HomeMy WebLinkAboutORD-2021-020 Contract Approval for Southern Human Services Center Roof and HVAC Replacement and Approval of Budget Amendment #14-B 1 ORD-2021-020 ORANGE COUNTY BOARD OF COMMISSIONERS ACTION AGENDA ITEM ABSTRACT Meeting Date: June 15, 2021 Action Agenda Item No. 8-o SUBJECT: Contract Approval for Southern Human Services Center Roof and HVAC Replacement and Approval of Budget Amendment #14-B DEPARTMENT: Asset Management Services (AMS) ATTACHMENT(S): INFORMATION CONTACT: Angel Barnes, 919.245.2628 Steven Arndt, 919.245.2658 Gary Donaldson, 919.245.2453 PURPOSE: To: 1) Approve a construction contract with Riggs-Harrod Builders, Inc. for the replacement of the existing roofing system and Heating, Ventilation, and Air Conditioning (HVAC) equipment at the Southern Human Services Center; 2) Authorize the County Manager to execute the Agreement and to execute any subsequent amendments for contingent and unforeseen requirements up to the approved budget amount on behalf of the Board, upon final County Attorney review; and 3) Approve Budget Amendment #14-B. BACKGROUND: In Fiscal Year (FY) 2019-2020, the Orange County Board of County Commissioners (BOCC) approved the HVAC equipment replacement and, in FY2020-2021 , approved the replacement of the existing roof system for the Southern Human Services Center building. The existing roof and HVAC systems are both greater than 20 years old, and in poor/failing condition. In April 2020, Orange County received a completed Feasibility Study for the Roof and HVAC systems. The Roof Feasibility Study confirmed that the roof was in need of replacement and recommended some repairs for immediate action until the replacement could be scheduled. The HVAC Feasibility Study recommended replacing the existing equipment with like in kind, but also recommended upgrading the pneumatic devices and controls with Direct Digital Controls. FINANCIAL IMPACT: The construction contract with Riggs-Harrod Builders, Inc. is a not-to- exceed amount of $1,348,479. This budget amendment also allows for additional funding of $208,450, which is over and above the construction contract, to cover the upgrade of the HVAC controls from pneumatic to Direct Digital Controls to meet the energy efficiencies and code requirements. The total costs of the project, including the upgrade to the HVAC controls, is $1,556,929. To cover the increased costs of the HVAC project costs, including the controls upgrade, staff is recommending transferring $674,629 from the Information Technologies Capital 2 Project. These funds from the Information Technologies Capital Project were part of the Spring 2021 financing package, but are eligible for the use of available American Rescue Plan Act (ARPA) funds, so the source of funds is being substituted, and the financing proceeds will be used to cover the HVAC and controls cost. This budget amendment provides for the use of ARPA funds in the Information Technologies Project, provides for the transfer of financing proceeds, and amends the following Capital Project Ordinances: Information Technologies Project(Net Change of$0)— Project#30007 Revenues for this project: Current Budget FY 2020-21 FY 2020-21 FY 2020-21 Amendment Revised Budget Alternative Financing $12,273,245 $674,629 $11,598,616 ARPA Funds $0 $674,629 $674,629 From General Fund $1,595,257 $0 $1,595,257 From County Capital $200,000 $0 $200,000 Total Project Funding $14,068,502 $0 $14,068,502 Appropriated for this project: Current Budget FY 2020-21 FY 2020-21 FY 2020-21 Amendment Revised Budget Information Technologies $14,068,502 $0 $14,068,502 Project Total Costs $14,068,502 $0 $14,068,502 HVAC Projects ($674,629) — Project#30018 Revenues for this project: Current Budget FY 2020-21 FY 2020-21 FY 2020-21 Amendment Revised Budget Alternative Financing $3,670,200 $674,629 $4,344,829 From General Fund $589,723 $0 $589,723 Total Project Funding $4,259,923 $674.629 $4,934,552 Appropriated for this project: Current Budget FY 2020-21 FY 2020-21 FY 2020-21 Amendment Revised Budget HVAC Projects $4,259,923 $674.629 $4,934,552 Total Costs $4,259,923 $674.629 $4,934,552 SOCIAL JUSTICE IMPACT: The following Orange County Social Justice Goals are applicable to this item: • GOAL: CREATE A SAFE COMMUNITY The reduction of risks from vehicle/traffic accidents, childhood and senior injuries, gang activity, substance abuse and domestic violence. • GOAL: ENABLE FULL CIVIC PARTICIPATION Ensure that Orange County residents are able to engage government through voting and volunteering by eliminating disparities in participation and barriers to participation. Replacement of the building roof system and HVAC equipment will create a safe working environment for staff. 3 ENVIRONMENTAL IMPACT: The following Orange County Environmental Responsibility Goal impact is applicable to this item: • ENERGY EFFICIENCY AND WASTE REDUCTION Initiate policies and programs that: 1) conserve energy; 2) reduce resource consumption; 3) increase the use of recycled and renewable resources; and 4) minimize waste stream impacts on the environment. RECOMMENDATION(S): The Manager recommends that the Board: 1) Authorize Orange County to enter into a Construction Agreement with Riggs-Harrod Builders, Inc. for the replacement of the existing roofing system and Heating, Ventilation, and Air Conditioning (HVAC) equipment at the Southern Human Services Center; 2) Authorize the County Manager to execute the Agreement and to execute any subsequent amendments for contingent and unforeseen requirements up to the approved budget amount on behalf of the Board, upon final County Attorney review; and 3) Approve Budget Amendment #14-B.