ACTION AGENDA ITEM ABSTRACT
Meeting Date: June 9, 2020
Action Agenda
Item No. 2
SUBJECT: Discussion and Decisions of FY2020-25 Capital Investment Plan
DEPARTMENT: County Manager and Finance and Administrative Services
ATTACHMENT(S): INFORMATION CONTACT:
A. FY2020-25 Capital Investment Plan Bonnie Hammersley, (919) 245-2300
Budget Amendment List Travis Myren, (919) 245-2308
(Any Updates to the list will be Gary Donaldson, (919) 245-2453
provided prior to the meeting) Paul Laughton, (919) 245-2152
PURPOSE: FY2020-25 Capital Investment Plan - Accept the Five Year Capital Investment Plan
and Approve the Intent to Adopt Capital Funding for FY2020-21 .
BACKGROUND: For over 20 years, the County has produced a Capital Investment Plan (CIP)
that establishes a budget planning guide related to capital needs for the County as well as
Schools. The current CIP consists of a 5-year plan that is evaluated annually to include year-to-
year changes in priorities, needs, and available resources. Approval of the CIP commits the
County to the first year funding only of the capital projects; all other years are used as a planning
tool and serves as a financial plan.
Capital Investment Plan — Overview
The FY 2020-25 CIP includes County Projects, School Projects, and Proprietary Projects. The
School Projects include Chapel Hill-Carrboro City Schools, Orange County Schools, and Durham
Technical Community College — Orange County Campus projects. The Proprietary Projects
include Water and Sewer, Solid Waste Enterprise Fund, and Sportsplex projects.
The CIP has been prepared anticipating moderate economic growth of approximately 2% in
property tax growth over the next five years, and 4% sales tax growth in Years 2-5. Sales Tax
proceeds for Year 1 (FY 2020-21) are estimated to decline by 4.5% due to the current coronavirus
pandemic. Many of the projects in the CIP will rely on debt financing to fund the projects.
The items below include revisions made to the following Capital Projects since the presentation
of the Manager's Recommended Capital Investment Plan on April 2, 2019:
• At the May 14, 2020 Budget Work Session, staff included a revised Schools Capital
Projects Summary reflecting adjustments made in regards to changes to the FY 2020-21
budgeted ADM percentages, based on changes made from the time of the original CIP
presentation and the FY 2020-21 Manager's Recommended Operating Budget
presentation. The impact of these numbers changed the CHCCS % from 60.14% to
59.99%, and changed the OCS % from 39.86% to 40.01%.
2
FINANCIAL IMPACT: The Five Year Capital Investment Plan is a long-range financial planning
tool with a financial impact in FY2020-21, if the first year of the CIP is approved by the Board of
County Commissioners with the adoption of the Annual Operating Budget.
SOCIAL JUSTICE IMPACT: There are no Social Justice Goal impacts associated with this
item.
ENVIRONMENTAL IMPACT: There are no Orange County Environmental Responsibility Goal
impacts associated with this agenda item.
RECOMMENDATION(S): The Manager recommends that the Board accept the Five Year
Capital Investment Plan and Approve the Intent to Adopt Capital Funding for FY2020-21.
BOARD OF ORANGE COUNTY COMMISSIONERS(BOCC) Agenda Item 2
ATTACHMENT A 3 DRAFT-CIP Amendment List
Amendment# Sponsor CIP Budget Page Department Amendment Amount
20-21CIP-001 Commissioner Dorosin 135 Educatioin Move the Durham Tech Expansion Project planning $ 1,000,000.00
up to year 1
20-21CIP-002 Commissioner Dorosin 135 Education Move Durham Tech Expansion Project phase 2 up to $ 14,000,000.00
ear 2
20-21CIP-003 Commissioner Dorosin 135 Education Move the Durham Tech Expansion Project phase 3 $ 11,547,911.00
up to year 3
20-21 CIP-004 Commissioner Dorosin Various County CIP Projects Delay the following CIP projects from Year 1 (FY 20- $ (3,200,000.00)
21)to Years 6-10: Conservation Easements
($1,000,000);Roofing Projects(25,000);EMS
Substation-Morgue Project($675,000);Blackwood
Farm Park($350,000);IT($900,000);Vehicle
Replacements($250,000)
20-21 CIP-005 Commissioner Dorosin Various County CIP Projects Delay the following CIP projects from Year 2(FY 21- $ (8,479,526.00)
22)to Years 6-10: Soccer.com($4,589,000);some
IT Infrastructure($1,500,000);Millhouse Road Park
($400,000);Lands Legacy($500,000);Lake Orange
Dam($50,526);Little River Park,Phase II
($500,000);Roofing Projects($250,000);Twin
Creeks Park($220,000);Old Courthouse Square
($220,000);Vehicle Replacements($250,000)
20-21 CIP-006 Commissioner Dorosin Various County CIP Projects Delay the following CIP projects from Year 3(FY $ (14,868,385.00)
2022-23)to Years 6-10: Millhouse Road Park
($6,400,000);Twin Creeks Park($3,780,000);
Conservation Easements($1,000,000);Blackwood
Farm Park($300,000);Fairview Park($2,000,000);
Courthouse Square($390,000);IT($748,385);
Vehicle Replacements($250,000)
20-21CIP-007 Commissioner Price 135 Education Move the Durham Tech Expansion Project planning $ 1,000,000.00
up to year 1
20-21CIP-008 Commissioner Price Various County CIP Projects Remove the following CIP projects from Year 1 (FY $ (1,100,000.00)
20-21): EMS-Substation-Morgue project
($675,000);Millhouse Road Park($300,000);
Roofing Project($25,000);Vehicle Replacements
($100,000)
20-21CIP-009 Commissioner Price 135 Education Move Durham Tech Expansion Project phase 2 up to $ 14,000,000.00
year 2
20-21CIP-010 Commissioner Price Various County CIP Projects Delay the following CIP projects from Year 2(FY 21- $ (6,041,300.00)
22)to Years 6-10: Soccer.com($4,589,000);some
IT Infrastructure($382,300);Little River Park,Phase
II($500,000);Roofing Projects($250,000);Twin
Creeks Park($220,000);Vehicle Replacements
($100,000)
BOARD OF ORANGE COUNTY COMMISSIONERS(BOCC) Agenda Item 2
ATTACHMENT A 4
DRAFT-CIP Amendment List
20-21CIP-011 Commissioner Price 135 Education Move the Durham Tech Expansion Project phase 3 $ 11,547,911.00
up to year 3
20-21 CIP-012 Commissioner Price Various County CIP Projects Delay the following CIP projects from Year 3(FY $ (10,930,000.00)
2022-23)to Years 6-10: Millhouse Road Park
($6,400,000);Twin Creeks Park($3,780,000);
Blackwood Farm Park($300,000);Courthouse
Square($350,000);Vehicle Replacements
($100,000)
20-21CIP-013 Staff 44 Roofing Projects Remove$25,000 from Year 1 (FY 2020-21)and $ (275,000.00)
$250,000 from Year 2(FY 2021-22)related to the
Design Costs and Roof Replacement of the Main
Library
20-21 CIP-014 Staff 53 EMS Substations Reduce the Morgue portion of the EMS Substation $ (675,000.00)
project in Year 1 (FY 2020-21)from$1.2 million to
$525,000
20-21 CIP-015 Staff 82 Solid Waste Projects Defer Recycling Operations-Vehicle/Equipment $ (570,800.00)
Replacements of$570,800 from Year 1 (FY 2020-
21)to Year 2(FY 2021-22)