HomeMy WebLinkAbout2021-313-Planning-Renaissance Planning Group-Contract Amendment #1v 0.1
NORTH CAROLINA
CONTRACT AMENDMENT #1
ORANGE COUNTY
THIS FIRST CONTRACT AMENDMENT (“Amendment”) is made and entered into this 1st day of June, 2021 by and
between ORANGE COUNTY (hereinafter referred to as “County”) and Renaissance Planning Group, Inc., (hereinafter
referred to as “Consultant”).
WITNESSETH:
THAT WHEREAS, the County and Consultant entered into a contract dated March 24, 2020, (hereinafter the “Original
Agreement”), for the provision of services for updating the 2017 Orange County Transit Plan with an internal
designation of 2020-214-E; and
WHEREAS, the County and Consultant desire to amend the Original Agreement while keeping in effect all terms and
conditions of the Original Agreement not inconsistent with the terms and conditions set forth below.
NOW THEREFORE, for and in consideration of the mutual covenants and agreements made herein, the parties agree to
amend the Original Agreement as follows:
1.Attachments A “Task List and Milestone Dates” and B “Pay Schedule” shall be replaced in their entirety with
Attachments A2 “First Update to Task List and Milestone Dates” and B2 “First Update to Pay Schedule”.
2.The compensation for the additional work included in this Amendment shall be eight thousand four hundred
and six dollars ($8,406.00). Article 5 of the Original Agreement is amended to reflect a maximum payable
not-to-exceed amount of two hundred ninety five thousand six hundred and twenty four dollars
($295,624.00).
3.Except for the changes made herein, the Original Agreement shall remain in full force and effect to the extent
it is not inconsistent with this Amendment. In the event there is a conflict between the terms of the Original
Agreement and the terms of this Amendment, this Amendment shall control.
IN TESTIMONY WHEREOF, this Amendment has been executed by the parties hereto, as of the date first above
written.
ORANGE COUNTY CONSULTANT
______________________________ __________________________________
Bonnie Hammersley Daniel Hardy, P.E. PTP
County Manager Principal in Charge
DocuSign Envelope ID: C7BE3DD6-9CBE-4401-AF7E-6829845BD7B9
5/28/20216/2/2021
v 0.1
ORANGE COUNTY—DEPARTMENT USE ONLY
______________________________________________________________________________
Party/Vendor Name: Renaissance Planning Group, Inc. Party/Vendor Contact Person: Caroline Dwyer Contact Phone: 919-636-
5032 Party/Vendor Address: 316 Holland St. City Durham State: NC Zip: 27701 Department: Planning and Inspections Amount:
$8,406 Purpose: Contract Amendment #1 Budget Code(s): 10695020 720215 Vendor # 66034 (N/A if new vendor) Vendor is a
BOCC consultant? Yes No Contract Type: (Check one) New Renewal Amendment Effective Date 6/1/21
Approved by Board Yes No Agenda Date: N/A
This agreement is approved as to technical form and content and I as Department Director affirmatively state work on this project has
not been initiated prior to execution of the agreement:
Department Director’s Signature ________________________________________ Date: ________
Agreements for emergency services or repair are not subject to the above affirmation. If services related to this agreement have
already begun or been completed please briefly describe the nature of the emergency condition that was addressed:
Information Technologies
(Applicable only to hardware/software purchases or related services) This agreement has been reviewed and is approved as to
information technology content and specifications:
Office of the Chief Information Officer___________________________________ Date: ________
Risk Management
This agreement is approved for sufficiency of insurance standards, specifications, and requirements:
Office of the Risk Management Officer___________________________________ Date: _________
Financial Services
This instrument has been pre-audited in the manner required by the Local Government Budget and Fiscal Control Act:
Office of the Chief Financial Officer ____________________________________ Date: _________
Legal Services
This agreement is approved as to legal form and sufficiency:
Office of the County Attorney __________________________________________Date: ________
Clerk to the Board
Received for record retention:
All Docusign contracts must be copied to the Clerk upon completion: occlerkdocs@orangecountync.gov
The following signature block is for hard copies only and is not required for Docusign contracts:
Office of the Clerk to the Board __________________________________________Date:_________
DocuSign Envelope ID: C7BE3DD6-9CBE-4401-AF7E-6829845BD7B9
6/1/2021
6/2/2021
6/2/2021
6/2/2021
Attachment A2
UPDATED SCOPE OF WORK AND MILESTONE DELIVERABLE SCHEDULE
The Work Plan in the January 6, 2020 Qualifications Statement from Renaissance Planning updated below, in
Attachment B and supplemented in Attachment C, will act as the formal contract work scope.
Task 1: Meetings and Presentations % of Task Total Completion Date
Task 1A: 5 staff meetings (Phase 1) 17% 8/1/2020
Task 1B: 5 staff meetings (Phase 2) 17% 2/1/2021
Task 1C: 3 board meetings 10% 10/1/2020
Task 1D: 3 board meetings 10% 2/1/2021
Task 1E: 4 stakeholder presentations (final plan) to local governments:
Chapel Hill, Carrboro, Hillsborough and Orange County 14% 9/30/2021
Task 1F: 5 additional Policy Steering Committee (PSC) Meetings 18% 9/30/2021
Task 1G: 4 additional Board meetings 14% 9/30/2021
Task 2: Transit Choices Brochure and Regional Connections Opportunities (RCO) Report
Task 2A: TCB annotated outline 10% 5/1/2020
Task 2B: TCB draft 30% 6/1/2020
Task 2C: TCB final 10% 7/15/2020
Task 2D: RCO annotated outline 10% 5/1/2020
Task 2E: RCO draft 30% 6/1/2020
Task 2F: RCO final 10% 7/15/2020
Task 3: Public Engagement Round 1
Task 3A: Draft public engagement plan 10% 4/30/2020
Task 3B: Final public engagement plan 10% 5/15/2020
Task 3C: Transit summit draft materials and event preparation 35% 6/15/2020
Task 3D: Delivery of transit summit 35% 6/15/2020
Task 3E: Memo - key themes 10% 6/15/2020
Task 4: Conceptual Transit Scenarios
Task 4A: Draft conceptual scenario maps/graphics 30% 1/31/2021
Task 4B: Final conceptual scenario maps/graphics 20% 5/31/2021
Task 4C: Conceptual scenario draft memo 30% 1/31/2021
Task 4D: Conceptual scenario final memo 20% 5/31/2021
Task 5: Balanced and Preferred Scenarios
Task 5A: Draft balanced and preferred scenarios maps/graphics 30% 7/9/2021
Task 5B: Final balanced and preferred scenarios maps/graphics 20% 7/16/2021
Task 5C: Balanced and preferred scenarios draft memo 30% 7/23/2021
Task 5D: Balanced and preferred scenarios final memo 20% 7/30/2021
Task 6: Public Engagement Round 2
Task 6A: Transit summit draft materials and event preparation 45% 6/30/2021
Task 6B: Delivery of transit summit 45% 6/17/2021
Task 6C: Memo - key themes 10% 6/30/2021
Task 7: Implementation Plan
Task 7A: Methodology memo 30% 8/6/2021
DocuSign Envelope ID: C7BE3DD6-9CBE-4401-AF7E-6829845BD7B9
Attachment A2
Task 7B: Draft implementation plan 60% 8/16/2021
Task 7C: Final implementation plan 10% 8/31/2021
Task 8: Final Report
Task 8A: Annotated outline and design template 20% 9/1/2021
Task 8B: Draft final report 70% 9/17/2021
Task 3C: Final final report 10% 9/30/2021
GRAND TOTAL
DocuSign Envelope ID: C7BE3DD6-9CBE-4401-AF7E-6829845BD7B9
Attachment B2
UPDATED PAY SCHEDULE
Billing will take place based on the completion of each sub-task from the below table.
Task 1: Meetings and Presentations Task Total: $ 27,088
Task 1A: 5 staff meetings (Phase 1) $ 4,670
Task 1B: 5 staff meetings (Phase 2) $ 4,670
Task 1C: 3 board meetings $ 2,803
Task 1D: 3 board meetings $ 2,803
Task 1E: 4 stakeholder presentations (final plan) to local governments:
Chapel Hill, Carrboro, Hillsborough and Orange County $ 3,736
Task 1F: 5 additional Policy Steering Committee (PSC) Meetings $ 4,670
Task 1G: 4 additional Board meetings $ 3,736
Task 2: Transit Choices Brochure (TCB) and Regional Connections Opportunities (RCO) Report Task Total: $55,077
Task 2A: TCB annotated outline $ 5,508
Task 2B: TCB draft $ 16,523
Task 2C: TCB final $ 5,508
Task 2D: RCO annotated outline $ 5,508
Task 2E: RCO draft $ 16,522
Task 2F: RCO final $ 5,508
Task 3: Public Engagement Round 1 Task Total: $45,081
Task 3A: Draft public engagement plan $ 4,508
Task 3B: Final public engagement plan $ 4,508
Task 3C: Transit summit draft materials and event preparation $ 15,778
Task 3D: Delivery of transit summit $ 15,779
Task 3E: Memo - key themes $ 4,508
Task 4: Conceptual Transit Scenarios Task Total: $20,753
Task 4A: Draft conceptual scenario maps/graphics $ 6,226
Task 4B: Final conceptual scenario maps/graphics $ 4,151
Task 4C: Conceptual scenario draft memo $ 6,225
Task 4D: Conceptual scenario final memo $ 4,151
Task 5: Balanced and Preferred Scenarios Task Total: $44,341
Task 5A: Draft balanced and preferred scenarios maps/graphics $ 13,302
Task 5B: Final balanced and preferred scenarios maps/graphics $ 8,869
Task 5C: Balanced and preferred scenarios draft memo $ 13,302
Task 5D: Balanced and preferred scenarios final memo $ 8,868
Task 6: Public Engagement Round 2 Task Total: $36,509
Task 6A: Transit summit draft materials and event preparation $ 16,429
Task 6B: Delivery of transit summit $ 16,429
Task 6C: Memo - key themes $ 3,651
Task 7: Implementation Plan Task Total: $38,835
Task 7A: Methodology memo $ 11,650
DocuSign Envelope ID: C7BE3DD6-9CBE-4401-AF7E-6829845BD7B9
Attachment B2
Task 7B: Draft implementation plan $ 23,300
Task 7C: Final implementation plan $ 3,885
Task 8: Final Report Task Total: $27,940
Task 8A: Annotated outline and design template $ 5,588
Task 8B: Draft final report $ 19,558
Task 3C: Final final report $ 2,794
GRAND TOTAL $ 295,624