DATE: October 6, 2020
TO: Board of County Commissioners
FROM: Gary Donaldson, CFO
RE: 2016 School Bond Projects
There was a Board request to include the referenced subject as an Information Item for the
October 6, 2020 Virtual Business Meeting records.
Please note, this is the same School bond projects summary provided at the September 24, 2020
Joint BOCC/Schools meeting. There will be quarterly updates as to the status of the 2016 School
bond projects.
Cc: Bonnie Hammersley, County Manager
Attachments
2
Chapel Hill-Carrboro City Schools 2016 Bond Issuance Projects Update
Projected Actual(as of
Completion Date Current Approved August 31,
Project Project Status of All Projects Budget 2020) Available
Building A and Building D(new buildings)-Final stages;awaiting
occupancy permits
Building E(CTE)-Ongoing;expected 10/15
Chapel Hill High School Building B,C(existing)-Ongoing renovations
Demolition Old Building A(main bldg)-Ongoing w/scheduled Substantial
demo removal by 11/15 Completion
Student Parking Lot(new)-Scheduled by December 31st scheduled for
Substantial completion:January 15th 1/15/2021 $ 68,000,000 $ 58,020,144 $ 9,979,856
Project on hold. Fund expenditures were completed for design
Lincoln Center Conversion fees.Requested transfer of the remaining funds for the completion
of the Chapel Hill High School project. No new status $ 1,436,000 $ 796,868 $ 639,132
These Preliminary Planning Funds were provided to CHCCS as part
of the FY 2015-16 CIP to be"shovel'ready"for a project or
Preliminary Planning Funds projects;these funds would be reimbursed from approved Bond
Referendum funds $ 750,000 $ 750,000 $ -
Total Bonds Issued to Date
$ 70,186,000 $ 59,567,012 $ 10,618,988
Bonds Yet to Be Issued Scheduled Final Tranche of 2016 Bond Funds in FY 2021-22
$ 1,922,000
Grand Total of 2016 Bonds
$ 72,108,000
3
Chapel Hill High School/Lincoln Center Projects (Major Facility Renovations project in CIP)
Project Original Budget Revised Budget Actuals* Balance Remaining Notes
Chapel Hill High School 68,000,000 68,000,000 58,020,144 9,979,856 Bond Funds
CHHS-Major Renovations -this amount not included in Combined Bond Project
600,900 598,478 598,478 - Older Facilities Funding
Totals Below
Total 68,600,900 68,598,478 58,618,622 9,979,856
Available Funds(Capital Reserve Funds):
Lincoln Center Conversion 1,436,000 1,436,000 796,868 639,132 Bond Funds
Major Facility Renovations 1,724,900 1,733,892 - 1,733,892 All in a Contingency account
Total 3,160,900 3,169,892 796,868 29373,024
Grand Total-Major Facility Renovations 71,761,800 71,7689370 59,415,490 12,352,880
Actuals as of Munis Report through 8131120
Total Exps(est.
Combined Bond Projects: by CHCCS)
Chapel Hill High School Project 74,168,678
Lincoln Center Project(includes$750K in Preliminary Planning Exps) 1,546,868
Total 75,715,546
Total Revs(est.
by CHCCS)
Bond Funds-Chapel Hill High School 68,000,000
Bond Funds Used-Lincoln Center 796,868
Apply Unused Bond Funds from Lincoln Center towards the CHHS Project 639,132
Advanced Preliminary Planning Funds-Bond Funds 750,000
Final Tranche of 2016 Bond Funds in FY 2021-22 1,922,000
Total 2016 Bond Funds 72,108,000
Estimated Sales Tax Reimbursements 1,200,000
Use of Available Contingency Funds-Major Facility Renovations Project(53053) 1,733,892
75,041,892
Surplus/(Deficit) (673,654)
Deficit to be Covered with available School Capital Outlay Fund Balance-CHCCS 673,654
Surplus/(Deficit) 0
4
Orange County Schools 2016 Bond Issuance Projects Update
Projected Actual(as of
Completion Date Current Approved August 31,
Project Project Status of All Projects Budget 2020) Available
ALS-have started last phase;CP-completed in 2019;CE-will be
Roofing Projects completed this year;GAB-completed in 2020;OHS-assessing
final phase; 22-Dec $ 4,056,993 $ 1,072,934 $ 2,984,059
Property Acquisition Completed/occupied January 2020
Jan-20 $ 3,100,000 $ 3,104,353 $ (4,353)
Cedar Ridge High School Addition on schedule for completion in January 2021;within budget
tan-21 $ 14,500,000 $ 8,198,106 $ 6,301,894
OHS 98%completed;beginning CRHS. Will then move to middle
School Safety/Security schools: ALS,GHMS,CW Stanford. Elementary schools to follow
based on completion of the vestibule projects Projected
completion all schools--January 2021 Jan-21 $ 2,500,000 $ 12,550 $ 2,487,450
Design assessment completed on six schools: Central Elementary,
AL Stanback middle,New Hope Elementary,Hillsborough
Elementary(specific buildings),Grady Brown Elementary and Work to continue
Efland Cheeks Elementary;schools prioritized according to during summers for
Mechanical Systems greatest need;Central Elementary design nearing completion with at least next three
bid date projected during Q1 2021. ALS projected thereafter. years.
SOW exceeds funding so prioritization will continue in order to
maximize available funds.
$ 10,871,007 $ 9,341,369 $ 1,529,638
Two phase project at CP. Phase I anticipated to be completed
10.2020.Phase 11 anticipated completion August 2021. Phase 11
Classroom/Building Improvements SOW anticipated to exceed funding so prioritization will continue
in order to maximize available funds. 21-Aug $ 1,000,000 $ 72,607 $ 927,393
These Preliminary Planning Funds were provided to OCS as part of
the FY 2015-16 CIP to be"shovel'ready"for a project or projects;
Preliminary Planning Funds these funds would be reimbursed from approved Bond
Referendum funds $ 478,000 $ 478,000 $ -
Total Bonds Issued to Date
$ 36,506,000 $ 22,279,919 $ 14,226,081
Bonds Yet to Be Issued Scheduled Final Tranche of 2016 Bond Funds in FY 2021-22
$ 11,386,000
Grand Total of 2016 Bonds
$ 47,892,000
5
Orange County Schools 2016 Bond Projects
Project Original Budget Revised Budget Actuals* Balance Remaining Notes
Roofing Projects 4,056,993 4,056,993 1,072,934 2,984,059 Bond Funds
Property Acquisition 3,100,000 3,100,000 3,104,353 (4,353) Bond Funds
Cedar Ridge High School Addition 14,500,000 14,500,000 8,198,106 6,301,894 Bond Funds
School Safety/Security 2,500,000 2,500,000 12,550 2,487,450 Bond Funds
Mechanical Systems 10,871,007 10,871,007 9,341,369 1,529,638 Bond Funds
Classroom/Building Improvements 1,000,000 1,000,000 72,607 927,393 Bond Funds
Total 36,028,000 36,028,000 21,801,919 14,226,081
Available Funds:
Bond Funds Provided in
Preliminary Planning Funds-approved in FY 2015-16 CIP 478,000 478,000 478,000 - Advance of Bond
Referendum
Repurposed Funds from Other OCS Capital Projects in FY 2017-18 to
Mechanical Systems Project - 1,463,407 - 1,463,407 Repurposed Funds
Total 478,000 1,941,407 478,000 1,463,407
Grand Total-Major Facility Renovations 36,506,000 37,969,407 22,279,919 15,689,488
*Actua/s as of Munis Report through 8131120
Total Exps(est.
Bond Projects: by OCS)
Roofing Projects 4,056,993
Property Acquisition 3,104,353
Cedar Ridge High School Addition 14,500,000
School Safety/Security 2,500,000
Mechanical Systems 10,871,007
Classroom/Building Improvements 1,000,000
Advanced Preliminary Planning Funds in FY 15-16 CIP-Bond Funds 478,000
Total 36,510,353
Final Tranche of 2016 Bond Funds in FY 2021-22 11,386,000
Grand Total 47,896,353
Total Revs(est.
by OCS)
Bond Funds-Roofing Projects 4,056,993
Bond Funds-Property Acquisition 3,100,000
Bond Funds-Cedar Ridge High School Addition 14,500,000
Bond Funds-School Safety/Security 2,500,000
Bond Funds-Mechanical Systems(includes Repurposed Funds from FY 17-18: 10,871,007
Bond Funds-Classroom/Building Improvements 1,000,000
Advanced Preliminary Planning Funds in FY 15-16 CIP-Bond Funds 478,000
Total 2016 Bond Funds 36,506,000
Final Tranche of 2016 Bond Funds in FY 2021-22 11,386,000
Estimated Sales Tax Reimbursements -
Grand Total 47,892,000
Surplus/(Deficit) (4,353)