're in) 5. Doing 3 dimensional modeling now when building schools — coordination at every step (REVIT system) 6. Concrete based, spray foam insulation, brick/metal panel veneer — proven construction technology 7. Solar panels are really expensive but key for the payback(8-12 years) for energy efficiency 8. Daylighting reduces need for artificial lighting and saves costs 80 9. Sharing tech of the building with students so they understand 10. All LED lighting, need for specific color, 11. Have to have bottle fillers (kids are demanding them) 12. Doing less LEED certified focus since much of that technology is now standard in school design/build iv. Construct 1. Seeing a lot more construction manager at risk (larger districts with multiple projects) 2. Eliminating energy costs over 20 years and can put the savings back into the construction of the building a. Tom can provide this comparative data 3. Procore is the project management system of the day a. Web based, can schedule, document and photo management, communications, quality control access, monthly drone flights to record progress—really helpful for documentation and avoids conflict 4. Supply chain issues a. 56-58 weeks to order a generator b. Steel vs concrete plank because couldn't find steel (or gluelam) c. Have to do lots of work ahead of time to understand availability of workforce and materials for the project d. Be sensitive to having to push schedules out because the supply chain is so limited (pushes costs out and general conditions) e. Have to be able to adapt to the new construction environment (not the same as it was 5 years ago and have to be really flexible) v. Community 1. Design looks to match the pedagogy of the clients/residents of community (both exterior and interior) c. Questions: i. Renee Price: Concern about safety in schools — some of the slides show how open the campuses are — what do you do about safety? 81 1. Law enforcement typically prefer wide open areas to be able to see everything going on outside and inside 2. Work with them on hard entrances/exits (LE can get there within 5-6 minutes) 3. Lots of cameras— school administrators and law enforcement can see cameras at any time ii. Renee Price: Schools look to be large with multiple levels — how are the fire exits integrated to quickly get large numbers of people out of the building 1. Tom—line of sight is integrated with purposeful of intersections (avoid hidden corners) 2. Can close off sections for fire and can control access in an emergency 3. Exits are all within 250 feet (part of code) but do try to limit exterior exits (all controlled by remote access systems) iii. Bonnie Hauser: Do kids do better academically in these facilities? 1. Tom — they are polling to understand that (especially around performance with more collaborative spaces) 2. Eric — kids treat buildings differently — when they're new and nice they treat them better and stop each other from mistreating it iv. Bonnie Hauser: have about 30 schools between the 2 districts and most are obsolete — how do you build so that these new schools will last 100 years? 1. Tom - Design is key — have to be built to be flexible (can be easily renovated or reconstructed) a. Concrete base - have to be able to withstand hurricanes (natural environment and the wear and tear schools get) b. Terrazzo floors almost exclusively are added to the schools c. Floors are ground and don't have to be waxed and stripped d. Use carpet tiles so only have to replace the tile, not the whole room e. 100 years may be overstating but 50-60 years is reasonable v. Jean Hamilton: how do these compare to the DPI standards and what is required in a school? 82 1. Tom — work closely with DPI — they require classroom sizes and the building"program" a. DPI tends to be more appreciative of the designs rather than discerning b. More of a dialogue than a review (use DPI as a resource rather than a management structure) c. Department of Insurance does all of the code review d. DPI standards are a minimum but don't capture new design standards vi. Jean Hamilton: cost — pre pandemic what would be the cost per square footage compared to now 1. Tom - Inflation is driving the market right now. No such thing as a credit a. Have seen an upwards trend in cost b. Used to be upper $300's per sq foot, now closer to $500's c. Seeing some decrease now (steel almost doubled a few months ago — had to look at alternative products) d. Thinks will stabilize — chip shortage is still out there e. Just bidded out a project and it came in under budget — may be a litmus test for the market 3. Discussion and Next Steps a. Is SAPFO still possible for June? i. Rebecca will work with Planning team to see if can get a combination of staff to present b. Is technology still an area of interest for the group? c. What should we be planning for maintenance of buildings? Should we have a guideline for cost per square foot that is shared between districts? i. Next Meeting — discussion of a design standard policy for both districts? ii. Patrick Abele — could we focus on one or 2 systems such as mechanical systems or roof design 1. New school construction is completely different from renovating older facilities (harder to standardize) iii. Steve Arndt — spent a lot of time in higher ed facilities management 1. It's important to understand that we should take the operating costs into account when build new 83 buildings—lots of info about there about how to standardize—don't have to start from scratch a. Steve will provide info iv. Eric Allen- if we have design standard guidelines could use them for bidding (and life cycle management guidelines) 1. This group could construct along with consultants 4. Next Meeting is Wednesday, June 15, 2022 a. SAPFO 5. Meeting after that a. Design Standard Policy/Guidelines for both Districts Discussion Adjourn Capital Needs Work Group virtual meetings are open to the public to attend remotely. Should any member of the public wish to view this meeting, please click the following link to register: Capital Needs Workgroup Registration Link After registering, you will receive a follow-up email which will allow you to access and view the meeting. If you have any comments or questions, would like to submit any written comments to the group, or would like an emailed copy of the entire agenda package for this meeting, please email Rebecca Crawford at rcrawfordAoran eg countync.gov before 3:00 pm on May 16, 2022 84 EDUCATIONAL FACILITIES PLANNING AND DESIGN sfL+a ARCHITECTS Project Experience Northwest Harnett Elementary School,New Construction,Harnett County Schools Erwin Elementary School,New Construction,Harnett County Schools McDeed's Creek Elementary School,New Construction,Moore County Schools Aberdeen Elementary School,New Construction,Moore County Schools Southern Pines Elementary School,New Construction,Moore County Schools Harding HS Renovations/Additions,Charlotte Mecklenburg Schools South Mecklenburg HS Renovations/Additions,Charlotte Mecklenburg Schools Pinecrest HS and Union Pines HS gymnasium/cafeteria additions,Moore County Schools Westmoore ES Addition,Moore County Schools Johnsonville ES Phase I&Phase II Add/Reno,Harnett County Schools Highland/Overhills/Harnett Primary Additions,Harnett County Schools Highland Middle School,New Construction,Harnett County Schools Penderlea K-8 School,New Construction,Fender Public Schools Ahoskie Elementary School,New Construction,Hertford County Public Schools PRINCIPAL—IN—CHARGE West Rowan Elementary School,New Construction,Rowan-Salisbury School System Thomas W. Hughes, A I A, REFP, LEED AP Blair Elementary School,New Construction,New Hanover County Schools Turrentine Middle School,Walkway Renovation,Alamance-Burlington Schools Within the educational facilities planning and design Boone Trail Elementary School,New Construction,Harnett County Schools community,Tom is recognized for supporting a collaborative Poplar Springs ES,New Construction,Stokes County Schools and interactive approach to educational planning and design. Southeastern Middle school Addition/Renovation,Stokes County Schools His approach starts with your educational program,promotes Bleinheim Elementary/Middle School,New Construction,Marlboro County Schools an understanding of your vision and goals for curriculum and Dillon Auditorium/Admin Offices,New Construction,Dillon School District 4,SC instruction,and works with your communities as a whole to *Dillon Middle School,New Construction,Dillon School District 4,SC develop innovative and creative learning environments for Clio Elementary/Middle School Addition&Renovation,Marlboro County Schools,SC students and teachers.Tom has over 35 years of educational *Rocky Mount HS,New Construction,Nash-Rocky Mount School System facilities planning and design,specialized in K-12 facilities,and Southeastern Middle School Addition/Renovation,Stokes County Schools is a Recognized Educational Facilities Professional(REFP)as *Career&Technical Education Center,Alamance-Burlington School System accredited by the Association for Learning Environments(fomerly New Century International ES&Regional Public Library,Cumberland County Schools,NC CEFPI).AS a LEED AP,he is well-versed in the design of High Lakeview High School/Middle School Addition,Dillon School District4,SC Performance educational facilities and LEED certification. Tom Lakeview Elementary Addition/Renovation,Dillon School District 4,SC has provided leadership on over 100 school projects in his career Latta Early Childhood Center,New Construction,Dillon School District 3,SC and brings a unique perspective on the design of educational *Snipes Academy ofArts and Design,New Hanover County Schools environments for the 21St century learner. Wagram Classroom Addition/PE Classroom Addition,Scotland County Schools Clio Elementary/Middle School Addition&Renovation,Marlboro County Schools,SC Registered Architect - NC, SC Croatan HS Auditorium Addition,Carteret County Schools East Carteret HS Addition&Renovation,Carteret County Schools,NC PrOfe5510nd1 Affiliations Ft Awards: Knightdale ES Additions,Wake County Public School System American Institute of Architects Newport ES Addition&Renovations,Carteret County Schools Association for Learning Environments (A4LE) Fred A.Smith ES Addition&Renovations,New Hanover County Schools A41LE NC Chapter, Board Member/Past President White Oak ES Addition&Renovations,Carteret County Schools NCARB Certified With Other Firm Construction Specifications Institute (CSI) Highland ES,Alamance-Burlington School System Recognized Educational Facilities Professional (REFP) Nation Ford High School,Fort Mill School District,SC LEEDO Accredited Professional Northern ES,Guilford County Schools Chapel Hill-Carrboro High School Education India Hook Elementary School,Rock Hill,SC University of Richmond, Bachelor of Arts Whitesides ES,Charleston County schools,SC Syracuse University, Master of Architecture *WG Pearson ES,Durham Public School System *LEED Certified facility 333 FAYETTEVILLE STREET, SUITE 225, RALEIGH, NC (919) 573-6350 85 ORANGE COUNTY BOARD OF COMMISSIONERS CHAPEL HILL-CARRBORO BOARD OF EDUCATION ORANGE COUNTY BOARD OF EDUCATION Capital Needs Work Group June 15, 2022 Meeting—8:30-10am Due to current public health concerns, the Capital Needs Work Group is conducting a Virtual Meeting on June 15, 2022. Members of the Group will be participating in the meeting remotely. 1. Welcome—Commissioner Jean Hamilton, Chair of Work Group 2. Orange County Schools Adequate Public Facilities Ordinance (SAPFO) Discussion—Orange County Planning and Inspections 3. Discussion and Next Steps 4. Next Meeting is Wednesday, July 20, 2022 a. Design Standard Policy/Guidelines for Both Districts Adjourn Capital Needs Work Group virtual meetings are open to the public to attend remotely. Should any member of the public wish to view this meeting, please click the following link to register: Capital Needs Workgroup Registration Link After registering, you will receive a follow-up email which will allow you to access and view the meeting. If you have any comments or questions, would like to submit any written comments to the group, or would like an emailed copy of the entire agenda package for this meeting, please email Rebecca Crawford at rcrawfordAoran eg countync.gov before 3:00 pm on June 13, 2022 86 ORANGE COUNTY BOARD OF COMMISSIONERS CHAPEL HILL-CARRBORO BOARD OF EDUCATION ORANGE COUNTY BOARD OF EDUCATION Capital Needs Work Group June 15, 2022 Meeting—8:30-10am Due to current public health concerns, the Capital Needs Work Group is conducting a Virtual Meeting on June 15, 2022. Members of the Group will be participating in the meeting remotely. 1. Welcome—Commissioner Jean Hamilton, Chair of Work Group Attendees: Bonnie Hauser, Jonathan Scott, Jean Hamilton, Gary Donaldson, Rani Dasi, Perdita Holtz, Travis Myren, Greg Wilder, Patrick Abele, Rhonda Rath, Renee Price, Andre Stewart, Eric Allen, Carrie Doyle, Kirk Vaughn, Steve Arndt, Dr. Nyah Hamlett, Dr. Monique Felder 2. Orange County Schools Adequate Public Facilities Ordinance (SAPFO) Discussion—Orange County Planning and Inspections a. Perdita Holtz from OC Planning and Inspections shared a presentation explaining the purpose, administration, and history of SAPFO b. Patrick Abele i. For OCS, Mebane is not a participant of the SAPFO process or MOUs and OCS is facing a tremendous amount of growth from the part of the county — those students aren't considered until they come to school 1. There are other mechanisms the schools are having to use in addition to SAPFO 2. OCS approved spot ordinances for some new developments in that part of the county — will have to update GIS maps, etc. since advertised as districted in OC a. Send updates to new Planning Director, Perdita, and Brian Carson 3. Travis — we've had discussions with Mebane to be a part of SAPFO—they are reluctant to be tied to the CAPS process but send us their numbers a. If capacity didn't exist in district, wouldn't approve the development 4. Jean— would be helpful to put the Mebane data into our model so we know ahead of time what's happening and when we need to build new 87 schools or renovate since CAPS is unlikely to be used ii. Pre-K: how is SAPFO addressing Pre-K given that those numbers aren't addressed in the numbers used for capacity? 1. Perdita: a committee of elected officials from BOCC and BOE were working on it prior to COVID but it was paused 2. Pre-K numbers are now tracked in the SAPFO report iii. Bonnie: special set-asides and special settings aren't included in SAPFO either iv. Bonnie: SAPFO doesn't predict school replacement — both districts are facing declining enrollment so don't need new capacity but about when we need maintenance and school replacements 1. Jean: let's get the capacity correct(including pre- K, Mebane, etc.) and then maintenance/replacement is outside of SAPFO c. Patrick: as people in Hillsborough look at SAPFO reports it looks like we have plenty of seats and are open to development, same with Mebane,but there are developments in queue that are filling seats that aren't included in the SAPFO reports i. Need a crosswalk with CAPS and SAPFO to see all seats needed ii. Lots of development that is coming quickly but we can't see it until it's actually here iii. Jean:how can re-establish the Pre-K group so we can get the numbers into SAPFO 1. Travis: each agency appointed 2 representatives for the Pre-K group so we can initiate that meeting again and broaden the scope d. Carrie: adding Pre-K numbers is also about adding different space—same with special setting students e. Eric: Eric reviewed OC construction settings and classroom size numbers have changed dramatically from DPI (DPI #s are smaller than OC construction standards) i. Are we going to look at class size, and what is a reasonable time frame to review 1. Perdita: hasn't changed for many years but DPI standards are included in the SAPFO #s a. Capacity goes down as DPI updates their standards ii. When we reduce the size of the school with same # of kids we're running out of room 88 f. Jean: What are the numbers currently for capacity? i. Eric: we've been tracking those and can share them ii. Makes it tricky to house kids when we are renovating g. Jean: where do the capacity standards exist? An ordinance? i. Travis: no—policy only but can be amended ii. Can email to group h. Bonnie: Is SAPFO a standard tool for capacity building in other districts? i. Eric: his experience is that most districts use DPI standards (online) ii. Rani: clarified how we get ahead of capacity planning and what other tools are other districts using 1. Could the SAPFO task force consider this question and do benchmarking? iii. Renee: SAPFO is pretty unique to OC iv. Perdita: some other districts attempted similar ordinances but were tied to impact fees, which were struck down — original intent was to recognize that development had an impact on school capacity v. Bonnie: we're realizing SAPFO is out of date and so should we be looking at revisiting SAFPO or replacing it vi. Perdita: the modeling and predicting part is used by many other districts; we do include growth in Mebane n our projections 1. Includes those developments/units approved but not yet built vii. Patrick: in other districts they never wait until the kids show up—once CAPS certificates are signed the districts begin planning 1. Happy to reach out to other districts to understand how they plan 2. Having to redistrict kids coming from western OC to Cedar Ridge rather than Orange High because of capacity at Cedar Ridge (planned for this 5 years ago — anticipated would need additional capacity so did expansion to accommodate) 3. Orange Middle School and Culbreth Middle School most likely do not meet standards for room sizes) either OC or DPI but according to SAPFO looks like it meets capacity (older schools) 4. Alamance Co. Is already building schools on the border with OC to account for growth in 89 developments shared with OC but OC isn't building new schools 5. Thanks to County staff for all of their work — bound by the same restrictions schools are and have done their best(Perdita, Ashley, and Craig) viii. Jean: should make the broader scope of the SAPFO work group more immediate l. Pre-K, space at schools, don't wait on kids to get to school and predict ahead of time based on capacity, account for age of schools 2. This is a board issue—SAPFO report has been on consent and we haven't really thought about or considered it a. Staff have done a great job of doing what we've asked them to do but the board needs to figure out what changes are needed to update b. Renee: previous boards have been very active in the review of SAPFO but in the past couple of years it's been placed on consent and no one asked to pull it — COVID may have impacted this i. In the past have pointed out issues with SAPFO, Mebane has always been an issue (definitely should work more closely with Mebane) ii. Have had long discussions about Pre-K with school boards and Finance (Maggie Chotas may have minutes from those meetings) ix. Rani: Echos everything Patrick said 1. Encourage us to be really specific in next steps, very urgent 2. Willing to be a part of the team to review and discuss (have participated in the past) 3. Thanks so much to Perdita for all of her help in understanding context 4. Bonnie: can we send a recommendation forward to boards sooner rather than later (doesn't have to replace, can just update) or include in our final report? 5. Jean: let's discuss that during next steps x. Renee: hard to plan for capacity with charter schools — kids going back and forth (numbers going to charter schools is increasing) 90 xi. Jean: with numbers of kids per development that are planned, how do we check that against the actual numbers from those developments attending schools? (check that our assumptions are accurate) i. Bonnie: how difficult would it be to update capacity projections with numbers from Eric and Patrick with Pre-K, Mebane, etc i. Perdita: wouldn't be that difficult — models are fairly automated 3. Discussion and Next Steps a. Next Steps: i. Jean: envision that the Capital Needs Work Group would recommend changes to SAPFO as a part of the final report that goes to different boards ii. Renee: agree — this group doesn't need to focus on making policy 1. A review of SAPFO is needed iii. Travis: could start at a staff level with SAPFOTAC to work through concerns and then use that group to escalate to boards iv. Rani: report is important but don't want us to hold our ideas until have a perfect report 1. Could we go ahead and share that SAPFO is understating capacity and recommend to review process for SAPFO through the SAPFOTAC to see if need to make changes for future capacity planning v. Renee: could the next Joint meeting review recommendations made for changes by SAPFOTAC? 1. Could be done at next meeting this fall vi. Jean: SAPFOTAC can start working on this immediately to update policy and make it more accurate 1. Board representatives on that can go back to boards and report out on work happening 2. Jean could report out at next BOCC meeting 3. Need to work on a report from Capital Needs Work Group, too vii. Bonnie: should we think through what we say to boards about changes to be made (unified update to each board) 1. Update formula (how far off are the numbers from SAPFO?) 2. Update or replace SAPFO 3. Can we all get a copy of the ordinance? a. Jean: online on county website 4. Why do we keep putting out wrong numbers when we know they're wrong? 91 viii. Renee: pinpoint all of the things that are problematic, make a list, and then make a list of what we're looking for 1. If we're looking for Mebane#s and Mebane isn't participating, that's a problem 2. Do we continue using our formulas with using a standard 3 bedroom house for generating student #s (is this still accurate) 3. Has had issues with SAPFO from day 1 but have learned to live with it 4. How do we integrate universal Pre-K#s? 5. Can bring up at next BOCC meeting but should put it on the agenda for the next meeting in the fall ix. Patrick: did an analysis a few years ago with Craig and compared actuals with projections based on developments and found that projects are pretty accurate (some developments are underestimated and others are overestimated) 1. If we're looking at a formula, should run at 100% capacity rather than 105% for E, 107% for middle, and 110% for high schools a. Most districts use 100% b. Have to have seats for kids when they show up c. Eric: agrees about using 100% capacity #s x. Carrie: Likes the plan to review this fall but look at specific problems 1. Districts can share specific examples of issues such as the Orange High/Cedar Ridge re- districting xi. Jean: What do we do about the older schools in addition to capacity? 1. Group has talked about financing, needs of older schools, what new schools can bring, capacity, next month talking about design standards a. What else do we need to talk about that we haven't addressed to get the full picture that can be put into a report? b. Email Jean with any ideas i. Patrick: safety and security ii. Rani: school needs iii. Bonnie: we don't have enough money to do what we need to do 92 iv. How do we finance what we need? 2. Do we need a consultant? A professional to help us figure out what needs to be done and how to finance it? xii. Renee: Durham Co. is going to do a bond referendum in a few years for—$440 million and are planning for it now to do an overhaul of schools 1. Need safe and modern classrooms 2. Will have an impact on Orange County a. Parents, teachers, and community members will compare OC to Durham Co. 3. Durham is planning videos and ambassadors to share info with public and plan xiii. Bonnie: Guilford did something similar with $800 million bond,worked with consultant on a joint planning effort and came up with $2 billion facility plan 1. We could ask Guilford how they did it xiv. Jean: Can we use ARPA $ to hire a consultant? xv. Eric: leaving CHCCS to work for a private developer to manage the Guilford building project(Wake is doing the same with Cumming Project Management—fees are paid out of the bond) 1. Will be happy to come back and share information about that process with this group 2. Will be a 10 year project over 20 schools a. $500 million for life cycle replacements 3. Goal is to use as many Guilford County-based companies as possible 4. Next Meeting is Wednesday, July 20, 2022 a. Design Standard Policy/Guidelines for Both Districts Adjourn Capital Needs Work Group virtual meetings are open to the public to attend remotely. Should any member of the public wish to view this meeting, please click the following link to register: Capital Needs Workgroup Registration Link After registering, you will receive a follow-up email which will allow you to access and view the meeting. If you have any comments or questions, would like to submit any written comments to the group, or would like an emailed copy of the entire agenda package for this meeting, please email Rebecca Crawford at rcrawford&oran_eg countync.gov before 3:00 pm on June 13, 2022 93 ORANGE COUNTY NORTH CAROLINA SCHOOLS ADEQUATE PUBLIC FACILITIES ORDINANCE (SAP FO) - ADOPTED 2003 Presented by: Perdita Holtz,AICP Special Projects & GIS Supervisor Orange County Planning Department 94 ADOPTION NUTS & BOLTS An Ordinance of the County and Towns Based on Statutory Zoning Authority Two `overlay' districts were created; one for each school district Signatory local governments adopted necessary provisions into their respective zoning and subdivision regulations Inter-local Memorandum of Understanding ( MOU ) for each appropriate Board of Education ( BOE), County, and associated town (s) which defined elements/parameters of SAPFO 95 To the `maximum extent practical' : Approval of new residential development will become effective only when it can reasonably be expected that adequate public school facilities [i .e., student capacity] will be available to accommodate the new development Local Governments approve development Synchronized with the availability of capacity Boards of Education determine, within MOU parameters School districts will use their best efforts to construct new schools and permanent expansions or additions to existing schools in accordance with the CIP County will use its best efforts to provide funding to carry out the CI P 96 ELEMENTS OF THE ORDINANCE MEMORANDA OF UNDERSTANDING A Topic T Level of Service Elementary Schools — 105% of capacity (combined) Standard Middle Schools — 107% of capacity (combined) High Schools — 110% of capacity (combined) Topic Building Capacity Standard 2003 NC Department Public Instruction and updates (e.g. Class Size) Topic Capital Investment Program (County) Standard 5 to 10- year plan 97 ELEMENTS OF THE ORDINANCE MEMORANDA OF UNDERSTANDING A Topic Student Growth Rate Average five different student projection models Standard and updates (actual historical numbersp ) Topic Student Generation Rate Standard 2001 TISCHLER Study and updates (2009, 2014) 98 SAPF,O ADMINISTRATI YSTE Two PARTS - - L &-I -�Wk- 1 . Capital Improvement Planning (CIP) Needs (County and Board of Education) Annual budget review 2 . Certificate of Adequate Public Schools (CAPS) ( Local Governments and Board of Education ) Development approval process 99 PART ONE - CAPITAL IMPROVEMENT PLANNING ( CIP ) NEEDS Historic enrollment Actual November enrollment update Student projections compared to actual existing capacity Identifies new capacity needs in the future Completely new school Renovation and expansion School Construction standards contain school sizes ( including targeted maximum number of students in elementary, middle, and high schools) 100 PART ONE - CAPITAL IMPROVEMENT PLANNING ( CIP ) NEEDS PROCESS A November Orange County requests student membership (enrollment) and capacity numbers (based on November 15 ) from schools December BOCC accepts numbers December - March Student membership and projections are utilized during the budget process (BOCC and BOE) Schools Technical Advisory Committee (SAPFOTAC) meets to January review draft report and 10-year student projections March Draft report distributed to SAPFO partners for comment Draft report and 10-year student projections presented to elected April officials May Final report is certified by the BOCC 101 PART o - CAPS SYST IT kN a A test of new development impacts using Student Generation Rates (SGR's) against available capacity CAPS issued if capacity exists, OR CAPS deferred until Part 1 CIP needs and associated funding for more capacity is achieved Historically, the identification of future CIP capacity has been far enough in advance to foresee and construct new capacity without CAPS deferral CAPS system was previously suspended for a certain school level in 2005 until new capacity was constructed for a certain level ioz PARITkNO - CAPS SYSTE-17". _J Certificate of Adequate Public Schools (CAPS) contained in a multi-part, integrated Excel workbook Tracks existing membership and capacity Test for and log new development impacts ( multi- year as appropriate) against capacity levels Local governments review development projects BOE and school staff confirms adequate capacity CAPS certificate given to local government from BOE for final development approval 103 - OTHER AsPECTI, SAPFOTAC (SAPFO Technical Advisory Committee) also monitors and informally reports : Changes in class size averages at the state level Charter school enrollment and impacts Pre-K membership COVID impacts (alternative projections) Future school construction projects Major residential development projects 104 FOUR ELEMENTs nF • PROGRAM COMPREHENSIVE CAPITAL PLAN IMPROVEMENT (public facilities PROGRAM AND planning) BUDGET (finance) ADEQUATE CAPS PUBLIC MANAGEMENT FACILITIES SYSTEM ORDINANCE (administrative) (regulation) 105 SAPF ONSIDERATIONS A CC What doesn't SAPFO do? Identify school-by-school capacity needs Level only (elementary, middle, high ) Determine per pupil funding Identify school maintenance/repair needs SAPFO is better attuned for capital facilities planning for new capacity needs rather than to defer development ( i . e. CAPS) Tied to residential land use and student membership/capacity due to residential development QUESTIONS AND COMMENTS 107 ORANGE COUNTY BOARD OF COMMISSIONERS CHAPEL HILL-CARRBORO BOARD OF EDUCATION ORANGE COUNTY BOARD OF EDUCATION Capital Needs Work Group July 20, 2022 Meeting—8:30-10am Due to current public health concerns, the Capital Needs Work Group is conducting a Virtual Meeting on July 20, 2022. Members of the Group will be participating in the meeting remotely. 1. Welcome—Commissioner Jean Hamilton, Chair of Work Group 2. Design Standard Policy/Guidelines for Both Districts 3. Discussion and Next Steps 4. Next Meeting is Wednesday, August 17, 2022 Adjourn Capital Needs Work Group virtual meetings are open to the public to attend remotely. Should any member of the public wish to view this meeting, please click the following link to register: Capital Needs Work_rgroup Registration Link After registering, you will receive a follow-up email which will allow you to access and view the meeting. If you have any comments or questions, would like to submit any written comments to the group, or would like an emailed copy of the entire agenda package for this meeting, please email Rebecca Crawford at rcrawfordAoran eg countync.gov before 3:00 pm on July 18, 2022 108 ORANGE COUNTY BOARD OF COMMISSIONERS CHAPEL HILL-CARRBORO BOARD OF EDUCATION ORANGE COUNTY BOARD OF EDUCATION Capital Needs Work Group July 20, 2022 Meeting—8:30-10am Due to current public health concerns, the Capital Needs Work Group is conducting a Virtual Meeting on July 20, 2022. Members of the Group will be participating in the meeting remotely. 1. Welcome—Commissioner Jean Hamilton, Chair of Work Group a. Attendees: Jean Hamilton, Bonnie Hauser, Gary Donaldson, Patrick Abele, Steve Arndt, Al Ciarochi, Andre' Stewart, Kirk Vaughn,Greg Wilder,Nyah Hamlett,Rebecca Crawford,Carrie Doyle, Jonathan Scott, Monique Felder 2. Design Standard Policy/Guidelines for Both Districts a. Jean: frame conversation today around design standards only, save maintenance standards for another discussion b. Jean: what design standards are used for the school districts? i. Patrick: primary driver of school facility construction across the state is DPI standards 1. Has prototype school designs in addition to standards a. hgps://www.dpi.nc.gov/media/570/down load b. hgps://www.dpi.nc.gov/media/569/down load 2. OC has own design standards — worked with former AMS director to review both DPI and OC standards to find commonalities a. Roofing, energy efficiencies, b. Have heard the cost of doing business in OC from contractors is very high because of the OC specific construction and design standards, zoning is harder to get plans approved — could OC standards be driving up costs c. OC has more initiatives in terms of green policies and energy efficiencies than other counties i. Could we focus on DPI standards but layer over the energy 109 efficiency and sustainability policies? Paused this discussion during COVID. ii. Would help with alignment between two districts to use DPI standards. iii. Ex.Don't need to build an athletic stadium for capacity in case make it to state playoffs. Can build standard size and rent if ever need more seating ii. Jean: Steve, where do we find the OC design standards? 1. Steve: not in county policy but county uses LEED as our county standards — used within design community 2. Al: echoed Patrick and Steve's comments about importance of standards and LEED 3. Patrick: drywall and insulation are not going to protect students and staff in an active shooter situation 4. Jean: do we need county-wide design standards? a. Al: school needs do vary from county building but in his experience design standards are not typically at a local level unless it's a local ordinance that says all new school buildings must be built to a silver LEED standard—just want to make sure we don't restrict ourselves in terms of cost(Platinum may be the standard but then we can't afford to build it in lean economic times). 5. Bonnie: are there standards on size? a. Al: size of the school may depend on the capacity needed b. Jean: hearing the county has additional standards on top of DPI — are districts speaking of the Uniform Development Ordinance? (page 286) C. https://www.oran_ec�ountync._ov�/Do cumentCenter/View/7179/UDO-MO ST- CURRENT-updated-050319 i. Al: these are baseline standards d. Jean: everyone review UDO standards and then discuss at next meeting about whether they are restricting our progress. 110 e. Steve: county is going through a Climate Action Plan. Part of that will be recommendations about sustainability of OC construction that may impact school construction f. Bonnie: are there standards for building for long term sustainability but charter schools are building cheaper and may not last as long. Has anyone see any standards that shift public schools towards more of the charter school model? iii. Al: you get what you pay for. Drywall is cheaper than block wall but won't last. VCT the is cheaper than polished concrete but concrete is cheaper in the long run and will last longer. 1. Trends in school design come and go — open concept has come around twice in his career 2. Updated standards are applied to new spaces as schools add or replace capacity, not just when buildings are replaced. a. Patrick: This was the approach for the new wing at Cedar Ridge High School 3. Discussion and Next Steps a. Jean: Is there anything in the UDO that has maintenance standards?Not sure—Check with Planning i. http://server3.co.orange.nc.us:8088/weblink/DocView.aspx?id=410 5&searchid=2fObaaa8-15f6-4c36-bdda-99ae9d14cdff&dbid=0 ii. hqps://www.orangecountytic.gov/DocumentCenterNie w/7179/UDO-MO ST-CURRENT-updated-050319 1. Beginning page 286 b. Bonnie: are there any building maintenance standards in the DPI guidance? i. Al: experience has been that maintenance is a local choice ii. Steve: often maintenance standards are set but funding isn't available to replace according to the standards 1. Renovations and replacements are an intermediary step between maintenance and new construction c. Bonnie: are there any financing standards we should consider for how much to budget for school maintenance? i. Al: could the finance people find a benchmark for % of operating budget to put in for ongoing maintenance? What does the county do? 111 ii. Nyah: shared Loudon County Capital Asset Program Fund model via email: https://www.loudoun.gov/DocumentCenterNiew/1641 24/13 a---Capital-As set-Preservation-Program-Fund d. Jean: Group has met seven times, has been very valuable in understanding the breadth of the issues facing — aging schools aren't serving our students well i. Time to write a report on what we've learned— state of our capital needs - and have recommendations for next steps in the report ii. Would like to have a draft of the report/executive summary for our next meeting in August to be reviewed by group and discuss whether to approve 1. Would then go to BOCC and school boards for review a. Would like to get a consultant to review the needs and come up with a 10 year plan to address needs in both districts i. What policy changes do we need to make 2. Need buy-in from group — would continue to meet but as an advisory group to consultant iii. Bonnie: agrees with Jean's idea iv. Jean:we need a sub-committee—Jean,Bonnie,OC staff, member of staff from each district(total of 5 people) 1. Jean will reach out to people individually outside of the meeting v. Carrie: agrees with plan and thanked chair and vice chair for leadership — should we add a board member from CHCCS to the sub-committee? vi. Bonnie — how hard is it to hire and offer competitive salaries for school facilities staff? 1. Al: Qualified people are out there but salaries are hard — can be rewarding even if not able to pay as much as in private sector 2. Patrick: depends on local contractors — have a large HVAC/mechanical contractor in Hillsborough and often lose HVAC mechanics to that company and to area universities a. No career ladder so how do they do that to retain staff? Help with licensing? Job shadowing with current high school students as a recruitment tool 4. Next Meeting is Wednesday, August 17, 2022 112 a. Discuss UDO school design standards and whether too restrictive b. Monique: Could we keep in mind that reopening schools next month and some members of the group may not be able to attend the meeting i. Jean: if report isn't ready won't meet. If report is ready and can't attend, feel free to submit comments ahead of time Adjourn Capital Needs Work Group virtual meetings are open to the public to attend remotely. Should any member of the public wish to view this meeting, please click the following link to register: Capital Needs Workgroup Registration Link After registering, you will receive a follow-up email which will allow you to access and view the meeting. If you have any comments or questions, would like to submit any written comments to the group, or would like an emailed copy of the entire agenda package for this meeting, please email Rebecca Crawford at rcrawford(a�oran eg countync.gov before 3:00 pm on July 18, 2022 113 Appendix 2: Existing School Building Inventory Chapel Hill Carrboro City Schools Orange County Schools School Name Year Built Age School Name Built Year Age Lincoln Center 1950 72 Central Elementary 1952 70 Glenwood 1952 70 Efland Cheeks 1952 70 Elementary Global Elementary Carrboro 1957 65 Hillsborough 1952 70 Elementary Elementary Estes Hills 1957 64 River Park 1956 66 Elementary Elementary Phillips Middle 1962 60 Orange High 1962 60 Frank Porter 1963 59 Orange Middle 1968 54 Graham Elementary Chapel Hill High 1966 56 Grady Brown 1974 48 Elementary Seawell 1969 53 New Hope 1991 31 Elementary Elementary Culbreth Middle 1969 53 AL Stanback Middle 1995 27 Ephesus 1972 50 Pathways 2000 22 Elementary Elementary CHCCS 1977 45 Cedar Ridge High 2002 20 Maintenance McDougle Middle 1994 28 Gravelly Hill 2006 16 Middle East Chapel Hill 1996 26 Partnership 2006 16 High Academy Scroggs 1999 23 Elementary Smith Middle 2001 21 Rashkis 2003 19 Elementary Carrboro 2007 15 Elementary Morris Grove 2008 14 Elementary Phoenix Academy 2009 13 Northside 2013 9 Elementary �. ' • • - • District Facility Pictures a.ti In Aging Infrastructure Ali Egress Issues k _ � Chapeli i • City Schools �r Campus Security Jssues Lighting 1 r ' Orange Aging Infrastructure ADA Egress Issues _ � County Schools �- : 1 F, Campus Security Issues Lighting