August 11, 2020
Mr. Robert Williams
Solid Waste Director
Orange County Solid Waste Management
PO Box 17177
Chapel Hill, NC 27516-7177
Re: Eubanks Road C&D Landfill, Permit No. 68-04
Proposal for Permit to Construct, Phase 2 and 3
DAA #R00592-226N
Dear Mr. Williams:
This letter is to serve as our work order request for the subject task. A scope of work and
fee proposal is presented below.
1.0 INTRODUCTION
Orange County (County) has requested a proposal to prepare and submit the permit
application to construct Phases 2 and 3 of the Eubanks Road C&D Landfill. Draper Aden
Associates (DAA) will prepare and submit a permit request to the North Carolina Department of
Environmental Quality (NCDEQ) in accordance with Rule .1603(a)(2). Current permit drawings
and reports prepared by Draper Aden Associates in 2017 and 2019 will be utilized. Draper Aden
Associates will update permit documents needed for the permit submittal and will update
drawings based on the recent 2020 topographic survey. The following discussion presents a
scope description and a not-to-exceed fee proposal for the work necessary to prepare and
submit the permit renewal request.
Work will be conducted in accordance with this proposal and the existing contract
between Orange County, hereinafter referenced as "County", and Draper Aden Associates,
hereinafter referenced as "Engineer".
2.0 BASE SCOPE OF SERVICES
2.1 Permit to Construct Application: DAA will assist the County in preparing and submitting
a permit to construct request to the NCDEQ to construct Phases 2 and 3 of the C&D
Landfill. The permit request will include the following:
DocuSign Envelope ID: D2193F1C-ECD7-4E1F-86D9-499117BF12A2
Robert Williams – PTO for C&D Phase 2 & 3
August 11, 2020
Page 2 of 7
P:\R00\500\R00592\R00592-226N\PROPOSAL-CONTACT\PRO Williams- C&D Ph 2&3 PTC - CTC Jr.docx
Facility Plan to update information regarding waste stream, remaining capacity, and
other pertinent data;
Engineering Plan including facility standards, design calculations and technical
specifications;
Construction Quality Assurance Plan;
Operations Report including waste screening plan, inspection forms, and monitoring
plan;
Closure and Post-Closure Plan:
DAA will meet in person or teleconference with NCDEQ to address any review comments
that may be received.
2.2 Design/Construction Drawings: DAA will develop a set of permit drawings per the
original permit and update to permit drawings to indicate current operational areas and
to reflect proposed grading for the construction of Phase 2 and 3. It is assumed the
drawings will include the following sheets:
Cover sheet
Existing conditions
Overall Facility Plan
Phase 2 Base Grades
Phase 3 Base Grades
Phase 3 Final Grades
Details
2.3 Design Hydrogeologic Memorandum: DAA will generate a design hydrogeologic
memorandum to be attached to the Permit to Construct application. The memorandum
will use previous existing field studies and data collected since 1999 for the various permit
applications, groundwater monitoring plans, and hydrogeologic studies conducted by
DAA and other consultants. No additional filed studies, groundwater readings, borings,
or lab testing are to be completed.
2.4 Project Bid Manual and Contract Documents: DAA will prepare a project manual,
contract documents, final construction drawings, and technical specifications to be
advertised by the County for bids. DAA will finalize the construction drawing set (100%
design) by incorporating comments from previous reviews. DAA will incorporate the
project special provisions, bid tabulation, and the front-end and standard technical
specifications, and will prepare the final bid package project manual. The County will be
responsible for cost of advertising and bidding the project. DAA will assist the County in
DocuSign Envelope ID: D2193F1C-ECD7-4E1F-86D9-499117BF12A2
Robert Williams – PTO for C&D Phase 2 & 3
August 11, 2020
Page 3 of 7
P:\R00\500\R00592\R00592-226N\PROPOSAL-CONTACT\PRO Williams- C&D Ph 2&3 PTC - CTC Jr.docx
advertising the project for bid. Deliverables will include a project manual (Front End and
Technical Specifications) and final construction drawings.
2.5 Bid Administration: DAA will assist the County in advertising the project for bid, assist
in conducting a bid opening, evaluate the bids received, and make a recommendation of
award to the County. If appropriate, DAA will assist in negotiations with the low bidder.
Upon Award of the Bid by the County, DAA will prepare and assist in proper execution of
the contract documents, respond to contractors’ questions, provide input for addenda (if
required), and provide technical support through the contracting process. DAA will assist
the County in obtaining and reviewing construction contract documentation and other
preliminary actions through issuance of formal Notice-to-Proceed.
2.6 Construction Services/CQA Inspections: During construction, we will assist the County in
administration of the construction agreement between the County and Contractor. We will
provide services to include the following:
participation in a pre-construction meeting and other periodic project meetings (typically
weekly while site work is ongoing) to review construction progress
issue record of meetings
Implementation of the CQA plan to include:
a. site visits to inspect the work including reporting of observations and
recommendations regarding suitability of the work and schedule progress
b. testing of soils and aggregate as prescribed in the project CQA Plan
review of shop drawings for site-related materials and maintenance of a shop drawing log
interpretations in writing or in the form of supplemental drawings necessary for performance
of the work
review of contractor payment applications and recommendations for payment
preparation of change orders and construction change directives
conduct inspections and punch lists as part of final project close-out
request and assemble final written guarantees, affidavits and other contract closeout
documents from the Contractor prior to approval of final payment to the Contractor
preparation of as-built, or record drawings based on Contractor mark-ups
Final certification inspection by a PE and PG per NCDEQ rules.
serve as agent of the County as described in the contract documents
This proposal is based on an estimated 60 calendar day period of construction activities that
require daily oversight or testing. Inspections are assumed to be part time and limited to
a maximum 6 hours onsite per day average. Due to the nature of the services under this task,
it will be billed on a time and material basis.
DocuSign Envelope ID: D2193F1C-ECD7-4E1F-86D9-499117BF12A2
Robert Williams – PTO for C&D Phase 2 & 3
August 11, 2020
Page 4 of 7
P:\R00\500\R00592\R00592-226N\PROPOSAL-CONTACT\PRO Williams- C&D Ph 2&3 PTC - CTC Jr.docx
3.0 DELIVERABLES
DAA shall provide one set of draft drawings and reports (Facility Plan, Engineering Plan,
Construction QA Plan, Operations Report, Closure and Post-Closure Plan) for review by the
County. The Engineer shall incorporate comments received from the County into a final package.
The final Permit to Construct application (drawings and reports) shall be submitted to the NCDEQ
and a copy shall be submitted to the County.
In addition, DAA will prepare final Contract and Construction Documents for use in
obtaining bids and for use in construction of the project.
4.0 EXCLUSIONS
For services not expressly set forth in writing in this proposed scope, or signed
attachments to this proposal, the Engineer assumes no duty to the County to perform such
additional services.
5.0 ASSUMPTIONS/CONDITIONS
The Scope of Services presented in Section 2.0 is based upon the following assumptions
and conditions.
Current topographic mapping performed by DAA in April 2020 will utilized as a basis
for design.
The Engineer will respond to NCDEQ comments arising from its initial review. NCDEQ
comments that require information beyond the scope of services of this proposal,
including requests by NCDEQ for additional information beyond this scope, will be
considered additional services.
The base liner system and closure cap design will remain the same as in the current
permit. Changes to the liner and cap design may be considered as additional services.
The County will be responsible for any fees paid to regulatory entities.
Local review or permits will not be required. The previous obtained Erosion and
Sediment Control Plan approval is still applicable and will not need updating.
Public meetings or hearings are not anticipated.
DocuSign Envelope ID: D2193F1C-ECD7-4E1F-86D9-499117BF12A2
Robert Williams – PTO for C&D Phase 2 & 3
August 11, 2020
Page 5 of 7
P:\R00\500\R00592\R00592-226N\PROPOSAL-CONTACT\PRO Williams- C&D Ph 2&3 PTC - CTC Jr.docx
6.0 SCHEDULE
The following task will be completed based on the anticipated schedule:
Submit PTO Permit Application Package for County Review August 14, 2020
Submit PTO Permit Application to NCDEQ August 18, 2020
Contract and Construction Documents ready for Bid September 18, 2020
Receive Bids October 15, 2020
Construction November 2020 – January 2021
Review timelines by NCDEQ or other review agencies are not guaranteed and may affect the
schedule presented above.
7.0 COMPENSATION
The actual cost of providing the services described above will be based either upon a
lump sum amount or upon time expended and materials (T&M) consumed. The County will not
be invoiced for T&M items below for time not expended or material not utilized. Invoices are
issued monthly and are due upon receipt. Standard DAA billing rates shall be used for billing
purposes.
TASK FEE
1 Permit to Operate Application & Report $ 13,000
2 Design/Construction Drawings $ 19,500
3 Design Hydrogeologic Memorandum $ 12,300
4 Project Manual/Contract Documents $ 8,700 5 Bid Administration Services $ 8,400 6 Construction Services/CQA Inspections $ 43,100 *
TOTAL $ 105,000
* Task 6 to be billed as T&M
7.0 TERMS AND CONDITIONS
The proposed services will be provided in accordance with the conditions presented
herein and an existing agreement between Draper Aden Associates and Orange County Solid
Waste Management. Depending upon the duration of the project and the contract date, the
unit rates used to prepare this estimate may be modified. Prior to any changes in the unit rates,
the County will be notified, and the modifications will be approved.
DocuSign Envelope ID: D2193F1C-ECD7-4E1F-86D9-499117BF12A2
Robert Williams – PTO for C&D Phase 2 & 3
August 11, 2020
Page 6 of 7
P:\R00\500\R00592\R00592-226N\PROPOSAL-CONTACT\PRO Williams- C&D Ph 2&3 PTC - CTC Jr.docx
We appreciate the opportunity to present this proposal to the County and look forward
to working on this task with you. If you have any questions, please contact us.
Sincerely,
DRAPER ADEN ASSOCIATES
C. Tyrus Clayton, Jr., PE
Principal/Regional Growth Leader
DocuSign Envelope ID: D2193F1C-ECD7-4E1F-86D9-499117BF12A2
Robert Williams – PTO for C&D Phase 2 & 3
August 11, 2020
Page 7 of 7
P:\R00\500\R00592\R00592-226N\PROPOSAL-CONTACT\PRO Williams- C&D Ph 2&3 PTC - CTC Jr.docx
Orange County Solid Waste
Eubanks Road C&D Landfill, Permit No. 68-04
Proposal for Permit to Construct, Phase 2 and 3
Draper Aden Associates Proposal No. R00592-226N
AUTHORIZATION TO PROCEED
______________________________________ ________________
Orange County Solid Waste Management Date
THIS INSTRUMENT HAS BEEN PRE-AUDITED IN THE MANNER REQUIRED BY THE LOCAL
GOVERNMENT BUDGET AND FISCAL CONTROL ACT:
______________________________________ ________________
Office of the Chief Financial Officer Date
THIS SCOPE OF WORK IS SUBMITTED PURSUANT TO THE TERMS OF THE AGREEMENT
DATED FEBRUARY 22, 2017
BETWEEN DRAPER ADEN ASSOCIATES AND ORANGE COUNTY.
__________________________________ _______________
C. Tyrus Clayton, Jr., PE Date
Principal
Draper Aden Associates