Meeting Date: September 17, 2019
Action Agenda
Item No. 8-e
SUBJECT: Link Building Remediation Project — Rejection of Bids
DEPARTMENT: County Manager, Asset
Management Services
ATTACHMENT(S): INFORMATION CONTACT:
Travis Myren, Deputy County Manager,
919-245-2308
Steven Arndt, AMS Director, 919-245-
2658
John Roberts, County Attorney, 919-
245-2318
PURPOSE: To authorize the County Manager to reject all bids for the Remediation of the John
M. Link, Jr. Government Services Center project that were opened on Thursday, September 5,
2019, and to rebid the project.
BACKGROUND: Over a period of time, the John M. Link, Jr. Government Services Center
facility has developed a number of water intrusion issues related to deficiencies in the building
envelope. Earlier this year, plans and specifications were developed to address these issues,
and the project was advertised for bids in August 2019, with the primary purpose of the project
being remediation of the water intrusion issues and effects thereof. Bids for the project were
opened on Thursday, September 5, 2019, with the result of an apparent low bid of $4,286,300.
Upon review of the apparent low bid, County staff re-evaluated the County's needs related to
the project and bid evaluation and determined that more information is needed from all bidders
to thoroughly and diligently examine the project bids. Due to the size of the project, Board of
Commissioners' approval is required to reject the bids.
FINANCIAL IMPACT: There are no direct financial impact associated with this item.
SOCIAL JUSTICE IMPACT: There is no Orange County Social Justice Goal impact associated
with this item.
ENVIRONMENTAL IMPACT: There are no Orange County Environmental Responsibility Goal
impacts associated with this item.
RECOMMENDATION(S): The Manager recommends that the Board reject all bids for the
Remediation of the John Link Government Center project that were opened on Thursday,
September 5, 2019, and authorize the Manager to notify all bidders and rebid the project.