Loading...
HomeMy WebLinkAbout2022-106-E-AMS-Racanelli Construction South-Various additions to Visitors BureauRevised 07/20 ORANGE COUNTY CHANGE ORDER REQUEST Change Order No. 1 NORTH CAROLINA _____________________________________________________________________________________________________________ _ Date: 02/08/2022 Project: Visitors Bureau 2-18 Department: AMS Department Address: 308 West Franklin Street, Chapel Hill NC Project: Visitors Bureau Upfit Contractor: Racanelli Construction South, Inc Contractor Address: : 1091 Pemberton Hill Road, Suite 102, Apex NC Effective date of original contract: 12/02/2020 This change order increases decreases the contract time by 240 days. Check here if no impact to contract time . Will this change order impact the date of substantial completion? Yes No. If yes, the amended date of substantial completion is: 04/08/2022 ______________________________________________________________________________________________________________ _ Full Description of Change: Additional changes made to the Visitors Bureau at 308 West Franklin Street. Mop closet door, Lentels, Wood Door Swap, Dumpster Coral Removal, IT Closet Changes, Adjustments to Framing, Re-wiring, Transfer Grill and Fans, Replace Toliets, Outside Repairs, Electrical Work, Life Safety, Carpet Installation, Wood Work. Reason for Change: Various additions to 308 West Franklin Street, Chapel Hill. Please see attached Change Orders: #2, 3, 4, 5, 6, 7, 8, 9, 11, 12R, 13, 15, 17 and 18. ______________________________________________________________________________________________________________ _ Original contract sum: $ 267,170.00 Contract sum prior to this change order: $ 348030.00 Amount of this change order: $ 43,770.00 Total sum of the contract including this change order: $ 391800.00 _______________________________________________________________________________________________________________ This change order is executed to amend the contract time or contract sum. It shall not be construed to impact the original contract, project, services, or work in any other manner. All other terms of the Original Contract remain in effect. _____________________________ _____________________________ Approved and executed this 8th day of February, 2022. _______________________________ Contractor Owner Architect (when retained) By:____________________________ By:___________________________ By:___________________________ DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 3/10/2022 3/11/20223/16/2022 Revised 07/20 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 ORANGE COUNTY—DEPARTMENT USE ONLY _____________________________________________________________________________________________________ Party/Vendor Name: Racanelli Construction South, Inc Party/Vendor Contact Person: Scott Drebitko Contact Phone: 919-363-3600 Party/Vendor Address: 1091 Pemberton Hill Road, Suite 102 City Apex State: NC Zip: 27502 Department: AMS Amount: $43770.00 Purpose: Various additions to Visitors Bureau Budget Code(s): 37600530-803000 Vendor # 62962 (N/A if new vendor) Vendor is a BOCC consultant? Yes No Contract Type: (Check one) New Renewal Amendment Effective Date Approved by Board Yes No Agenda Date: This agreement is approved as to technical form and content and I as Department Director affirmatively state work on this project has not been initiated prior to execution of the agreement: Department Director’s Signature ________________________________________ Date: ________ Agreements for emergency services or repair are not subject to the above affirmation. If services related to this agreement have already begun or been completed please briefly describe the nature of the emergency condition that was addressed: Risk Management This agreement is approved for sufficiency of insurance standards, specifications, and requirements: Office of the Risk Management Officer___________________________________ Date: _________ Financial Services This instrument has been pre-audited in the manner required by the Local Government Budget and Fiscal Control Act: Office of the Chief Financial Officer ____________________________________ Date: _________ Legal Services This agreement is approved as to legal form and sufficiency: Office of the County Attorney __________________________________________Date: ________ Clerk to the Board Received for record retention: All Docusign contracts must be copied to the Clerk upon completion: occlerkdocs@orangecountync.gov The following signature block is for hard copies only and is not required for Docusign contracts: Office of the Clerk to the Board __________________________________________Date:_________ Revised 07/20 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 2/18/2022 3/12/2022 3/15/2022 3/16/2022 Orange County Visitor Center Racanelli Change Order Request Racanelli Construction South, Inc.Proposal and Pricing Summary 1091 Pemberton Hill Road, Suite 102 RCS Project #20-008 Apex, NC 27502 Date:7/21/2021 Submitted To: JGA Architects 308 West Rosemary Street Chapel Hill, NC 27516 Attention : Josh Gurlitz via email Item Qty Unit Labor Unit Price Material Unit Price Sub Unit Price Labor Total Material Total Subcontractor Total Total 1 Martin Architectural Products: Quote: (attached)1 LS $ 2,365.00 $ 2,365.00 $ 2,365.00 2,365.00$ 2,365.00$ Small Tools & Consumables @ %on -$ General Conditions -$ Labor Burden 38%on $0 -$ Sales Tax on Materials 7.25%on $0 -$ Racanelli Construction South Overhead & Profit @ 10%on of RCS's work -$ Racanelli Construction South Overhead & Profit @ 5%on 2,365.00$ of Subcontractors work 118.25$ Bond & Insurance Premium @ 2.3%on 2,483.25$ 57.11$ TOTAL AMOUNT OF CHANGE ORDER REQUEST 2,540$ TOTAL TIME (CALENDAR DAYS) REQUESTED FOR THIS CHANGE 0 Authorized By Architect:Date: CC: COR# 2 Per sheet A103 there is no schedule for the double doors at the mop closet. We are pleased to provide the following change order request to provide doors, frame, and hardware. Change Order Request accepted and authorized for contract Change Order Notes: We reserve the right to claim additional cost and time extensions associated with this COR at a later time. We Have Not been authorized to proceed with this work. This Proposal may be withdrawn from us if not accepted within 10 Days. By: Peter K. Muzzillo Project Manager DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 511 EAST CHATHAM STREET CARY, NC 27511 PHONE: 919-469-9661 FAX: 919-469-9630 To: MAP Change #: Job Name: Location: Attn:Martin Job #: Tag #Add Deduct Quantity Amount 17 $ 325.00 1 $ 325.00 $ 975.00 1 $ 975.00 $ 900.00 1 $ 900.00 $ 2,200.00 7.25%Sales Tax $ 165.00 $ 2,365.00 Accepted: Date: Date: NOTE: Note:Attached is a proposal for a change request to our contract. A written response with authorization to proceed is required to process this change. Authorization of the change request acknowldeges that you are in receipt of the proposal and that there will be an adjustment to the contract value and/or adjustment to the duration of the time required to complete this scope of work NOTE: Change Order Proposal Racanelli Construction South, Inc. 1 Orange County Visitor Bureau 308 West Franklin Street, Chapel Hill, NC Peter Muzzillo 345821 Fully Welded HM Frame 5-0 x 7-0 A contract change is being made. Reason for change: Addition of Mop Closet Opening as original plans and door schedule did not not this in scope. Description Total Pair of Wood Doors Pre Finished 2/2-6 x 7-0 x 1 3/4" Hardware Set 5 - 6 Hinges, Flushbolts, Lock, OH Stops, Kickplates, Silencers Lump Sum Signed copy of change must be returned to our office (not by fax) before change can be executed. Please notify our office within seven (7) working days from this date if your records do not correspond. Your immediate attention is appreciated. Martin Architectural Products Project Manager Changes to the scope of work may impact project schedules and duration. We are proceeding with this change. Please issue a change order. We are not proceeding without a formal change order. Please issue a change order ASAP. DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Material Cost Breakdown Material Material List Price Cost Sell HM Frame $446.00 $309.00 $325.00 Wood Doors (2) $1,400.00 $927.00 $975.00 Hinges $196.00 $98.00 $103.00 Lockset $779.00 $413.00 $433.00 Flush Bolts $50.00 $30.00 $31.50 Overhead Stops $492.00 $170.00 $179.00 Kickplates $220.00 $132.00 $136.50 Dust Proof Strike $26.00 $16.00 $16.00 Silencers $3.00 $0.98 $1.00 Totals = $3,612.00 $2,095.98 $2,200.00 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 MOP CLOSET DOORS NOTINCLUDED IN SCHEDULEThese plans have been reviewed for code compliance. This plan review doesnot relieve the contractor of their responsibility to comply with all applicablecodes. The issuance of a permit based on these plans shall not prevent thebuilding official from thereafter requiring a correction of errors inplans,construction or violations of the code. This copy of the plans must be keptat the site of work and shall be open to inspection by the building official or theirauthorized representative ALL PLANS MUST BE KEPT ON JOB IN SCALE OR AT LEAST 1/4' SCALE FOR INSPECTIONSAPPROVED Town of Chapel Hill NC Building Department JOBSITE COPYDocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Orange County Visitor Center Racanelli Change Order Request Racanelli Construction South, Inc.Proposal and Pricing Summary 1091 Pemberton Hill Road, Suite 102 RCS Project #20-008 Apex, NC 27502 Date:8/2/2021 Submitted To: Orange County P.O. Box 8181 Hillsborough, NC 27278 Attention : Alan Dorman Item Qty Unit Labor Unit Price Material Unit Price Sub Unit Price Labor Total Material Total Subcontractor Total Total 1 J&A Tradesmen: Lintels: (invoice attached) 1 LS $ 445.00 $ 445.00 $ 445.00 2 Racanelli Labor to Cut Openings 4 HRS $ 50.00 $ 200.00 $ 200.00 3 Tools 1 LS $ 202.00 $ 202.00 $ 202.00 4 5 200.00$ 202.00$ 445.00$ 847.00$ Small Tools & Consumables @ %on -$ General Conditions -$ Labor Burden 38%on $200 76.00$ Sales Tax on Materials 7.50%on $202 15.15$ Racanelli Construction South Overhead & Profit @ 10%on 493.15$ of RCS's work 49.32$ Racanelli Construction South Overhead & Profit @ 5%on 445.00$ of Subcontractors work 22.25$ Bond & Insurance Premium @ 2.3%on 1,009.72$ 23.22$ TOTAL AMOUNT OF CHANGE ORDER REQUEST 1,033$ TOTAL TIME (CALENDAR DAYS) REQUESTED FOR THIS CHANGE 0 Authorized By Architect:Date: CC: COR# 3 Door openings 06 and 07 are going into an existing masonry wall not shown on the drawings. Per the structural engineer's direction we are pleased to provide a cost to cut the openings and install lintels. Change Order Request accepted and authorized for contract Change Order Notes: We reserve the right to claim additional cost and time extensions associated with this COR at a later time. We Have been authorized to proceed with this work.By: Peter K. Muzzillo Project Manager DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Josh Gurlitz <josh@joshgurlitz.com> 308 W Franklin Augustus Neville <neveng@aol.com>Tue, Jul 20, 2021 at 4:02 PM Reply-To: Augustus Neville <neveng@aol.com> To: "josh@joshgurlitz.com" <josh@joshgurlitz.com> Josh, A lintel for the 4" block wall is no problem. Just place an L4 x 4 x 5/16 in the joint above the opening and bear 8" on each side. However, the contractor pointed out a location where 2 - 2 x 10's span 16'+ and support 6'-6" of equipment load. These 2 x 10's will support a design load of only 17psf for the supported floor area. I recommend that these 2 x 10's be replaced with 2 - 2 x 10 LVL's. Gus DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 5816 Heritage Ln. Raleigh, NC 27606 Phone: 919-422-8968 E-Mail: ja.services@outlook.com Invoice August 2, 2021 Invoice No. 004 Contact Name: Racanelli Construction South Inc. Pete Muzzillo (919) 363-3600 pmuzzillo@racanelliconstruction.com Project Location: 308 Franklin St. Description Amount CO1: Install lintels- Labor & Material $ 445.00 CO 2: Tile removed in bathroom $560.00 Total $ 1,005.00 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Orange County Visitor Center Racanelli Change Order Request Racanelli Construction South, Inc.Proposal and Pricing Summary 1091 Pemberton Hill Road, Suite 102 RCS Project #20-008 Apex, NC 27502 Date:8/4/2021 Submitted To: JGA Architects 308 West Rosemary Street, Suite 302 Chapel Hill, NC 27516 Attention : Josh Gurlitz Item Qty Unit Labor Unit Price Material Unit Price Sub Unit Price Labor Total Material Total Subcontractor Total Total 1 MAP Change Order Proposal: (Attached)1 LS $ 677.26 $ 677.26 $ 677.26 2 3 4 5 677.26$ 677.26$ Small Tools & Consumables @ %on -$ General Conditions -$ Labor Burden 38%on $0 -$ Sales Tax on Materials 7.25%on $0 -$ Racanelli Construction South Overhead & Profit @ 10%on -$ of RCS's work -$ Racanelli Construction South Overhead & Profit @ 5%on 677.26$ of Subcontractors work 33.86$ Bond & Insurance Premium @ 2.3%on 711.12$ 16.36$ TOTAL AMOUNT OF CHANGE ORDER REQUEST 727$ TOTAL TIME (CALENDAR DAYS) REQUESTED FOR THIS CHANGE 0 Authorized By Architect:Date: CC: COR# 4 We are pleased to offer the following change order request to furnish and install solid core wood door finished to match approved stain color Caramel. This cost includes an expedited fee to receive doors in 4-5 weeks in lieu of 12-14 weeks with extended factory lead times. Change Order Request accepted and authorized for contract Change Order Notes: We reserve the right to claim additional cost and time extensions associated with this COR at a later time. We Have Not been authorized to proceed with this work. This Proposal may be withdrawn from us if not accepted within 10 Days. By: Peter K. Muzzillo Project Manager DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 511 EAST CHATHAM STREET CARY, NC 27511 PHONE: 919-469-9661 FAX: 919-469-9630 Change Order Proposal To:Racanelli Construction South, Inc.Date:July 30, 2021 MAP Change #:2 Job Name:Orange County Visitor Bureau Location:308 West Franklin Street, Chapel Hill, NC Attn:Peter Muzzillo Martin Job #:345821 A contract change is being made. Reason for change: Obtaning finished wood doors in expedited time to complete the project in accordance to schedule. Tag #Add Deduct Quantity Description Amount Wood Doors $45.00 14 Obtaining finished wood doors in 4 to 5 week sin lieu of 12-14 weeks with extended factory lead times. $630.00 Lump Sum $630.00 Sales Tax $47.26 Total $677.26 Accepted:Martin Architectural Products Date: Date: Project Manager NOTE:Changes to the scope of work may impact project schedules and duration. Note:Attached is a proposal for a change request to our contract. A written response with authorization to proceed is required to process this change. Authorization of the change request acknowldeges that you are in receipt of the proposal and that there will be an adjustment to the contract value and/or adjustment to the duration of the time required to complete this scope of work NOTE:Signed copy of change must be returned to our office (not by fax) before change can be executed. Please notify our office within seven (7) working days from this date if your records do not correspond. Your immediate attention is appreciated. We are proceeding with this change. Please issue a change order. We are not proceeding without a formal change order. Please issue a change order DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 1 Peter Muzzillo From:Josh Gurlitz <josh@joshgurlitz.com> Sent:Thursday, July 22, 2021 3:16 PM To:Peter Muzzillo Subject:Orange County Visitors Bureau Attachments:Stl Lintels and wood long span.pdf Hi Peter: This email will cover several items: 1) The owner has made their door finish selection. The doors should be: Species: White Birch (Rotary) Stain Color: Caramel 2) I am attaching the letter from Gus Neville regarding the (new) lintels and the discovered structure. Note that he believes that the existing beams are not adequate for the mechanical load above, even though they have actually been supporting the mech equip. Based on his analysis, I believe we should use the LVL's in this location as designed. Where the existing beams are not supporting the mechanical equipment, we can delete the LVL's that were shown. 3) I hope we can pick up some credits to offset the mop closet doors. COR 2 is expensive. Best.................Josh -- Josh Gurlitz JGA Architects tel 919.929.7595 cell 919.357.5875 Chapel Hill, North Carolina DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Orange County Visitor Center Racanelli Change Order Request Racanelli Construction South, Inc.Proposal and Pricing Summary 1091 Pemberton Hill Road, Suite 102 RCS Project #20-008 Apex, NC 27502 Date:8/25/2021 Submitted To: JGA Architects 308 West Rosemary Street, Suite 302 Chapel Hill, NC 27516 Attention : Josh Gurlitz Item Qty Unit Labor Unit Price Material Unit Price Sub Unit Price Labor Total Material Total Subcontractor Total Total 1 Peak City Building LLC: (Proposal Attached)1 LS $ 2,200.00 $ 2,200.00 $ 2,200.00 2 $ - 3 4 5 -$ 2,200.00$ 2,200.00$ Small Tools & Consumables @ %on -$ General Conditions -$ Labor Burden 38%on $0 -$ Sales Tax on Materials 7.25%on $0 -$ Racanelli Construction South Overhead & Profit @ 10%on -$ of RCS's work -$ Racanelli Construction South Overhead & Profit @ 5%on 2,200.00$ of Subcontractors work 110.00$ Bond & Insurance Premium @ 2.3%on 2,310.00$ 53.13$ TOTAL AMOUNT OF CHANGE ORDER REQUEST 2,363$ TOTAL TIME (CALENDAR DAYS) REQUESTED FOR THIS CHANGE 0 Authorized By Architect:Date: CC: COR# 5 Per the owner's request we are pleased to offer the following proposal to remove the dumpster coral located in the parking lot of 308 West Franklin Street. This price includes demolition and placing in the onsite dumpster of the steel perimeter posts and wood fence walls, cold patching of asphalt, and debris removal. Change Order Request accepted and authorized for contract Change Order Notes: We reserve the right to claim additional cost and time extensions associated with this COR at a later time. We Have Not been authorized to proceed with this work. This Proposal may be withdrawn from us if not accepted within 10 Days. By: Peter K. Muzzillo Project Manager DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 DATE 8/25/2021 Quotation #100 Customer ID Racanelli Quotation valid until:9/4/2021 Prepared by:Gage Mason SALESPERSON P.O. NUMBER SHIP DATE SHIP VIA F.O.B. POINT TERMS Due on receipt QUANTITY DESCRIPTION UNIT PRICE TAXABLE?AMOUNT 1 Wood Fence Demolition 850.00$ 1 Metal Post Demolition to Asphalt 1,000.00$ 1 Asphalt Patching 350.00$ SUBTOTAL 2,200.00$ TAX RATE SALES TAX -$ OTHER -$ TOTAL 2,200.00$ QuotationPeak City Building LLC Comments or Special Instructions:Chapel Hill Orange County Visitor Bureau - Dumpster Corral Demolition. This Proposal includes all LABOR, MATERIALS, EQUIPMENT, & SALES TAX. If you have any questions concerning this quotation, contact Gage Mason, (919-608-5878) - gagemason033@gmail.com Phone: (919) 608-5878 Email: gagemason033@gmail.com No Job Too Big, No Job Too Small! 1006 Purple Glory Drive Apex, NC 27502 Quotation For: Peter Muzzillo 1091 Pemberton Hill Rd - Suite 102 Apex, NC 27502 (919) 363-3600 pmuzzillo@racanelliconstruction.com DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 QUANTITY DESCRIPTION UNIT PRICE TAXABLE?AMOUNT THANK YOU FOR YOUR BUSINESS! Page 2 of 2 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Orange County Visitor Center Racanelli Change Order Request Racanelli Construction South, Inc.Proposal and Pricing Summary 1091 Pemberton Hill Road, Suite 102 RCS Project #20-008 Apex, NC 27502 Date:9/17/2021 Submitted To: JGA Architects 308 West Rosemary Street, Suite 302 Chapel Hill, NC 27516 Attention : Josh Gurlitz Item Qty Unit Labor Unit Price Material Unit Price Sub Unit Price Labor Total Material Total Subcontractor Total Total 1 MAP Quote Attached 1 LS $ 2,122.58 $ 2,122.58 $ 2,122.58 2 D&G Quote Attached 1 LS $ 984.00 $ 984.00 $ 984.00 3 4 5 3,106.58$ 3,106.58$ Small Tools & Consumables @ %on -$ General Conditions -$ Labor Burden 38%on $0 -$ Sales Tax on Materials 7.25%on $0 -$ Racanelli Construction South Overhead & Profit @ 10%on -$ of RCS's work -$ Racanelli Construction South Overhead & Profit @ 5%on 3,106.58$ of Subcontractors work 155.33$ Bond & Insurance Premium @ 2.3%on 3,261.91$ 75.02$ TOTAL AMOUNT OF CHANGE ORDER REQUEST 3,337$ TOTAL TIME (CALENDAR DAYS) REQUESTED FOR THIS CHANGE 0 Authorized By Architect:Date: CC: COR# 6 Per the owner's request and Bulletin 3 propsed changes to room #15 we are pleased to provide the following cost to reframe the door opening for a double 2x7 outswing SC wood door with locking jambs. All labor, material, framing and finish work is included. Cost to run data home run conduit will be submitted separatley. Please be advised the lead time on material is frame 2 weeks, doors 3-4 weeks, hardware 4-6 weeks. In the event this change of work delays C of O issuance an extension of time will be claimed at a later date. Change Order Request accepted and authorized for contract Change Order Notes: We reserve the right to claim additional cost and time extensions associated with this COR at a later time. We Have Not been authorized to proceed with this work. This Proposal may be withdrawn from us if not accepted within 10 Days. By: Peter K. Muzzillo Project Manager DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 511 EAST CHATHAM STREET CARY, NC 27511 PHONE: 919-469-9661 FAX: 919-469-9630 Change Order Proposal To:Racanelli Construction South, Inc.Date:September 14, 2021 MAP Change #:3 Job Name:Orange County Visitor Bureau Location:308 West Franklin Street, Chapel Hill, NC Attn:Peter Muzzillo Martin Job #:345821 A contract change is being made. Reason for change: Redesign of closet 08 - room 015 - Addition of pairs of wood doors and frame & hw Tag #Add Deduct Quantity Description Amount 08 $350.00 1 Fully Welded HM Frame 6-0 x 7-0 $350.00 $990.00 1 Pair of Wd Doors Birch Un Finished 2/3-0 x 7-0 x 1 3/4"$990.00 $900.00 1 Hardware Set 5 - 3 Hinges, Flushbolts, OH Stops, Kickplates, Silencers $594.00 Lump Sum $1,934.00 Sales Tax $188.58 Total $2,122.58 Accepted:Martin Architectural Products Date: Date: Project Manager NOTE:Changes to the scope of work may impact project schedules and duration. Note:Attached is a proposal for a change request to our contract. A written response with authorization to proceed is required to process this change. Authorization of the change request acknowldeges that you are in receipt of the proposal and that there will be an adjustment to the contract value and/or adjustment to the duration of the time required to complete this scope of work NOTE:Signed copy of change must be returned to our office (not by fax) before change can be executed. Please notify our office within seven (7) working days from this date if your records do not correspond. Your immediate attention is appreciated. We are proceeding with this change. Please issue a change order. We are not proceeding without a formal change order. Please issue a change order DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 1 Peter Muzzillo From: jose manuel <jgildgdrywallinc@gmail.com> Sent: Tuesday, September 7, 2021 3:50 PM To: Peter Muzzillo <pmuzzillo@racanelliconstruction.com> Subject: Re: OCVC Chapel Hill NC rigid insulation & patches redo 2 door openings & install HM frames (knock down 3 pcs) $984 On Tue, Sep 7, 2021 at 11:59 AM Peter Muzzillo <pmuzzillo@racanelliconstruction.com> wrote: Approved Sent from my iPhone On Sep 7, 2021, at 11:39 AM, jose manuel <jgildgdrywallinc@gmail.com> wrote: rigid insulation & R13 on perimeter walls $1,605. patch existing drywall materials $355 labor $1,875 equipment to reach height ceiling area $400 -- **new cell phone number** D & G Drywall Inc, Jose M Gil phone 336 972 1386 fax 336 941 9582 jgildgdrywallinc@gmail.com Po Box 30123 Winston, Salem NC 27130 -- DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Orange County Visitor Center Racanelli Change Order Request Racanelli Construction South, Inc.Proposal and Pricing Summary 1091 Pemberton Hill Road, Suite 102 RCS Project #20-008 Apex, NC 27502 Date:9/17/2021 Submitted To: JGA Architects 308 West Rosemary Street, Suite 302 Chapel Hill, NC 27516 Attention : Josh Gurlitz Item Qty Unit Labor Unit Price Material Unit Price Sub Unit Price Labor Total Material Total Subcontractor Total Total 1 D&G Quote Attached 1 LS $ (900.00) $ (900.00) $ (900.00) 2 Paint Master Quote Attached 1 LS $ 600.00 $ 600.00 $ 600.00 3 4 5 (300.00)$ (300.00)$ Small Tools & Consumables @ %on -$ General Conditions -$ Labor Burden 38%on $0 -$ Sales Tax on Materials 7.25%on $0 -$ Racanelli Construction South Overhead & Profit @ 10%on -$ of RCS's work -$ Racanelli Construction South Overhead & Profit @ 5%on (300.00)$ of Subcontractors work Bond & Insurance Premium @ 2.3%on (300.00)$ TOTAL AMOUNT OF CHANGE ORDER REQUEST (300)$ TOTAL TIME (CALENDAR DAYS) REQUESTED FOR THIS CHANGE 0 Authorized By Architect:Date: CC: COR# 7 Per your request we are pleased to offer the following change order proposal to remove framing from the project west side of Room 010. We will provide surface mounted conduit and prep and paint the existing break wall. Change Order Request accepted and authorized for contract Change Order Notes: We reserve the right to claim additional cost and time extensions associated with this COR at a later time. We Have Not been authorized to proceed with this work. This Proposal may be withdrawn from us if not accepted within 10 Days. By: Peter K. Muzzillo Project Manager DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 1 Peter Muzzillo Subject:FW: FW: OCVB From: jose manuel <jgildgdrywallinc@gmail.com> Sent: Friday, September 17, 2021 11:30 AM To: Peter Muzzillo <pmuzzillo@racanelliconstruction.com> Subject: Re: FW: OCVB credit for wall $900 On Fri, Sep 17, 2021 at 8:36 AM Peter Muzzillo <pmuzzillo@racanelliconstruction.com> wrote: Whats the credit to remove this framing? Peter Muzzillo Project Manager Racanelli Construction South, Inc. 1091 Pemberton Hill Road, Suite 102 Apex, NC 27502-4265 919.363.3600 Office 919.363.3700 Fax 919.760.7503 Mobile pmuzzillo@racanelliconstruction.com www.racanellinc.com Confidentiality Notice: This e-mail message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient, please contact the sender by reply e-mail, delete and then destroy all copies of the original message. From: Peter Muzzillo Sent: Monday, August 30, 2021 3:21 PM To: 'jose manuel' <jgildgdrywallinc@gmail.com> Subject: OCVB Jose DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 2 Can you give me a deduct to remove the framing from the below brick wall? The owner wants to paint the brick. Thanks, DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 3 Peter Muzzillo Project Manager Racanelli Construction South, Inc. 1091 Pemberton Hill Road, Suite 102 Apex, NC 27502-4265 919.363.3600 Office 919.363.3700 Fax 919.760.7503 Mobile pmuzzillo@racanelliconstruction.com www.racanellinc.com Confidentiality Notice: This e-mail message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient, please contact the sender by reply e-mail, delete and then destroy all copies of the original message. -- **new cell phone number** D & G Drywall Inc, Jose M Gil phone 336 972 1386 fax 336 941 9582 jgildgdrywallinc@gmail.com Po Box 30123 Winston, Salem NC 27130 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 1 Peter Muzzillo Subject:FW: OCVB From: corissa@paintmasterllc.com <corissa@paintmasterllc.com> Sent: Friday, August 27, 2021 7:45 AM To: Peter Muzzillo <pmuzzillo@racanelliconstruction.com> Subject: RE: OCVB Good morning Peter, Price to prep and paint brick is $600.00 Thank you Corissa Hemenway Vice President 1310 Corporation Pkwy Ste J Raleigh NC 27610 Direct 919 212 3070 Fax 919 212 3071 Corissa@paintmasterllc.com -----Original Message----- From: Peter Muzzillo [mailto:pmuzzillo@racanelliconstruction.com] Sent: Thursday, August 26, 2021 3:29 PM To: corissa@paintmasterllc.com Subject: RE: OCVB 8x20 is the size of the wall. Peter Muzzillo Project Manager Racanelli Construction South, Inc. 1091 Pemberton Hill Road, Suite 102 Apex, NC 27502-4265 919.363.3600 Office 919.363.3700 Fax 919.760.7503 Mobile pmuzzillo@racanelliconstruction.com www.racanellinc.com Confidentiality Notice: This e-mail message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient, please contact the sender by reply e-mail, delete and then destroy all copies of the original message. DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 2 -----Original Message----- From: corissa@paintmasterllc.com <corissa@paintmasterllc.com> Sent: Thursday, August 26, 2021 12:44 PM To: Peter Muzzillo <pmuzzillo@racanelliconstruction.com> Subject: Re: OCVB Peter Please send dimensions. Thank you Corissa ---- Peter Muzzillo <pmuzzillo@racanelliconstruction.com> wrote: > Corissa, > > The owner wants to paint this brick at the work room left hand side wall. Can you give me a price to prep and paint? Luis can send you dimensions if needed. > > Peter Muzzillo > Project Manager > Racanelli Construction South, Inc. > 1091 Pemberton Hill Road, Suite 102 > Apex, NC 27502-4265 > 919.363.3600 Office > 919.363.3700 Fax > 919.760.7503 Mobile > pmuzzillo@racanelliconstruction.com<mailto:pmuzzillo@racanelliconstruc > tion.com> www.racanellinc.com<http://www.racanellinc.com/> > Confidentiality Notice: This e-mail message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient, please contact the sender by reply e-mail, delete and then destroy all copies of the original message. > DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Orange County Visitor Center Racanelli Change Order Request Racanelli Construction South, Inc.Proposal and Pricing Summary 1091 Pemberton Hill Road, Suite 102 RCS Project #20-008 Apex, NC 27502 Date:9/28/2021 Submitted To: JGA Architects 308 West Rosemary Street, Suite 302 Chapel Hill, NC 27516 Attention : Josh Gurlitz Item Qty Unit Labor Unit Price Material Unit Price Sub Unit Price Labor Total Material Total Subcontractor Total Total 1 In wall data conduit 1 LS $ 2,000.00 $ - $ - $ 2,000.00 $ 2,000.00 2 Floor box race way 1 LS $ 4,000.00 $ - $ - $ 4,000.00 $ 4,000.00 3 2x2 White Access Panels 1 LS $ 122.24 $ - $ - $ 122.24 $ 122.24 4 RCS Labor to install access panels 3 HRS $ 35.00 $ 105.00 $ 105.00 $ - $ - $ 105.00 5 RCS Supervision of electrical work 8 HRS $ 50.00 $ 400.00 $ 400.00 $ - $ - $ 400.00 6 Paint Conduit 1 LS $ 300.00 $ 300.00 $ 300.00 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - 505.00$ -$ 6,422.24$ 6,927.24$ Small Tools & Consumables @ %on -$ General Conditions -$ Labor Burden 38%on $505 191.90$ Sales Tax on Materials 7.25%on $0 -$ Racanelli Construction South Overhead & Profit @ 10%on 696.90$ of RCS's work 69.69$ Racanelli Construction South Overhead & Profit @ 5%on 6,422.24$ of Subcontractors work 321.11$ Bond & Insurance Premium @ 2.3%on 7,509.94$ 172.73$ TOTAL AMOUNT OF CHANGE ORDER REQUEST 7,683$ TOTAL TIME (CALENDAR DAYS) REQUESTED FOR THIS CHANGE 5 Authorized By Architect:Date: CC: COR# 8R1 Per IT departments request to run individual raceways to the above ceiling. We are pleased to offer the following proposal to run raceways individually in wall and terminate above ceiling. As per the 9/23 onsite meeting we propose to run floor boxes and window data to the attic area incased in one surface mounted conduit to be painted in field. Cost includes (2) access panels and blocking. Please note the additional data boxes that were added will be submitted separate. Change Order Request accepted and authorized for contract Change Order Notes: We reserve the right to claim additional cost and time extensions associated with this COR at a later time. We Have Not been authorized to proceed with this work. This Proposal may be withdrawn from us if not accepted within 10 Days. By: Peter K. Muzzillo Project Manager DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 SUNNYDALE ELECTRIC OF NORTH CAROLINA, INC. sunnydalenc.com Sunnydale Electric of North Carolina, Inc. 7119 Wexford Woods Trl Raleigh, NC 27613 dena.sunnydale@gmail.com Proposal 1172 ADDRESS Racanelli Construction Services - VISITOR'S CENTER DATE 09/27/2021 TOTAL $6,000.00 DATE ACTIVITY DESCRIPTION QTY RATE AMOUNT OFFICE DEDICATED FLEX 1 2,000.00 2,000.00 RUN FLOOR BOXES & WINDOW DATA TO ATTIC AREA as per conversation 1 4,000.00 4,000.00 TOTAL $6,000.00 JOB: ORANGE COUNTY VISITOR'S BUREAU This includes demoing the existing concrete at the window area and getting them into the wall to feed the data/AV in the window area which was not included in our previous proposal. Total of $6000, does not include the concrete repair. THANK YOU. Accepted By Accepted Date DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Orange County Visitor Center Racanelli Change Order Request Racanelli Construction South, Inc.Proposal and Pricing Summary 1091 Pemberton Hill Road, Suite 102 RCS Project #20-008 Apex, NC 27502 Date:9/23/2021 Submitted To: JGA Architects 308 West Rosemary Street, Suite 302 Chapel Hill, NC 27516 Attention : Josh Gurlitz Item Qty Unit Labor Unit Price Material Unit Price Sub Unit Price Labor Total Material Total Subcontractor Total Total 1 Arnold Service: Quote Attached.1 LS $ 918.00 $ 918.00 $ 918.00 2 3 4 5 918.00$ 918.00$ Small Tools & Consumables @ %on -$ General Conditions -$ Labor Burden 38%on $0 -$ Sales Tax on Materials 7.25%on $0 -$ Racanelli Construction South Overhead & Profit @ 10%on -$ of RCS's work -$ Racanelli Construction South Overhead & Profit @ 5%on 918.00$ of Subcontractors work 45.90$ Bond & Insurance Premium @ 2.3%on 963.90$ 22.17$ TOTAL AMOUNT OF CHANGE ORDER REQUEST 986$ TOTAL TIME (CALENDAR DAYS) REQUESTED FOR THIS CHANGE 0 Authorized By Architect:Date: CC: COR# 9 Per RFI#4 the transfer grills located above 016 and 017 are required to be relocated due to lack of clearance with the hallway ceiling. We are pleased to offer the following proposal to relocate the transfer grills per the mechanical engineer's response on 9/20/2021. Change Order Request accepted and authorized for contract Change Order Notes: We reserve the right to claim additional cost and time extensions associated with this COR at a later time. We Have Not been authorized to proceed with this work. This Proposal may be withdrawn from us if not accepted within 10 Days. By: Peter K. Muzzillo Project Manager DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Orange County Visitor Center Racanelli Change Order Request Racanelli Construction South, Inc.Proposal and Pricing Summary 1091 Pemberton Hill Road, Suite 102 RCS Project #20-008 Apex, NC 27502 Date:10/6/2021 Submitted To: JGA Architects 308 West Rosemary Street, Suite 302 Chapel Hill, NC 27516 Attention : Josh Gurlitz Item Qty Unit Labor Unit Price Material Unit Price Sub Unit Price Labor Total Material Total Subcontractor Total Total 1 Tim McCarter Plumbing: (Quote Attached)1 LS $ 700.00 $ 700.00 $ 700.00 2 3 4 5 700.00$ 700.00$ Small Tools & Consumables @ %on -$ General Conditions -$ Labor Burden 38%on $0 -$ Sales Tax on Materials 7.25%on $0 -$ Racanelli Construction South Overhead & Profit @ 10%on -$ of RCS's work -$ Racanelli Construction South Overhead & Profit @ 5%on 700.00$ of Subcontractors work 35.00$ Bond & Insurance Premium @ 2.3%on 735.00$ 16.91$ TOTAL AMOUNT OF CHANGE ORDER REQUEST 752$ TOTAL TIME (CALENDAR DAYS) REQUESTED FOR THIS CHANGE 0 Authorized By Architect:Date: CC: COR#11 The existing water closets that were scheduled to remain were not in acceptable condition. This is the cost to replace them. Please review the product data included in this COR. Change Order Request accepted and authorized for contract Change Order Notes: We reserve the right to claim additional cost and time extensions associated with this COR at a later time. We Have Not been authorized to proceed with this work. This Proposal may be withdrawn from us if not accepted within 10 Days. By: Peter K. Muzzillo Project Manager DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Highline® Comfort Height® Two-piece elongated chair height toilet bowl K-4199 Features •Elongated bowl offers added room and comfort. •Comfort Height® feature offers chair-height seating that makes sitting down and standing up easier for most adults. •Combines with a K-4467/-RA, K-4468/-RA, or K-4841/-RA tank to create a complete 3999/-RA, K-3979/-RA, or K-3949/- RA toilet. Installation •Standard 12" (305 mm) rough-in. •Three-bolt quick-connect installation. Recommended Products/Accessories K-4467 Toilet tank, 1.28 gpf K-4841 Toilet tank, 1.28 gpf K-4467-RA Toilet tank, 1.28 gpf K-4841-RA Toilet tank, 1.28 gpf K-23726 Drain treatment Included Components Additional Components: Bolt cap accessory pack Codes/Standards ASME A112.19.2/CSA B45.1 KOHLER® Toilets and Seats Limited Warranty See website for detailed warranty information. Available Colors/Finishes Color tiles intended for reference only. Color Code Description 0 White 96 Biscuit 47 Almond 7 Black Black™ 1-800-4KOHLER (1-800-456-4537) Kohler Co. reserves the right to make revisions without notice to product specifications. For the most current Specification Sheet, go to www.kohler.com. 5-29-2021 06:38 - US/CA/MX DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Highline® Comfort Height® Two-piece elongated chair height toilet bowl K-4199 No image available. This product is a component and not intended to be a standalone installation. Technical Information All product dimensions are nominal. Toilet type:Two-piece, Floor-mount Bowl shape:Elongated Flush type:Class Five® Trap passageway:2-1/8" (54 mm) Water surface size:11-3/8" x 8" (289 mm x 203 mm) Rim to water surface: 5-3/8" (137 mm) Rough-in:12" (305 mm) Seat-mounting holes: 5-1/2" (140 mm) Notes Install this product according to the installation instructions. 1-800-4KOHLER (1-800-456-4537) Kohler Co. reserves the right to make revisions without notice to product specifications. For the most current Specification Sheet, go to www.kohler.com. 5-29-2021 06:38 - US/CA/MX DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Wellworth® Toilet tank, 1.6 gpf K-4468 Features •1.6 gpf (6.0 lpf) •Left-hand Polished Chrome trip lever. •Combines with the K-4199 bowl to create a complete K-3979 Highline toilet, combines with the K-4198 bowl to create a complete K-3978 Wellworth toilet, and combines with the K-4197 bowl to create a complete K-3977 Wellworth toilet. •Coordinates with other products in the Wellworth collection. Technology •Single-flush gravity uses the force of gravity and a precision- engineered tank to create a strong siphon during flushing. •KOHLERs canister flush valve harnesses the natural force of gravity and optimizes flushing performance. •Class Five® flushing technology offers virtually plug-free performance and rinsing power for a clean bowl. Installation •Supply line sold separately. Recommended Products/Accessories K-4197 Round-Front Bowl K-4198 Elongated Bowl K-4199 Two-piece elongated chair height toilet bowl K-23726 Drain treatment Codes/Standards ASME A112.19.2/CSA B45.1 KOHLER® Toilets and Seats Limited Warranty See website for detailed warranty information. Available Colors/Finishes Color tiles intended for reference only. Color Code Description 0 White 96 Biscuit 47 Almond 7 Black Black™ 1-800-4KOHLER (1-800-456-4537) Kohler Co. reserves the right to make revisions without notice to product specifications. For the most current Specification Sheet, go to www.kohler.com. 5-29-2021 19:21 - US/CA DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Wellworth® Toilet tank, 1.6 gpf K-4468 No image available. This product is a component and not intended to be a standalone installation. Technical Information All product dimensions are nominal. Toilet type:Two-piece, Bowl-mount Notes Install this product according to the installation instructions. 1-800-4KOHLER (1-800-456-4537) Kohler Co. reserves the right to make revisions without notice to product specifications. For the most current Specification Sheet, go to www.kohler.com. 5-29-2021 19:21 - US/CA DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Orange County Visitor Center Racanelli Change Order Request Racanelli Construction South, Inc.Proposal and Pricing Summary 1091 Pemberton Hill Road, Suite 102 RCS Project #20-008 Apex, NC 27502 Date:10/13/2021 Submitted To: JGA Architects 308 West Rosemary Street, Suite 302 Chapel Hill, NC 27516 Attention : Josh Gurlitz Item Qty Unit Labor Unit Price Material Unit Price Sub Unit Price Labor Total Material Total Subcontractor Total Total 1 Demo, Trim, Guardrail: (J&A Services Proposal Attached)1 LS $ 12,705.60 $ 12,705.60 $ 12,705.60 2 Painting: (Paintmaster Proposal Attahced)1 LS $ 6,445.00 $ 6,445.00 $ 6,445.00 3 Mopsink Demo (BY RCS)1 LS $ 500.00 $ 500.00 $ 500.00 4 Cleaning of fascia board (BY RCS)1 LS $ 500.00 $ 500.00 $ 500.00 5 Electrical Demo (Sunnydale Proposal Attached)1 LS $ 250.00 $ 250.00 $ 250.00 6 Louver (CAC Proposal Attached)1 LS $ 358.00 $ 358.00 $ - $ 358.00 7 Gate for dumster corral budget 1 LS $ 3,500.00 $ 3,500.00 $ 3,500.00 8 Dumpster 1 EA $ 650.00 $ 650.00 $ 650.00 1,000.00$ 358.00$ 23,550.60$ 24,908.60$ Small Tools & Consumables @ %on -$ General Conditions -$ Labor Burden 38%on $1,000 380.00$ Sales Tax on Materials 7.25%on $358 25.96$ Racanelli Construction South Overhead & Profit @ 10%on 1,763.96$ of RCS's work 176.40$ Racanelli Construction South Overhead & Profit @ 5%on 23,550.60$ of Subcontractors work 1,177.53$ Bond & Insurance Premium @ 2.3%on 26,668.48$ 613.38$ TOTAL AMOUNT OF CHANGE ORDER REQUEST 27,282$ TOTAL TIME (CALENDAR DAYS) REQUESTED FOR THIS CHANGE 0 Authorized By Architect:Date: CC: COR# 12 Per the owner's request we are pleased to offer the following proposal for exterior upgrades not included in the bid documents. This cost includes removing and replacing rotted ply wood trim to replaced in kind, remove and replace damaged crown molding, remove and replace siding, remove and replace damaged window sill and molding, new wood gaurdrails at deck, removal of black cables, demo of exterior fans, gate for dumpster corral (this is a budget until design is provided) demo of mopsink is included, provide 26"x24" louver with insect screen, new paint for all new and existing trim, cleaning of fascia. If exterior sheathing needs replaced this will result in an added cost of $50 per sheet and includes building wrap. This cost excludes permitting, point up of existing masonry and pressurewashing of existing masonry, and downspout connections. Change Order Request accepted and authorized for contract Change Order Notes: We reserve the right to claim additional cost and time extensions associated with this COR at a later time. We Have Not been authorized to proceed with this work. This Proposal may be withdrawn from us if not accepted within 10 Days. By: Peter K. Muzzillo Project Manager DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 5816 Heritage Ln. Raleigh, NC 27606 Phone: 919-422-8968 E-Mail: ja.services@outlook.com Proposal October 11, 2021 Contact Name: Racanelli Construction South Inc. Pete Muzzillo (919) 363-3600 pmuzzillo@racanelliconstruction.com Project Location: 308 West Franklin St. Chapel Hill, NC Description Amount Replace hand rails $ 3,798.40 Replace siding $ 4,228.00 Replace 140 ft. of crown molding -20ft. 1x4, 14 2x8 Trim boards $ 4,679.20 We propose hereby to furnish labor and material to complete in accordance with the above specifications for the sum of to be determined Any alteration or division from above specification involving extra costs will be executed only upon written order and will become an extra charge over and above the estimate. All agreement contingent upon strikes, accidents, or delays beyond our control. Respectfully submitted by Javier Ortiz Note-the proposal may be withdrawn by us if not accepted within 30 days. DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 1 Peter Muzzillo From: corissa@paintmasterllc.com <corissa@paintmasterllc.com> Sent: Thursday, October 7, 2021 12:52 PM To: Peter Muzzillo <pmuzzillo@racanelliconstruction.com> Subject: OC Visitors Center Hey Peter, Cost to paint all exterior wood (doors, frames, windows, soffit/fascia etc) $6,445.00. Thank you Corissa Hemenway Vice President 1310 Corporation Pkwy Ste J Raleigh NC 27610 Direct 919 212 3070 Fax 919 212 3071 Corissa@paintmasterllc.com DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 1 Peter Muzzillo From:Joye Fields <joye@chetadams.com> Sent:Wednesday, October 13, 2021 3:13 PM To:Peter Muzzillo Subject:RE: 308 West Franklin Street Chapel Hill Peter- Per the information below: LOUVER BY RELIABLE 1 24”W x 26”H, Model 445RD, 4” Deep, Extruded Aluminum Drainable Fixed Blade Louver with flanged frame, aluminum insect screen, loose clip angles, and Kynar 2-coat finish to match. 1 LOUVER, YOUR COST, FREIGHT ALLOWED…..$358.00 (plus tax). Let me know if you have any questions. Thank you, Joye Fields Chet Adams Company, Inc. 4904 Waters Edge Drive, Suite 240 Raleigh, NC 27606 Phone: 800-849-6331 / 919-851-6331 www.chetadams.com From: Peter Muzzillo <pmuzzillo@racanelliconstruction.com> Sent: Wednesday, October 13, 2021 12:28 PM To: Joye Fields <joye@chetadams.com> Subject: 308 West Franklin Street Chapel Hill Hi Joye, Can you give me a price for a 26” t x 24” w aluminum louver with bug screen and flange? I want to match something similar to the attached. Peter Muzzillo Project Manager Racanelli Construction South, Inc. 1091 Pemberton Hill Road, Suite 102 Apex, NC 27502-4265 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Orange County Visitor Center Racanelli Change Order Request Racanelli Construction South, Inc.Proposal and Pricing Summary 1091 Pemberton Hill Road, Suite 102 RCS Project #20-008 Apex, NC 27502 Date:10/26/2021 Submitted To: JGA Architects 308 West Rosemary Street, Suite 302 Chapel Hill, NC 27516 Attention : Josh Gurlitz Item Qty Unit Labor Unit Price Material Unit Price Sub Unit Price Labor Total Material Total Subcontractor Total Total 1 Demo, Trim, Pressure Wash and Paint 1 LS $ 11,196.00 $ 11,196.00 $ 11,196.00 3 Mopsink Demo (BY RCS)1 LS $ 500.00 $ 500.00 $ 500.00 5 Electrical Demo (Sunnydale Proposal Attached)1 LS $ 250.00 $ 250.00 $ 250.00 6 Louver (CAC Proposal Attached)1 LS $ 358.00 $ 358.00 $ - $ 358.00 7 Gate for dumster corral budget 1 LS $ 3,500.00 $ 3,500.00 $ 3,500.00 8 Dumpster 1 EA $ 650.00 $ 650.00 $ 650.00 500.00$ 358.00$ 15,596.00$ 16,454.00$ Small Tools & Consumables @ %on -$ General Conditions -$ Labor Burden 38%on $500 190.00$ Sales Tax on Materials 7.25%on $358 25.96$ Racanelli Construction South Overhead & Profit @ 10%on 1,073.96$ of RCS's work 107.40$ Racanelli Construction South Overhead & Profit @ 5%on 15,596.00$ of Subcontractors work 779.80$ Bond & Insurance Premium @ 2.3%on 17,557.15$ 403.81$ TOTAL AMOUNT OF CHANGE ORDER REQUEST 17,961$ TOTAL TIME (CALENDAR DAYS) REQUESTED FOR THIS CHANGE 0 Authorized By Architect:Date: CC: COR# 12R1 Per the owner's request we are pleased to offer the following proposal for exterior upgrades not included in the bid documents. This cost includes removing and replacing siding, removal of black cables, demo of exterior fans, gate for dumpster corral (this is a budget until design is provided) demo of mopsink is included, provide 26"x24" louver with insect screen, new paint for all new and existing trim, cleaning of fascia. If exterior sheathing needs replaced this will result in an added cost of $50 per sheet and includes building wrap. This cost excludes permitting, point up of existing masonry and pressurewashing of existing masonry, and downspout connections. Change Order Request accepted and authorized for contract Change Order Notes: We reserve the right to claim additional cost and time extensions associated with this COR at a later time. We Have Not been authorized to proceed with this work. This Proposal may be withdrawn from us if not accepted within 10 Days. By: Peter K. Muzzillo Project Manager DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 5816 Heritage Ln. Raleigh, NC 27606 Phone: 919-422-8968 E-Mail: ja.services@outlook.com Proposal October 11, 2021 Contact Name: Racanelli Construction South Inc. Pete Muzzillo (919) 363-3600 pmuzzillo@racanelliconstruction.com Project Location: 308 West Franklin St. Chapel Hill, NC Description Amount Replace hand rails Replace siding $ 3,228.00 Replace 140 ft. of crown molding -20ft. 1x4, 14 2x8 Trim boards Option 2 Power wash, caulking and paint. Replace damaged trim (2x8 trim boards, 2 window seals, 20ft of 1x4) $ 7,968.00 We propose hereby to furnish labor and material to complete in accordance with the above specifications for the sum of to be determined Any alteration or division from above specification involving extra costs will be executed only upon written order and will become an extra charge over and above the estimate. All agreement contingent upon strikes, accidents, or delays beyond our control. Respectfully submitted by Javier Ortiz Note-the proposal may be withdrawn by us if not accepted within 30 days. DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 1 Peter Muzzillo From:Joye Fields <joye@chetadams.com> Sent:Wednesday, October 13, 2021 3:13 PM To:Peter Muzzillo Subject:RE: 308 West Franklin Street Chapel Hill Peter- Per the information below: LOUVER BY RELIABLE 1 24”W x 26”H, Model 445RD, 4” Deep, Extruded Aluminum Drainable Fixed Blade Louver with flanged frame, aluminum insect screen, loose clip angles, and Kynar 2-coat finish to match. 1 LOUVER, YOUR COST, FREIGHT ALLOWED…..$358.00 (plus tax). Let me know if you have any questions. Thank you, Joye Fields Chet Adams Company, Inc. 4904 Waters Edge Drive, Suite 240 Raleigh, NC 27606 Phone: 800-849-6331 / 919-851-6331 www.chetadams.com From: Peter Muzzillo <pmuzzillo@racanelliconstruction.com> Sent: Wednesday, October 13, 2021 12:28 PM To: Joye Fields <joye@chetadams.com> Subject: 308 West Franklin Street Chapel Hill Hi Joye, Can you give me a price for a 26” t x 24” w aluminum louver with bug screen and flange? I want to match something similar to the attached. Peter Muzzillo Project Manager Racanelli Construction South, Inc. 1091 Pemberton Hill Road, Suite 102 Apex, NC 27502-4265 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Orange County Visitor Center Racanelli Change Order Request Racanelli Construction South, Inc.Proposal and Pricing Summary 1091 Pemberton Hill Road, Suite 102 RCS Project #20-008 Apex, NC 27502 Date:12/30/2021 Submitted To: JGA Architects 308 West Rosemary Street, Suite 302 Chapel Hill, NC 27516 Attention : Josh Gurlitz Item Qty Unit Labor Unit Price Material Unit Price Sub Unit Price Labor Total Material Total Subcontractor Total Total 1 Demo, Trim, Pressure Wash and Paint 1 LS $ 12,196.00 $ 12,196.00 $ 12,196.00 3 Mopsink Demo (BY RCS)1 LS $ 500.00 $ 500.00 $ 500.00 5 Electrical Demo (Sunnydale Proposal Attached)1 LS $ 450.00 $ 450.00 $ 450.00 6 Louver (CAC Proposal Attached)1 LS $ 358.00 $ 358.00 $ - $ 358.00 7 Gate for dumster corral 1 LS $ 1,500.00 $ 1,500.00 $ 1,500.00 8 Dumpster 1 EA $ 800.00 $ 800.00 $ 800.00 Racanelli Supervision 2 DY $ 232.00 $ 464.00 964.00$ 358.00$ 14,946.00$ 16,268.00$ Small Tools & Consumables @ %on -$ General Conditions -$ Labor Burden 38%on $964 366.32$ Sales Tax on Materials 7.25%on $358 25.96$ Racanelli Construction South Overhead & Profit @ 10%on 1,714.28$ of RCS's work 171.43$ Racanelli Construction South Overhead & Profit @ 5%on 14,946.00$ of Subcontractors work 747.30$ Bond & Insurance Premium @ 2.3%on 17,579.00$ 404.32$ TOTAL AMOUNT OF CHANGE ORDER REQUEST 17,983$ TOTAL TIME (CALENDAR DAYS) REQUESTED FOR THIS CHANGE 0 Authorized By Architect:Date: CC: COR# 12R2 Per the owner's request we are pleased to offer the following proposal for exterior upgrades not included in the bid documents. This cost includes removing and replacing siding, removal of black cables, demo of exterior fans, gate for dumpster corral (built out of PT 2X4 and fence boards) demo of mopsink is included, provide 26"x24" louver with insect screen, new paint for all new and existing trim, window trim, entry doors, cleaning of fascia. If exterior sheathing needs replaced this will result in an added cost of $50 per sheet and includes building wrap. This cost excludes permitting, point up of existing masonry and pressurewashing of existing masonry, handrails at deck, and downspout connections. Change Order Request accepted and authorized for contract Change Order Notes: We reserve the right to claim additional cost and time extensions associated with this COR at a later time. We Have Not been authorized to proceed with this work. This Proposal may be withdrawn from us if not accepted within 10 Days. By: Peter K. Muzzillo Project Manager DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Orange County Visitor Center Racanelli Change Order Request Racanelli Construction South, Inc.Proposal and Pricing Summary 1091 Pemberton Hill Road, Suite 102 RCS Project #20-008 Apex, NC 27502 Date:10/26/2021 Submitted To: JGA Architects 308 West Rosemary Street, Suite 302 Chapel Hill, NC 27516 Attention : Josh Gurlitz Item Qty Unit Labor Unit Price Material Unit Price Sub Unit Price Labor Total Material Total Subcontractor Total Total 1 Sunnydale Electric: Estimate Attached 1 LS $ 2,675.00 $ 2,675.00 $ 2,675.00 2 Demo and replace sheetrock: D&G Estimate Attached 1 LS $ 1,600.00 $ 1,600.00 $ 1,600.00 3 4 5 4,275.00$ 4,275.00$ Small Tools & Consumables @ %on -$ General Conditions -$ Labor Burden 38%on $0 -$ Sales Tax on Materials 7.25%on $0 -$ Racanelli Construction South Overhead & Profit @ 10%on -$ of RCS's work -$ Racanelli Construction South Overhead & Profit @ 5%on 4,275.00$ of Subcontractors work 213.75$ Bond & Insurance Premium @ 2.3%on 4,488.75$ 103.24$ TOTAL AMOUNT OF CHANGE ORDER REQUEST 4,592$ TOTAL TIME (CALENDAR DAYS) REQUESTED FOR THIS CHANGE 0 Authorized By Architect:Date: CC: COR# 13 Per bulletin 5 we are pleased to offer the following change order request to provide (2) dedicated 20 amp circuits and (2) data outlets, and one dedicated circuit to the data closet. Its required we demo sheet rock and patch due to clearence restrictions with the feed. Change Order Request accepted and authorized for contract Change Order Notes: We reserve the right to claim additional cost and time extensions associated with this COR at a later time. We Have Not been authorized to proceed with this work. This Proposal may be withdrawn from us if not accepted within 10 Days. By: Peter K. Muzzillo Project Manager DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 SUNNYDALE ELECTRIC OF NORTH CAROLINA, INC. sunnydalenc.com Sunnydale Electric of North Carolina, Inc. 7119 Wexford Woods Trl Raleigh, NC 27613 dena.sunnydale@gmail.com Proposal 1174 ADDRESS Racanelli Construction Services - VISITOR'S CENTER TOTAL $3,425.00 DATE ACTIVITY DESCRIPTION QTY RATE AMOUNT Hand Dryers Dedicated Circuits 2 375.00 750.00 Big TV Power & Data in Open Area 2 dedicated circuits and 2 dedicated data lines from panel and data closet via underground and over-head conduit lines. 1 2,000.00 2,000.00 #6 Ground from panel to data closet.1 300.00 300.00 2nd Dedicated Circuit to data closet.1 375.00 375.00 TOTAL $3,425.00 JOB: OCVB - EXTRAS THANK YOU. Accepted By Accepted Date $2,675 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 DEMO AND REPLACE SHEETROCKDocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Orange County Visitor Center Racanelli Change Order Request Racanelli Construction South, Inc.Proposal and Pricing Summary 1091 Pemberton Hill Road, Suite 102 RCS Project #20-008 Apex, NC 27502 Date:11/23/2021 Submitted To: JGA Architects 308 West Rosemary Street, Suite 302 Chapel Hill, NC 27516 Attention : Josh Gurlitz Item Qty Unit Labor Unit Price Material Unit Price Sub Unit Price Labor Total Material Total Subcontractor Total Total 1 EXIT LIGHTS 4 EA $ 225.00 $ 900.00 $ 900.00 2 EMERGENCY LIGHTS 2 EA $ 200.00 $ 400.00 $ 400.00 3 EGRESS LIGHTS 2 EA $ 250.00 $ 500.00 $ 500.00 4 EXTERIOR EGRESS LIGHT 1 EA $ 350.00 $ 350.00 $ 350.00 2,150.00$ 2,150.00$ Small Tools & Consumables @ %on -$ General Conditions -$ Labor Burden 38%on $0 -$ Sales Tax on Materials 7.25%on $0 -$ Racanelli Construction South Overhead & Profit @ 10%on -$ of RCS's work -$ Racanelli Construction South Overhead & Profit @ 5%on 2,150.00$ of Subcontractors work 107.50$ Bond & Insurance Premium @ 2.3%on 2,257.50$ 51.92$ TOTAL AMOUNT OF CHANGE ORDER REQUEST 2,309$ TOTAL TIME (CALENDAR DAYS) REQUESTED FOR THIS CHANGE 0 Authorized By Architect:Date: CC: COR# 15 After testing the existing exit and emergency lights the will not stay illuminated for a minimum of 15 min. The exterior emergency egress lights are also not staying illuminated for more than 1 min which will not pass inspection. Below is the cost to replace these fixtures only. We believe an egress light will be required at the front entry door that cost is included as well. Change Order Request accepted and authorized for contract Change Order Notes: We reserve the right to claim additional cost and time extensions associated with this COR at a later time. We Have Not been authorized to proceed with this work. This Proposal may be withdrawn from us if not accepted within 10 Days. By: Peter K. Muzzillo Project Manager DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 1 Peter Muzzillo From:econtractor1@gmail.com Sent:Tuesday, November 23, 2021 7:40 AM To:Peter Muzzillo Subject:OCVB I believe we will finish today. There are a couple things you should know. All the exits and emergency lights were shown as existing and none will stay lit for 15 min minimum so we are replacing them. The emergency egress lights that are out the side and back doors also won’t stay lit for more than 1 min so we are replacing them too. $225 each for the exits x 4 $200 each for the emergency lights x 2 $250 each for the egress x 2 The question is whether they want us to add an egress light out the front door. My guess is the City will require but I could be wrong. So we can add it now for $350 or we can wait and see if the Fire Marshal requires it? Jay Hughes Sunnydale Electric Inc DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Orange County Visitor Center Racanelli Change Order Request Racanelli Construction South, Inc.Proposal and Pricing Summary 1091 Pemberton Hill Road, Suite 102 RCS Project #20-008 Apex, NC 27502 Date:1/25/2022 Submitted To: JGA Architects 308 West Rosemary Street, Suite 302 Chapel Hill, NC 27516 Attention : Josh Gurlitz Item Qty Unit Labor Unit Price Material Unit Price Sub Unit Price Labor Total Material Total Subcontractor Total Total 1 LDR CREDIT ATTACHED 1 LS $ (530.00) $ (530.00) $ (530.00) 2 3 4 5 $ (530.00) (530.00)$ (530.00)$ Small Tools & Consumables @ %on -$ General Conditions -$ Labor Burden 38%on $0 -$ Sales Tax on Materials 7.25%on $0 -$ Racanelli Construction South Overhead & Profit @ 10%on -$ of RCS's work -$ Racanelli Construction South Overhead & Profit @ 5%on (530.00)$ of Subcontractors work Bond & Insurance Premium @ 2.3%on (530.00)$ TOTAL AMOUNT OF CHANGE ORDER REQUEST (530)$ TOTAL TIME (CALENDAR DAYS) REQUESTED FOR THIS CHANGE 0 Authorized By Architect:Date: CC: COR# 17 Credit for carpet installation labor. Change Order Request accepted and authorized for contract Change Order Notes: We reserve the right to claim additional cost and time extensions associated with this COR at a later time. We Have Not been authorized to proceed with this work. This Proposal may be withdrawn from us if not accepted within 10 Days. By: Peter K. Muzzillo Project Manager DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 LDR FLOORING CONTRACTORS 2208-G Associate Drive Raleigh, NC 27603 (919) 662-9880 Fax: (919) 662-3770 SPECIALIZING IN COMMERCIAL AND RESIDENTIAL FLOORING ______________________________________________________________________________ Carpet * Resilient Flooring * Hardwood Flooring * Ceramic Tile * Polished Concrete Quality Remains Long After The Price Is Forgotten L D R CHANGE ORDER PROPOSAL BID DATE: DECEMBER 20, 2021 PROJECT NAME: ORANGE CO VISITORS CENTER PROJECT LOCATION: CHAPEL HILL, NC ARCHITECT: JOSH GURLITZ WE ACKNOWLEDGE 0 ADDENDUM WE PROPOSE TO FOLLOWING DUE TO A CHANGE ON THE SCOPE OF WORK AS DESCRIBED BELOW: DEDUCT THE LABOR TO INSTALL CARPET TILE AND RUBBER BASE FROM THE SCOPE OF WORK. CHANGED TO PROVIDE MATERIALS ONLY DEDUCT CHANGE - $ 530.00 PLEASE SIGN AND DATE BELOW TO ACCEPT THIS CHANGE ORDER PROPOSAL: SIGNATURE: ___________________________________ DATE: __________________ PROPOSAL EXPIRES IN 40 DAYS FROM DATE OF BID DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Orange County Visitor Center Racanelli Change Order Request Racanelli Construction South, Inc.Proposal and Pricing Summary 1091 Pemberton Hill Road, Suite 102 RCS Project #20-008 Apex, NC 27502 Date:1/25/2022 Submitted To: JGA Architects 308 West Rosemary Street, Suite 302 Chapel Hill, NC 27516 Attention : Josh Gurlitz Item Qty Unit Labor Unit Price Material Unit Price Sub Unit Price Labor Total Material Total Subcontractor Total Total 1 LDR Invoice Attached 1 LS $ - $ - $ 275.00 $ - $ - $ 275.00 $ 275.00 2 $ - $ - $ - $ - $ - $ - $ - 3 $ - $ - $ - $ - $ - $ - $ - 4 $ - $ - $ - $ - $ - $ - $ - 5 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - -$ -$ 275.00$ 275.00$ Small Tools & Consumables @ %on -$ General Conditions -$ Labor Burden 38%on $0 -$ Sales Tax on Materials 7.25%on $0 -$ Racanelli Construction South Overhead & Profit @ 10%on -$ of RCS's work -$ Racanelli Construction South Overhead & Profit @ 5%on 275.00$ of Subcontractors work 13.75$ Bond & Insurance Premium @ 2.3%on 288.75$ 6.64$ TOTAL AMOUNT OF CHANGE ORDER REQUEST 295$ TOTAL TIME (CALENDAR DAYS) REQUESTED FOR THIS CHANGE 0 Authorized By Architect:Date: CC: COR#18 Added cost to box out each electrical floor box with wood flooring. Not shown on drawings. Change Order Request accepted and authorized for contract Change Order Notes: We reserve the right to claim additional cost and time extensions associated with this COR at a later time. We Have Not been authorized to proceed with this work. This Proposal may be withdrawn from us if not accepted within 10 Days. By: Peter K. Muzzillo Project Manager DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 LDR FLOORING CONTRACTORS 2208-G Associate Drive Raleigh, NC 27603 (919) 662-9880 Fax: (919) 662-3770 SPECIALIZING IN COMMERCIAL AND RESIDENTIAL FLOORING ______________________________________________________________________________ Carpet * Resilient Flooring * Hardwood Flooring * Ceramic Tile * Polished Concrete Quality Remains Long After The Price Is Forgotten L D R CHANGE ORDER PROPOSAL BID DATE: DECEMBER 20, 2021 PROJECT NAME: ORANGE CO VISITORS CENTER PROJECT LOCATION: CHAPEL HILL, NC ARCHITECT: JOSH GURLITZ WE ACKNOWLEDGE 0 ADDENDUM WE PROPOSE TO FOLLOWING DUE TO A CHANGE ON THE SCOPE OF WORK AS DESCRIBED BELOW: ADDITIONAL LABOR NEEDED TO CUSTOM CUT AND FRAME FLOORING AROUND ELECTRICAL BOXES IN THE HARDWOOD FLOOR BID TOTAL - $ 275.00 PLEASE SIGN AND DATE BELOW TO ACCEPT THIS CHANGE ORDER PROPOSAL: SIGNATURE: ___________________________________ DATE: __________________ PROPOSAL EXPIRES IN 40 DAYS FROM DATE OF BID DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 Here is the data: Change Order #2 - Mop Closet Doors $2,540.00 Change Order #3 - Lentels $1,033.00 Change Order #4 - Wood Door Swap $727.00 Change Order #5 - Dumpster Coral Removal $2,363.00 Change Order #6 - IT Closet Changes $3,337.00 Change Order #7 - Adjustments to Freaming -$300.00 Change Order #8 - Re-wiring $7,683.00 Change Order #9 - Transfer grill and Fans $986.00 Change Order #10 - (Rejected ) $0.00 Change Order #11 - Replace Toilets $752.00 Change Order #12R - Outside Repairs $17,983.00 Change Order #13 - Electrical Work $4,592.00 Change Order #14 - (Rejected -vents) $0.00 Change Order #15 - Life saftey $2,309.00 Change Order #16 (Rejected - addational Pating) $0.00 Change Order #17 - Carpet Installation -$530.00 Change Order #18 - wood work $295.00 Total: $43,770.00 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75 DocuSign Envelope ID: AD739F8A-DC0E-420A-8A82-5B83E8828F75