Loading...
HomeMy WebLinkAboutAgenda 04-26-22; 12-2 - Information Item - Memorandum - Blackwood Farm Park Phase II Construction Project Progress Information Update 1 ORANGE 'COUNTY Department of Environment, Agriculture, Parks&Recreation MEMORANDUM To: Board of County Commissioners Bonnie Hammersley, County Manager From: Marabeth Carr, Landscape Architect Copies: David Stancil, Director, Department of Environment,Agriculture, Parks& Recreation Date: April 26, 2022 RE: Blackwood Farm Park Phase II -Construction Project Progress Update The purpose of this memo and update is to provide a status report on the ongoing Blackwood Farm Park construction project. Project Description: In June 2021,the Board of County Commissioners authorized a construction contract for the development of Blackwood Farm Park, Phase II.The contract of$2,802,000 with J Kester and Rose of Fuquay-Varina, NC was executed and construction began in August 2021. Background: Consistent with previously-approved construction drawings and bid documents developed by the contracted firm of Susan Hatchell Landscape Architecture, PLLC for the park construction, this project includes a new entrance into the park off NC 86 and the widening of NC 86 for new turning lanes into the park.Also included are a new parking area and loop driveway to the existing entrance (for special events). The construction project also includes developing an amphitheater that can accommodate concerts and performances, a large picnic shelter that can also double as a stage, two vault toilets, and a park office and maintenance area. Construction continues at the site at this time. Because of weather issues during the winter and early spring, the project is currently approximately three weeks behind schedule - with a completion date anticipated late-summer of 2022. Please note this contract does not include renovating the historic farmhouse which is also underway under a separate contract, along with the proposed disc golf course in the early planning stages. Attachments: Attachment A—Photos of the construction underway 2 Photos of the construction progress at Blackwood Farm Park Phase II Attachment A Widening of Highway 86 for the new turning lanes into the Park J _ The new entrance into the Park and parking area I .r The new connector driveway to the exiting entrance for special events 'l 3 r The parking area is underway with the vault toilets in the background ready to be installed The Amphitheater is well underway! VIA The new park office and garage l waiting for the windows and doors r � -