HomeMy WebLinkAboutAgenda - 10-01-2003-8oORANGE COUNTY BOARD OF COMMISSIONERS ACTION AGENDA ITEM ABSTRACT Meeting Date: October 1, 2003 Action Agenda Item No. ~ '~ SUBJECT: Whiffed Human Services Center Renovation -Progress Report and Request for Authorization for Additional Debt Funding to Complete the Project DEPARTMENT: Public Works PUBLIC HEARING: (Y/N) No Purchasing & Central Services Budget ATTACHMENT(S): Attachment 1 - 5/16/03 Public Works INFORMATION CONTACT: Director Memo Wilbert McAdoo, extension 2625 Attachment 2 - 7/21/03 Public Works Pam Jones, extension 2650 Director Memo Donna Dean, extension 2151 Attachment 3 - 9/16/03 Change Order TELEPHONE NUMBERS: Summary Hillsborough 732-8181 Attachment 4 -WHSC Project Cost Chapel Hill 968-4501 Summary Durham 688-7331 Attachment 5 -WHSC Building Diagram Mebane 336-227-2031 PURPOSE: To discuss the status of the Whiffed Human Services Center (WHSC) renovation project and to request authorization for additional debt funding to complete the project. BACKGROUND: Renovations at the Whitted Center have progressed well since the Board last received a written update in July 2003. Work in the "B" Building as well as the Central Recreation Building has been completed. Renovations in the "A" Building are progressing. Basement level HVAC and electrical demolition work is complete and ductwork and lighting installation in the basement level of the building is approximately 95 percent complete. First floor HVAC and electrical demolition work is approximately 98 percent complete and ductwork and lighting installation in the first floor of the building is approximately 50 percent complete. Second floor HVAC and electrical demolition work is approximately 98 percent complete and ductwork and lighting installation in the second floor of the building is scheduled to begin in the next two weeks. As previously reported, over the course of the project, several hidden conditions were uncovered as the ceilings were removed to install the new ductwork. The accompanying memoranda from the County Public Works Director (Attachments 1 and 2) detail the additional work that was required in order to address these items, address life safety issues, as well as to bring the 70-year plus old building into closer compliance with the North Carolina Building Code. While the existing budget for the project has covered the cost of the substantial change orders (Attachment #3) required to address these issues (life safety, structural repairs, fire alarm 2 installation, bat guano eradication and asbestos abatement for example), funds are insufficient to complete the renovation work that was proposed to coincide with the HVAC replacement. The remaining renovation work, which basically includes painting and floor covering replacement for Building A is recommended for completion in conjunction with the HVAC project in order to avoid the repeated and significant disruption of operations in the building at a later date. The Board is requested to approve funding for this work and other expenses as cited under the Financial Impact section; and to authorize the Manager or his designee to award bids and execute the necessary paperwork, thereby allowing the project to continue within the timeframe that allows the occupants to return to the Whiffed Building as scheduled in December 2003. This is the same work that the Board authorized to be awarded during the summer break, however, the purchase orders were not executed pending completion of the structural work and subsequent assessment of the funding sufficiency. FINANCIAL IMPACT: The table below compares currently available revenue for the project with total projected project costs (see attachment #4 for additional detail). Staff estimates that an additional $475,000 will be needed to complete the project. Remaining work includes replacement of attic insulation (related to the bat guano abatement), painting, flooring and door/wall repairs and moving expenses. This renovation work will be completed in phases over the next few months as the HVAC contractors complete their portion of the work and clear the area. Materials to complete the work will be purchased directly by the County through existing State and GSA (federal government) contracts, thereby minimizing the County's overall costs. To the extent needed, labor will be bid for the various components, such as painting, installation of flooring, etc. Available funding for project $3,260,860 Anticipated roject expenditures $3,735,754 itiona un s ee a to omp ete Project $474,894 Last spring, the Board reviewed unfunded capital needs identified by County and school staffs. These were identified as high priority needs that should be addressed in the near future, but for which no specific funding source had been identified. Examples of this category of projects included renovations at the Northern Human Services Center and construction of a new Animal Shelter. Commissioners asked staff to assess how the unfunded projects might fit into the County's plans to seek loans from financial institutions over the next few years. That assessment will be presented to the Board at its October 27, 2003 work session on Capital Investment Plan issues. In the meantime, the estimated $475,000 needed to complete the Whitted Center renovation in a timely way should be added to the list of urgent but unfunded County capital improvements. Staff recommends that the Board indicate its intent to include $475,000 in additional funding for the Whiffed Center project, to be obtained through alternative financing. That authorization will permit staff to encumber and expend the additional funds required to complete flooring, painting, etc. Upon approval of this request for additional funding, staff will bring an updated Whiffed Human Services Center Capital Project Ordinance forward for Board approval. RECOMMENDATION (S): The Manager recommends that the Board: 1. Approve the expenditure of an additional $475,000 to cover costs associated with the completion of the Whiffed Center renovation; and 2. Direct staff to include this amount in the updated five year plan for the issuance of County bonds and alternative financing, to be presented during the October 27, 2003 Capital Investment Plan work session; and 3. Authorize the Manager or his designee to contract with vendors for the referenced renovation work (painting, flooring, etc) when that work exceeds the $20,000 threshold for Board approval, except that amounts exceeding $50,000 would need Board approval. 4 DATE: May 16, 2003 TO: John Link, County Manager FROM: Wilbert McAdoo, Public Works Director RE: RICHARD E. WHITTED HUMAN SERVICES RENOVATIONS/ UPDATE BACKGROUND The Richard E. Whiffed Human Services Center, a former high school, was acquired by the County from the Orange County school system in approximately 1975. Renovation plans were developed in 1978 to facilitate use primarily as office space, and health clinic areas. The recreation building was primarily maintained for recreation related activities, with establishment of a small suite of offices. Minor additional modifications have taken place over the years, primarily through subdivision of larger areas to create more private office space. The heating ventilation and air conditioning (HVAC) system installed at that time was primarily designed to minimize energy demand by severely limiting the intake of outside air which would require cooling during the hot summer months and heating during the cold winter months. Few changes had been made to the Whiffed Human Services Center since the original renovations. In 2002, the Board of County Commissioners approved replacement of the HVAC system in the Richard E. Whiffed Human Services Center, including the Central Recreation building. The project included removal of all existing acoustic the ceiling systems and lighting in conjunction with the HVAC replacement. In addition, new floor coverings and paint are being installed while spaces are vacated for the renovations. Additional extensive renovations were undertaken by the Health Department in the clinic areas to improve service delivery to the public. The bid from Environmental Air Systems of Greensboro, NC was accepted and work was initiated in August 2002. Work was phased as follows for completion: 1. Central Recreation Building 2. Boiler replacement 3. Richard E. Whiffed `B' Building (Health, DSS) 5 4. Replacement of cooling tower with chiller 5. Richard E. Whitted `A' Building (Library, DSS, Housing & CD, etc.) INTRODUCTION Central Recreation staff were temporarily relocated to space in the basement of the Whiffed `A' building, following relocation of Department on Aging staff to existing DOA facilities, and OPT staff to a modular office building located at the Public Works complex. The scope of work in the Central Recreation building included replacement of the existing HVAC system, as well as air conditioning the gymnasium, which had previously been unconditioned space. All existing acoustic the ceilings and lights were replaced, and some additional lighting was installed, especially on the building exterior. Also included was removal of all asbestos composition floor the (ACT) throughout the building. Lobby and corridor areas and Activity Area 3 were replaced with rubber floor tile. Activity Area 1 was replaced with linoleum the and the office areas were replaced with carpet tile. All areas were painted including the entire gymnasium. Simultaneously with Recreation Building renovations, the boiler located in the mechanical room (`A' building basement), was replaced and brought on-line in November 2000. Work in the Central Recreation Building was completed, and the building reoccupied in December 2002. During the renovations in the `B' building, Health Department staff were relocated to areas in the `A' building basement, a modular health clinic building on the site of the deconstructed former Orange Industries building, leased dental clinic and offices and other remote locations. DSS staff were primarily relocated to the `A' building basement and Southern Human Services Center. The scope of work for the `B' building included replacement of the existing HVAC system, replacement of acoustic the ceilings and lights, painting and replacement of data lines on all three floors. On the First and Second floors, wood tongue and groove flooring was refinished in several office areas, while rubber the was installed in corridors. Rubber floor the and sheet vinyl 6 designed for medical facilities was installed throughout the basement level (clinic area). In addition, the Health Department incorporated significant modifications to the clinic area, including creation of new exam rooms and offices and improvements in others. Installation of a new high-density file system for DSS was also incorporated into the renovation project. Simultaneously with `B' building renovations, the cooling tower was replaced with a new chiller for provision of cooled air throughout the complex. The new chiller was brought on-line in April 2003 and is providing cooling for the Recreation and `B' buildings. Work in the `B' Building has also now been completed with the exception of minor "punchlist" items, with Health and DSS reoccupying the building in the first weeks of May 2003. The scope of work for the `B' building renovations had to be expanded once ceilings were removed and non-compliant items (structural and fire code related) were exposed. Other changes were identified by the Inspections department and the fire marshal related to modern fire code, life safety and Americans with Disabilities Act (ADA) compliance (fire doors, handrails in stairwells, etc.). The cost of these repairs was approximately $100, 000. CURRENT STATUS The contractors have moved operations to the `A' building as it was vacated. Health Department administrative staff were returned from the `A' building and other remote locations to their permanent offices in the `B' building. Clinic staff have been returned from the modular clinic to the renovated `B' building clinic. Dental clinic staff will return to the `B' building the week of May 19. DSS staff have been returned from the `A' building. In addition, DSS staff normally located in the `A' building have "doubled up" in `B' building offices, including several 'offices "on loan" from the Health Department while `A' building renovations are completed, and others have been temporarily relocated to the Southern Human Services Center. A temporary "mini Library" has been established in the modular building on the former Orange Industries building site, with the majority of books having been placed in storage during this phase of the renovations. Housing and Community Development staff have also been stationed in the modular building. As in the `B' building, the scope of work includes replacement of the entire HVAC system, acoustic the ceilings and lights, installation of new data lines, replacement of flooring and painting. As acoustical the ceiling was removed in REWHS A Building, the contractor discovered hidden conditions which requires additional repairs. These conditions include the removal of load bearing support walls, columns and structural members. The majority of these conditions originate from the 1978 renovation project. Additionally there are some fire code/life safety issues that must be addressed. Public Works is working with the inspections department, the fire marshal and the consulting engineer to determine the scope of the repairs and the associated cost. 8 DATE: July 21, 2003 TO: John Link, County Manager FROM: Wilbert McAdoo, Public Works Director RE: RICHARD E. WHITTED HUMAN SERVICES RENOVATIONS/ UPDATE The renovation work at REWHS A Building is progressing. The HVAC and electrical demolition work is 95 % complete. The asbestos abatement project for the floor the in the basement level is complete. The bat guano abatement project is complete. The basement level new ductwork is 75% complete. On May 20, 2003, The Orange County Board of Commissioners authorized the manager to approve and staff to execute any change orders, not to exceed a cumulative total of $100,000 that may become necessary through August 19, 2003. The staff communicated that we would provide the BOCC with a written report on the nature and scope upon the manager's approval of such change orders. As the drop ceilings were removed we discovered 4 hidden structural conditions, which required change orders to address. The first condition relates to the structural problems mentioned in the May 16, 2003 memorandum from Public Works Director, Wilbert McAdoo re: Richard E. Whiffed Human Services /Update. Bilger Engineering inspected the roof and ceiling structure and identified failed or inadequate structural elements in four different areas. Bilger Engineering conducted inspections performed analysis and developed drawings and specifications to correct the structural problems. The work includes: 1. In the area above the main library where the stacks are located, the work involves the replacement of 2 wood roof truss, repair to ceiling joist, installation of roof drains and removal of plaster and replacement with drywall. 2. In the front section of the library, wood joist, wood beams and wood bearing walls that support the office area in several locations do not have adequate support. In all these locations new 2X12 wood beams will be installed 9 3. Above the main floor level in the office area adjacent to the library, a support beam need to be shored up and repair of a masonry chase. 4. On the second floor a 2x8 ceiling joist was cut to accommodate a plumbing pipe and must be repaired. The area will be returned to the original position and new wood support added. Environmental Air Systems developed a change order request in the amount of $56,017.00 for the above-described work, which was approved by Orange County staff on July 16, 2003. Once dropped ceilings were removed, Environmental Air Systems identified materials that could contain asbestos and requested that testing be conducted on those materials. The materials identified were 12x12 ceiling tiles; ceiling the glue; drywall joint compound; brick mortar; and wall plaster. Quantum Environmental conducted a limited asbestos building inspection of the REWHS Center and prepared a report. The purpose of the inspection was to identify remaining asbestos-containing materials on the project site. The only material that contained asbestos was of the non-friable type in the ceiling the glue at levels between 3% and 5%. The area where the glue for the ceiling tiles is located is mainly in the corridors and stairwell and limited amounts in the space previously occupied by Adult Day Treatment. The glue is above the ceiling the and requires the removal and disposal of the ceiling the and unfastening and support of conduit piping and electrical wiring to access the glue. Additionally, the second floor corridor has an additional layer of drywall below the 12x12 ceiling the and glue that must be removed and replaced. Environmental Air Systems solicited a proposal from PCS Inc. an asbestos abatement contractor and provided a change order for asbestos ceiling the glue removal and associated work in the amount of $33,465.00. Orange County staff approved a change order in the amount of $33,465.00 on July 16, 2003. The total amount of change orders during this period is $89,482.00. The approval of these change orders will allow the project to continue without disruption and allow for continued progress toward completion. 10 To: Donna Dean, Budget Director From: Wilbert McAdoo, Public Works Director Date: September 16, 2003 Re: Environmental Air Systems, Inc. (EAS) change orders HVAC Systems Replacement CO #l: Furnish and install an energy management control system as manufactured and installed by Siemens Technology. Amount: $75,000.00 dated 1/6/03 CO #2: Exterior lighting changes on the Recreation Building to provide photocell control of the outdoor lights as outdoor lighting control does not exist in the Recreation Building Amount: $3364.00 dated 1/29/03 CO #3: Install one additional category SE data cable to each location shown on drawings to receive data outlet. All cabling is to be terminated and tested to BICSI standards and results provided on disc. Amount: $20562.00 dated 1/29/03 CO #4: Repair of the drywall ceiling to restore fire separation on level 1 and 2 of the "B" Building, and upgrades of electrical distribution system involving removal of PVC conduit installed in the return air plenum on level 1 of "B" Building. Life safety to comply with Orange County Building Inspections code requirements. Amount: $15240.00 dated 2/3/03 CO #5: Installation of fifty additional data outlets in Building "B" as requested by :Dick Taylor. Installation of a 2" conduit into the telecommunications room in Building "A" as requested by Dick Taylor. $9665.00 dated 2/25/03 CO #6: Modifications for the Dental Lab to conform to the requirements of the Patterson Dental Supply, Inc. drawings 1 & 2 dated 1/24/03 Modifications for the Health Dept requested by Owner as outlined in the Corley Redfoot Zack, Inc Project instructions dated 3/3/2003 and as discussed in job meetings on 3/13/03 and 3/19/03. Amount: $17784.00 11 CO #7: Modifications outlined in RNM field report dated March 2, 2003, RNM supplemental fire alarm drawings #FA1-FAS dated March 14, 2003, and structural repairs outlined in Bilger Engineering sketches dated February 22, 2003 and March 8, 2003. Modifications are required by the County of Orange Buildings Inspections department, for the purpose of improving the egress capability of the facility in the event of a fire, and the structural integrity of the buildings Amount: $90550.00 dated 4/8/03 CO #8: Additional fire alarm system devices as required by the County of Orange Buildings Inspections Dept. for final approval. Concrete slab repair in "B" Building. Amount: $4792.00 dated 6/30/03 CO #9: Environmental Air Systems & Evans Electric has proceeded as directed to bring the existing electrical distribution system into code compliance. Most if not all of this work has been completed. Upgrade the battery pack on the fire alarm panel as opposed to replacing the existing panel as recommended on COR 13, which this proposal replaces. Furnish & install the necessary telephone cable & outlets for Building "A" Amount: $50296.00 dated 6/30/03 CO #10: Structural repairs as outlined in the July 4, 2003 memo from Bilger Engineering, to repair damaged ceiling /roof structure over the Library Amount: $56254.00 dated 7/28/03 CO #1 l: Building A ceiling the glue/adhesive asbestos abatement as outlined in Power Component Systems, Inc July 11, 2003 quotation and Associated Air Rary. Monitoring services as outlined in EI Inc. July 23, 2003 quotation. Amount: $36,659.00 dated 8/7/03 CO #12: Removal of plaster lath from the second floor corridor ceiling, resulting from the ceiling the glue/adhesive removal, as described in Tide-Up Construction Company, Inc August 7, 2003 proposal Amount $3500.00 dated 8/14/03 CO #13: Additional work associated with the drywall & structural changes to Building "A"EAS proceeded with covering the overhead wood structure in the main entrance to the Library with drywall where plaster lath was removed. Amount: $2020.00 dated 9/2/03 Total Amount of Change Orders To Date: $385,686.00 12 Whitted Human Services Center Project Cost Summary Project Total Original Expenditures 8~ Estimated Estimated Project Encumbrances to Expenditures Project Category Estimates Date To Complete Costs Heating, Ventilation & Air Conditioning (HVAC); Data Wiring and Health Clinic Renovations Original Contract $2,328,874 $2,328,874 $0 $2,328,874 Change Orders to Date $0 $385,700 $0 $385,700 Professional Fees for Engineering and Design $175,540 $184,610 $0 $184,610 Asbestos Abatement $20,865 $0 $20,865 Bat Guano Abatement $0 $62,250 $0 $62,250 Painting and Flooring $500,000 $160,455 $283,000 $443,455 Moving Expenses $0 $0 $180,000 $180,000 Insulation $0 $0 $30,000 $30,000 Contingency $51,000 $0 $100,000 $100,000 Total Estimated Project Costs $3,055,414 $3,142,754 $593,000 $3,735,754 Funding Available for Project $3,260,860 $3,260,860 Difference in Available Funding and Estimated Project Costs ($474,894) NOTES: Change orders include structural repairs, life safety requirements W J a a U W V W Z Q 2 D H H 'S w 0 Q ~-+ ~ ~ •- ~j m m c ~ o ~] ~ ~ ~ Z . ~ V ._ V V ~ Q ~ _ ~ ~- ~ ~~ ~S m .~.~ L .F.+ 0 1