HomeMy WebLinkAboutAgenda - 03-19-2002 - 9a l
ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: March 19, 2002
Action Ag7�_
Item No.
SUBJECT: Approve Funding for the Design and Construction Phase of Chapel Hill-
Carrboro City Schools (CHCCS) Elementary School #9 Located at
Meadowmont
DEPARTMENT: Budget PUBLIC HEARING: (Y/N) No
ATTACHMENT (S): INFORMATION CONTACT:
Donna Dean 245-2151
Attachment 1. Chronology of Elementary TELEPHONE NUMBERS:
School #9 Hillsborough 732-8181
Attachment 2. Comparison of Elementary#9 Chapel Hill 968-4501
Project Costs to Commissioner Adopted Durham 688-7331
Elementary School Construction Standards Mebane 336-227-2031
Attachment 3. February 7, 2002 Memo from
Bill Mullin re: Elementary School #9
Construction Bids
Attachment 4. Bid Tabulation for
Construction of Elementary#9
Attachment 5. November 20, 2001 Site Plan
for Schools and Town Use Agreement
Attachment 6. CHCCS Elementary#9
Construction Capital Project Ordinance
PURPOSE: To receive an update on CHCCS Elementary School #9 and allocate
November 2001 bond funds for the Design and Construction Phase of the new school
(including site work, construction and associated start-up costs), in accordance with
Commissioner approved Policy on Planning and Funding School Capital Projects.
BACKGROUND: On February 21, 2002, the CHCCS Board of Education approved a
single prime contract bid award to Resolute Building Company to construct Elementary
School #9 at Meadowmont. The base amount of the bid totaled $10,830,000. With the
acceptance of twelve alternates, the total contract price is $10,921,250. This bid included
costs for site work/grading and construction of the school. CHCCS has requested that the
BOCC approve an amended capital project ordinance for Elementary #9 that will bring the
anticipated final CHCCS/County cost for the project to $12,560,784. The November 2001
school bond referendum included $12.8 million for construction of Elementary #9.
In November 2000, the Board of Commissioners approved a Policy on Planning and
Funding School Capital Projects. That policy identifies two levels of school construction
projects — Level 1 and Level 2. Level 1 projects are those projects that have a relatively
2
small scope of work and can be accomplished using a single prime contractor, in-house
staff or entail purchasing equipment and vehicles. Level 2 projects are major projects that
require several phases to complete. For these projects, the Commissioners approve
project funding in four phases:
• Concept/Pre-Planning Phase — includes preliminary programming and design
work that would result in conceptual drawings and preliminary cost estimates.
• Planning Phase — includes siting the facility, construction of infrastructure, and
preparation of construction documents in preparation for bidding process.
• Design and Construction Phase — includes final design, facility construction
and purchase of equipment, furnishings, technology, and one-time start up
items.
• Final Accounting Phase — provides a reconciliation of actual project
expenditures with approved budget.
As defined in the policy outlined above, construction of Elementary School #9 in the
CHCCS district is a Level 2 project and therefore requires that the Board of
Commissioners approve the project at the various phases outlined above. Funding for
the school, to be constructed at the Meadowmont subdivision in Chapel Hill, comes
from a combination of pay-as-you-go monies and the voter approved November 2001
bond referendum. Attachment 1 of this abstract, Chronology of Elementary #9,
outlines the project's activity to date.
It is important to note that, per an agreement between CHCCS and the Town of Chapel
Hill, the project bid includes upgrading the originally planned multi- purpose room to a
community gymnasium. The Town of Chapel Hill has agreed to provide the District with
a total of $750,000 to offset costs associated with the upgrade. In addition, the bid
includes construction of playing fields associated with the Town's planned park at
Meadowmont. Per an agreement between CHCCS, the Town and East West Partners
(developers of Meadowmont), East West Partners plan to provide $824,052 to offset
the cost of the playing fields. The table below outlines the components of the approved
bid from Resolute:
on ri u ion
from Project
Responsible Project Partner Partner
Elementary School#9 in accordance with BOCC CHCCS $9,347,198
approved School Construction Standards
Upgrade of multipurpose room to community Town of Chapel Hill $750,000
gymnasium
Playing fields for Town park East West Partners $824,052
(developers of Meadowmont)
Total Awarded Construction Bid $10,921,250
Attachment 2 of this abstract provides a comparison of Elementary #9 estimated project
costs to Commissioner adopted Elementary School Construction Standards.
3
FINANCIAL IMPACT:
Table 1 below outlines the estimated cost to construct Elementary #9, including the
community gymnasium and additional playing fields.
Table 1
Estimated
Phase Cost Funding Source
Concept/Pre-Planning Phase (Approved 12/06/00)
Schematic Design $107,184
Town Approval Process $25,000 Project Savings at Smith Middle School
Total Concept/Pre-Planning Phase $132,184
Planning Phase (Approved 03/03/01)
Design Development $142,911 Project Savings at Smith
Middle School and
Town Approval Process $72,000 Appropriation of School
Construction Documents $225,367 Capital Fund Balance
Bidding (approved on 12/11/01) $36,000
Professional fees (examples include project November 2001 Bond
scheduler, OWASA and Town Fees)
(included in 3/19/02 request) $442,357
Total Planning Phase $918,635
Design and Construction Phase (Approved 12/11/01)
Pre-grading $166,850
Contingency $32,150 November 2001 Bond
Sub-Total Design and Construction Phase
(approved 12/11/01) $199,000
Design and Construction Phase (Requested 3/19/02)
Construction and Site Work Contract $10,921,250
Furniture and Equipment $477,645
November 2001 Bond (less
Technology $750,585
$1,574,052 contributions
One-time (Non-Personnel Start Up Costs) $400,000 fr m Town of Chapel Hill and
Contingency $335,637 East West Developers)
Sub-Total Design and Construction Phase
(requested 3119102) $12,885,117
Total Estimated Cost of Elementar #9 $14,134,936
Less: Town of Chapel Hill Project Contribution ($750,000) For community gymnasium
Less: East West Developers Contribution ($824,152) For playing fields
Total CHCCS/County Cost of
Elementary#9 $12,560,784
4
Table 2 below outlines total available funding for Elementary#9:
Table 2. Funding Available for Elementary#9
Project
Funding
Savings from Smith Middle School $380,000
School Capital Fund Balance $192,462
Appropriation
2001 Bond Funds $12,800,000
Total CHCCS/County Funds Available
for Elementary#9 $13,372,462
Town of Chapel Hill Contribution $750,000
East West Partners Contribution $824,052
Total Funds Available for Elementary#9
$14,946,514
Actual site and construction work have not started for Elementary #9, so it is difficult to
accurately project any ultimate project savings. As with all new construction projects,
there are many uncertainties. For example, there is a potential that as site work begins,
contractors may encounter large rock beds that require a significant amount of work
over and above the current contract price.
As outlined in the School Facilities Planning and Funding Policy, the final phase of level
2 projects is the Final Accounting Phase. At the close of the project, this phase will
reconcile actual project expenditures with the approved budget and provide the Board
with a "final accounting" of the project.
If a project balance exists at the completion of the Elementary#9 project, CHCCS has
indicated that they would like the Commissioners to consider establishing a Future
Projects Planning Fund. That mechanism would allow project balances remaining after
the final accounting phase to be used for preliminary planning for other high priority
approved Capital Investment Plan projects. It would also permit the District to proceed
on schedule with the project prior to total project funding being identified and secured.
RECOMMENDATION (S): The Manager recommends that the Board of County
Commissioners receive the project update for CHCCS Elementary School #9 and adopt
the attached Elementary School #9 Construction Capital Project Ordinance.
. 5
THIS PAGE INTENTIONALLY LEFT BLANK.
03/14/02
6
Attachment 1. Chronology of CHCCS Elementary#9 Located at Meadowmont
• Concept/Pre-Planning Phase
December 2000 - The Commissioners appropriated $132,184 in funding for the
initial phase, Concept/Pre-Planning, for this project. Funding for this phase came
from savings in the Smith Middle School construction project. The appropriation
provided funding for conceptual drawings (schematics) and preliminary permit
fees (for the Town of Chapel Hill) for the school.
• Planning Phase
February 7, 2001 — Per the Commissioner approved policy, the Board of County
Commissioners should appoint a representative to work directly with the Board of
Education as it plans and constructs a new facility. The Board appointed Chair
Halkiotis as its Commissioner.representative.
March 6, 2001 - CHCCS staff presented preliminary plans to the Board of
Commissioners for review. Those plans adhered to the County's Elementary
School Construction Standards and included a multipurpose room instead of a
gymnasium.
At that time, the Commissioners appropriated an additional $440,462 for the
Planning Phase of the project. Funding for this phase came from Smith Middle
School construction project savings ($247,816) and an appropriation of$192,462
from the School Capital Project Fund Balance. Specifically, this phase entailed:
• Refining the schematic plans;
• Developing construction and site work details;
• Producing project drawings that fix the building size and characteristics
(including building elevations, exterior finishes, and mechanical, electrical and
plumbing systems).
During the Town of Chapel Hill approval process last spring, the Chapel Hill
Town Council requested that the CHCCS Board of Education include a full-size
community gymnasium instead of the multipurpose room. Estimated costs
associated with this upgrade are $750,000.
July 2001 - The CHCCS Board of Education approved the concept of including
,the gym in the design plans providing that the District and the Town could agree
on how to compensate CHCCS for the additional construction costs.
September 24, 2001 - During the joint meeting of the two school boards and the
Commissioners, CHCCS staff presented revised plans for Elementary #9 that
included the gymnasium. At that time, the Town and Board of Education had not
agreed on the specifics of how Chapel Hill would compensate the district for the
gymnasium cost. One proposal included the Town re-instating its financial
7
support of school resource officers and offering the district a joint-use agreement
for the proposed Homestead Center aquatic center. Under that particular plan,
the Town would have scheduled additional time for the district's high school swim
teams.
After reviewing the plans, the Commissioners asked the CHCCS Board of
Education to request full funding of the gym construction cost from the Town of
Chapel Hill in lieu of accepting the proposal of dedicated swim time. Since that
time, the Town Council has agreed to reimburse the district in three annual
installments of$238,000 beginning in fiscal year 2002-03 for a total of $714,000.
In addition, the Town has agreed to credit the school system $36,000 for plan
review fees.
November 6, 2001 -Voters approved the November 2001 bond referendum that
included $12.8 million to complete Elementary#9.
November 26, 2001 The Town of Chapel Hill approved a Special Use Permit
for Elementary#9.
December 11, 2001 — County Commissioners appropriate $235,000 of recently
approved bond funds to cover three project components — construction bidding,
pre-grading of the site and project contingency.
Hzzacnmenz z. %,omparmon of cieiiieiiiaiy ttV r-IVJVL;L t,.Vaw tV %..VrlunwawuGl P%UVNacu cICn119niaRy .a�.nvVi
Construction Standards -
Estimated Costs for Elementary#9
School(Including Gymnasium and Estimated Costs for Elementary#9
Approved School Construction Playing Fields per bid awarded by School(Excluding Gymnasium and
Standards CHCCS BOE 2121102) Playing Fields)
Student Capacity 600 600 • 600
Square Footage 95,225 94,234 11) 90,980
Square Feet per Student 158.7 157.1 151.6
Construction Cost $8,570,250 $10,168,810 $8,594,658
Cost Per Square Foot $ 90 $ 108 $ 94
including all acquisition related costs
such as surveys and professional
Site Acquisition fees. $400,000 $0 $0
Number of Acres: 16 22 22
Cost Per Acre: $25,000 $0 donated site $0 donated site
Site Development $857,025 $955,290 $955,290
%of Construction Cost 10.0% 9.4% 11.1%
Fees $942,728 $1,014,819 $1,014,819
%of Construction Costs and Site Development 10.0% 9.1% 10.6%
Moveable Equipment $428,513 $477,645 $477,645
%of Construction Cost 5.0% 4.7% 5.6%
(includes cabling and equipment for
voice, video and data distribution
Technolo systems) $785,606 $750,585 $750,585
Cost per square foot $8.25 $7.97 $8.25
Construction Contingency $471,364 $367,787 $367,787
Developmen 5.0% 3.6% 4.3%
Start-Up Costs Jon Personnel One time start-up costs $330,000 $400,000 $400,000
%of Construction Cost 3.9% 4.7%
Upgrade Multi-Purpose Room to a Community Gymnasium(4)
Total $12,785,485 $14,134,936 $12,560,784
Total Cost Per Square Foot $ 134.27 $ 150.00 $ 138.06
Capital Cost per Student Capacity
(capacity as set by school board) $ 21,309.14 $ 23,558.23 $ 20,934.64
Capital Cost per Student Capacity
(capacity as set by construction
standards report) $ 21,309.141 $ 23,558.23 $ 20,934.64
N .
A44ach rnen+ 3
9
CHAPEL HILL - CARRBORO CITY SCHOOLS
750 Merritt Mill Road
Chapel Hill, North Carolina 27516-2881
Telephone: (919) 967-8211
Fax: (919) 969-2474
Neil G. Pedersen Steve Scroggs, Assistant Superintendent
Superintendent for Support Services
William J. Mullin, Director of Facilities
Management
MEMORANDUM TO: Steve Scroggs
FROM: Bill Mullin
SUBJECT: Elementary School #9
Construction Bids
DATE: February 15, 2002
On February 7, 2002, bids were opened for the construction of Elementary School #9.
The project received excellent participation from contractors. Competitive bids were
received from ten general contractors, six plumbing contractors, eight mechanical
companies, eight electric companies, and five companies that bid on the fire protection
sprinkler system. State law permits projects of this scope to be bid as a single and
multi prime project and Elementary School #9 was bid in both formats.
The bid documents were prepared with alternates. This structure offers flexibility in
awarding contracts within the project budget and provides a mechanism for selecting
desired upgrades. Additionally, alternates identify the cost associated with speck
aspects of work.
The attached Bid Tabulation prepared by the architects lists each contractor's
submitted costs. The low single prime contractor bid submitted by The Resolute
Building Co. in the amount of$10,830,000 is recommended. Accepting 12 of the 14
alternates is also recommended. Alternate #2, specifying a contractor to perform door
and hardware work, is not recommended due to cost. Alternate#10, an ice storage
system, does not meet the life cycle cost analysis criteria established prior to the bid
and is not economically viable. The total cost of the recommended bid with 12
altemates is $10,921,250 and is within budget.
10
As stated, the project was also bid as a multi prime project. The comparative cost of
the multi prime bids is $10,869,500. The single prime contract has a small premium of
$51,750. This represents less than half a percent higher cost but is outweighed by the
coordination and control benefits associated with a single prime project. The architects
and Facilities Management believe that a single contractor will bring value to the
process by simplifying decision-making and response time. As we work with the Town
of Chapel Hill and the developers, East West Partners, these attributes will be very
beneficial in controlling costs and maintaining schedule.
The construction bid submitted by The Resolute Building Co. includes 11.5% minority
participation. This represents a high minority participation rate compared to other major
projects bid by the district in recent years. Additionally, the contractor is responsible to
provide documentation regarding the efforts used to solicit minority contractors and the
actual contractors who will participate in the work.
The project bid includes upgrades and work that will be reimbursed by the Town of
Chapel Hill and East West Partners. The Town will provide $750,000 to upgrade the
multi purpose room to a community gymnasium and East West Partners is providing
$824,052 to construct the Town play fields and associated amenities. This work is
included in the recommended contract with The Resolute Building Co.
The number of participating contractors produced a competitive bid. The base bid cost
for Elementary School #9, adjusted to reflect the reimbursements, is $101.74 per
square foot. This compares to other district projects as follows:
School Year Cost
Smith Middle School 1999 $ 94.99 per sf
Scroggs Elementary School 1998 $ 95.50 per sf
ECHHS Phase II 1997 $113.32 per sf
McDougle Elementary School 1995 $ 90.64 per sf
ECHHS Phase 1 1994 $ 95.18 per sf
Elementary School #9 is designed to meet the district's High Performance Energy
guidelines. The building is 35% more energy efficient than building code and includes
features such as daylighting, solar domestic hot water, photovoltaic panels, and
rainwater recovery system. Another of the school's features, that is not normally
included in school construction, is the-fire safety sprinkler system.
The project design team and Facilities Management recommend acceptance of the bid
from The Resolute Building Co. with alternates totaling $10,921,250. After School
Board review, funding will be requested from County Commissioners.
i A 4
Mr.William J.Mullin February 13,2002
1 1 1 CORLEY REDFOOT ZACK D.0 RE: Elementary School#9 Bid Tabulation page 2
ARCHITECTS • ENGINEERS • P L A X d E R S Therefore,we recommend the following for your consideration under the Single Prime Contract
February 13,2002
The apparent low bidder for the single prime contract was submitted as follows by:
The Resolute Building Co.,200 Cloister Court Chapel Hill,NC 27514:
William J.Mullin Director Base Bid: $10,830,000
Facilities Management AIL 411: 9,90D
Chapel Hill-Caaboro City Schools AIL#3: 46600
750 South Merritt Mill Road AIL#4: 6,600
GLENN D.CORLEY.AIA Chapel Hill,North Carolina 27516 AIL#5: 0
Pnsidenl.CEO
KENNETH E.REOFOOT,AIA RE: Elementary School#9 at Meadowmont AIL 06: 0
✓irrp,e AIL 07: 550
e(de°t proms#0031. AIL#8: Q
MARK xACK,AIA BID TABULATION
✓icePmideut AIL#9: W15W
P UHAAEEL L .HAMMERSLEXPE Dear Mr.Mullin: AIL#12: 15=
AIL#13: 11,500
AA oatCE W.SIrNCH,AIA In accordance with your request,I am sending you the certified bid tabulation Alt#14: t�0
AssoriRre for the above-referenced Bids for both S TOTAL:. $10,921,250
projert Ingle Prime and Multi-Prime
ANDREW R.CROICKSHANK,ALA Contracts were opened and read aloud at 4:00 PM,February 7,2002.
Associate
Please note the following. The apparent low bid total for the single prime contract is$51,750 higher
DAVID M.TAYLOR,AIA We recommend acceptance of the following alternates in conjunction with the than the total of the low multi-prime contract bids for the same package. Due to the tight
HARRY
Associate work required under the Base Bid: construction schedule for the School,and the need for it to open on time to alleviate the over-
NARRY M IEHSEN crowding in the existing elementary schools,we recommend moving forward with the single prime
Auu:.te AIL#1: Add porcelain the In lieu of vinyl the flooring in the Main Lobby, contract
KENNETH L SMITH Reception area and corridor leading to the Media Center
A cs,uiate Alt#3: Add irrigation to the Town Practice Field The single prime contract method of delivery offers the School Board a building onstruction project
AIL#4: Add irrigation to the School Play Field with a single source responsibility,in contrast with the multi-prime contracts for separate
AIL#5: Use of materials with recycled content i.e.,asphalt paving, plumbing;mechanical,electrical and fire protection disciplines. We believe that the single prime,
acoustical ceiling the and vinyl the floorin& contract method,with The Resolute Building Company,is the best way to proceed with this project.
AIL#6: Use low-water usage dishwasher
AIL#7: Add waterless urinal to Men's toilet room adjacent to Minority business enterprise participations,according to the information provided by Resolute In
Gymnasium their proposal,will be 11.5%of the Bow Bid amount
Alt.#8: Use Siemens Automatic Temperature Controls
PO sox 2368 AIL#9: Use Versa-Lok retaining wall system at Town Soccer Field Based on our knowledge that the total bid,Including the al
Chapel Hill,NC 27515-23e8 Alt.#il: Use fiber-mesh-reinforced exterior concrete sidewalks at front g g Proper alternates,is within the Schools
entrances system's budget,we propose proceeding as soon as possible with preparation of the Construction
222 Cloister coin► AIL#12 Use High-Efficiency Condensing Boilers Contract for Elementary School#9 at Meadowmont
Chapel Hill,NC 27514-2212 AIL#13: Use Chillers that utilize R-134A Refrigerant
Aicee d IIA
AIL#14: Add potable water and a drinking fountain to Town Soccer Fieldt
E.Red A[A
Please note that we do not recommend accepting AIL#10,the ice storage de nt
system. The cost is too high to justify,based on the life-cycle cost analysis
presented to the School Board in late December,2001. Also,we do cot KER-esw/0031-bi&tnb
recommend accepting Alternate#2,which stipulates the use of a specific vendor Endosm
to supply the doors,door frames and hardware for the'project This alternate
was designed to provide a single-source vendor to minimize coordination
problems during the construction process,however,the cost is too high to
(9l9)942-8586 Telephone justify, CDR[EY REDFOOT ZACKwr
(919)929.4802 Fax
r
r
r
COR= BEDFOOT ZACK, ac.
DID TABULATIOM
HLEKERTAEY SCHOOL #9 AT MEADOWMOXT
Chapel Hill-Carrboro City Schools
Project #0031
3:00 PM, February 7, 2002 12
MULTI-PRIME 5% aid Add. MBE
FIRE PROTECTIOM COMTEACTOR License Mo. Bond Board POEM RASE RID
Allied Fire Protection, Inc. 16286 yes yes yes $165,500
Raleigh, MC
Associated Fire Protection, Inc. 16333 yes yea yes $175,615
Clayton, MC
Capital City Sprinkler, Inc. so bid
Raleigh, MC
Crawford Sprinkler Co. 09881 yes yes no $295,000
Raleigh, MC
High Point Sprinkler, Inc. 24914 yea yp yes $176,535
Thomasville, MC
JaD Sprinkler Company, Inc. 16269 yes 2 yes $176,665
Clayton. MC
COBLEY $EDFOOT ZACK, ae.
DID 2SNULATIOM
ELODDATAR! SCHOOL #9 AT IDMZKR mMT
Chapel Hill-Barrboro City Schools
Project #0031
3:00 PM, February 7, 2002
Fz� I-PRTMB 5♦Hid Add. - MBE Alt. #4:
RICAL COMTBACTOB License Mo. Bond Beard POBM BASE BID Irrigation of
School Pield
lectrical Construction 22348 yes yes' yes ¢ 953,000 $ 800
te, MC
ss 213 you yes yes $1,121,900 $ 300
Burlington, MC
Mayne J. Griffin Electric 16529 no yes yes
Holliston, MA
Morino Electrical a 20959 yes yes yes $1,098,000 $1,000
Mechanical
Carrboro, MC
Port City Electric Company 9590 yes yes yes $1,246,000 blank
Mooresville, MC
Quality Electric Co., Inc. 3495 yes 2 yes $1,497,800 $2,625
Durham, MC
Triangle Electrical Services 19008 yea yes yes $1,060,000 no cost
Chapel Hill, MC
Vaughan Electric Co., Inc. 14 yes you yes $1,197,341 n/a
Durham, MC
Vick Brothers Electric 3003 yes yes yes $1,200,000 $2,275
Asheboro, MC
CORLEY rEDFOOT ZACK, su.
DID TAULATION
ELRKENTARr SCHOOL #9 AT KEADOMM)UT
Chapel Hill-rar±l.- City Schools
Project #0031
3s00 PM, February 7, 2002 13
MULTI-PRIM 5% Bid Add. NBN
MECRANZCAL CONTRACTOR License No. Bond Redd ]FORM BASS BID
Baker Mechanical, Inc., Wilson, NC 04177 yes yes yes $1,486,000
CCI Systems, So. Boston, VA no bid
Comfort Engineers, Durham, NC 9342 yes yes you $1,594,000
Cooper Mechanical Contractors 2580 yes;% yea yes blank •**
Sanford, MC
Meckworks, Inc., Beaufort, NC 11295 yes yes as $1,610,000
southern Piping Company, Raleigh, NC 7422
, you
yes Yes $1,333,000
Superior Mechanical, Inc. 12051 yes yes yes $1,420,000
Randleman, NC
WATCO Corporation, Garner, NC 2881 yes yes yes $1,439,860
Williams Mechanical Corporation 05820 yes yes yes $1,370,000
Lugoff, SC
Nam-Pam Alt. #D Alt. #10 Alt. 12 Righ- Alt. 13
MRCHANICAL CONTRACTOR Bienaas ran storage Rff.COndeas Soil Chillers R-134A
CamtsoL System Refrigerant
Baker Mechanical, Inc. no change $164,000 $35,000 $100,000
CCI Systems no bid
Comfort Snginsers no change $162,600 $26,200 $ 22,900
Cooper Mechanical Contractors - $1,399,000 $ 60,000 r $26,000 $ 21,000
Meckworks, Inc. no change $150,000 $30,000 no quote
Southern Piping company no Change $151,000 $18,000 $ 10,000
Superior Mechanical Inc. no change $227,500 $55,800 $122,000
WATCO Corporation $10,000 $ 80,900 $26,350 $ 2,200
Williams Mechanical Corporation no Change $169,000 $10,500 $ 83,200
ran ri arm Was 161t Name BiLd Was supposed wr en.
amount of $1,399,000 was incorrectly mitten on the bid form for Alternate #8. According to the School Board
Attorney, the clerical error made does not render the bid unacceptable= therefore, Cooper Mechanical
Contractors' Baas Bid is $1,399,000.
" I
CORLEY REDFOOT ZACK, me.
DID TADULATION
BLHISSTARY 8CBOOL #9 AT 1RIDOWNODT
Chapel Hill-Carrboro City Schools
Project 40031
300 PM, February 7, 2002
MULTI-PRIME 5%Did Add. MDR Alt. #7a Waterless
PLUMING CONTRACTOR Licause No. bond Deed FORK DAM BID Urinals
ABL a Associates, Plumbing LLC 19909 yea yes yea $747,000 $ S00
Raleigh, NC
Acme Plumbing a Heating 1208 yes 2 yes $800,800 $ 675
Durham, NC
Bradburn Plumbing Co., Inc. 5101 yes you yes $756,760 $ 400
Durham, NC
Brown Brothers Plumbing 282 yes yes yes $968,800 $ 402
Durban, MC
Morin& Electrical i Mechanical no bid
Carrboro, NC
868 Machanical, Inc. 20196 yes you yes $673,800 no Change
Raleigh, NC
Tommy V. Strigo, Inc. no bid
Burlington, NC
Williams Mechanical Corp. 05820 yes yes yes $72,900 $2,500
Lugoff, SC
Triangle Mechanical Contractor 4169 yea ran yes $862,416 $ 400
Garner, Inc
•+ NOTE: According to Mr. Williams of Williams Mechanical Corp., the Baas Bid of $72,900 is incorrect, and they could
not honor the price quoted. The Base Bid is therefore rejected.
Elementary School Y9 at Meadormont, Multi-Prime General Bid, page 3 of 3
14
M LTI-PRXMZ Alt. 6 Alt. 9 Alt. 11 Alt. 14
GRNSRAL CONTRACTOR Low-rater Retaining Rainf. Ezt. Mater to Torn
Dishwasher Well Concrete Soccer FLOW
at Toro Slabs
Field
American South General no change $23,000 $ 700 $ 2,300
Contractors
Barnhill Contracting Co. no change $ 6,800 $ S00 $ 5,500
Bordeauz Construction Co. no change $ 5,330 ($ 670) $ 7,000
Centurion Construction Co. no change $18,150 $ 1,450 $ 2,370
DeVere Construction Co. no bid
McDonald-York, Inc. no change $ 8,888 no change $ 3,920
Miller Building Corp. no change $ 3,000 $ 500 $ 5,200
Pena-Co Construction Inc. no bid
The Resolute Building Company -0- $20,500 $15,200 $ 2,400
R. N. Rouse 4 Co., Inc, no change $ 3,000 $ 600 $ 4,000
Sheloo, Inc. $ Soo $24,500 $ 5,000 $ 7,000
J. M. Thompson Company -0- $ 5,360 $ 4,200 $ 3,700
Elementary School 49 at Meadormont, Multi-Prime General Bid, page 2 of 3
MULTI-PRINZ Alt. 1 Alt. 2 Alt. 3 Alt. 4 Alt. 5 -
GRNERAL CONTRACTOR Porcelain Door Skim Field School Field Recycled
Tile supplier Irrigation Irrigation Materials
American South General $18,000 $23,000 $ 8,500 $12,000 no change
Contractors
Barnhill Contracting Co. $10,300 $20,000 $ 4,600 $17,500 $10,600
Bordeaux Construction Co, $27,564 $46,861 $11,962 $13,200 $12,000
Centurion Construction Co. $ 6,375 $25,000 $ 6,120 $ 6,500 no change
Devere Construction Co. no bid
McDonald-York, Inc. $28,568 $23,740 $23,600 $20,744 no change
Miller Building Corp. $11,200 $41,900 $ 5,700
$11,900 no change
Pena-Co Construction Inc. no bid
The Resolute Building C $ 9,900 $71,950 $ 4,600 $ 5,800 -0-
R. N. Rouse i Co., Inc. $ 6,500 $41,700 $ 5,700 $ 5,700 $5,000
Shelco, Inc. $26,000 no change $15,000
$12,000 no change
J. M. Thompson Company $11,485 -0- $10,200 $12,900 $13,000
CORLEY BEDFOOT ZAM, ..e.
HID TABULATION
• ELEWESTARY SCHOOL f9 AT uE&DOWMONT
Chapel Bill-Carrbozo City Schools
Project 40031 15
300 PM, February 7, 2002
MULTI-PRINE 5% aid add. MBR
CEaEYAL CONTRACTOR License No. Bond Recd WORM BASE AID
American South General Contractors 34536 yea yes yes $8,297,000
Sanford, NC
Barnhill Contracting Co. 3194 yes yes yes $8,366,453
Raleigh, HC
Sordeauz Construction Co. 9266 yes yes yes $6,372,100
Durham, NC
centurion Construction CO. 12332 yes yes yes $7,890,000
Raleigh, Me
DeVere Construction Co. no bid
Alps", MI
McDonald-York, Inc. 45371
Raleigh, NC yu yes yes ¢9,159,700
Miller Building Corp, 2078 yes yu YOU $8,147,000
Raleigh, NC
Peace-CO Construction Inc. no bid
Raleigh, NC
The Resolute Suilding Company 14397 yes yes yes $7,563,300
Chapel Bill, NC
R. N. Rouse s Co., Inc. 732 yes yes. yes $7,744,000
Raleigh, NC
Shelco, Inc. 9515 yea yes yea $8,052,000
Raleigh, NC
J. M. Thompson Company 474 yes yes yes $7,734,000
Raleigh, NC
Multi-Pries General Bid page 1 of 3
Elementary School 49 at Meadommoat, Single Prime Bid, page 4 of 4
it
SINGLE PRIMR Alt. 11 Alt. 12 Alt. 13 Alt. 14
GEBERAL CONTRACTOR Reint. Ext. Nigh-Effic. Chillers Water to Torn
concrete Condensing with R-134A Soccer Field
Slabs Boilers Refrigerant
American South General $ 700 $40,000 $20,000 ¢2,300
Contractors
Barnhill Contracting Co. $ 500 $19,000 $11,000 $5,500
Rordeauz Construction Co. ($670) $ 110 $ 75 $7,000
centurion Construction Co. $1,450 $37,000 $100,000 $2,320
DeVere Construction Co. no bid
McDonald-York, Inc, no bid
Miller Building Corp. $ 500 $111000 $87,000 $5,000
Penn-Cc Construction Inc. no bid
The Resolute Building Company $15,200 $20,000 $11,500 $2,400
R. N. Rouse c Co., Inc. $ 600 $10,700 $10,500 $7,000
Shelco, Ina, $5,000 $20,000 $10,000 $7,000
J. M. Thompson Company $4,200 -0- -0- $3,700
Elementary School 19 at Meadowmont, Single Prime Bid, page 3 of 4
16
SINGLE PRINZ Alt. 6 Alt. 7 Alt. 8 Alt. 9 Alt. 10 -
GRNERAL CONTRACTOR Low-rater Waterless Siessins Retaining Mall Ice Storage
Dishwasher Drinals Controls at Town Field System
American South General no change $ 500 $20,000 $25,000 $ 60,000
Contractors
Barnhill Contracting Co. no change $ 500 no change $ 6,800 $160,000
Bordeaux Constructioa Co, no change $ 425 no change $ 5,330 $ 954
Centurion Construction Co. no change $1,000 no change $18,150 $166,000
DeVere Construction Co. no bid
McDonald-York, Inc. no bid
Miller Building Corp. no change $2,600 no change $ 3,000
¢183,100
Penn-Cc Construction Inc. no bid
The Resolute building any -0- $ 550 -0- $20,500 $155,000
R. N. Rouse 8 Co., Inc. no change no change no chaaga ¢ 3,000 $156,000
shelco, Inc. $500 $ 440 ao change $24,500 $115,000
J. M. Thompson Company -0- $ 600 -0- $ 5,360 $ 930
■NOTES According to John Thompson, J. M. Thompson Company's bid of $930 for Alternate 810, ice storage, is incorrect
and JMT could not honor the price quoted; therefore, the alternate bid is rejected.
Elementary School 89 at Meadowmoat, Single Prima Bid, page 2 of 4
SINCLS PRINZ Alt. 1 Alt. 2 Alt. 3 Alt. 4 Alt. 5 -
GEMZR&L CONTRACTOR Porcelain Door Tama Field School Held Recycled
Tile Supplier irrigation Irrigation Materials
American South General $18,000 $23,000 $ 8,500 $12,000 no change
Contractors
Barnhill Contracting Co. $10,300 $21,200 $ 4,700 $16,400 $10,600
Bordeaux Construction Co. $27,584 $46,861 $11,962 $15,600 $12,000
Centurion Construction Co. $ 8,375 $25,000 $ 6,120 $ 7,300 no change
DeVere Construction Co. no bid
McDonald-York, Inc. no bid
Miller Building Corp. $11,200 $41,900 $ 5,700 $11,900 no change
Pena-Cc Construction Inc. no bid
The Resolute Building company $ 9,900 $71,950 $ 4,600 $ 6,600 -0-
R. N. Rouse i Co., Inc. $ 8,500 $41,700 $ 5,700 $ 5,700 $ 5,000
8halco, Inc. $28,000 $23,000
$15,000 $12,000 no change
J. M. Thompson Company $11,485 -0- J $13,000 $15,700 $13,000
CORLEY F.EWOOT ZACK, ,.�.
DID TADMLDiION
ELENEMTARY SCROOL 19 AT MBADONVAM 17
Chapel Will-Carrboro City Schools
project $0031
4:00 PM, February 7, 2002
SINGLE PRIME 5%Bid Add. MBE
GENERAL CONTRACTOR License no. Bond Recd FORM DUE DID
American south General Contractors 34536 yes yes yes $11,564,000
Sanford, NC
Barnhill Contracting Co. 3191 yes yes yea $11.586,025
Raleigh, NC
Bordeaux Construction co. $266 yes yes yes $11,449,000
Durham, NC
Centurion Construction Co. 12332 yam yes yes $11,133,000
Raleigh, NC
DeVere r^astruction Co. no bid
Alpena, MI
McDonald-York, Inc. no bid
Raleigh, NC
Miller Building Corp. 2078 yes yes ys $11,396,000
Raleigh, NC
Peas-Co Construction Inc. no bid
Raleigh, Nc
The Resolute Building Company 14397 yes yes yes $10,830,000
Chapel Rill, NC
R. N. Rouse a Co., Inc. 732 yes yes yes $10,924,000
Raleigh. MC
shelco, Inc. 9515 yes yes Ys $11,111,000
Raleigh, NC
J. M. Thompson company 474 yes yes yes $10,989,000
Raleigh, NC
Single Prime Did Page 1 of 4
II
BID TABUIMION
Elementary School #9 at Meadownont
Chapel Hill-Carrboro City Schools
Chapel Hill, NC
Project #0031
Opened at 4300 PM, February 7, 2002
Bids as shown on the attached eleven (11) pages, opened at 4300 PM, February 7,
2002, have been checked and.validated and-are hereby certified as correct.
eth E. edfoot, AIA, Vice President
��.•`. .....o f
6565
++ CO /
cu
ma•a.u.n
Q Parking Summary
ParkingProvidtd j / ASPHALT
113 mg.car spaces /
Gr Y� RSA'�r eASK erBALL ODU AT
WITH
GOALS AND O compact car Spa= 6 I S i7 accessible parking spae /:, • i'�4'
,
%STRIPING,
Taal: 120 spaces provided on sire / �� /.•� ��„� ' ,r11 `'\�.
Building Square Footago/ I� +� :+r' 1 0A
PHASE ONE 95M SF-' i/ • • —• LsoQ6o _ \ Yarn* „:F\4p
PHASETWO I2,000 S ?/ Mj etB AA DSCiiRGOL ' r-• �� �40
Total Square Footage: 107.000 S.F. f':/ ` W
RECYCLING D
f ruy T •�
FrAaJG. ' ` GROUN 9Rm L✓rr�r�r ''.•.I-.•. I�
i 2 ,p
it
\ i I
it"_`-�,.r..—•� '\. t .1n�' v
ONESTORY p
WFINIPT ZW.73R `
! 1 R�wOA7L�ANDD Amumricmmmwmi ELMAINTARY
SCHOOL p
11 SPRIGGING IRRIGA-noKsPRIGGtNG, • - -
9YADD 6•TOPSO149FNCHE�S. - p
ALTERNATE TRANI RECEPTACLES,
F7INDID GOALS,SCOREBOARD,
R, \ \ �.�•. '"f;- _� -
d �� BY OIHERi SIGNAGSASPHALT /s'!�'r--.-.• -�"•�-�-_- -.E ::�;.=;:
i I ATH,FENCING ETC. ` \\ /' r T °""•K"'W' -- -__ �__
1 � �!•• s'PEDESTRIAN � 4:! �( I I i j
1a'GATE. GATE • , V/ '..-.._..--.-..-.--..-..-..L..-..-.-1..-..-..J..-..-.-I.-..-....I-.
' 1 l
SITE PLAN FOR SCHOOLS AND CHAPEL FILL-CARRBORO ccrx ScHooLs
CORLEY REDFOOT ZACx
' �- TOWN USE AGREEMENT ELEMENTARY SCHOOL#9
1 ' ' •» ••••• NOVEMBER 20,2001 CHAPEL HILL,NORTH CAROLINA
1�indieas -rown Melds
Attachment 6
Elementary School #9 Construction 19
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital
project is hereby adopted.
Section 1. The project authorized provides funds to construct Elementary School #9 for
the Chapel Hill Carrboro City Schools. Funding for the project comes from
savings from the Smith Middle School Construction Project, an appropriation
from the School Capital Project Fund Balance, and proceeds from the
November 2001 voter approved bond referenda.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through Through
2000-01 FY 2001-02 2001-02
Sales Tax $0 $0 $0
Impact Fees $0 $0 $0
PSBF $0 $0 $0
Bond Funds $0 $11,988,322 $11,988,322
cans er from Smith
Middle School Ca ital $380,000 $0 $380,000
Appropriate Appropriatea runa ance
(School Capital Project
Fund) $192,462 $0 $192,462
Total Project Funding $572,462 1 $11,988,322 $12,560,784
Section 4. The following is appropriated for this project:
Through Through
2000-01 FY 2001-02 2000-01
Concept/Pre-Planning $132,184 $0 $132,184
Planning $440,278 $478,357 $918,635
Design and Construction $0 $9,513,948 $9,513,948
Equipment/Furnishings $0 $477,645 $477,645
Technolo $0 $750,585 $750,585
One-1115 e k.Non
Personnel) Start Up
Costs $0 $400,000 $400,000
Contin enc - $0 $367,787 $367,7871
Totall $572,462 $11,988,322 $12,560,784
Section 5. This Ordinance, originally adopted December 9, 2000, shall remain in effect
until June 30, 2002.
Adopted this nineteenth day of March 2002.