HomeMy WebLinkAboutORD-2019-018 Approval of Budget Amendment #8-A for Repair of the Soltys Adult Day Health Space at the Passmore Center 1
ORD-2019-018
ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: May 2, 2019
Action Agenda
Item No. 8-e
SUBJECT: Approval of Budget Amendment #8-A for Repair of the Soltys Adult Day Health
Space at the Passmore Center
DEPARTMENT: Asset Management Services
ATTACHMENT(S): INFORMATION CONTACT:
Alan Dorman, 919-245-2627
Travis Myren, 919-245-2308
PURPOSE: To approve Budget Amendment #8-A for the repair of the space occupied by the
Florence Gray Soltys Adult Day Health Program at the Passmore Center.
BACKGROUND: Recently, surface staining that had the appearance of mold was discovered in
the fitness room of the space occupied by the Florence Gray Soltys Adult Day Health Program
("Soltys") at the Passmore Center. As soon as these stains were identified, the fitness room
was sealed off and the areas of possible mold were contained to ensure the safety of clients and
staff. Air and surface sampling was conducted and confirmed the presence of mold on several
pieces of furniture and on several places on the west and north walls of the fitness room.
Further testing within the wall cavity identified some additional mold. A remediation and repair
proposal was developed by a certified remediation contractor based on the report provided by
the industrial hygienist that performed the air and surface testing.
The underlying cause of the mold in the fitness room is the lack of insulation in the walls that
separate the cold air of the Sportsplex ice rink from the warm air within the Soltys' space. This
means that the wall surface is cool and allows for condensation, and which has created an
environment for mold to grow.
The repair will include:
• Removal and cleaning of the contents of the fitness room.
• Removal of the contaminated sheet rock wall from inside of the fitness room.
• Rebuilding the wall with the addition of insulation to help avoid future issues.
Total estimated project time from the start of construction is one month. Soltys will continue to
provide services during the construction process so every effort will be made to minimize the
impact of construction on the Soltys clients and staff.
2
As this project was not anticipated as part of the Capital Projects budget, a budget amendment
is necessary to finance this project. The budget amendment provides for the creation of the
following Capital Project Ordinance:
Soltys Remediation at Passmore Center($110,564) - Project# 10071
Revenues for thisproject:
Current FY 2018-19 FY 2018-19
FY 2018-19 Amendment Revised
Alternative Financing $0 $110,564 $110,564
Total Project Funding $0 $110,564 $110,564
Appropriated for this project:
Current FY 2018-19 FY 2018-19
FY 2018-19 Amendment Revised
Construction $0 $110,564 $110,564
Total Costs $0 $110,564 $110,564
FINANCIAL IMPACT: Financing proceeds from the scheduled Fall 2019 financing package will
fund this project.
SOCIAL JUSTICE IMPACT: The following Orange County Social Justice Goal is applicable to
this item:
• GOAL: ENSURE ECONOMIC SELF-SUFFICIENCY
The creation and preservation of infrastructure, policies, programs and funding necessary
for residents to provide shelter, food, clothing and medical care for themselves and their
dependents.
The repair of the space occupied by the Florence Gray Soltys Adult Day Health Program at the
Passmore Center will ensure that it can continue to provide its services to the residents of the
County.
RECOMMENDATION(S): The Manager recommends that the Board approve Budget
Amendment #8-A for the repair of the space occupied by the Florence Gray Soltys Adult Day
Health Program at the Passmore Center.