Orange County Capital Needs Advisory Task Force
Report to the Board of County Commissioners
June 12, 2009
BACKGROUND
In Febnaary 2001, the Orange County Board of County Commissioners appointed a 27-
member Orange County Capital Needs Advisory Task Force. The primary purposes of
the Task Force were to review multiple proposed projects which had been identified by
various entities and to recommend to the Board of County Commissioners the preferred
elements and size of the planned November 2001 bond referendum. The Board of
County Commissioners charged the Capital Needs .Advisory Task Force with the
following: --
• Review the immediate needs for new schools in the 10-year Capital
Improvement Plan (CIP), as identified by the Orange County and Chapel Hill-
Carrboro City Schools
• Review the capital needs identified by County departments in requests submitted
for the 2001 2011 CIP
• Familiarize itself with long range school capital funding policies as adopted by
the Board of Commissioners
• Familiarize itself with recommendations developed by the School Constnaction
Standards Task Force, the Space Needs Task Force, the Affordable Housing
Task Force, the Community College Task Force, the Library Task Force, and the
Master Aging Plan (MAP)
• Familiarize .itself with the Lands Legacy Program and future recommendations
and plans
• Confirm the need for, and timing of, new school construction projects,
considering current and projected student populations
• Provide recommendations on the possible elements of a November 2001 bond
referendum with the items listed in orcier of importance from most important to
less important
• Provide recommended sizes and estimated costs for each bond referendum
element recommended by the Task Force as well as any portion of the costs
shared by the proposing/recommending entities
• Ensure that each recommended element complies with the appropriate adopted
policies of Orange County for Joint Capital Facilities Development, the Orange
2
County Debt Management Policy, and the Orange County Capital Funding Policy
as well as all other relevant adopted policies of the County
• Ensure that all elements are accessible to and senie residents throughout
Orange County -
• Complete its work by May, 2001
MEETINGS AND PRESENTATIONS
The Task Force met in a series of nine meetings, beginning in March. The initial
meetings provided members with presentations and information on the numerous
capital needs projects which were proposed. The Task Force heard a presentation on
affordable housing from the Affordable Housing Task Force, a Board of County
Commissioner-appointed group that had invested the previous nine months reviewing
affordable housing issues and needs in the County. For educational needs, Task Force
members heard presentations from Orange County Schools (OCS) and Chapel Hill-
Carrboro City Schools (CHCCS) as well as from representatives of Durham Technical
Community College concerning a possible satellite community college campus in
Orange County. For parks and recreational needs, the Towns of Chapel Hill, Can-boro,
and Hillsborough as well as representatives of Orange County provided presentations
to the Task Force. It is worth noting that Chapel Hill and Carrboro jointly submitted their
requests and that the Town of Hillsborough and Orange County had, to some degree,
also coordinated their proposed projects. The parks and recreational needs presented
also included 1) information from representatives of the Soccer Task Force, a Board of
County Commissioner-appointed body that had conducted acommunity-wide
evaluation of the demand for soccer facilities and programs in the County; and 2) the
Open Space Task Force, another Commissioner-appointed body that reviewed open
space needs and requests throughout the County.
The Capital Needs Advisory Task Force also heard presentations on facility needs
associated with County government, Representatives of the Library Services Task
Force, the Master Aging Plan Task Force, the Justice Facilities Task Force, arid the
Space Needs Study Task Force all addressed the members with proposed projects.
The areas discussed included libraries, senior centers, justice facilities, Orange
Enterprises (a job-training/employment program for residents experiencing employment
barriers), and County govemment buildings. The County buildings projects included
administrative ofFices, a Farmers Market, and an Animal Control facility..
All of the November 2001 bond project requests submitted to the Task Force, totaling
$153.fi million, are detailed in Appendix C of this report.
3
AREAS OF CONCERN
During the presentations, Task Force members were given ample opportunity to ask
questions of the various presenters and fully develop an .understanding of the prajects
proposed. A few areas caused concern for Task Force members. One area that raised
definite concern for several Task Force members pertained to the high school plans for
Chapel Hill-Carrboro City Schools. CHCCS had proposed additions/expansions at both
Chapel Hill High and East Chapel Hill High to address facility needs and future student
population growth. Task Force members voiced a concern that this would not positively
and adequately address future high school space needs for the system. Among other
things, the increase in numbers of students at each school would have detrimental
effects on the schools' operations and overall success and would also preclude some
students from certain educational opportunities due to the sheer numbers of students
competing for limited spots. With this in mind, the Task Force ultimately included in its
recommendation a proposal that the facilities at Chapel Hill High be expanded to
address facility needs and future student population growth. However, the funds
requested for East Chapel Hill High would be directed toward the purchase of land and
planning for a third high schaol for the system. The actual construction of the third high
school would occur at some point in the next few years as funding, either from a future
bond referendum or from same other source, became available:
Another project area identified by some Task Force members needing some
modification was the Lands Legacy program. There were a substantial number of
possible projects proposed for this program, and this created significant confusion for
some members. To address this concem, the Task Force combined all the individual
projects into one "Lands Legacy" item so that any possible recommended funding could
be more easily detailed. This would also allow the funding to be allocated more
appropriately once specific properties were prioritized and pursued.
A last area identified by some Task Force members as causing some confusion related
to the Hillsborough Elementary Renovations and Central Office Expansion as proposed
by Orange County Schools. Initially categorized as.two independent projects, it was
brought to the Task Force's attention that the school renovation to provide 12 additional
classrooms could not proceed without the Central Office Expansion. This office ..
expansion would provide office space for the administrative staff that would be
displaced by the school renovation/additional classrooms. Following discussion by the
Task Force, these two interrelated improvements were incorporated into one project so
that any recommended allocation of funds would address the project in its totality.
CRITERIA
Following all presentations of the needs expressed by the various entities, the Task
Force developed criteria to be used to evaluate all of the projects. The criteria for
evaluating projects were as follows:
• Projects should have a useful life of 20+ years.
4
• Consider the number and spectrum of present and future citizens who
would benefrt directly and indirectly from the proposed project.
• Look for efficiencies, such as when multiple needs can be met.
• Schools should be given a high priority.
• Consideration should be given to projects or aggregates ofi $1 million or
more.
• Consider the timing and urgency of the project.
• Give consideration to projects which are clear, specific and ready to go.
• Consider whether it is a reasonable package/project that voters would
support.
• Consider whether a project addresses inequities in difFerent parts of the
county.
• Consider projects which can be combined with other sources of funding,
especially where county funds can be leveraged or matched
FINAL RECOMMENDATION PROCESS
In the final meetings, the Task Force began developing a recommended bond package.
Individual members were provided ballots on two occasions and asked to develop their
own bond package, applying the evaluation criteria. The first ballot asked members to
defiail elements of proposed bond packages based on maximum total bond amounts ofi
$60, 72, and 84 million. Members were also asked to develop their own bond
proposals based on an undefined total bond amount. The results of the first round of
balloting were tallied and presented to the group. Afiter discussing these results and
receiving further information on the projects, the Task Force pursued a second round of
balloting with only one total bond amount of $80 million. The Task Force members
reviewed the results of that balloting along with two possible bond packages that had
been developed by the Task Force Co-Chairs based on the results of the two rounds of
voting. The members subsequently requested that the Co-Chairs make several
revisions to one of the possible bond packages, including an increase in the total bond
amount to $85 million. The Task Force members further determined that they would
meet one last time to fiormally approve the recommended bond package.
The Co-Chairs made the revisions requested by the members and the Task Force met
for the last time to officially approve the final package. Due to the substantial
agreement among the members, the package totaling $85 million was approved by
consensus and a formal vote was not required. The Co-Chairs asked if any members
5
had a desire to submit a minority report recommendation or if anyone wanted to submit
any additional written information as an attachment to the Task Force's report. No Task
Force member expressed a desire to exercise these options.
ORANGE ENTERPRISES
It should be noted that one proposed bond project, although not included in the
recommendation, received substantial support from the Task Force. It entailed facilities
improvements for Orange Enterprises. Due to the somewhat limited funding requested
for these improvements ($525,000), the possibility that other funding may be available
for it, and counsel from county staff, the Task Force did not recommend this project for
inclusion in the November 2001 bond package. Nevertheless, the Task Force strongly
encourages the Board of Commissioners to support and adequately fund the Orange
Enterprises project through other means.
RECOMMENDED BOND PACKAGE
The Orange County Capital Needs Advisory Task Force has identified elements of a
bond package for recommendation to the Board of County Commissioners which would
.result in an $85,000,000 total bond amount. This would require an estimated general
fund property tax increase of 8.29 cents per $100 of assessed valuation. The
recommended bond elements include $4 million for two new senior centers with the
Task Force recommending that any remaining costs for the senior centers be paid with
other existing funding sources or by borrowing funds by private placement.
The bond package recommended by the Task Force is shown on the following page.
6
2001 Capital Needs Advisory Task Force Recommendation
for Bolnd Package
E m DesCriptian Amount of. Task Force
v c Request' Recommend
Renovations to Older Schools and 7,010,000 4,553,000
Facilities
New Elementa School-#9 13 556 000 13 556 000
v, New Elementa School #10 14 349 000 14349 000
High School Expansion/Planning for 7 883 000 000
000
6
~ New Hi h School ' ,
,
~ ' New Middle School 20 000 000 20 000 000
Oran a Hi School Renovations 950 000 950 000
Hillsborough Elementary and Central 8,090,000 3,032,000
Office
-o~~
~
Affordable Housing
14,000,000
4,000,000
Q
z
t, H
~ ~
Senior Centers ~~~
6,000,000
4,000,000
~ U
Carrboro Greenwa Develo ment 2 000 000 750 000
Carrboro G nasium Site Ac uisition 250 000 250 000
Smith Middle School Park 250 000 250 000
v, Cha el Hill Greenwa Develo ment 2 500 000 1 000 000
.Homestead Park A uatics Center 3 500 000 3 500 000
°- Southern Communi Park 5 000 000 2 000 ODO
Cedar Grove District Park 1 210 000 .1 210 000
Efland-Cheeks Park Phase II 750 000 750 000
Fairview Park 4 000 000 850 000
N ~j'
J ~ Lands Legacy c2> 12,825,000 4,000,000
Total $149,648,000 $85 OD0,000
Potential Tax Impact (in cents per 700
11.67
8.29
valuation
~°~ Other additional funding appears to be available.
cz) County to allocate funding based on adopted policy
The distribution of the recommended bond package is as follows:
Parkland
Senior Center
5 °,6
Affordable
Housing
5%
__.._~Is
73%
The Task Force used cost estimates fior the elementary and middle schools proposed
by the school systems based on the School Construction Standards policy developed
by the County and the two school systems. The Task Force accepted the estimates
from the .two school systems for the renovation and expansion projects. The costs of
the senior centers, parks and recreation projects, Lands Legacy acquisitions, and
affordable housing were based on estimates made by County staff and/or the task force
reports associated with each area. Amore descriptive listing of all the projects and
associated funding recommended by the Task Force is shown at Appendix B.
S
Conclusion
The Orange County Capital Needs Advisory Task Force is recommending an $85
million bond package that includes funding for three new, schools:
Orange County Schools
• middle school
Chapel Hill-Carrboro City Schools
• elementary school #9
• elementary school #10
The proposed bond package also includes funds for OCS for renovations at Orange
High School and Hillsborough Elementary and funds for expansion of the Central
Offices. Funds are included for CHCCS for renovations for older schools and facilities,
for expansion at Chapel HiII.High School, and for land purchase and planning for a third
high school. The recommendation also includes funds for additional park and
recreation facilities, for Lands Legacy acquisitions, for senior centers, and affordable
housing.
Due to the consensus reached by the Task Force members, there is no minority report from
the Task Force and there are no additional written comments from any Task Force
members.
9
APPENDICES
Appendix A Orange County Capital Needs Advisory
Task Force Members
Appendix B List and Description of Projects Included
in the Task Force's Recommended
Bond Package
Appendix C Needs Presented to Capital Needs
Advisory Task Force
Appendix D Orange County School Construction
Standards for Elementary, Middle and
High Schools
A-1
Appendix A: Orange County Capital Needs
Advisory Task Force Members
Co-Chairs
Leo Allison
Lisa Stuckey
Audrey Booth Allen Spalt
Jay Bryan Bill Strom
Keith Cook Patrick Sullivan
Steve Halkiotis Bill Waddell
Susan Halkiotis Hattie Vanhook
Barry Jacobs Roger Waldon
Hazel Lunsford Teresa Williams
Judy Margolis
Hervey McIver
Mariah McPherson ALTERNATES
Nancy Milio Margaret Brown
Whit Morrow _ Jack Chestnut
Doris Murrell Mark Dorosin
Mark Sheridan Gloria Faley
Florence Soltys Kevin Foy
B-1
Appendix B: List and Description of Projects
Included in the Task Force's
Recommended .Bond Package
Project Descriptions
The following summarizes information about the various projec#s that the Task Force was asked
to consider. The sources of this information are the presentations and handouts provided by
project presenters, various School and County staff, and Task Force members throu8hout the
review process.
Chapel Hill-Carrboro City Schools
1. Elementary School #9
Total Amount of Pro'ect $13,556,000
Funded b Other Sources 0
Amount Re uested to be funded b the Bond $.13,556,000
Description of the Project:
• 600 Student Elementary School
• Planned to Open in 2003
• 90,980 square feet based on School Construction Standards
• Current plan is facility will be constructed on donated land at
Meadowmont
2. Elementary School #10
Total Amount of Pro'ect $14,349,000
Funded b Other Sources Q
Amount Re uested to be funded b the Bond $14,349,000
Description of the Project:
• 600Student Elementary School
• Planned to Open in 2003
• 90,980 square feet based on School Construction Standards
• No current plan for location
B-2
3. Chapel Hill High School Expansion/Planning for New High School
Total Amount of Pro'ect 6,000,000
Funded b Other Sources 0
Amount Re uested to be funded b the Bond $6,000,000
Description of the Project:
• Allocation of $2 million for 8 classroom expansion at Chapel Hill High
• $3 million for purchase of land and $1 million for planning in
preparation for construction of a new third high school
4. Renovations to Oider Schools and Facilities
Total Amount of Pro'ects $7,010,000
Funded b Other Sources 1 0
Amount Re uested to be funded b the Bond $4,553,000
Description of the projects:
• Renovation work at Ephesus, Frank Porker Graham, and Seawall
Elementaries; Culbreth and Phillips Middle, and Chapel Hill High
• Various projects at schools include upgrade electrical wiring, intercom
system and lighting improvements, window replacements, restroom
improvements, ceiling renovations, and heating, ventilation, and air
conditioning system replacements
Orange County Schools
5. Middle School
Total Amount of Pro'ect $20,000,000
Funded b Other Sources 0
Amount Re uested to be funded b the Bond $20,000,000
Description of the Project: -
• 700 Student Middle School
• No current ,plan for location
• Planned to Open in 2004
• 132,000 square feet based on School Construction Standards
B-3
6. Renovations to Orange High School
Total Amount $950,000
Funded b Other Sources 1 0
Amount Re nested to be funded b the Bond $950,000
Description of the Projects:
• Renovations include new fire alarm and intercom systems,
enhancements to ceilings and. lighting, replace external doors, and
renovate media center and cafeteria
7. Hillsborough Elementary Renovation/Central Office Expansion
Total Amount $3,090,000
Funded b Other Sources 1 0
Amount Re nested to be funded b the Bond $3,032,000
Description of the Projects:
• Renovation of Existing Office Space at Hillsborough Elementary to
provide 12 Additional Classrooms and expand year round program
capacity from current 414 students
• Expansion of East King Street Central Offices for Administrative Staff
relocated from Hillsborough Elementary/House .all administrative
personnel at one facility
Affordable Housing
S. Affordable Housing
$4,000,000
• There are approximately 12,281 households in the County experiencing housing
problems and it is estimated that approximately six (fi) percent of the total
housing need (703 units) can be addressed during the next five (5) years.
• $4 million dollars in bond funds will provide approximately 200 affordable
housing units calculated at a total public subsidy of $20,000 per unit. These
funds will address 28% of the short-term housing target of 703 units in the next
five (5) years.
• Additionally, $4 million in housing bond funds will generate approximately $22.4
million in affordable housing stock. (200 units x $112,000 (estimated cost per
unit) _ $22.4 million)
• Types of housing activities to be implemented in the Housing Bond Program
include renovation of existing dwellings; the construction of new dwelling units;
and the acquisition of land for future housing development for low income renter
and owner-occupied families.
B-4
Senior Centers
9. Construction of Central Orange Multipurpose Center $2,000,000
• Current Hillsborough center is the oldest center, located in the Whitted Human
Services Center (which is a large government building shared with other human
service agencies)
• Facility lacks space to accommodate large groups of 40 or more
• Parking at current facility is limited
• Anew 15,000 square foot center in Hillsborough area is needed
• Would include adult day care
10.Construction of Southern Orange Multipurpose Center $2,000,000
• Existing center, established in 1991 in the Galleria Shopping Center, averages
over 200 people each day
• Lease expires in 2007
-Chapel Hill township has the highest concentration of older adults
• Anew 15,000 square foot center proposed for Southern Human Services Center
campus
Parks, Recreation, and Open Space
11. Carrboro Greenway Development $750,000
• Potential joint projects, along Morgan Creek and Bolin Creek, in conjunction with
Town of Chapel Hill greenways
• Acquire land and construct portions of a trail system to eventually connect
Carrboro, Chapel Hill greenways to County parks and open space
12. Carrboro Gymnasium Site Acquisition $250,000
• Acquire land for a gymnasium to meet recreation programming needs
13. Smith Middle School Park $250,000
• Innovative four-party venture (Carrboro, Orange County CHCCS, UNC-CH) to
co-locate playing fields with new middle school
• Funds would complete work already undertaken by County, Carrboro and
CHCCS to provide lighting for playing-fields and install bleachers
14. Chapel Hill Greenway Development $1,000,000
• Completion of Bolin Creek and/or Morgan Creek Greenways -- to link with Town
of Carrboro greenways and ultimately with County parks and open space
• Would match $1.76 million of Town funds for greenway development
B-5
15. Homestead Park Aquatics Center $3,500,000
• Proposed for location at Homestead Park
• Town has $1.315 million toward this facility, , and requests that remaining
$855,000 of 1997 County bond for Homestead Park go to this project
16.Southern Community Park ~ $2,000,000
• Concept plan underway for park along US 15/501 South, co-located with
Scroggs Elementary School
• $1 .million of 1997 County parks bond allocated to this project, which could serve
needs of~multiple jurisdictions in southern Orange
• Balance of playing fields and low-impact recreation expected
17. Cedar Grove District Park $1,210,000
• Co-located with Northern Human Services Center on NC 8G north of
Hillsborough
• Would add one regulation soccer field, one multi-purpose field and a playground,
with picnic area and nature trails along 20-acre pond
18. Efland Cheeks Community School Park (Phase II) $ 750,000
• Co-located with Efland Cheeks Elementary School in western Orange County
• Would add nature trails, parking and athletic field lighting to existing park
19. Fairview Community Park $ 850,000
• Existing 42 acre tract
• Present park includes a playground and picnic area
• Possible Orange County/Hillsborough joint venture to develop this park with
picnic shelters, soccer fields, softball fields, basketball courts and other
amenities
20. Lands Legacy $4,000,000
• County's adopted program for acquisition from willing sellers of important
resource lands
• Five areas of emphasis: 1) future parklands, 2) identified natural areas, 3).prime
or threatened farmland, 4) priority cultural and archaeological sites, and 5)
watershed stream buffers
• County Open Space Task Force and Lands Legacy Long-Term Priorities reports
would guide acquisitions of identified top priorities
Compiled by Orange County Budget Office
06/07/2001
Appendix C: Needs Presented to Capital Needs Advisory Task Force c-i
Through May 2, 2001
(shown in alphabetical order)
Request Description, Amount of Funding Requested
14,000,000
Affordable Housing ~'~ .throw bout h Counffordable Housing projects
County match required to match construction funds from
Community College the State - 4,000,000
County Facilities
Construction of Phase 1 of the Justice Facility (located 6,000,000
~ ~ on Downtown Cam us .in Hillsborou h
c c°~ Construction of a three-story addition to the Government 7,400,000
a ~ Services Center
~ ~ Renovations of Planning and Ag Building and
475,000
~ a~
construction of a Farmers Market
~ ~ Renovations of Southern Human Services Conference 100,000
Center and rounds
Total Level 1 Projects 13,975,000
-a Construction of new Animal Shelter/Animal Control 1
400
000
~ facili ,
,
Addition of Emergency Operating Center at the County's 840
000
y ~ Emer en Mana ement facili ,
°o Expansion of existing Public Works Administration
'o T Building to accommodate bath Public Works 574,000
a ~ Administration and Oran a Public, Trans ortation
`~ Renovation of 112 North Churton Street offices and
~ Court Street Annex to allow for relocation of Economic 100,000
J Develo ment Commission and Child Su ort offices
Total Level 2 Projects 2,914,000
~„~ ~ ~ c Construction of building addition to Southern Human
~ ~ o o
~ Services Center (ta include the Health Department 3,000,000
~ m N
m Dental Clinic current) located in leased s ace
J a ~ ~° Renovation of Whitted Human Services Center 6,700,000
Total Level 3 Projects 9,700,000
Total Counfy Facilities 26,589,000
Orange County library Construction of new Library, Historical Archive and 437,500
Stora a Facili
Orange Enterprises Expand current facility _ 525,000
Compiled by Orange County Budget Office
O6/07/2001
C-2
Appendix C: Needs Presented to Capital Needs Advisory Task Force
Through May 2, 2001
(shown in alphabetical order)
Request ~ Description ~ Amount of Funding Requested
and Open Space
University Statian/New Hope Park -Acquisition of 75 to
150 acres in University Station/New Hope area (northern 1,700,000
Chapel Hill Township); could be school/park co-location
Bingham District Park -Transaction costs for acquisition
of 100 acres in northern Bingham Township (located on 50,000
land owned by OWASA)
Northern Chapel Hill Township Rustic Woodland Trail -
Acquisition of several isolated strips of land that connect
Town of Chapel Hill and County Parks to Triangle Land 600,000
Conservancy trails and Duke Forest open space
network, tying together Town greenways system and
New Hone oven spaces
"Mason Farm to Jordan Lake" Rustic Woodland Trail -
Acquisition of 1-to-2 isolated strips of land to connect
UNC lands at Masan Farm/Botanical Garden to Durham 100,000
County line (to pickup connection to Jordan Lake
Joint TowMCounty Open Space Projects (Town Parks
N and/or Gt~eenway Plans) -Acquisition space for Towns, cz~
~ consistent with joint parks/open space criteria, identified
~ b Town lans/a roved b .Coup
~ Top priority NC Natural Heritage sites -Acquisition of
~ (by purchase or easement) 500 acres in Chapel Hill, 3,250,000
~ Bin ham, Cheeks, Hillsborou hand Eno Townshi s
U
Top priority Unprofecfed Prime Forests -Acquisition of
(by purchase or easement) 300 acres of unidentified and 1,800,000
Seven Mile Creek Nature Preserve -Acquisition of (by
purchase or easement) 500 acres toward Seven Mile 2,500,000
Pickards Mountain Natural Area -Acquisition of 25
additional acres adjacent to Triangle Land Conservancy 125,000
easements at Pickards Mountain in Bingham Township
Conservation Easements in Cane Creek, Upper Eno,
Back Creek and Little River watersheds -Acquisition of
conservation easements on 900 acres of farmland per 1,400,000
year (to protect water quality and prime or threatened
Chapel Hill Township District Park Phase 1, with
Camboro -Construct 3 multipurpose playing fields (one 1,500,000
of which is a regulation soccer field), nature and
environmental trails, picnic areas, and basketball courts
Compiled by Orange County Budget Office
Ofi/07/2001
Appendix C: Needs Presented to Capital Needs Advisory Task Force C-3
Through May 2, 2001
(shown in alphabetical order)
Requ®st Description
Cedar Grove District Park -Construct 2 multipurpose
playing fields (one of which is a regulation soccer field),
la round, icnic area and nature trails
Sauthem Community Park -Construction of community
park that could serve residents in Chapel Hill, Carrboro
~
c and southern Oran e
Fairview Community Park -Construct 2 multipurpose
~ la in fields, icnic area and basketball court
Efland-Cheeks Park (Phase ll) -Construct nature trails,
~ athletic fields li htin and additional arkin
~ River Park -Construct gazebo, walking trails and other
~, amenities on County owned land adjacent to
~ Courthouse and Eno River
~j Northern Chapel Hill Township Rustic Woodland Trail -
Design and layout unimproved rustic woodland trail, with
botanical markers for environmental ro rams
Undesignated Funds -For facility development at a
current or future ark facili
Tofa/ County Request
IMUniCiDal R®auests
Amount of Funding Requested
1,210,000
(2)
(2)
750,000
iz> .
300,000
1,000,000
16,285,000
Homestead Park A uatics Center 3,500,000
Chapel Hill Southern Cammuni Park 5,000,000
Greenwa Develo ment 2,500,000
Total Chapel Hil! Request 11,000,000
Greenwa Develo ment 2,000,D00
Carrboro Hillsborough Road Neighborhood Park (land 1,000,000
a uisition and ark develo ment
G mnasium Site Ac uisition 250,000
Smith Middle School Park 250,000
Total Carrboro Request 3,500,000
Fairview Park 4,000 000
Hillsborough Gold Park 200,000
River Park 200,000
Total Hillsborough Request 4,400,000
Total Parkland and Open Space Request
s)
35,185,000 ~
Senior Centers ~.vnsiruwvn ar c senior cei uGi s wi ie w~a-eu u i v~ iaNc~ 6,000,000
Hill and one located in Central/Northern Oran a Coun
Compiled by Orange County Budget Office
06/07/2001
Appendix C: Needs Presented to Capital Needs Advisory Task Force ~-~
Through May 2, 2001
(shown in alphabetical order)
R®quest ~ Description ~ Amount of Funding Requested
New Elementary School #9 -Construction of a 600
o student elementary school (located on the donated 13,556,000
~ Meadowmont site too en Au ust 2003
c i New Elementary School #?0 -Construction of a 600
~' student elementary school (located on land recently 14,349,000
V
0 urchased b the Coun too en Au ust 2003
o High School Expansions -Construction of additions at
Chapel Hill High and East Chapel Hill High to allow for 7,883,000
V additional 320 seats at each of the two schools
Renovations to Older Schools and Facilities -
~ Renovations include: electrical service, lighting,
~ windows, heating, ventilation and cooling systems, 7,010,000
C] ceilings, bathroom facilities, fire alarm systems,
communications s stems, indoor air uali
Total CHCCS Request 42,798,000
New Middle School -Purchase of land and construction
of a 700 student middle school 20,000,000
w Central Ofl"ice Expansion -Construct addition to
c administrative office building that will allow staff currently
~
housed at Hillsborough Elementary School to be 1,650,000
~ relocated
Hillsborough Elem®ntary Renovations -Upgrades and
v expansion of County's year-round elementary school 1,440,000
~, constructed in 1952
Orange High School Renovations -Renovations
O include: cafeteria and media center upagrades, fire
alarm system, ceiling, external doors, lighting (to take 950,000
place as Cedar Ridge High School opens in August
Tata/ OCS Request 24,040,000
Total School Request 66,83$,000
Total All Requests $153,574,500
~'~ Affordable Housing Task Force indicated that their alternate request is 5% of total bond package.
~2~ Funding request included in requests from municipalities; needs identified in County's Open Space Task Farce
Report
~3~Tawn of Hillsborough request totaled $175,000 for River Park; County's Open Space Task Force Report identified
$200,000 as needed to complete the project
cap Request amount rounded up to nearest $1,000
n-1
Appendix D: ,Orange County School
Construction Standards for
Elementary, Middle, and High
Schools
(See Next Page)
~,, .L• D-2
L
~ ~.. t ~/ 1. r-7
.~~~ / i fr.' f ' 1 fC:
School Construction Standards
Background
In ~eazly 1995 the Board of County Commissioners appointed an eight member work group to
develop school construction standazds for new facilities built in the Orange County School and
Chapel Hi1UCarrboro City School districts, The School Facility Construction Standards Work
Crroup included two representatives from the Board of County Commissioners, two
representatives from each of the twa School Boazds, and two parent representatives:
Orange County Boazd of Commissioners Moses Carey
Chapel Hill/Carrbaro City School Boazd Stephen Halkiotis
Mary Bushnell
Orange County School Boazd - Nick Didow
Susan Davenbarger
Pazent Representatives Larry Haverland
Bill Boyarsky
Dick Snow
The Boazd of County Commissioners adopted in May 1996 school standards for elementary and
_, middle schools. These construction standards are outlined in this report.
Elementary School
The total square footage of the Basic School, as outlined in this section of the report, is 83,160
square feet. There aze two tiers added to the Basic School. Tier A provides additional storage
:space for use of the facility for afterschool programs. The additional storage space is 1,400
squaze feet with- 462 square feet for circulation, bringing the total for Tier A to 1,$62 additional
square feet. Tier B includes space identified by the School Systems as desirable for an
elementary school. Tier B adds 13,240 square feet with approximately 5,920 square feet for
storage, 1,000 square feet for a Student Commons azea and the balance primarily for additional
teacher workspace and conference rooms.
1. - Capacity
The capacity of the elementary school is 600 students.
2. School Sites
The elementary school site is based on the NC Public School Facility Standazds which
requites an elementary school to have a minimum of ten usable acres plus• one usable acre
D-3
3~
per each .100 average daily membership (ADNI). The minimum school site fora 600
student elementary school is l6 acres.
Consideration is to be given to community use of the;. facility and recreational facilities
which could possibly increase the size of the school site.
Classrooms and Associated Storage •
A. Regular Classrooms
Basic School - 26,400 sq. ft.
Tier A -Add 1,200 sq. ft.
Tier B. -Add 3,500 sq. ft.
Classrooms are based on the following number of students:
• Kindergarten through Third Grade - 23 students per classroom
• Fourth and Fifth Grades - 26 students per classroom
Zocal Basic Standard NCPublic School Facility
(Sq. Ft) Standards (Sq. FY).
Aindergarten (4 rooms) 1,200 1,200
Grades T - 3 (Y3 rooms) 1,200 1,000 -1,200
Grades d - S ($ rooms) 1,000 $50 -1,000
Total square footage for regular classrooms in the Basic School is 26,400 squaze feet.
Tier A includes 1,200 square feet for additional storage in the classroom which would
allow classrooms to be used for afterschool programs. Other storage space for afterschool
programs is included in the multi-purpose/physical,_education section of this report.
Additional classroom storage is ,included in 't'ier B. The total amount of additional
storage space is 3,4p0 square feet. Small ~ project rooms for grades 4 and 5 are also
included in this tier, adding 400 square feet.
B. Pre-School Area Basic School -1,700 sq. ft.
Classroom size for children ages three and four is recommended by the .State to be 1,200
to 1,400 square feet. The standards adopted by the Boazd of County Commissioners
includes 1,700 squaze feet for this area: - -
C. Special /Exceptional Children Basic School - 4,500 sq. ft.
Speech/Language Tier B -Add S50 sq. ft.
Programs far exceptional children vary greatly, depending on focal factors. The State
suggests a minimum of 100 squaze feet be provided for each student.
D -4
The adapted standards include the following space for the Basic School for
special/exceptional speech/language education:
Speech/Language Rooms 500
Learning Disabilities Classroom 2 rooms at 500 sq ft. each
P/A Classroom- 1,200
BEH ~ 1,200
Additional space included in Tier B includes: storage for the Learning/Disabilities
classroom .(200 squaze feet) and for the speech/language classrooms (100 square feet).
Offices for the Speech/Languages teacher are included in this tier adding 300 square feet
to the school. An office area totaling 250 square feet is included for the Learning
Disabilities program.
4. Art Education anal Music Basic School - 2,400 sq. ft.
Tier B -Add 450 sq. ft.
The following table compares the local adopted standards for a Basic School with the
~- . Standards established by the State Department of Public Instruction:
Local Basic NCPublic School Facility
Stacndards (Sq. Ft) Standards (Sq. Ft).
Music:
~• General Music 1,000 850 -1,000
• Music Library. _. 200
• Music Office 0 ~ 150
Art Roam. ~ 1,400 1,000 - 1,400
Creative Movement in multipurpose room 1,800 - 2,000
Tier_ B includes 450 additional squaze feet for art storage (250 square feet) and music
storage (200 square feet).
5.. Physical Education Basic School 5,050 sq. ft.
. Tier A - Add 200 sq. ft.
In addition to the space outlined in the table below, the NC Public School Facility
Standazds state that K-6 indoor physical education areas should also include additional
square footage for an office, storage and toilets for boys and for girls.
b-5 .
Local Basic NCPublic Sc~iool Facility
Standards, (Sq: Ft) Standards (Sq. Ft).
Multipurpose/Indoor 3,6.00 3,600
PE
PE Storage 200 included in standazds but amount of
required space not specified
Stage S00 included in standards but amount of
required space not specified
Stage Storage 4S0 _
Tier A includes additional storage, space totaling 200 squaze feet for afterschoal storage.
The State provides that the school's media center should be located on the ground floor,
be a single story and be convenient to all learning areas of the school. The capacity of the
center should be 10% of the membership of the school (60 students.) The following table
compares the State Public School Facility Standards with the local adopted standards.
Local Basic NC Public School Facility
Standards (Sq. Ft) ~ Standards (3q. Ft).
Main Room , 3,000 2,400 to 3,600
Support Areas ~ 1,200 1,200
Computer Room ~ not included SSO - 1,000
Vdeo Production Room not included ~ ~ .300
Equipment Storage see storage SO
6. Media Center
Basic School - 4,200 sq. ft.
A computer roam is not included in the Basic School since technology is integrated into
the classrooms and space is provided in each classroom for computers.
u
7. Small Group/Resource Rooms
Basic School -1,350 sq. ft.
The State Standazds require that one or more small group classrooms be provided for
remediation, conferences, guidance, testing; etc. for groups of up twelve individuals.
Zoca! Basic Standards NC Public School Facility
Standards
Remediation 3 roams at 4S0 sq.ft. each at least one room at 4S0 sq. ft.
/Resource Labs
tt- 6
8. Administration
The. following table compazes the
standards:
.Basic School -1,650 sq. ft.
Tier B -Add 300 sq. ft.
State Standards to the local adopted construction
Local Basic Standards
NC Public School Facility
Standards (Sq. FY).
Principal's Office 200 200
Assistant Principal 150 150 sq. ft per office
Reception Area 400 400
Secretary 150 150
SIMS S-S 150 120
Workroom/Storage ~ 200 200
Conference Room ~ 200 200
Record Storage 100 100
General Storage 100. 100
Tier B includes larger room sizes for the principal's office (50 squaze feet), for the
.. reception azea (100 squaze feet), a larger conference room (50 square feet) and additional
storage above the State guidelines (100 square feet).
9. Student Support Areas
Basic School -1,100 sq. ft.
Tier B -Add 100 sq. ft.
This general azea includes counseling rooms, guidance rooms, and health services. The
State suggests that schools with more than one guidance counselor will need additional
space.
Zocal Basic
Standards ~(Sq.
NCPublicSchool Facility
Standards (Sq. Ft).
v~K..~~ nvvrwi.canury 400 450
Specialists
Counselor Office - 300 150 each office
Other Student Services 200 200
Health Room 200 200
Tier-B includes an office for the Health function (100 squaze feet).
D-7
].0. Staff Support Areas Basic School - 5,600 sq. ft.
Tier B - Add 2,400 sq. ft.
The State recommends that combined or shared space for teacher's offices/workspace be
provided: There should be at least one centralized workroom that. houses equipment such
as the copy machine, dupiicatar, specialized computers, etc. The size of the lounge area is
detenxuned by the building plan and faculty size. The lounge .should provide limited
kitchen facilities.
local Basic NCPublic Schaal Facility Standards
Standards (Sq. Ft).
Teachers.' The State requires that for grades K-3,
Workroamr: 100 to 125 square feet be provided for
teacher affices/workspace. Far grades 4
and above, $0 to X00 square feet per
teacher is required.
• Kindergarten 300
• Grades 1,2,3 900
• Grades 4,5 600 -
Additional Teacher 500
_
Warkspace/O~ces
Teachers' 1,000 required but size varies
Launge/Workarea -
Itinerant Support 300 300
Tier B includes additional workrooms for the kindergarten level (300 square feet), ane
conference roam per grade level (1,500 square feet), a general conference room (200
square feet) and aspeech/language conference mom (400 square. feet).
1].. Cafeteria/Food Service
Basic School - 4,500 sq. ft.
Tier B -Add 200 sq. ft.
The State uses a formula for determining the appropriate size for the dining room and
kitchen area. The dining area should provide between 12 and 14 square feet per pupil
dining. Based on three seatings; the size of the dining room should be at least 2,400
square feet and 2,800 square feet. The kitchen space is based on the number of meals
served. A kitchen preparing 500 ,meals should be at least 1,51 S square feet. A kitchen
b-8
.preparing 7S0 meals should be at least 1,93$ square feet. The adopted standards include a
dining azea of 2,400 square feet and akitchen/serving area of 2,100.
Tier B includes additional storage for tables and chairs totaling 200 squaze feet.
12. Miscellaneous/Commons
Basic School -13,00 sq. ft.
Tier B -Add 1,855 sq, ft.
This area includes miscellaneous space such as additional storage, book storage and
School Commons area. In addition, this area includes additional toilets which are
required by the State Facility Standazds but are calculated as part of the overall
circulation multiplier which is applied to the total square footage (see next section).
Locad Basic Standards. - NC Public School Facility
(Sq. Ft) Standards (Sq. Ft).
CustodiaX Storage 500 500
. Book Storage $00 ~ SOO
Tier B includes a Commons area (1,000 sq. ft.) and toilets which are calculated over and
above the circulation factor of 33 percent.
13. Circulation
A multiplier of 33 percent is included for space such as storage, mechanical rooms,
hallways, toilets, walls, etc. The multiplier is applied to the total square footage of the
Basic. School plus each additional level.
14, Cost Per Square Foot.
For planning purposes, building costs aze calculated based an $90 per square foot for
construction.
Maiddle School
The total squaze footage of the Basic School, as outlined in this section of the report, is
approximately 113,400 square feet. There aze two added to the Basic School.. Tier A includes
increased space for the afterschool programs, increasing the squaze footage by a total of 1,620
square feet. The remaining tier includes nearly 17,200 square feet of which a large portion is for
special project rooms, additional commons space and additional teacher workspace.
D-9
].. Capacity
The capacity of the middle school is 700 students.
2. School Sites 1
The middle school site is based on the NC Public School Facility Standards which
requires that a middle school have a minimum of 1 S usable acres plus one usable acre per
each 100 average daily membership (AD1V1). Therefore the minimum school site fora 700
student middle school is 22 usable acres.
3. Classrooms and Associated
Storage Basic School - 32,SOU sq. ft.
Tier B -Add 2,550 sq. irt.
The Basic School includes classrooms at the upper end of the range provided by the State
Department of Public Instruction. The lazger classrooms. allow technology to be
integrated into the classrooms. Regular Classrooms are based on 1,000 squaze feet per
classroom, science classrooms and Exceptional Education Classrooms are each 1,200
square. feet per classroom. The Resource Rooms for Exceptional Education include two
small rooms at 450 square feet each and two lazger rooms at 600 squaze feet each.
Local Basic Standards (Sq.
,~)
NCPulSlic School
Facility Standards (Sri
Regular Classrooms (22) 22,000 ~ 18,700 - 22,000
Science Classrooms (G). 7,200 6,000 - 7,200
Exceptional Education 1,240 100 sq. ft. per student
Classroom
Exceptional Education 2,100 . . ~. 450 sq. ft. per room
Resource Rooms (4)
Total sc~uaze footage for regular classrooms, science classrooms .and exceptional
education classrooms and resource.rooms in the Basic School is 32,500 squaze feet.
Included in Tier B for the middle school is 300 square feet additional storage. In addition
three 750 square feet student project rooms (one for each grade level) provides space for
students to work on special projects.
n-1
4. Art Education /Music/Creative Movement
and Theater Arts
Basic School - 9,600 sq. ft.
Tier B -Add 1,130 sq. ft.
The following table compares the Local. basic standards for a Basic School with the
Standards established by the State Department of Public Instruction. Note that the Stage
is to be built as part of the cafeteria A separate auditorium is not included in the Basic
School. The State Standards provides that, if programming allows, the instrument and
vocal music rooms can be combined.
.Local Basic Standards NCPublic School Facility
. (Sq. Ft) Standards ~ (Sq. Ft).
Music:
• Instrument Music 1,500 1,000 to 1,200
• Vocal Music ~ 1,200 1,000 to 1,200
• ~ Electronic Music not included in Tier A p
• Practice Rooms not included ifi Tier A~ 0
• Instrument Storage included as part of Should be provided but space
circulation/classroom amount not specified
Visuad Arts Raom 1,500 ~ 1,200 to 1,500
Creative Movement
~
` 1,800
- .4,000 (includes stage)
` ~.~:.;
TheaterArts 1,800 1,800 to 2,000
Stage and Stage Storage ~ 1,$00 4,000 includes lobby
Tier B includes one large practice room (200 square feet) one small practice room (80
square feet), wardrobe storage (4S0 square feet) and one electronic music room (400
square feet). If an auditorium was added, additional square footage would be required.
5. Physical Education Basic School 12,000 sq. ft.
Tier A - Add 1,200 sq. ft.
Tier B - Add 500 sq. ft.
The State standards for physical education do not specify the amount of square footage
for physical education. The Standards do require a minimum court area for the
gymnasium of least 42 feet by 74 feet with six feet on each side of the court and eight feet
on each end of the court for safety. The gymnasium should include dressing and shower
areas, offices and some storage. Assembly and spectator use may require increased size.
~-xi
Local Basic Standards NC Public School Facility Standards
Locker Rooms (Z)
7,200
2,400
see note above
to be provided although space not
defined
Office 500
Weight room 900 not required for a middle school
Storage 100 required but amount not specified
Health Classroom 900
Tier A provides additional space that would allow after school use. This includes a multi-
purpose room (900 sq. ft.) plus additional storage (300 sq. ft.): Included in Tier B is a
lazger gymnasium (300 sq, ft.) and additional storage (200 sq. ft.)
6. Media Center
Basic School - 5,640 sq. ft.
Tier B -Add 60 sq ft.
The State provides that the school's media center be located on the ground floor, be a
single story and be convenient to a111earning areas of the school. The capacity of the center
should be 10% of the membership of the school (70 students.). The following table compares the
State Public School Facility Standazds with the local adopted standazds. .
Local Basic NC Public School Facility
Standards (Sq. Ft) Standards (Sq. Ft).
Main Room . 4,000 .2,800 to 4,200
Workroom/O~ce 600 Total support area is 1,880
Storage:
• Periodical _ 200
~ Audio Visual 90
Audio Visual Equipment 250
Conference Room 200
Professional Library 200
Telecommunications Raom 100
Tier B includes additional storage for periodicals (50 square feet) and for audio visual
(10 square feet).. -
D-12
'~.
Parent/Community Center
Tier B - 400 sq. ft.
8.
Space identified by the Schools dedicated for use .by pazents and the community is
included in Tier B. The State does not require this space.
Administration
Basic School -1,800 sq. ft.
Tier S -Add 50 sq. ft. .
The following table shows the space included in the Basic School far Central
Offices/Administration:
Local Basic NCPublic School
Standards (Sq. Ft) .Facility Standards (Sq.
' ~ - ,Ft).
Principal's Office 200 200
Assistant Principal (2) 300 150 sq, ft. each
. - Reception Area 300 400
Clerical 200 150
SIMSS-5 ~ 150 120
Workrooir~/StorageJMaidroom 250 200
,... Conference Room 200 200
Record Storage 200 100
Tier B includes additional space for clerical/office management staff (50 sq. ft:),
9. Student Support Areas Basic School -1,000 sq. ft.
. - Tier B -Add 1,450 sq, ft.
This general area includes counseling rooms, guidance/family specialists rooms, and
. health services. The State standards state that schools with more than one guidance
counselor will need additional space.
Local Basic NCPublic School Facility
Standards (Sq. Ft) Standards (Sq. Ft).
Guidance Rooms/Famidy
Specialists
• Counselor's Offices 450 -150 each counselor
• Other Offices 150 varies
• Conference Room 200 varies
Health Room 200
200
n-13
Tier B includes a Peer Advisor/Conflict Mediator's Room (2Q0 sq. ft.), counselors'
offices lazger than the 150 square feet required (150 sq. fC.), a reception/waiting area (100
sq. ft.), additional group counseling azea (250 sq. ft.),;additaonal testing/canference azea
(100 sq. ft.), offices for psychologist, social worker and speech therapist (150 sq. fl.), an
office for the nurse (150 sq, fl.); and additional health space including additional space
for a cat azea, reception azea and toilet in the health suite (350 sq ft.) One toilet is
required but is included in the overall circulation of the building.
7.0. ~ Staff Support Areas Basic School - 3,$.00 sq. ft.
- Tier B - Add 2,000 sq. ft.
The State recommends that combined ar shared space for teacher's offices/workspace be
provided.. There should be at least one centralized workroom that houses equipment such
as the copy machine, duplicator, specialized computers, etc. The size of the lounge azea is
determined by the building plan and faculty size. The lounge should provide limited
kitchen facilities. Included' in the Basic School is one workspace for each grade (450 sq.
ft. each) and a teacher's lounge (450 sq. ft.). Tier A includes ~ additional workspace far
teachers, including offices and conference rooms. Tier B includes additional conference
rooms and teacher workspace. Note that the squaze footage for Tiers 1 and 3 are based on
the space identified for the professional staff for the elementary school,
Local Basic 1VC Public School Facility Standards
Standards (Sq. Ft).
Teachers' A'orkroortts: 1,350 For grades 4 and above, 80 to 100 square
feet per teacher is xequired.
Teachers' ~ ~ 450 required but size varies according to the
LoungelWorkarea ~ facility and other additional space.
Tier A includes additional offices and workspace for teachers totaling 2,000 square feet.
Tier B includes additional workrooms, offices and conference space.
].],. Cafeteria/Food Service Basic School -. 5,240 sq. ft.
The State uses a formula for det~!~n~rig the appropriate size for the dining room and
kitchen azea The dining azea should provide between 12 and 14 square feet per pupil
dining. Based on three seatings, the size of the dining room should be at a nv.nimum
2,400 square feet to 2;800 squaze feet. The kitchen space is based on the number of meals
D-14
served. A kitchen preparing 750 meals should be at least 1,938 square feet. The Local
basic standards for the Basic School includes a dining azea of 3,300 square feet and a
kitchen/serving area of 1,940 square feet.
12. Miscellaneous/Commons
Basic School - 3,400 sq. ft.
Tier B -Add 1,855 sq. ft.
This azea includes miscellaneous space such as additional storage, receiving area, book
storage and School .Commons area.
Loco! Basic Standards
NC Public School Facility
Standards (Sq. Ft).
Receiving Area ~ 200
CustodiaUBook ~ 900
Storage -. .
Book Storage : S00
Student Commons 1,500 ~ 1,500
Tier B includes a larger activities lobby (500 sq. ft.) and three academic house centrums
at 1,000 square feet each (tota13,500 sq. ft.).
13. Circulation
A multiplier of 35 percent is included for space such as storage, mechanical rooms,
hallways, toilets, walls, etc. The multiplier is applied to the total square .footage of the
Basic School plus each additional level. A larger circulation factor than the factor used
far an elementary school is necessary for a middle school due to the more complex nature
of the facility (laboratories, additional plumbing, .etc,) and additional space needed for the
hallways (student lockers): - .
X4. Cost Per Square Foot
For planning purposes a cost of $95 per square foot far construction is to be used.
Other Facility Considerations
Technology
Technology for new school construction projects should include funds for the installation of
cabling network within the school. The network should be designed to accommodate voice, data
and video educational requirements. Realizing that specifics for the technology infrastructure
b,15
,.,~
may differ depending upon user needs a cost allowance as suggested by the Department of Public
Instruction of $1.75 per building square foot should be used.
Equipment such as computers, file servers, printers, telephones, copiers, facsimiles, and video .
recorders should also be included in the budget. For, planning purposes, an estimate of $4.00 per
square foot is to be used. - ~~
Energy Efficiencies
An approved industry standard that measures energy use is the British .Thermal Unit (BTU).
Electric and natural gas consumption can easily be converted into BTUs and comparative
analysis can be developed. Today's energy efficient schools should operate in the range of
40,000 to 50,000 BTU per square foot. This range allows for computer equipment in classrooms
and after hour use of facilities. If an energy usage target is established for construction of new
schools, the planners have the flexibility of specifying the mix of mechanical systems, chillers,
daylighting techniques, roofing systems, insulation, energy management systems, etc. to achieve
the agreed upon energy goal. An integral pant of the equipment specification process includes the
development of life cycle cost analysis data regarding the proposed equipment.
The energy BTU goal and life cycle cost analysis should be a required amendment in the contract
between the school system and architect/engineer. Other recommendations in this area include:
(1)all ,classrooms should have exterior exposure with windows; and (2) heating and cooling
systems should be easily interchangeable.
Site Yssues
The property size of new schools should at a minimum follow established recommendations
from the Depaztinent of Public Instruction. These are:
Elementary.School 10 usable acres plus 1 usable acre per 100 students
Middle School 15 usable acres plus 1 usable acre per 100 students
High School ~ 30 usable acres plus 1 usable acre per 100 students
School systems should actively pursue partnering agreements with. the towns and the. County
Parks and Recreation Departments, private developers, and businesses in an effort to maxirrLe
shared facilities.
Other site considerations include:
1. Landscaping and buffers should be included in all school plans.
2. Athletic. fields at the high school and middle school level should be equipped with
irrigation systems. At a minimum, irrigation should be installed on the primary
b-16
event field. Additionally, water should be available for plants and grass in the
immediate vicinity of the buildings.
3. Covered walkways should be provided at the student drop-off areas, main
entrances, and bus loading areas.
4. Adequate parking for staff and visitors should be provided. The following -
- minimum recommendations are made regarding the size of parking facilities at
- new schools: .
Elementary School 600 100
Middle School 700 120
Materials
Construction materials should be selected based on low maintenance and high.durability. The life
cycle~of each new school is a minimum of 50 yeazs.
a
Elementary School
Capacity 600 Students _
Basic
School Additions to Ba
Tier A sic School
~ Tier B Total
Classrooms and Associated Storage 34,100 . -x,200 4,650 39,950
Regulaz Classrooms (25) 26,400 1, 200 3,400 3I, 000
Small Project Rooms (Grades 4 & 5~ (2) 400 400
Science Project Room (1) 1,200 1,200
Preschool Area (1) 1,700 1,700
Special/i~xcepttanal Children/Speech
Language (7 rooms) 4, 800 850 S, 650
Art Education and Music 2,400 ~ 450 2,850
Physical Education s,oso 200 s,2So
Media Center 4,2ao a;2oo
Small Group Resource Rooms 1,350 x,35o
Administration x,650 300 x,950
Student Support Areas _ x,x0o 100 1,2110
Health 200 100 300
Counseling 900 900
Staff Support Area s,6oo 1,400 7,000
Teachers' Offices/Workrooms 4,300 300 4,600
Conference Rooms 500 500
General Conference Room 200 200
Speech/Language Conference Room 4DD 400
Teachers' Lounge/VVorkaxea 1,000 ~ 1,000
Itinerant Support 300 300
Cafeteria/Food Service 4,500 200 4,700
Miscellaneous/Commons 1,300 - x,855 3,155
Custodial General Storage 500 ~ 500
Book Storage 800 800
Student Commons - 1,000 1,000
Additional Toilets above those
Calculated as part of pCirculation" ~ 855 855
Subtotal 61,250 1,400 .8,955 71,605
Circulation at 33%a of Subtotal 20,2x3 462 2,955 23,630
Total Square Faatage 81,463 1,862 11,9x0 95,235
D-17
n-1s
Middle School
Capacity 700 students
Basic Additions to Basic School
School Tier A Tier $ ~ Total
Classrooms and Associated Storage 3z,5oo x,55o 3S,o5o
Regular Classrooms (22) 2Z, 000 300 7.2,300
Science Classrooms (6) 7,200 7,200
Exceptional Education Classroom
(1)/Resource Rooms (4) 3,300 3,300
Student Project Rooms (3) 2,250 2,250
Art Education and Music (Cultural Arts) 9,600 l,lso 10,730
Exploratorles 9,000 1,000 10,000
Foreign Language Classroom 2,000 2,000
Career Explorations Lab and Resource
Room 1,000
1,000
Applied Technology Lab and Resource
~~ 3,500
3,500
Consumer Education Lab and Resource
Room 1,500 I,500
Computer Lab and Resource Room 1,000 1,000
Video Production Lab - - 1,000 1,000
Physical Education lz,ooo 1,200 ~ soo 13,700
Media Center 5,640 60 5,700
Parent/Coanmunity Center 40o aoo
,~; minictraNpn 1,800 SO 1,$50
Student Support Areas . l,ooo l,aso a,4so
Health zoo soo 700
CounselinglGuidauce 800 950 1,750
Staff Support Ares 3,800 2,000 5,800
Teachers' Offices/Worlaooms 3,350 1,250 ~ ~
Conference Rooms (one per grade level) 750 750
Teachers' Lounge/Workarea 450
.
450
Cafeteria/Food Service 5,240 5,z4o
Miscellaneous/Commons 3,400 3,600 7,000
Receiving Area 200 200
Baolc Storage/Central Supply Storage 1,700 100 1,800
Student Commons 1,500
1,500
Activities Lobby 500 500
Academic House Centrums
(3 ®1000 scl.ft
each) 3,000 3,000
subtot~r 83,980 l,zoo 12,740 97,9zo
Circulation at 35% of Subtotal 29,393 420 4,a59 3a,Z72
Total Square Footage 113,373 1,620 1'7,199 132,1.92
D-19
Estimated Cost of New Facilities .
Elementary School Capacity =600 students Square Footage 95 225
Square Ft. per Student 188.7 .
COtistructian COSt Cost Per Square Faot $ 90 $ 8,570,250
Site Acquisition ,Acres:, 16
Average Cost Per Acre: 25,000 $ 400,000
Site Development As a percentage of Construction Cost 109b $ 857,025
Fees As a percentage of Construction Costs and Site Development 1p%, 942,728
Moveable Equipment As a percentage of Construction Cost ~ 5 % $ 428,513
Technology Cost per square foot ~ $ 8:25 $ 785,606
(includes cabling and equipment for voice, video and data distribution systems)
Construction Contingency As a percentage of Construction Cost and Site Development 5Ro $ 471,364
Start-Up Costs Non Personnel One time start-up costs $ 330,000
Total $ 12,785,485
,,',
~:~;:
Middle School Capacity = 700 students Square Footage ~ 132 192
Square Ft. per Student 188.8 .
Construction Cost Cost Per Square Foat ~ $ 95 $ 12,558,240 .
Site Acquisition Acres: 22
Average Cost Per Acre 25,000 $ 550,000
Site Development As a percentage of Construction Cost 10%~ $ 1,255,824
Fees - . As a percentage of Construction Costs and Site Development 10% 1,381,406
Moveable Equipment As a percentage ~of Construction Cost 5 ~ $ 627,912
Technology Cost per square foot _ $ 8.75 $ 1,090,584
~ ('includes cabling anaf equipment for voice, video and data distribution systems)
Construction Contingency As a percentage of Construction Cost and Site Development ~ 5%~ $ 690,703
Start-Up Casts Non Persotmel Start Up =one time $ 350,000
Total $ 18 504,670
R
Orange County, North Carolina
approved
Apri1.20,1999
b-zo
,S
~-zl
Approved 4/201yy
Table of Contents
Backgrounds,,, _ _-: .. , , l
Capacity ~ X ~ '
School Sites 1
Interior Building Space Allocations
. Classroom Standards 2
1Vledia Center Standards ~ 3
Physical Education Standards 3
Administration Standards ~ 3
Student Support Areas Standards ~ ~ 4
Staff Support Areas Standards 4
Cafeteria/Foad Service Standards 4
Commons/CirculationlEntries/BuiYding Support Standards 4
Cast per Square Foat ~ 5
Dther Facility Considerations
Technology Infrastructure ~ 5
Energy Efficiencies
S
Materials ~ 5
Appendices
Appendix A -Space Allocatian/Square Footage Assignments (1, 000 Student Capacity) d
Appendix B -Space Allocation/Square Footage Assignments (1,500 Student Capacity) 9
Appendix C -Estimated Cast of New High School 12
Appendix D -Energy Efficiency in Public Schools I3
s
e
b`22
Approved 4/20/99
High School Construction Standards
Background
In September 1997, the Orange County Boazd of County Commissioners convened a High. School
Construction Standards Task Force. This six-member task force included two representatives from the
Boazd of County Commissioners and two representatives from each of the two School Boards.
Orange County Board of County Commissioners Moses Carey
Stephen Hallaotis
Chapel Hill-Carrboro City School Board. Elizabeth Carter
Ken Touw
Orange County School Board ~ Susan Dovenbazger
Rick Kennedy
In developing standards for future high school construction in Orange County, the task force used North
Carolina Department of Public Instruction (DPl) guidelines far a "typical high school"; space profiles for
East Chapel Hill High School; and information developed by Orange County Schools staffmembers. The
task force paid particulaz attention to;
`~~`~`~'~ ~ • The ability to expand a new high school's capacity from 1,000 children to 1,500;
• Location of a new high. school;
. • Energy efficiency standards and day lighting; and,
• Cost control and construction management.
The task force agreed that the DPI guidelines were reasonable standards to use at the local level.
Appendices A and B include square footage standards as outlined by the State, modified to reflect local
needs as recommended.by the task force. DPI guidelines aze viewed by the State: as minimum space
requirements, and in many fiinctional areas, Orange County standards allow for mare space to provide
greater flexibility to meet the educational specifications that will be developed for any new high school's
program of instruction.
Capacity '
The capacity of the Orange County standard. high school is 1,000 students with the ability to expand to
1,500 students in future years as necessary. -
School Sitcs
'I'he March 1988 North Cazolina Public School Facilities'Guidelines report recommends a high school site
have a minimum of thirty usable acres plus one usable acre per each 100 average daily membership
(students). The minimum school site fora 1,000-student high school is forty acres, and fora 1,500-
student high school, it is forty-five acres.
Approved 4/20/99
D~23
Minimum acreage refers to usable land, land that can be developed. Additional acreage should be
considered to account for areas that cannot be built upon, such as steep slopes, wetlands, rights-of--way, .
easements, setbacks, buffers, or poor soils, Another reason to consider additional acreage is the need to
meet requirements imposed by local ordinances, Restrictions governing the ratio of land that can be .
disturbed within a development and the permitted amount of impervious surface will affect the ultimate . " • '
size of the site. In addition, acreage for on-site pazlting needs should also be considered. Spaces should
be provided for all staff, itinerant specialists, and visitors. Pazking should be provided. for one-thud or
more of the student population.
Community use of the facility and physical education fields could possibly increase the size of the school
site, For e~cample, if a stadium and spectator pazking aze anticipated, ~an additional area of ten acres or
more may be necessary. The expanding number of high school athletic teams is another reason for a
larger school site. In addition to football and soccer teams, athletic facilities may also be required for
lacrosse and field hockey teams.
The Orange County high school standazd profile cites a range of 40-fi0 acres, to accommodate the
potential acreage additions that may be necessary because of specific site topography, configuration, or
athletic Facilities.
Interior Building Space Allocations
1. Classroom Standards
The Orange County stamiards are within the ranges provided by the State Department of Public
Instruction and provide far technology to~be integrated into the classrooms. Square footage for regulaz
classrooms allows for five computers and ranges from 850 to 950 square feet per classroom. Squaze
footage for other classrooms . = science, exceptional children, arts education, and worlc~'arce
development - is based on the function that each serves. The narrative below provides additional
information not detailed in the Appendices.
Remediation and Resource Labs -One or more small-group classrooms sb:ould be provided- for
remediation, conferencing, guidance, and testing far groups up to twelve. Some smaller rooms may
also be needed in addition to the 450 square foot rooms to allow far smaller group activities. Orange
County standards provide for 900-1,800 square feet for this function, depending on the design capacity
of the high school:
Exceptional Education -Programs for exceptional children vary depending on local factors which may
result in spaces that are larger than the DPI minimum guidelines. Additional support spaces may be
necessary for exceptional education purposes depending upon the program. Specialized spaces, such
as cooking areas, toilets, bath/shower rooms, laundries, observation rooms, and special equipment to
accommodate certain disabilities may be required.- Orange County standards provide for 1,250-3,300
squaze feet for this function, depending on the design capacity of the high school.
Instrumental and Yocal Classrooms -The State Department of Public Instruction facility guidelines
indicate that their square footage guidelines for both the Instrumental Classroom and the Vocal
Classroom/Music Library maybe small. Some references recommend l0-l 8 square feet per singer for
Vocal Rooms (more if choreographed) and 25-35 .squaze feet per student for~Tnstrumental Rooms.
b-
Approved 4/20/99
Class sizes for these programs are often large; 40-80 students or more is not unusual. The Prange
County standards provide for a range of 2,800-3,600 squaze feet'for these classrooms.
Dance Classroom -Dressing rooms and access to showers for dance students are desirable in high,
schools. If located adjacent to the gymnasium locker rooms, this space can be combined. 1,800-2,OQ0'
square feet aze included in the Orange County standards for this function..
Workforce Development ; Facilities for high school Workforce Development programs are often large,
extensively equipped, and more expensive than regular classrooms. because of their similarity to
industry. Squaze footage included in the appendix indicates the guidelines as. outlined by DPZ. A
basic high school vocational education program must offer at least three of the workforce development
programs, Many high schools offer all seven programs including agricultural, health occupations,
business, family and consumer sciences, marketing, technology, and trade and industrial. The number
and types of laboratories depend on local factors. More than one laboratory for a program such as
family and consumer sciences education may be necessary in lazger schools. Another factor to
consider is the co-use of the dazkroom of a school. A lazger-than~standazd darkroom with additional
storage could serve art and. science programs as well as .workforce development programs. The
Orange County high school standazds assume that all seven programs may be provided. Space is
allocated for each, with the total ranging from 10,750 to 16,100 square feet.
2. Media Center Standards
The capacity for the media center of the school should be ten percent of the average daily membership
of the school. State guidelines recommend that the media center be located on the ground floor, be
single .story, and convenient to all learning a;eas of the school. Minimum support areas include
offices, work/production rooms, conference rooms, periodical storage, audiovisual equipment. storage,
and spaces for professional collections. State guidelines recommend that the media center's location
should not preclude future expansion of the facility. Orange County standards provide far 7,740 to
8,740 square feet for this function, depending on the design capacity of the high school,
3. Physical Education Standards
The State square footage guidelines for high school physical education facilities vary. Orange County
gymnasium standards include space for two play courts, spectator seating, dressing, and shower areas,
storage, and a lobby. Showers should be available for both physical education and athletic programs.
In addition to the main gymnasium, Orange County standards provide for-an auxiliary gym. of 6,500
squaze feet in the 1,500 student profile, in keeping with DPT recommendations to incorporate this
space for high schools with 1,200 or more students.
4. Adnvnistration Standards
The size of the Central Office will vary according to staffing. Partition construction should allow for
flexibility of recommended space. Orange County high school standards provide for a range of 2,200-
2,350 squaze feet for administration.
n-z5
Approved 4/20/99
S. Student Support Areas Standards
The State provides space guidelines for smaller high schools with one guidance counselor. Larger
schools require additional counselor offices,, and 3 or 5 offices are included in the 1,000 and 1,,500.. • • '
student Orange County high school profiles, respectively. The reception area may need to be
expanded to handle the number of-students ;who may use catalogs and' other materials in the guidance
center.. Areas designated for other student services may house social workers, psychologists, ar other
health professionals. Overall student support space ranges from 1,550 to 1,850 square feet.
6. Staff Support Areas Standards
DPI recommends combined or shared office and workspace areas for teachers. This provides for mare
efficient and flexible use of offices .and workspaces. Guidelines state that eff ciency can be
significantly enhanced by providing teacher office/planning areas in an area separate from but near to
the classroom. By providing a separate space for planning, telephoning, and other work, classrooms
are available for all periods of the day. In addition, workspace should be provided for instructional,
lab, and clerical teacher assistants. One office/waxkspa~ce per projected itinerant teacher plus an
appropriate number for volunteers .and student teachers is recommended. One or maze centralized
workroom(s) is/are recommended for copy machines, specialized computers, and other equipment and
supplies that are not typically located in teacher offices/workspaces, Faculty size and building layout
will determine the. size and number of lounges. It is recommended that limited kitchenette facilities be
included in each lounge. Orange County standard ,profiles provide for a range from 4,760 to $,433
square feet for staffsupport space, depending on the school's design capacity.
7. Cafeteria/Food Service Standards
The minimum guidelines for nutrition facilities are based on a traditional program that includes full-
servicekitchen. and seating to accamrnodate the entire student body in shifts. Dining room azea maybe
reduced for schools with open lunch policies, although this is not assumed in Orange .County
standards. The dining area size is determined by dividing the number of participating children.by the- -.
number of Beatings multiplied by the square footage per pupil (size = ADM /number of Beatings x
square foot per pupil). For the Orange County standards, three Beatings are assumed for the 1,000-
student high school while four Beatings are assumed for the 1,SOO~student school.
,, .
8. Commons/Circulation/EntriesBuilding Support Standards
This azea includes corridors, stairs, school commons areas, entries, mechanical .areas, and storage.
Camidors receive a high volume of traffic during class changes. Wide, generous corridors of 12 feet
significantly enhance safety and security. Gammons, not corridors, should be designed as the social
' center for students. Location and design of commons areas aze more important than size. Bus rider
entries and automobile rider-entries should receive equal attention. DPI square footage guidelines for
building support areas .vary from school ~to school. For Orange County standards; a lazger allowance
for circulation and building support is provided at the high school level than at the elementary (33%)
or middle school (35%) level. The high school profile allows 45% of other building square footage
for these functions.
. Approved 4/20/99
Cost per. Square Foot
$110 per square foot for construction is the 1998 assumed cost of high school construction. Prevailing
mazket factors, inflationary impacts, and the use of alternative design such as the unitary systems
approach should be factored in, as appropriate far future high school planning. . '
Other Facility Considerations
1. Technology Infrastracture
The State Department of Public Instruction encourages school systems to install up-to-date technology
infrastructure for use by all students, faculty, and staff. -When funds aze not available for the
installation of complete systems, the State recommends that school systems provide empty conduits
and cable trays. In addition, space should also be allocated for local and wide area networks, file
servers and other equipment. Wiring closets may be replaced with fiber-optic cable. 'This may be a
more cast efficient manner to provide connectivity.
For. planning purposes, the Department of Public Instruction suggests a cast allowance for technology
infrastructure of $8.25 per building squaze footage. This is consistent with the construction standazds
adopted for elementary and middle schools in Orange County.
2. Energy Efficiencies
During the planning process, special attention should be given to creating fiscally sound energy
efficiencies, Ways to achieve this include: ~ _
Choosing efficient lighting systems and energy management controls,
Considering solar orientation, earth integration, and plantings and landscaping in
• siting the facility, •
• Selecting energy efficient heating, ventilation, and air conditioning system_ s; and
• Exploring solaz energy including day lighting and passive solar heating.
Life cycle cost analyses should be used. when choosing energy systems. • Appendix•D provides further
detail as presented bythe County Engineer to the High School Construction Standazds Task Force.
.,,
3. Materials
Construction materials should be selected based on low maintenance and high durability. The
presumed life cycle of each new high school is a minimum of fifty years,
D-27
Approved 4/20/9y
tiign ~cnooi ~,ons~rucnon ~ranaaras .tippena~.x n ~ .
SpaceAllo~tior~/Squ~ Foo~ageAssigmr,~s -(1,000 Student Capacity)
• 1000 studear capacity
. Square Footage Total Square Ft
From To # rooms Prom Ta
Classrnoms
Regular classroom with 5 computers 850 950 22 18,700 ~ 20,900
SsdrT 18,700 20,900
Scaaxe Lads, Prep grad St+o~e
P ysical Science 100 1,200 1 1,200 1,200
Biology 1,200 1,200 2 2,400 2,400
Physics 1,200 1,200 1 1,200 1,200
Earth SC1Pnr`p 1,400 1,400 1 ~ 1,400 1,400
Chemistry 1,500 1,500 1 1,500 1,500
Storag Prep Roams (Biology, Chemistry, Physics 250 per 2 labs 2 500 500
. ~ ~ ~ • ~ ~ Sr~T ~ ~ 8,200 8,200
Remediation & resource labs 450 450 1 450 450
Ssrb•T ~ ~ ' ~ 450 ~ 450
Ex~ptiorxrl ~iildre-z •
Exceptional Cl~ildmn Self-Contained (8 to 12 student
ca a . $00 1,200
. 1 800 1,200
Exceptional Education Resource Room (for groups up to
12 450 .•450 1 450 450 `~~
. .• . ~ .. ~ ~ Sxb~T ... . ~ 1,250 1,650
Arts Eiart
~trnmc~nta], ClassrDOJx~ w lockers 1,800 2,100 1 1,800 2,100
Vocal Classroom 1,000 1,500 1 1,000 1,500
J.natrua~ent storagexoom 400 600 1 400 600
Music Library 200 200 1 ~ 200 200
Xnstrument Re air ~ 150. ~ 150 1 150 150
Office (each) ~ 150 150 1 150 150
Unif oxm Storage 400 600 1 400 600
Practice Room 55 60 1 55 60
Ensemble Practice Rr~gm 150 200 1 150 200
Visual Arts Classroom 1,200 1,500 1 1,200 1,500
Clap Storage 40 60 1 40 60
Art Material Storage 80 150 1 80 150
Theater Arts Classroom _ 1,800 2,000 1 1,800 2,000
Theater Arts Auditorium
• 8/seat; capacity 1/3
to 1/2 ADM 333 to 500 seats 2,667 4,000
Stage, Storage & Dressing Rooms ~
Light, Lock Vestibule, Lobby, Concession
Dance Classroom ('including storage) 3,000
800
1,800 5,000
2,000
2,000 1
1
1 3,D00
800
1,800 5,000
2,000
2,000
$y~T ~ 15,692 22,270
D~
Approved 4/20/99
High School Construction Standards Appendix A
n._ w 11 /n r . ,_
J GL(.C 17: LLI~CLL4LU/!/ J NG6/G 1 L~1LLL !1 ~S L ~ ~ (J{./(J ~ l
. ~ 1000 student ca aci
. S Footage Total Square
Fmm To # rooms From T
Ll~~kftvice ~~
. Agricultural Education 2,500 3,000 1 2,500 .
Business Education - ' 1,200 1,400 1 1,200
Family and Consumer Sciences Education 1,400 2,000 1 1,400
Health Occupatians 2,000 2,500 1 2,000
Marketing Education ('including store) 1,500 2,000 1 1,500
Technology Education 1,300 2,200 1 1,300.
Trade and Industrial Education 850 3,000 1 850
~•: ~ ~ .... _~~.:.,,~... ,::SST ~ .r,;..,; ~ .. 10y750 ie
Media Center
Main. Room 5 sq ft per ADM 1 5,000 '
Support Areas 2,000 2,000 1 2,000
V Studio 400 400 1 400
Conrxol/Editang 260 260 1 260
Equipment Storage 80 80 1 80
. " ~ , ~ ~.Sr~rT ~ ~ •~~ . ~ 7,740 ;
Physical Education
Gymnasium Play Area 2 play courts 62 x 100 court 12,400 1:
Spectator Seating 400 500 pear 4
000
100 seats 100 seats ,
Gymnasium Dressing, Shower, Storage, Lobby _ 3,000
Wrestling competitive) • 3,000 3,000 1 3,000 -
Resistive Exezrise (weight lifting) 2,000 3,000. 1 2,000
~Y Gymnasium ~ ~ commended for ' h schoo with 1,200 or more studea
• . , -*:. .. .. ssdrT - .. ~ . . 24,400 2E
Administration
Principal's a 200 200 1 200
Assistant Principal (each) 150 150 2 ~ 300
Reception Area 400 400 1 400
Secretary ~, 150 • 150 2 300 .
SIlV1S 9-12 200 200 1 200
Other Student Services 200 200 1 200
Workroo Storage 200 200 1 200
~~ ~~ - 20o zoo i 200
Record Storage ~ 100 iQ0 1 100
General storage ioo 100 1 100
s~T ~ 2,200
D-29
Approved 4/20/99
High School Construction Standards Appendix A ~ .
S All~/S Foa~a Assi 1,00o S~irda~
100 0 student ca aci
Square Footage Total Sq uare~Ft '
_ From - Ta # xooms From To
Student Support Areas
Guidance 300 300 1 300 300
Reception/Career Center 400 400 1 400 400
Cauaselor Office 150 150 3 450 450
Other Student Services 200 200 1 200 200
Health Room & To~1et 200 200 1 200 200
'SulrT 1,,550 1,550
Staff Sup ort Areas
Group Teacher Office/Plauning (per teacher) 80 100 45 3,600 4,500
Special Assistaat/Itineraat Teacher Offic .Workspace (per
teacher 80 100 7 560 700
Workroom 300 800 1 - 300 800
Lounge 300 1,333 1 300 1,333
.- " - ~ ~ ~ ~ - SuhT 4,760 7,333
Cafeteria/Food Service
Dining Room Seating Area (square f eet per pupil) assumes 3
seatings 14 20 333 4,6b7 6,667
Serving (20% - 25% of dining area) ~ 933 1,66 ''
Kitchen (assumes 1,5001unches served far 1,000 cap 2,880 2,$80 1 2,880 2,880
Srr~T ~ ~ ~ ~ ~ 8,480 "11,213
TatalAssi~Space Z04,i72 126,D07
Gammons/Circulation Entries/Building Sup ort (45%) 46,877 56,703 4b,877 56,703
Total Building Area.
v„ ~.
Tatul Sgr~Fe~ per5tx~lem ~ 151 1 S3
.~; ~~
3
e
b-
Approved 4/2p/9g
b-31
Approved 4/20/99
High School Construction Standards Appendix B ~ .
S Allacation/S For~td Assz 1;500 Stzsder~r
. ~ ~' 1500 student ca aci
S Footage Total S ~t
From - To # roams From To
Workfrn~Dece~opm~t
Agricultural Education 2,500 3,000 1 2,500 3,000
Business Education 1,200 1,400 1 1,200 1,400
Family and Consumer Sciences Education 1,400 . 2,000 1 1,400 2,000
Health Occupations 2,000 2,500 1 2,000 2,500
Marketing Education ('including store) 1,500 2,000 1 1,500 2,00
TechnologyEducation 1,300 2,200 1 1,300 2,200
Trade and. Industrial Education 850 3,000 1 850 3,000
:• ^., ;. _ ~ ~ . ~Sz~bT ~ ~ ' . ]:0;750 ~ 16,100
Media Center .
Mafia Room ~ 4 sq ft per ADM 1 6,000 6,000
Support Areas ~ 2,000 2,000 . 1 2,000 2,000
Video S ~ 400 400 1 400 400
Cantrol/Editing 260 260 1 260 260
Equipment Storage 80 80 1 80 80
...,Sr~T ~ ~ ~ 8,740 8,740
Physical Education
Gyxxwasium Play Area 2 play courts 62 x 100 court 12,400 12,400
Spectator Seating 400 per
100 seats 500 pe
100 seats ~ 6,000 7,500
Gymnasium Dressing, Shower, Storage, Lobby 4,000 4,000
Wrestling. (competitive) 3,000 3,000 1 3,000 3,000
Resistive Exexcise weight liftin ~ 2,000 3,000 1 2,000 3,000
Auxiliary Gymnasium 6,500 6,500 1 ~ 6,500 . 6,500
Sr~b~7" ~ ~ 3'3,900 36,400
Administration x
Principal's ice ~ 200 200 1 200 200
Assistant Principal (each ~ 150 150 3 450 450
Reception Area 400 400 1 400 400
Secretary 150 150 2 300 30'0
SM 9-12 200 200 1 200 200
Other Student Services Z00 200 1 200 200
Workroom/Storage _ 200 200 ], 200 200
Conference Roam 200 200 1 Z00 200
Record Storage 100 100 . 1 100 100
General Storage 100 100 1 100 100
SulrTcral 2,350 ~ 2,350
D-32
Approved 4/20AJ9
~,
1)-3.3
Approv®d X1/20/99
High School
Construction Standards
Appendix C
Esfimafed Cosf of New High ,School
.~~,,
Student Capacity 1000 1500
Total Sq uare Ft Total Sq uare Ft
From To Frnm To
Total Square Footage 151,049 182,710 211,487 251,345
Construction Cost Cost Per Square Foot $110 $16,615,381 $20,098,063 $23,263,554 $27,647,943
Site Acquisition Acres 40 50 45 60
Average Cost Per Acre $30,000 $1,200,000 $1,500,000 $1,350,000 $1,800,000
Site Development As a percentage of
Construction Cost 10% $1,661,538 $2,009,806 $2,326,355 $2,764,794
Fees As a percentage of
Construction Cost and Site ~
Develo menf 10°~ $1,827,692 $2,210,787 $2,558,991
' $3,041,274
Moveabi~ Equipment As a percentage of
Construction Cost 5% $830,769 $1,004,903 $1,163,178 $1,382,397
Technology Cost Per Square foot $8.25 $1,246,154
(includes scal/ng and equipment for volts, video and data dlstrfbutlon syst®ms) $1,5D7,355 $1,744,767 $2,073,596
Construction ~. As a percentage of
Contingency Construction Cost and Site
Develo ment 5% $913,846 $1,105,393 $1,279,495 . $1,520,637
Start-Up Costs Non-personnel; one time start-dp w- •-
costs ~ - $399,927 $483,754 $559,946 $.665,477
Total. Estimated Cost
>. $24,695,346 $29,920,112 $34,246,330 $40,896,177
A-34
Approved 4/20/99
Energy Efficiency in Public-Schools
Appendix D
Overview
The following outline of technologies, strategies, tools, and issues does not represent any new concepts
for school construction standards and financing policy makers. Rather, the emphasis here is to present
those concepts in a single simple document that indicates that creating fiscally sound energy efficiencies
and achieving real savings in energy and energy technology expenditures are a matter of planning and
balance.
Eneray Savings Tools and,Strategi~s
• Energy Efficient Lighting - efficient lighting types (fluorescent, metal halide,. high pressure
and Lighting Design sodium), proper lighting levels, lighting controls (occupancy sensors,
level controls, etc.), task lighting, multi-stage lighting, etc.
• Energy Management Controls -Thermostats, HVAC setback controls, etc.
• Siting -solar orientation, earth integration, plantings/landscaping
• Energy Efficient Heating, Ventilation - High efficiency motors, fuel selection, system design,
and Air Conditioning zoning, thermal storage, heat reuse, natural convection
• Building Shell -color,. thermal mass, insulation, location of windows, window glazing (diffusion,
high transmittance, etc.) interior and exterior reflectance, ceiling height
• Solar Energy - daylighting and passive solar heating
Important terms an'd concerts for develorin4 energy savings strategies, .
• Eiectrical Energy cost components -Peak demand charge, time of day rates, usage costs
• ~Energy.use goal - The lowest target for or limit of a building's energy use (in British Thermal
Units [BTU's] per square foot per year)
' ° ~ Town of Chapel Hill Energy Ordinance sets goal at 30% less than NC State
. ~ Building Code requirements
~ US Department of Energy Building Energy Performance Standards range
from 36,000 BTU's per square foot per year for elementary schools to x0,000
BTU's per square foot per year for high school gymnasiums
• Energy use budget -The upper limit of building's energy use in BTU's per square foot per year
• Life cycle cost analysis -The annualized cost of installing or constructing, operating and
maintaining any component or feature of building over its useful life or
'some portion thereof deemed appropriate in analysis