Racanelli Change Order Request
Racanelli Construction South, Inc. Proposal and Pricing Summary
1001 Pemberton Hill Road,Suite 202 RCS Project#19-008
Apex,NC 27502 Date: 11/11/2019
Submitted To:
Orange County
131 West Margeret Lane COR#2
Hillsborough, NC 27278
Attention : Angel Barnes via email
Per RCS PCO#2 dated 11/11/19, we are pleased to provide the following proposal per on-site request of Orange
County 11/5/19:
-Racanelli to look at pricing to install drainage underground between dock and new pad and daylight out to the wooded
area northeast of building. Per discussion with Tim Smith/Summit: Drainage pipe to be 6" smooth wall PVC.
Labor Material
Unit Unit Sub Unit Labor Material Subcontractor
Item Qty Unit Price Price Price Total Total Total Total
1 Racanelli(See attached) 1 LS $ 796.00 $ 328.00 $796 $328 $ 1,125.00
Subtotals $796 $328 $ 1,125.00
Small Tools&Consumables @ 7% on $ 796.00 $ 55.72
General Conditions $ -
Labor Burden 38% on $ 796.00 $ 302.48
Sales Tax on Materials 7.50% on $ 328.00 $ 24.60
Racanelli Construction South Overhead @ 10% on $ 1,507.80 $ 150.78
Racanelli Construction South Profit @ 5% on $ 1,658.58 $ 82.93
Insurance Premium @ 1.35% on $ 1,741.51 $ 23.51
TOTAL AMOUNT OF CHANGE ORDER REQUEST
TOTAL TIME(CALENDAR DAYS) REQUESTED FOR THIS CHANGE
Change Order Request accepted and authorized for contract Change Order
Authorized By Architect: Date:
Authorized By Owner: Date:
CC:
We Have Not been authorized to proceed with this work. By: saott W.DrebCtlzzo
This Proposal may be withdrawn from us if not accepted within 15 Days. Vice President
v
0
0
c
W
m'
Racanelli Construction South, Inc.
Piedmont Food&Ag Freezer Pricing Sheets PCO 2: Roof drinage extension o
aa,r� o.cc o srrc s— 0
v
ao
Unit Price TOTAL ESTIMATED—IFUnit Price TOTAL ESTIMATED OTAL ESTIMATED SUB TOTAL ESTIMATED MATT O
CODE DESCRIPTION . QUANTITY UNIT Labor LABORCOST Mat'I MATERIAL COST Unit Price Sub COST COST CODE m
REF
1 Material 4x5 downspout x 10' 1 EA 37.33 37 $ 37 w
2 Material 4x5 to 6"offset adapter PVC 1 EA 29.67 30 $ 30 4
3 Material 6"smooth wall PVC pipe(10') 6 EA 35.00 210 $ 210 °D
4 Material 6"smooth wall 90 degree fitting 1 EA 25.20 25 $ 25
m
51 Material PVC cement&primer 1 EA 26.00 26 $ 26
6 $
rn
IV
7 $ cn
8 Labor Procure mat.&tools,&del. 4 MH 30.63 123 $ 123
rn
9 Labor Hand excavation 10 MH 30.63 306 $ 306 4
w
10 Labor Pipe,downspout&adapter installation 6 MH 30_63 184 $ 184 OD
11 Labor Backfill&compact trench 4 MH 30.63 123 $ 123 n
12 Labor Clean up&return tools/equip 2 MH 30.63 61 $ 61
13 - $ -
14 $
15 $
16 $
17 $
18 $
19 $
20 $
21 $
22 $
23 $
24 $
25 $
26 $
27 $
J
$
$
1 is
SHEET TOTALS II II II II II 796 C 328 =� $ 1,125 �I
Check $ 1,125
DocuSign Envelope ID: BOOE2CO3-7FB1-43E1-B462-15595673B8DC
Racanelli Construction South, Inc. Potential Chang e
Racanelli 1001 Pemberton Hill Road, Suite 202
Apex, NC 27502 Order (PCO)
SUBMITTED TO: Piedmont Food and Ag Freezer
Orange County
131 West Margaret Lane RCS PROJECT NO.#
Hillsborough, NC 27278 19-008 PCO#2
ATTN;Angel Barnes PCO STATUS PCO. ISSUE DATE
1 11/11/19
DESCRIPTION OF CHANGE:
Per on-site request of Orange County 11/5/19:
• Racanelli to look at pricing to install drainage underground between dock and
new pad and daylight out to the wooded area northeast of building.
® DOCUMENTS ARE ENCLOSED.
SUBCONTRACTOR/SUPPLIER DISTRIBUTION:
STATUS:
1 ® Price quotations are requested within 3 working days from the date of this Potential Change Order. No work is
authorized until proposals are accepted and written authorization is given to proceed.
2 ❑ All concerned are authorized to proceed with the work of this Potential Change Order. Price quotations are requested
within 3 working days from the date of this PCO.
3 ❑ All concerned are authorized to proceed with the work of this Potential Change Order on a time and material basis.
Daily time and material slips must be signed by an authorized representative of RCS for verification of time and
materials utilized to complete the work requested.
CC: SWD/File BY: Scott W.Drebltlzo
DL/Field Senior Project Manager
NOTES: 1.)Subcontractors receive all PCO's via email unless otherwise noted.
2.)This change may affect project completion schedule. All Subcontractors must advise in writing of any impact of this change on their operation.
DocuSign Envelope ID: B00E2C03-7FB1-43E1-B462-15595673B8DC
DocuSign Envelope ID: BOOE2CO3-7FB1-43E1-B462-15595673B8DC mood and Ag Freezer
Racanelli Change Order Request
Racanelli Construction South, Inc. Proposal and Pricing Summary
1001 Pemberton Hill Road,Suite 202 RCS Project#19-008
Apex,NC 27502 Date: 1/7/2020
Submitted To:
Orange County
131 West Margeret Lane COR#3
Hillsborough, NC 27278
Attention : Angel Barnes via email
Per RCS PCO#3 dated 1/7/20, we are pleased to provide the following proposal to install epoxy flooring to match
existing in finish and thickness where the exterior walls were removed for the new freezer door openings.
Labor Material
Unit Unit Sub Unit Labor Material subcontractor
Item Qty Unit Price Price Price Total Total Total Total
1 Blair Duron Restoration,LLC(See attached) 1 LS $ 2,586.00 $ 2,586.00 $ 2,586.00
Racanelli:Patch/repair existing wall damage
between new door openings to allow for
2 epoxy cove base installation and repair. 4 MH $ 30.63 $122.521 $ 122.52
Subtotals J$122.52 $0 $ 2,586.00 $ 2,708.52
Small Tools&Consumables @ 5% on $ 122.52 $ 6.13
General Conditions $ -
Labor Burden 38% on $ 122.52 $ 46.56
Sales Tax on Materials 7.50% on $ -
Racanelli Construction South Overhead @ 10% on $ 2,761.21 $ 276.12
Racanelli Construction South Profit @ 5% on $ 3,037.33 $ 151.87
Insurance Premium @ 1.35% on $ 3,189.20 $ 43.05
TOTAL AMOUNT OF CHANGE ORDER REQUEST
TOTAL TIME(CALENDAR DAYS)REQUESTED FOR THIS CHANGE
Change Order Request accepted and authorized for contract Change Order
Authorized By Architect: Date:
Authorized By Owner: Date:
cc: SD/file
Notes: 1.)We reserve the right to claim additional cost and time extensions associated with this COR at a later time.2.)The epoxy color
selection will be matched to the existing as closely as possible, however it will most likely not be a perfect match and look like a patch.3.)
This COR includes 4"epoxy cove base to match existing at jamb returns and existing damages immediately adjacent to the new openings.
We Have been authorized to proceed with this work. By: Scott W.prebttl2o
This Proposal may be withdrawn from us if not accepted within 15 Days. Vice President
DocuSign Envelope ID: BOOE2CO3-7FB1-43E1-B462-15595673B8DC
Scott Drebitko
Subject: FW: Shot Blast slab in Hillsborough
Importance: High
From:Adam Blalock<adam@blairduron.com>
Sent:Tuesday,January 7, 2020 9:15 AM
To: Scott Drebitko<sdrebitko@racanelliconstruction.com>; Scott Wood <swood@racanelliconstruction.com>
Subject: RE: Shot Blast slab in Hillsborough
Importance: High
Scott,
We can provide the 24 square feet of epoxy patch and 6 linear feet of 4" integral cove base for$2,586.00 (Based on one
mobilization during normal business hours). Excludes caulking the top of the cove strip (by others).
We will get the epoxy color matched to the existing floor but keep in mind a patch is a patch is patch. It will probably
look like a patch, so please manage the customer's expectations.
If you have any questions please do not hesitate to contact me. Thank you for the opportunity and I look forward to
hearing from you.
Best Regards,
Adam Blalock
Blair Duron Restoration, LLC
NC Office
2001 W Garner Road
Garner, NC 27529
Office: 919-745-8211
Cell: 919-757-4430
**If this email constitutes an estimate or proposal;All pricing is based upon work being a capital improvement
project. No additional NC sales tax is applied. If work is classified as maintenance or repair work,please add the
current NC sales tax to the above pricing.
From: Scott Drebitko<sdrebitko@racanelliconstruction.com>
Sent: Monday,January 6, 2020 8:26 AM
To:Adam Blalock<adam@blairduron.com>; Scott Wood <swood@racanelliconstruction.com>
Subject: RE: Shot Blast slab in Hillsborough
Hi Adam,
Following up on the status of pricing for the epoxy at the two door openings.
1
DocuSign Envelope ID: BOOE2CO3-7FB1-43E1-B462-15595673B8DC
Thank you
Scott Drehitko
Vice President
Racaneiii Construction South,Inc.
1091 Pemberton Hill Road,Suite 102
Apex, NC 27502-4265
Tel: 919.363.3600
Fax:919.363.3700
Cell:919.812.5261
sdrebitko(a)racanelliconstruction.com
www.racanelIiconstruction.com
Confidentiality Notice: This e-mail message, including any attachments, is for the sole use of the intended recipient(s) and
may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited.
If you are not the intended recipient, please contact the sender by reply e-mail, delete and then destroy all copies of the
original message.
2
DocuSign Envelope ID: BOOE2CO3-7FB1-43E1-B462-15595673B8DC
Racanelli Construction South, Inc. Potential Chang e
Racanelli 1001 Pemberton Hill Road, Suite 202
Apex, NC 27502 Order (PCO)
SUBMITTED TO: Piedmont Food and Ag Freezer
Orange County
131 West Margaret Lane RCS PROJECT NO.#
Hillsborough, NC 27278 19-008 PCO#3
ATTN;Angel Barnes PCO STATUS PCO. ISSUE DATE
1 1/7/19
DESCRIPTION OF CHANGE:
Provide epoxy flooring to match existing in finish and thickness where the exterior walls were
removed for the new freezer door openings.
® DOCUMENTS ARE ENCLOSED.
SUBCONTRACTOR/SUPPLIER DISTRIBUTION:
Blair Duron Restoration
STATUS:
1 ® Price quotations are requested within 3 working days from the date of this Potential Change Order. No work is
authorized until proposals are accepted and written authorization is given to proceed.
2 ❑ All concerned are authorized to proceed with the work of this Potential Change Order. Price quotations are requested
within 3 working days from the date of this PCO.
3 ❑ All concerned are authorized to proceed with the work of this Potential Change Order on a time and material basis.
Daily time and material slips must be signed by an authorized representative of RCS for verification of time and
materials utilized to complete the work requested.
CC: SWD/File BY: Scott W.Drebltlzo
DL/SW/Field Senior Project Manager
NOTES: 1.)Subcontractors receive all PCO's via email unless otherwise noted.
2.)This change may affect project completion schedule. All Subcontractors must advise in writing of any impact of this change on their operation.