HomeMy WebLinkAboutAgenda - 01-21-20 12-8 - Information Item - Memorandum-Greater Triangle Commuter Rail (GTCR) Update 1
PLANNING & INSPECTIONS DEPARTMENT
Craig N. Benedict, AICP, Director
Administration 131 W. Margaret Lane
(919) 245-2575 Suite 201
(919) 644-3002 (FAX) ORANGE COUNTY P. O. Box 8181
www.orangecountync.gov NORTH CAROLINA Hillsborough, NC 27278
MEMORANDUM
TO: Board of County Commissioners
FROM: Craig Benedict, Orange County Planning Director
CC: Bonnie Hammersley, County Manager
Travis Myren, Deputy County Manager
DATE: January 16, 2020
SUBJECT: Greater Triangle Commuter Rail (GTCR) Update
Attached for your information is an update to the GTCR study that preliminarily evaluated
the Mebane to Selma rail corridor for commuter service.
Last year, the Board of Commissioners amended the Orange County Transit Plan to
include $75,000 to partner with Durham, Wake, and Johnston counties to update an
alternatives analysis for the Greater Triangle Commuter Rail project. This study represents
a preliminary evaluation of using the existing rail corridor used by Amtrak and freight for
commuter service. The total cost of related studies on the rail corridor and major
investment study (MIS) to date is approximately $1.7 million.
The study evaluates initial
• Ridership
• Cost of improvements (i.e. additional track, stations, and bridges)
• Operating costs
• Federal Funding Scoring
There have been over 15 meetings with project management partners including four
counties, GoTriangle, MPOs, and NC Railroad. Results of the study are now being shared
with governing boards of all partners.
The results of the study indicate that a connection between Durham and Wake Counties
may score well enough to qualify for federal funding while connections that include Orange
County would not score well enough. The attached PowerPoint illustrates the likely scores.
(See the table on Page 21 of this document).
Enclosures:
Attachment 1 — GTCR Preliminary Results PowerPoint
TIF 0 R w
A COMMUNITY INVESTMENT IN TRANSIT
Commuter Rail Update
January • •
a
3
Greater Triangle
Commuter Rail Study
Update of Alternatives
Analysis and Further Study
Draft/Preliminary
Findings Snapshot
4
Note
The Greater Triangle Commuter Rail project needs
additional study, coordination, and public engagement prior
to project design and implementation.
In the coming months, elected officials will consider
whether to proceed with this additional study.
GO FORWARD
A COMMUNITY INVESTMENT IN TRANSIT
Commuter Rail Background 5
The Commuter Rail Transit
project, as originally included ina�,- '
st riea�
the Wake and Durham county -�- m '°
1 �
transit plans, would run 37 miles '
a f�.
1
.f
from Garner to downtown r
Nanh R7P.
Raleigh, N.C. State, Cary, roC
P
Morrisville and the Research
Triangle Park continuing to 70
nsmie h 1
downtown Durham.
} esr Cary
fD0wn'mwV ram Wosr 64 ati Ca^Y3 <Sny
I e fsfglh Llhion
The current plan calls for: ;
�Evaluating up to eight trips in d01 h Ra (I` ' �°
each direction during peak hours SMr
with up to two trips each way 1y5 �-- �`°r °E2Mgr
f
10
during midday and evening
hours, for a total of twenty GC FORWARD
weekday round trips. A COMMUNITY INVESTMENT IN TRANSIT
6
WhyIs This StudyBeingConducted ?
• Give elected officials the data needed to decide whether to take
the project to the next phase of development
• Examine scenarios adding Johnston County/Selma and Orange
County/Mebane
• Refresh and update ridership estimates, infrastructure
assumptions, and cost estimates that were included in prior high-
level planning studies
• Identify additional activities necessary before initiating project
design and implementation
GO FORWARD
A COMMUNITY INVESTMENT IN TRANSIT
7
Who is ConductingStudy?This
Project Management Partners:
• Wake County
• Durham County
• Johnston County
• Orange County
• Capital Area Metropolitan Planning Organization
• Durham-Chapel Hill-Carrboro Metropolitan Planning Organization
• Research Triangle Foundation
• North Carolina Railroad Company
• GoTriangle
GO FORWARD
A COMMUNITY INVESTMENT IN TRANSIT
Altentatives
Ana
Develop Conceptsw
Perform
Preliminary
Operations Analysis w
Obtain Local
Funding
Commitment
Planning
Screen and Identity
Alternatives for
Further Study
Test and Refine
Alternatives
Obtain Concept
Concurrence and
initial Agreements
Preliminary Adopt Preferredl(/'`�\I
Engineering Alternative\
Initiate Informal
NEPA Scoping ^�
Perform Ad iinaf
Operatons
Analysis
DVe
ign
DesoConceptual Design
Obtain NEPA Class \../
of Action
Initiate Formal
NEPA Scoping
Complete
Preliminary Design
Obtain Preliminary
0 Final
Agreemerrts
Design Complete NEPA O
Advance Designe � '0
Finalize Local
Agreements
o
Begin Property
Acquisition \ O •
Prepareructio ro
Construction
Procurement
Secure Federal 1
Funding
0 Construction
Complete\e
Property
Acquisition
Construct
Infrastructure
Test Systems
o
Commission
Systems
Operate Pre-
Revenue Service 0-
Altentatives
Analysis
Develop Conceptsw
Perform
Preliminary
Operations Analysis w
Obtain Local
Funding
Commitment
Planning
Screen and Identify
Alternatives for
Further Study
Test and Refine
Alternatives
Obtain to
Concurrencence and
nitiai Agreements
Prel
in Adopt Preferred Engineerin Alternative
Initiate Informal
NEPA Scoping ^�
Perform Ad iinaf
Operatons
Analysis
Dve
evelop
Conceptual Design
Obtain NEPA ctass
ion \../
of Action
Initiate Formal
NEPA Scoping
Complete \✓
Preliminary Design
Obtain Preliminary �.../ 44
Agreemetrts 00
0 Final �� 1
Design CompleteNEPA1 1..../// O�► A C
Advance Design
00 •
Finalize Local '
Agreementso .10
Begin Property
Acquisition
Prepare for O•
Construction
Procurement
Secure Federal
Funding
0 Construction 1
•
Complete\�
Property
Acquisition
Construct
Infrastructure
Test Systems
o
Commission
Systems
Operate Pre-
Revenue Service 0-
Pre-
Sue planning
Perform
Alternatives
Analysis
Develop Concepts
Perform
Preliminary
Operations Analysis
Obtain Local
Funding
Commitment
Planning
Screen and Identify 0
Alternatives for O00
Further Study ?AE
Test and Refine
Alternatives
Obtain Concept A
Concurrence and0 O
Vj— Initial Agreements �� C
Adopt Preferred
Alternative
0
r'o� .•J
0
Preliminary
Engineering
Existing Rail Corridor
Freight Rail - Heavy Rail
• Freight operation constitutes the movement of goods and P.
cargo in freight rolling stock (e.g., boxcars, flatcars), which =
.. I
are typically hauled by diesel-powered locomotives. --- ----
• The North Carolina Railroad Company (NCRR) owns the r
317-mile corridor and Class I freight rail provider Norfolk
Southern operates and maintains the railroad through a
long-term lease with NCRR ---------
Intercity Rail - Heavy Rail, Shared Track
's.
• Intercity transit mode services covering longer distances titM
than commuter or regional trains
• The main provider of intercity passenger rail service in the
U.S. is Amtrak
• Four intercity passenger service routes run on the North
Carolina Railroad including the Carolinian and the Piedmont
which are sponsored by NCDOT
The North Carolina Railroad is built for the service it currently offers
Added capacity, including commuter rail, would require additional infrastructure, including added tracks
4 GO FORWARD
A COMMUNITY INVESTMENT IN TRANSIT
12
Finding: All Scenarios Necessitate Another Track
• Existing/Planned Traffic
• 27 freight and intercity passenger trains per day
• Scenario 1 : Three round trips in the peak periods
• +14 commuter trains per day (7 round trips)
• Scenario 2 : Five round trips in the peak periods
• +24 commuter trains per day ( 12 round trips)
• Scenario 3 : Eight round trips in the peak periods
• +40 commuter trains per day (20 round trips)
GO FORWARD
A COMMUNITY INVESTMENT IN TRANSIT
13
Busiest Stations in Raleigh and Durham
00 ( 00
Note: circle sizes are relative to the number of boardings at stations within each jurisdiction
Ja
GO FORWARD
A COMMUNITY INVESTMENT IN TRANSIT
14
Busiest Stations in Wake and Durham Counties
Durham
0
Note: circle sizes are relative to the number of boardings at stations within each county.
Vic::
RWARD
IN IN TRANSIT
15
This is a PreliminaryFeasibilityStudy
• Further detailed railroad capacity modeling would be needed to
confirm infrastructure requirements
• Cost estimates require further definition
o Cost estimates are planning-level
o No engineering has been performed yet as part of this study
o Cost estimates would be refined once preliminary engineering
work and railroad capacity modeling is completed
• Ridership estimates would require further refinement
GO FORWARD
A COMMUNITY INVESTMENT IN TRANSIT
16
Evaluated Eight Scenarios
End Points Round Range of Cap. O&M Cost Range of
Trips • • 119$] Ridership
Durham-Garner 8-2-8-2 $1.413 — $1.813 $29M 7.51K — 10K
Durham-Garner 5-1-5-1 $1.413 — $1.813 $20M 5K — 7.5K
Durham-Garner 3-1-3 $1.413 — $1.713 $13M 4.51K — 6K
Mebane-Selma 8-2-8-2 $2.513 — $3.213 $57M 8K — 11.5K
Mebane-Selma 5-1-5-1 $2.513 — $3.213 $40M 6K — 9K
Mebane-Selma 3-1-3 $2.3B — $3.113 $26M 5K — 7.5K
Hillsb.-Clayton 8-2-8-2 $1.813 — $2.413 $44M (+$15M) 8K — 11.5K
Durham-Clayton 8-2-8-2 $1.613 — $2.113 $37M (+$8M) 7.5K — 10K
■ Current Wake Transit Plan assumes $1.33B capital cost for Durham-Garner 8-2-8-2
• • • - • itu re D. •
Ridership: verageurrentearzonearorecast
GO FORWARD
A COMMUNITY INVESTMENT IN TRANSIT
17
Funding Capacity
Needs federal funding to be affordable
Orange: Incremental cost to include Hillsborough
and/ or Mebane is large relative to est. ridership
Johnston: Would require significant additional new
revenue
Durham and Wake: Affordability will depend on:
o Cost share
o Prioritization versus other investments
o Ability to control costs
18
Project Must Meet Set Criteria for Federal Funding
The Federal Transit Administration publishes guidelines for
project evaluation and rating as a part of the Federal New
Starts program
To be eligible for federal funding, projects must score a
Medium overall rating across a range of pre-determined
categories assessing financial factors, ridership and travel
demand projections, and corridor characteristics (e.g.
population and employment)
4111 GO FORWARD
A COMMUNITY INVESTMENT IN TRANSIT
dt
Mobility Improvements
(16.66%)
y Environmental Benefits
I (16.66%)
Congestion Relief
(1&r36%) 1 1 Project Justification'
Cost-Effectiveness I (50% of Overall Rating)
(16.66%)
i ..
t be
�Economic Development , -Medium
or better Ovefail Rating
Land use I Overall Project Rating
(16.66%)
Current Condition
(25%) � Local Financial �
Commitment of Funds Commitment,
(25%) (50%of Overall Rating) �
Reliability/Capacity
(60%)
FORWARDGO
COMMUNITY • .
20
Driven by �Six Project Justification Factors
Criterion Description Based on Cost Estimates and Ridership Modeling
Calculated Based on Average of Current Year (2018) and Horizon Year (2040) Models
Mobility Total annual trips on the project, with trips of riders from zero-car
Improvements households doubled
Environmental Monetized benefit of change in vehicle miles traveled, divided by
Benefits annualized cost (capital and O&M)
Congestion Relief New weekday trips on the project
Cost Effectiveness Total annual project trips divided by annualized cost (capital and O&M)
Criteria Based on Corridor Characteristics
Economic Qualitative score based on city and county- adopted plans and policies,
Development
their performance, the potential of the project to impact development
patterns and affordable housing plans and policies.
Quantitative and qualitative score based on existing station area
Land Use population density, jobs, affordable housing, central business district
parking ratio and cost, and built environment characteristics
21
Lower Service and Higher Cost Scenarios Do Not Score Well
Mebane-Selma 8-2-8-2 - • • Medium - • •
Mebane-Selma 5-1-5-1 - • • Weak Medium - • •
Mebane-Selma 3-1-3 - • Uo VIMWeak Medium - • •
Durham-Garner 8-2-8-2 Me d ium Medium - • •
Durham-Garner 5-1-5-1 Weak Medium Weak Medium - • •
Durham-Garner 3-1-3 Weak Medium Weak Medium - • •
Hillsb.-Clayton 8-2-8-2 Weak Medium Medium - • •
Durham-Clayton 8-2-8-2 Medium Medium - • •
Note: Scenarios rated as "Weak Medium" are projected to score at the low end of the Medium range, meaning
that if any single component score is reduced, the overall score would fall below the eligibility requirements
To be = ' funding,must GO FORWARD
rating A COMMUNITY INVESTMENT IN TRANSIT
• - Medium
22
Peer Comparison
• Prior Major Investment Study identified peer systems for
comparison of key metrics:
o System Capital Cost
o Capital Cost Per Mile
o Average Weekday Trips
o Average Trip Length
o Capital Cost Per Passenger Mile Traveled
o Operating Cost Per Passenger Mile Traveled
note: not all data were available for each peer system
GO FORWARD
A COMMUNITY INVESTMENT IN TRANSIT
System Capital Cost (2020$) 23
$3,000,000,000
$2,500,000,000
$2,000,000,000
$1,500,000,000
$1,000,000,000
$500,000,000
$0
°� �aQ O��a O
�Ne
GO FORWARD
System Capital cost in 2020$ A COMMUNITY INVESTMENT IN TRANSIT
Source: 2019 CRT MIS Report
Capital Cost (2020$)/Mile 24
$45,000,000
$40,000,000
$35,000,000
$30,000,000
$25,000,000
$20,000,000
$15,000,000
$10,000,000
$5,000,000 j ink I a
$0
ON
��ay a`\Q�
C,-A �� rya ��a �'� ram � a� C.°I,
GO FORWARD
System Capital Cost in 2020$ divided by length of system. A COMMUNITY INVESTMENT IN TRANSIT
Source: 2019 CRT MIS Report
Average Weekday Trips (2018) 25
20,000 18,127
17,815
18,000
16,000
14,000
12,000
10,000
8,000 6,170 6,405 6,502 7,341
6,000
4,000 ol EA 2,805 2,901 3,198
2,000 214 470 ,
0 d=w 1
'N .��'N `�� ��` ao� NO �"V �;L r� OLD ���
NO Ne,
e
op-
�o Coo t10, �a�\� �'`�o ��� c`��' � �aJ e�\�
1+1
�a
a�
GO FORWARD
Average Weekday Ridership for 2018. A COMMUNITY INVESTMENT IN TRANSIT
Source: NTD 2018 and GoTriangle FY2018 Bus Performance Report.
Average Trip Length (miles) 26
35
31
30
25 °esss
26 —
20 �� 16 17 18 19
JA 15
15 12 13
10
5
0
tea`` °tea` � a °��.
'`�`a� `�`�� �a`��a ee,+0
h °
P ` k �a
441
�a
a�
GC FORWARD
Average Unlinked Trip length. A COMMUNITY INVESTMENT IN TRANSIT
Source: NTD 2018 and GoTriangle FY2019 Bus Operations Report.
Capital Cost (2020$) / Annual Passenger Miles Traveled (2018) 27
$80
$70
$60
$50
$40
$30
$20 $17
$10
$0
06
oQCIO
.
GC FORWARD
Average System Capital Cost in 2020$ divided by total annual passenger miles traveled A COMMUNITY INVESTMENT IN TRANSIT
Source: NTD 2018 and 2019 CRT MIS Report.
Operating Cost (2019$) / Annual Passenger Miles Traveled (2018) 28
$3.50
., 3.01
$3.00
$2.50
$1.95
$2.00 $1.69
$1.50
6 $07 $
$1.00 $0.77
$0.57
$0.50
$0.00
a� 4 I I I
� "L6L ° o
.A Lr 4, �
`� �� o ; y s ;y06
Oa
�A� Oar a��`S yea �a C�° �� e��° a`�`
�� P
�a
GC FORWARD
Average System Operating Cost in 2019$ divided by total annual passenger miles traveled A COMMUNITY INVESTMENT IN TRANSIT
Source: NTD 2018, and GoTriangle FY19 Bus Operations Report
29
Remaining Study Effort
• Refine ridership and travel demand
modeling
• Additional funding capacity analysis
for Durham and Wake
• Discuss initial risk assessment with
GoTriangle Board
30
Potential Next Phase of Study
"Early Project Development Activities"
Rail Traffic Controller ( RTC) model
Preliminary engineering to evaluate critical risks only (e.g.
Downtown Durham grade crossings)
Additional ridership modeling
Public engagement, integrated with local plan updates
Agreements with funding partners, municipalities, and railroads
GO FORWARD
A COMMUNITY INVESTMENT IN TRANSIT
Pre-
planning
Perform
Alternatives
Analysis
Develop Concepts
i
Perform
Preliminary
Operations Analysis
Obtain Local
00� Funding
Commitment
O�
6`
Planning
Screen and Identify C
Alternatives for
Further Study
Test and Refine
Alternatives
Obtain Concept
Concurrence and
O initial Agreements
�O
v Adopt Preferred
�0 Alternative
�G2�
�L
�i
�Z�07�
` \ � �rrsnrccrnrFj
Initiate(Informal/
NEPA Scoping
Perform Additional
Operations
Analysis
Develop
Conceptual Design
Obtain NEPA Class
of Action
1 Initiate Formal
NEPA Scoping
Complete
O Preliminary Design
l Obtain Preliminary
Agreements
�,k Final
Design Complete NEPA
0
Advance Design
Finalize Local
Agreements
Begin Property
Acquisition
0 Prepare for
Construction
l Procurement
Secure Federal
�f► Funding
OOS
Construction
Complete
Property
Acquisition
Construct
Infrastructure
t*O Test Systems
Commission
Systems
C� J► Operate Pre-
0 0 � Revenue Service
G�lot
Revenue
Q
��� Service
33
Next Steps
• Present updated results and metrics
• Present risk assessment - GoTriangle board workshop on Jan . 22
• Primer on risk for transit capital projects
• Walk-through of initial risk assessment findings
• Consider pursuing early project development activities necessary
prior to initiating project design and implementation
• Consider adopting memorandum of understanding among project
management partners for early project development activities
• Roles, responsibilities, and goals of the project management partners,
municipalities, and other stakeholders if moving forward
Go FORWARD
A COMMUNITY INVESTMENT IN TRANSIT