CHANGE ORDER NO.: 8
Page 1 of 2
CHANGE ORDER
CHANGE ORDER NO.: 8 DATE:March 18,2019
Project: Historic Rogers Road Sewer Expansion Project
Contractor: Moffat Pipe, Inc.
Engineer/Architect: URS Corporation—North Carolina
CONTRACTOR is directed to make the following changes in the Contract Documents.
Description: Moffat Pipe,Inc. is requesting the following revisions to the substantial completion and final
completion dates of the contract to account for delays in the project considered to be no fault of their own
and beyond their control. Specifically, they have been delayed with excessive weather delays and delays
associated with the septic system emergency pump and haul set-up and operation for the property at 7619
Rogers Road, as well as numerous utility locates due to unmarked cable lines along Tallyho Trail. An
itemized list of the number of days associated with specific issues can be found in Attachment A--HRRA
Coordination Issues/Delays. This Change Order is for weather delays experienced between January 22,
20I9 and March 18, 2019, as well as non-weather delays experienced between November 2018 and
March 18,2019 and does not account for potential future delays from rock blasting,or any other item.
CHANGE IN CONTRACT SLIM OR PRICE: CHANGE IN CONTRACT TIME OR TIMES:
Original Contract Price Original Contract Times
$4,782,436.00 Final Completion: July 15,2018
Net change from previous Change Orders No. 1 to Net change from previous Change Orders No. I to
No.7: $180,683.44 No.7: 250 days
Contract Sum or Price prior to this Change Order Contract Times prior to this Change Order
$4,963,119.44 Final Completion: March 22,2019
Net Increase of this Change Order Net Increase of this Change Order
$0.00 Forty-two(42)calendar days
Contract Sum or Price with all approved Change Contract Times with all approved Change Orders
Orders
$4,963,119.44 Final Completion: May 3,2019
RECOMMENDED: REVIE D: - ACCE ED:
By, B By: Cu-
Engineer ange Con ractor
Krista Paredes-Toledo, PE Craig Benedict,AICP Jes DuCla
Date: 3/18/19 Date: � Date:
CHANGE ORDER NO.: 8
Page 2 of 2
The adjustment in Contract Sum or Price and/or Contract Time or Times stated in this Change Order shall
comprise the total price and/or time adjustment due or owed the CONTRACTOR for the work or changes
defined in this Change Order. By executing the Change Order, the CONTRACTOR acknowledges and
agrees that the stipulated price and/or time adjustments include the costs and delays for all work
contained in the Change Order, including costs and delays associated with the interruption of schedules,
extended overheads, delay, and cumulative impacts or ripple effect on all other non-affected work under
this Contract. Signing of the Change Order constitutes full and mutual accord and satisfaction for the
adjustment in Contract Sum or Price or Contract Time or Times as a result of increases or decreases in
costs and time of performance caused directly and indirectly from the change, subject to the current scope
of the entire work as set forth in the Contract Documents. Acceptance of the waiver constitutes an
agreement between OWNER and CONTRACTOR that the Change Order represents an equitable
adjustment to the Contract, and that CONTRACTOR waives all rights to file a claim on this Change
Order after it is properly executed.
IN WITNESS WHEREOF,the undersigned have caused the execution hereof:
CONTRACTOR:
MOFFAT ME INC
ATTEST: By:
Name: Jesse DuClau
Title: Contractor
Secretary Address: 4901 Unicon Drive
Date; ore aI s#,NC 27587
[Corporate Seal]
OWNER:
Orange Co�oty
By;/,
.
Name: Bonnie Hammers/
Title: Ora ge Cou ty Manager
Date: c�
Change Order 8 Request
Attachment A
Weather Delays
Anticipated/
Month Description Contract Actual/Impact Requested Notes
Jan 22- Rain/Snow/Sleet Delays and Impact 10 10 0 24,25,29
Feb Rain/Snow/Sleet Delays and Impact 10 14 4 11,12,13,16,17,19,20,21,22,23,24,25,26,28
18-Mar Rain/Snow/Sleet Delays and Impact 10 9 0 1,2,3,4,8,9,10,15,16
Subtotal 4
Work Delays
Month Description Days Notes
Feb-Mar Utility locating impacts along Tally H❑ 10
Nov-Mar Septic Repair/Bypasing 16
Subtotal 26
Total Work Days 30
Total Calendar Days 42
Total this request 42