Loading...
HomeMy WebLinkAboutORD-2019-039 Budget Amendment #2-C – Approval of an Intermediate Budget for the Link Government Services Center Remediation Project ORD-2019-039 ORANGE COUNTY BOARD OF COMMISSIONERS ACTION AGENDA ITEM ABSTRACT Meeting Date: November 7, 2019 Action Agenda Item No. 8-g SUBJECT: Budget Amendment #2-C – Approval of an Intermediate Budget for the Link Government Services Center Remediation Project DEPARTMENT: County Manager ATTACHMENT(S): INFORMATION CONTACT: Travis Myren, 919-245-2308 Steve Arndt, 919-245-2658 Gary Donaldson, 919-245-2453 PURPOSE: To approve a budget amendment totaling $975,000 to fund an intermediate budget for the Link Government Services Center Remediation Project. The intermediate budget would fund the temporary relocation of building occupants while a final project scope is approved and completed. BACKGROUND: The Link Government Services Center has experienced long term water infiltration into the building envelope. A remediation project has been planned, and the project has been let for bid twice. The first set of bids was deemed non-responsive because the apparent low bidder declined to share information with the County that would have been necessary to complete a comprehensive analysis of the bid. As a result, all bids were rejected on September 5, 2019, and the bid specifications were modified to require the missing information as a condition of the bid. The second set of bids was received on September 25, 2019. However, these bids were also rejected to afford the apparent low bidder an opportunity to establish a joint venture as a way to comply with the bid requirements. On October 20, 2019, moderate rainfall occurred at the Link Center and resulted in visible quantities of water penetrating the interior of the building. During this same time, indoor air quality tests began to indicate higher levels of biological contaminants compared to identical tests taken throughout the prior year. These changing conditions warranted a root cause analysis to confirm that the scope of the remediation project would correct the deficiencies that were allowing the additional water penetration. On October 24, 2019, an architect and building engineer performed a series of investigative demolition cuts into the building’s cavity wall. According to the architect’s report, these cuts 1 revealed, “…a critical element of the building envelope, the continuous sheathing, was in fact, not continuous.” The architect and engineer further reported that, “The breeches were irregular enough to confidently say that a contractor would not be able to find all breeches and seal them to prevent future water intrusion without removing all of the brick and cast stone.” The scope of the current remediation project that was bid on two previous occasions does not include this additional scope of work which would add to the projected cost and duration of the project and may approach the cost and duration of new construction. The architect who is contracted to work on the Link Remediation Project is scheduled to present findings to the Board of Commissioners at the November 19, 2019 meeting. At that time, the architect will also present options to proceed, including the probable costs and duration for each option. As these options are evaluated and implemented, both an industrial hygienist and an occupational health professional who have been working with the County on this project have advised relocating the building occupants on a short but reasonable timeline. Budget Amendment #2-C provides an intermediate budget of $975,000 to relocate the Link Government Services Center building occupants for the remainder of FY 2019-20. Of this total amount, $127,000 in PAYGO funds will be redirected from two projects in the FY2019-20 Capital Budget to the Asset Management Services operating budget to fund operational costs related to rent, utilities, and maintenance. These capital projects will now be funded with debt proceeds. The remaining remediation related costs of $848,000 will be budgeted in the Link Center Remediation Capital Project. This increase will be debt financed. Additional funds needed beyond FY 2019-20 will be included in future fiscal year budget appropriations. Upon approval of this budget amendment, the current Link Center occupants will be relocated to four different locations: • The Public Defender’s Office is being relocated to a leased building at 115 E. King Street. • Finance and Administrative Services, Public Affairs, the Arts Commission Director, and the Risk Manager will be relocated to a leased facility at 405 Meadowlands Drive. • The Homeless Services Coordinator will move to existing office space in the Housing and Community Development Department. • The remaining occupants, the County Manager’s Office and the Clerk’s Office, will move to the Whitted Building. The leased facilities and the Whitted facility will be modified to accommodate a long term relocation. This budget amendment amends the following Link Center Remediation Capital Project, as well as the Court Street Annex and Equipment & Vehicles Capital Project Ordinances: 2 Link Center Remediation Capital Project ($848,000) - Project #10069 Revenues for this project: Current FY 2019-20 FY 2019-20 Amendment FY 2019-20 Revised Alternative Financing $178,000 $848,000 $1,026,000 Total Project Funding $178,000 $848,000 $1,026,000 Appropriated for this project: Current FY 2019-20 FY 2019-20 Amendment FY 2019-20 Revised Professional Services $117,000 $110,000 $227,000 Construction $61,000 $738,000 $799,000 Total Costs $178,000 $848,000 $1,026,000 Court Street Annex Capital Project - Project #10004 Revenues for this project: Current FY 2019-20 FY 2019-20 Amendment FY 2019-20 Revised Alternative Financing $168,600 $20,000 $188,600 From General Fund $20,000 ($20,000) $0 Total Project Funding $188,600 $0 $188,600 Appropriated for this project: Current FY 2019-20 FY 2019-20 Amendment FY 2019-20 Revised Professional Services $17,500 $0 $17,500 Equipment $46,100 $0 $46,100 Construction $125,000 $0 $125,000 Total Costs $188,600 $0 $188,600 Equipment & Vehicles Capital Project - Project #30010 Revenues for this project: Current FY 2019-20 FY 2019-20 Amendment FY 2019-20 Revised Alternative Financing $2,083,423 $107,000 $2,190,423 From General Fund $107,000 ($107,000) $0 NCDOT Funds $349,627 $349,627 Total Project Funding $2,540,050 $0 $2,540,050 Appropriated for this project: Current FY 2019-20 FY 2019-20 Amendment FY 2019-20 Revised Vehicles $2,540,050 $0 $2,540,050 Total Costs $2,540,050 $0 $2,540,050 FINANCIAL IMPACT: This budget amendment would add $848,000 to the FY2019-20 Capital Budget, and move $127,000 from the Transfer to County Capital function of the FY 2019-20 General Fund to the Asset Management Services Budget as an intermediate step toward a full remediation of the Link Government Services Center. The intermediate budget would fund the 3 temporary relocation of building occupants for FY 2019-20 while a final project scope is approved and completed. SOCIAL JUSTICE IMPACT: There is no Orange County Social Justice Goal impact associated with this item. ENVIRONMENTAL IMPACT: The following Orange County Environmental Responsibility Goal impacts are applicable to this item • RESULTANT IMPACT ON NATURAL RESOURCES AND AIR QUALITY Assess and where possible mitigate adverse impacts created to the natural resources of the site and adjoining area. Minimize production of greenhouse gases. • ENVIRONMENTALLY PREFERABLE PURCHASING Promote the use of chemicals, materials, equipment, and systems which are officially recognized as to minimize environmental impacts. RECOMMENDATION(S): The Manager recommends that the Board approve Budget Amendment #2-C, authorize the County Manager to execute a lease for 405 Meadowlands Drive, and ratify the Manager’s signature for a lease for 115 East King Street. 4