HomeMy WebLinkAbout2019-245-E AMS - Sasser Companies Annex remediation DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
[Departmental Use Only]
TITLE BOE Water Mitigation
FY 2018-19
NORTH CAROLINA
CONSTRUCTION AGREEMENT OVER $250,000.00
ORANGE COUNTY
THIS CONSTRUCTION AGREEMENT (hereinafter called "Agreement"), made as of the 3rd day of
April, 2019, by and between Sasser Companies, Inc., (hereinafter called the "Contractor"), and Orange
County, a political subdivision of the State of North Carolina, (hereinafter called the "County," "Orange
County," or"Owner").
WITNESSETH:
That the Contractor and the Owner, for the consideration herein named, agree as follows:
1. CONTRACT DOCUMENTS; PRIORITY
The Contract Documents consist of this Agreement, the General Conditions which are fully
incorporated in this Agreement, the Request for Proposals, designer approved communications and/or field
orders, the Proposal, Construction Documents and Drawings and Written Specifications. The Contract
Documents form the Contract. In the event of any inconsistency between or among the Contract Documents
the Contract Documents shall be interpreted in the following order of priority:
a. This Agreement and incorporated General Conditions attached as Exhibit 1.
b. Designer approved and stamped construction documents and drawings and written
specifications.
c. Designer approved communications and/or field orders.
d. Request for Proposals and addenda thereto.
e. Proposal.
2. SCOPE OF WORK
The Contractor shall furnish and deliver all of the materials, and perform, and be fully responsible
for all of the Work required by this Agreement within the time period stipulated in a written Notice-to-Proceed
to be executed by the Contractor and Owner and in accordance with the following enumerated documents,
which are made a part hereof as if fully contained herein:
a. Construction Drawings prepared by N/A (Sheet Scope of Work Document and cost breakdown
dated 3/27/19)
b. Written specifications prepared by the Designer.
c. Sasser Companies, Inc. proposal dated January 22, 2019 which fully describes the work to be
performed, such work(hereinafter called the "Work").
Revised 12/18 1
DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
d. Related documents listed under Section 2 above.
3. TERM AND SCHEDULING
a. The Contractor agrees to commence work pursuant to the written Notice-to Proceed.
b. The Contractor agrees to complete substantially all Work included by December 31, 2019.
c. Time is of the essence with respect to all dates specified in the Contract Documents as
Completion Dates.
d. The Contractor shall perform the Work in the time, manner and form required by the Contract
Documents and as stipulated in a written Notice-to-Proceed to be executed by the Contractor
and Owner.
4. STANDARD OF CARE AND DUTIES OF CONTRACTOR
a. The Contractor shall exercise reasonable care and diligence in performing the Work in
accordance with the generally accepted standards of this type of Contractor practice throughout
the United States and in accordance with applicable federal, state and local laws and
regulations applicable to the performance of these services. Contractor is solely responsible
for the professional quality, accuracy and timely completion and/or submission of all work.
b. The Contractor shall not load or permit any part of the Work to be loaded with a weight that
will endanger its safety, intended performance or configuration.
c. Contractor shall be responsible for all Contractor, Subcontractor, and Sub-subcontractor errors
or omissions, in the performance of the Agreement together with the errors and omissions of
any agent or employee of the Contractor or any Subcontractor or Sub-subcontractor.
Contractor shall correct any and all errors, omissions, discrepancies, ambiguities, mistakes or
conflicts at no additional cost to the Owner.
d. Contractor is an independent contractor of Owner. Any and all employees of the Contractor
engaged by the Contractor in the performance of any work or services required of the
Contractor under this Agreement, shall be considered employees or agents of the Contractor
only and not of the Owner, and any and all claims that may or might arise under any workers
compensation or other law or contract on behalf of said employees while so engaged shall be
the sole obligation and responsibility of the Contractor.
e. Contractor shall at all times remain in compliance with all applicable local, state, and federal
laws, rules, and regulations including but not limited to all state and federal -discrimination
laws, policies, rules, and regulations and the Orange County Non-Discrimination Policy and
Orange County Living Wage Policy (each policy is incorporated herein by reference and may
be viewed at http://www.oran eg countync. ovg /departments/purchasing_division/contracts.php).
Any violation of the Orange County Non-Discrimination Policy is a breach of this Agreement
and County may immediately terminate this Agreement without further obligation on the part
of the County. This paragraph is not intended to limit and does not limit the definition of
breach to discrimination.
Revised 12/18 2
DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
f. If activities related to the performance of this Agreement require specific licenses,
certifications, or related credentials Contractor represents that it and/or its employees, agents
and subcontractors engaged in such activities possess such licenses, certifications, or
credentials and that such licenses certifications, or credentials are current, active, and not in a
state of suspension or revocation.
g. The Contractor shall supervise and direct the Work efficiently and with the Contractor's best
skill and attention. Except as specifically set forth in the Contract Documents the Contractor
shall be solely responsible for the means, methods, techniques, sequences and procedures of
construction, and for safety precautions and programs in connection with the Work. The
Contractor shall be responsible to see that the finished Work complies accurately with the
Contract Documents.
h. The Contractor shall appoint a competent Project Manager with general authority to manage
the Project for the Contractor. The Contractor shall also keep on the Project at all times during
the Work of the Contractor a competent Resident Superintendent and necessary assistants who
shall not be replaced without prior written approval by the Designer or by the Owner if a
Designer is not retained for the Project.
i. If, in the opinion of the Designer, any Subcontractor on the Project is incompetent or otherwise
unsatisfactory, such Subcontractor shall be replaced by the Contractor with no increase in the
Contract Price if and when directed by the Designer.
j. The Contractor shall attend all progress conferences and all other meetings or conferences.
The Contractor shall be represented at these progress conferences by a representative having
the authority of the Project Manager and by such other representatives as the Designer may
direct.
k. Costs and expenses of providing samples for and assistance in any testing shall be borne by the
Contractor. Any Work in which untested materials are used without approval or written
permission of the Owner and/or Designer shall be removed and replaced at Contractor's
expense.
1. The Contractor shall obtain all necessary permits including all permits required to complete the
Work in compliance with local, state, and/or federal law.
5. PAYMENT & TAXES
a. The Owner hereby agrees to pay to the Contractor for the faithful performance of this
Agreement, and the Contractor hereby agrees to perform all of the Work for a sum not-to-
exceed Five Hundred Fifty Five Thousand Seven Hundred Seventy Six Dollars ($555,776 ).
Not later than the fifth (5th) day of each calendar month the Contractor shall submit to the
Owner's Representative, generally the Designer if a Designer is retained on the Work, a
Request for Payment for work done during the previous calendar month.
(i) The Request for Payment shall be in form of a standardized invoice or AIA Document
G702-703 appropriately addressed to Owner's Representative at PO Box 8181,
Hillsborough NC 27278 and shall show substantially the value of work done during the
previous calendar month.
Revised 12/18 3
DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
(ii) The amount due for payment shall be ninety-five percent (95%) of the value of work
completed since the last Request for Payment and this amount shall be paid by the
Owner on or before the last business day of the month. Owner shall retain five percent
(5%) (the "Retainage").
(1) Upon Owner's Representative's certification that fifty percent (50%) of the
Work has been satisfactorily completed Retainage shall be reduced to two and
one half percent(21/2%).
(2) Upon Owner's Representative's certification that ninety percent (90%) of the
Work has been satisfactorily completed Retainage may be discontinued.
Retainage may be discontinued, at Owner's Discretion, so long as work
continues to be completed satisfactorily and on schedule.
(iii) Final payment shall not be due to the Contractor until thirty (30) days after Final
Completion of the Work, including punch list work, has been satisfactorily completed
and an appropriate Affidavit, Indemnification, and Release as required in Section 8(d)
below has been received by Owner.
b. Should Owner reasonably determine that Contractor has failed to perform the Work related to
a Request for Payment, Owner, at its discretion may provide the Contractor ten (10) days to
cure the breach. Owner may withhold the accompanying payment without penalty until such
time as Contractor cures the breach.
(i) Should Contractor or its representatives fail to cure the breach within ten (10) days, or
fail to reasonably agree to such modified schedule, Owner may immediately terminate
this Agreement in writing, without penalty or incurring further obligation to
Contractor.
(ii) This section shall not be interpreted to limit the definition of breach to the failure to
perform the Work related to a Request for Payment.
c. The Contractor has included in the Contract Price and shall pay all taxes assessed by any
authority on the Work or the labor and materials used therein. It shall be the Contractor's
responsibility to furnish the Owner documentary evidence showing the materials used and
sales and use tax paid by the Contractor and each of its subcontractors.
d. Should the Owner receive notice that the Contractor has failed to pay a Subcontractor for the
Work performed related to a Request for Payment, Owner shall have the authority to withhold
payment of the disputed amount until parties resolve their dispute. Failure to pay the
Contractor pursuant to this section of the Agreement shall not be deemed to be a breach of the
Agreement.
6. NON—APPROPRIATION
a. Contractor acknowledges that Owner is a governmental entity, and the validity of this
Agreement is based upon the availability of public funding under the authority of its statutory
mandate.
Revised 12/18 4
DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
b. In the event that public funds are unavailable and not appropriated for the performance of
Owner's obligations under this Agreement, then this Agreement shall automatically expire
without penalty to Owner immediately upon written notice to Contractor of the unavailability
and non-appropriation of public funds. It is expressly agreed that Owner shall not activate this
non-appropriation provision for its convenience or to circumvent the requirements of this
Agreement,but only as an emergency fiscal measure during a substantial fiscal crisis.
c. In the event of a change in the Owner's statutory authority, mandate and/or mandated
functions, by state and/or federal legislative or regulatory action, which adversely affects
Owner's authority to continue its obligations under this Agreement, then this Agreement shall
automatically terminate without penalty to Owner upon written notice to Contractor of such
limitation or change in Owner's legal authority.
7. NOTICES
Any notice required by this Agreement shall be in writing and delivered by certified or registered mail,
return receipt requested to the following:
Owner: Contractor:
Orange County Sasser Companies, Inc
Attn: AMS PO Box 10
P.O. Box 8181 Whittset,NC
Hillsborough,NC 27278 27377
8. MISCELLANEOUS
a. Duties and Obligations imposed by the Contract Documents shall be in addition to any Duties
and Obligations imposed by state, federal or local law,rules, regulations and ordinances.
b. No act or failure to act by the Owner or Contractor shall constitute a waiver of any right or
duty granted them under the Contract Documents, nor shall any act or failure to act constitute
any approval except as specifically agreed in writing.
c. The Work shall be tested and inspected as required by the Contract Documents and as required
by law. Unless prohibited by law the costs of all such tests and inspections related to state and
federal codes such as ADA, Administrative, Electrical, Plumbing, Mechanical and Building
Codes shall be borne by the Contractor. The costs for material and structural testing shall be
conducted by an independent third parry at the expense of the Owner. Delays related to any of
the aforementioned tests and inspections shall not be grounds for delaying the completion of
the work. If any such tests and inspections reveal deficiencies in the Work such that the Work
does not comply with terms or requirements of the Contract Documents and/or the
requirements of any code or law the Contractor is solely responsible for the cost of bringing
such deficiencies into compliance with the terms of the Contract Documents and/or any code
or law.
d. Should the Designer, if a Designer is retained for the project involving the Work, or Owner
reject any portion of the Work for failing to comply with the Contract Documents Contractor
shall immediately, at Contractor's expense, correct the Work. Any such rejection may be
made before or after substantial completion. If applicable, any additional expense borne by the
Designer under this section shall be paid at Contractor's expense.
Revised 12/18 5
DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
e. The County has designated (Angel Barnes)to act as the County's representative with respect to
the Project and shall have the authority to render decisions within guidelines established by the
County Manager and/or the County Board of Commissioners and shall be available during
working hours as often as may be reasonably required to render decisions and to furnish
information.
f. The Contractor shall not assign any portion of this Agreement nor subcontract the Work in its
entirety without the prior written consent of the Owner.
9. CONSEQUENTIAL DAMAGES
a. Owner and Contractor mutually waive any claim against each other for consequential damages.
Consequential Damages include:
(i) Damages incurred by Owner for loss of use, income, financing, or business.
(ii) Damages incurred by Contractor for office expenses, including personnel, loss of
financing, profit, income, business, damage to reputation, or any other non-direct
damages.
10. ENTIRE AGREEMENT
All of the documents listed, referenced or described in this Agreement, the written Notice-to-Proceed,
together with Modifications made or issued in accordance herewith are the Contract Documents, and the work,
labor, materials, and completed construction required by the Contract Documents and all parts thereof is the
Work. The Contract Documents constitute the entire agreement between Owner and Contractor. This
Agreement may be amended only by written instrument signed by both parties. Modifications may be
evidenced by facsimile signatures. If any provision of the Agreement or General Conditions shall be declared
invalid or unenforceable,the remainder of the Agreement shall continue in full force and effect.
[SIGNATURE PAGE TO FOLLOW]
Revised 12/18 6
DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
IN WITNESS WHEREOF, the Parties hereto have executed this Agreement as of the day and date
first above written in a number of counterparts, each of which shall, without proof or accounting for other
counterparts,be deemed an original contract.
ORANGE COUNTY: CONTRACTOR:
e�
By, Pun 4/18/2019 By: S,SSW 4/3/2019
Penny Rich, Chair Orange County Board Kevin Sasser, President
of County Commissioners Printed Name and Title
Revised 12/18 7
DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
Angel Barnes
From: Kevin Sasser <kevin2@sassercompanies.com>
Sent: Tuesday,January 22, 2019 5:12 PM
To: Angel Barnes
Cc: Lindsey Beck; Catherine Wise
Subject: FW: Open Items for Orange County
Attachments: Orange County DA's Office Crawlspace.pdf; Orange County DA's Office Gutter Drain and
Waterproofing.pdf, Orange County DA's Office Exhibit A.pdf; Orange County DA's Office
Exhibit B.pdf, Orange County DA's Office Exhibit C.pdf
Angel please see the revised HVAC number to include the tax below in red. Thank you for allowing me to correct my
mistake. As soon as I get the additional scope of work from Mr. Drake I will get that priced and if approved I will add
that to the line below shown as Controls, HVAC and Electrical.
Thanks,
jba.�..r.
Kevin Sasser
kevin2(a)sassercompanies.com/336-516-5140
Sasser Companies
844-449-1144/336-449-1151
7237 Pace Drive I Whitsett,NC 27377
http://www.sassercompanies.com
From: Kevin Sasser
Sent:Wednesday, December 19, 2018 6:04 AM
To: 'Angel Barnes' <abarnes@orangecountync.gov>
Subject: Open Items for Orange County
Good morning Angel, I have competed most of the requests but ran out of time to complete the actual proposals and
get them to you before your meeting. I have tried to answer all of your questions in order and will be available if you
need to call me with any questions. Could you give me a call to discuss this after your meeting so that I can confirm that
I'm heading in the right direction with all of the proposals.
Board of Elections Change Orders
HVAC$78,692.48 changed to$80,161.84 to include tax
Temporary AC$7,370.74
HVAC Electrical $26,795.00
Plumbing(Connect water heaters and drain cleaning) $1,313.37
Controls, HVAC& Electrical $19,493.35 (At cost)
Temporary moisture barrier and de-humidifiers$24,393.62
Stairwell removal, installing floor and mod clean $10,433.96
Remove insulation, remediate mold at chimney$1,465.79
Carpet removal, large return removal, abatement and flooring replacement(I did not figure content manipulation. I
would like to discuss how we will cordinate) $61,969.31
District Attorney Building
Roof investigation No Charge
DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
Cost for scoping drains, drain line repairs,waterproofing and re-grading estimate is attached
We are waiting on scope to price relocating vents, chimney cap, and chimney sealing
Crawl space estimate is attached
Battle Courtroom
I will send the scope today
We will be ready to turn courtroom over on Monday January 215t. Should this be pushed to February Vt for new
furniture delivery?
Parts for dehumidification will be here in January per Ron Lepann
Thanks,
S&TOMMMWIX—v
Kevin Sasser
kevin20sassercompanies.com/336-516-5140
Sasser Companies
844-449-1144/336-449-1151
7237 Pace Drive I Whitsett,NC 27377
http://www.sassercompanies.com
2
DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
Sasser_ Invoice
w
PO Box 10
Date: 10/17/2018
Whitsett, NC 27377
Invoice No. 80398
Bill To: Orange County Service at: Orange County BOE-Water Htrs
131 West Margarat Lane 208 S. Cameron Street
Hillsborough, NC 27278 Hillsboror, NC
Purchase Order Project Manager Customer ID-Job Number Terms
Kevin Sasser ORACOU 18-0509-103 Due Upon Receipt
Description Amount
Furnish material and labor to connect under sink water heaters 788.37
installed by Harris Brothers Electric&Controls, Inc.
Thank you for your business! Total Due: 788.37
Important Notes:
All Invoices more than 30 days old are charged a late fee of 1.5%per month or 18%per year of the unpaid amount with a minimum
monthly charge of$5.00 or such late fee allowed under applicable law,regulation or contract. A non-refundable convenience fee of 5%
will be charged to all credit card transactions. If your check is returned to us for insufficient funds, it will be resubmitted electronically
and your account will be debited for the amount plus any fees.
DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
COLEMAN PLUMBING, INC.
COLEMAN CONCRETE CUTTING CO. DATE iNV 1 E
PO BOX 2508 9/16/2018 264
BURLINGTON, NC 27216 PLEAS .INDICATE INVOICE CODE
PHONE: 336-570-2401 ON ALL PAYMENTS TO ENSURE
CORRECT POSTING TO ACCOUNT.
THANK YOU
BILL TO:
SASSER COMPANIES
PO BOX 10
WHITSETT, NC 27377 108 MANAGER: KE.VIN SASSER
**TERMS** JOB
ATTN: ACCOUNTS PAYABLE DUE UPON RE, 208 S.CAMERON STIHILLSBORO
DATES) DESCRIPTION QTY. AMOUNT
UPFITS
07/11/18 REMOVE(2)TOILETS(2)WALL SINKS, (1)WATER 2 MEN 2.5 HRS @$1201HR $300.00
FOUNTAIN,AND CAP OFF(2)LINES AS MATERIALS $30.18
REQUESTED.
08/01/18 CAP(4)DRAIN LINES AND(2) 1/2" COPPER 2 MEN 2.5 HRS @$1201HR $300.00
WATER LINES AS REQUESTED. MATERIALS $77.93
08/16/18 CAP(1) 1"WATER LINE, (2)3/4"WATER LINES 2 MEN 2 HRS @$1201HR $240.00
AT WATER HEATER AND(1) 1 112"VENT AS MATERIALS $124.75
REQUESTED.
8/31/18 CHANGE OUT WATER LINE UNDERNEATH 1 MAN 5 HRS @$851HR $425,00
TO WATER HEATER AS REQUESTED. MATERIALS $231.97
SUBTOTAL $1,729.83
LABOR SALES TAX
MATLS SALES TAX
`&IING NOTES,
ALL MON-FRI AFTERHOURS AND SATURDAYS ARE
BILLED AT TIME&ONE HALF.
SUNDAY CALLS ARE BILLED AT DOUBLE TIME.
** HOLIDAYS ARE BILLED AT DOUBLE TIME&
ONE HALF NO EXCEPTIONS
* HERE IS A MINIMUM BILLING RATE OF ONE HOUR
or, TOTAL $1,729,83
"Full payment including any retainer fee, is due upon presentation of Invoice. Payment is considered
PAST DUE if not received 10 days from Invoice Date shown above.Any invoice not paid IN FULL upon
presentation will be subject to a late fee and interest charge to be added at the rate of 24%per annum upon
the delinquent amounts and, if applicable, collection costs, attomey's fees and ALL court costs.
DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
Contract Startup Checklist
It is the responsibility of each agency to ensure all contractual obligations are met and contract
monitoring is documented. This checklist serves as a tool to assist the agency during that process.
(Include in the contract monitoring folder/binder.)
Completed By: Angel Barnes Department:AMS
Contract Begin/End Date:4/03 thru 12/31/19 Name of Vendor/Contractor: Sasser Companies
Contract Management Activities YES NO N/A
General
Does the contract file contain a copy of the signed, executed current contract? X
Does the contract file have a copy of all attachments listed in the contract? X
Does the contract file have all bid addendums? X
Does the contract file contain contact information and a call log for Contractor's key X
personnel?
Does the contract file contain a copy of Dispute Resolution Rules and Procedures? X
Does the contract file clearly state the Contractor's "Legal Notices" address? X
Does the contract file include a copy of the insurance certificate? X
Does the contract file contain any necessary licenses, certifications, etc.? X
Does the contract file contain all warranty information? X
Does the contract file contain all specifications, drawings or manuals incorporated into X
the contract by reference?
Does the contract file contain a list of all information furnished to the contractor during X
bidding?
Does the contract file contain a list of government furnished property or services? X
Signatures:
Capital Projects Manager Q'"a bm-u Date 4/18/2019
Asset Mgmt. Services Director Q '^ Date 4/23/2019
Deputy County Manager Pa"'S ftimv, Date 4/25/2019
Note: Once all signatures are received on contract and checklist, notice to proceed shall be issued.
Version 1 3/20/2019 Page 1
DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
Sasser_ Invoice
w
PO Box 10
Date: 10/3/2018
Whitsett, NC 27377
Invoice No. 80363
Bill To: Orange County Service at: Orange Cnty-BOE HVAC Electric
131 West Margarat Lane 208 Cameron Street
Hillsborough, NC 27278 Hillsborough, NC 27278
Purchase Order Project Manager Customer ID-Job Number Terms
Kevin Sasser ORACOU 18-0481-105 Due Upon Receipt
Description Amount
Electrical construction for HVAC units on 2nd floor and outside 23,300.00
units and cassette units on 1st floor.
15%Overhead &Profit 3,495.00
Thank you for your business! Total Due: 26,795.00
Important Notes:
All Invoices more than 30 days old are charged a late fee of 1.5%per month or 18%per year of the unpaid amount with a minimum
monthly charge of$5.00 or such late fee allowed under applicable law,regulation or contract. A non-refundable convenience fee of 5%
will be charged to all credit card transactions. If your check is returned to us for insufficient funds, it will be resubmitted electronically
and your account will be debited for the amount plus any fees.
DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
Angel Barnes
From: Shawn Cassell <shawnc@sassercompanies.com>
Sent: Friday, January 04, 2019 6:09 PM
To: Angel Barnes
Cc: Kevin Sasser
Subject: Chimney Quotes
Angel, the following is the budget numbers for the chimney repairs .One chimney on the BOE Building will
need some extensive repair .The other chimneys will not need this amount of repair .We based our budget
numbers from this one chimney .The scope and budget numbers are as follows
BOE Building - (4 chimneys)
1 - Remove existing caps
2 - Clean brick and mortar
3 - Point up and repair any damaged or missing brick
4 - Repair brick wash around top of chimneys
5 - Install clear waterproofing sealant on entire chimney
6 - Rework and seal roof flashing
7 - Install new standing seam copper chimney caps
8 - lift rental
9 - Supervision
Total Budget - $30,200.00
DA Building- (2 chimneys)
1 - Remove existing cps
2 - Clean brick and mortar
3 - Point up and repair any damaged or missing brick
4 - Repair brick wash around top of chimneys
5 - Install clear waterproofing sealant on entire chimney
6 - Rework and seal roof flashing
7 - Relocate bath vent to roof
8 - Install new standing seam copper chimney caps
9 - lift rental
10 - Supervision
Total Budget - $18,100.00
Please let me know if you need anything additional.
Thanks,
i
DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
Shawn Cassell
shawnc(a)sassercompanies.com/336-516-4725
Sasser Companies
Office:844-449-1144/Fax:336-449-1151
7237 Pace Drive I Whitsett,NC 27377
http://www.sassercompanies.com
2
DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
ORANGE COUNTY
NORTH CAROLINA
Asset Management Services
Date: March 27, 2019
Project: Board of Elections Water Mitigation
Background:
In August, 2018 Sasser Companies was awarded a contract for the remediation and HVAC relocation
at the Government Services Annex Building (Board of Elections). The HVAC relocation appropriated in
the FY2017-18 CIP, the remediation of the building became necessary due to the extremely wet/humid
weather and multiple flooding events, and therefore mold began to grow within the building and within
the HVAC system, once a portion of the occupied space was cleaned the mold returned within other
areas and therefore became emergent to clean the entire building for a full remediation.
The additional scope of work to complete the interior water mitigation includes the following:
1. This scope includes additional funding to cover the costs to meet a tight construction schedule
for the HVAC installation.
2. In order to move the Board of Elections staff in on schedule temporary air conditioning units
were required for staff to start the work to prepare for the election.
3. Electrical work required to connect the new HVAC units, reconnect all lighting fixtures after
remediation, and removing all unused power in the attic during deconstruction.
4. A portion of the work included installing individual hot water heaters for the sinks, the electrical
contract to purchase the hot water heaters did not include the plumbing connections, and the
HVAC relocation contract did not include any plumbing, therefore these plumbing costs are to
connect the plumbing for these hot water heaters. This change also includes cleaning the
basement floor drains to ensure flood waters are able to drain out quickly if flooding occurs.
5. When this project was designed in 2017 the design was not to change the HVAC system due to
humidity or environmental concerns. The system was design to replace the existing system.
However, due to the humidity and environmental concerns that arose prior to construction
additional humidity controls and a duct heater are to be installed to ensure humidity is monitored
and controlled going forward, including CO2 sensors and remote monitoring.
6. The water intrusion into the basement is still occurring and causing concerns within the first floor
of the building, based on the recommendations of the investigative engineer the emergent need
is for a temporary vapor barrier and dehumidifiers to be installed within the basement above the
flood plain. There will be four dehumidifiers installed per this change. The dehumidifiers will be
permanent to the building. The vapor barrier is only a temporary solution until the flood prone
area of the basement can be filled in, and the ground water can be diverted away from the
building.
7. Due to the basement and 1"floor having stairwell access this allows for contaminated air to
enter into the 1"floor ceiling and storage room. The stairwell shall be removed, and a floor
installed to create a telephone room. This will block the air from the basement from entering into
the 1 St floor.
P.O. Box 8181 * 131 West Margaret Lane,3rd Floor* Hillsborough, North Carolina 27278
Telephone:919 245-2625
Fax:919-644-3001
E-mail:AMService@orangecountync.gov
DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
Board of Elections Water Mitigation Scope of Work Descriptions&Details
8. During the remediation all of the attic walls, and existing insulation was removed. This allowed
the brick chimneys to be exposed to the interior of the attic. The chimneys currently need to be
repointed due to water entering through the bricks. Currently the insulation installed needs to be
removed and replaced. The area must be cleaned to remove any mold growth from the water
intrusion around all four chimneys.
9. Sealing of basement doors and installing new maintenance access door
10. Cleaning of data cabling to remove unused cables and securing existing cables.
Construction Costs:
HVAC Controls, Programming, Additional Unit, temporary units 155,000
Clean out interior drains in basement 1,313
Moisture Barrier/Humidifers 24,394
Stairwell removal and install floor 10,434
Remediation at each Chimney 1,466
Chimney Repairs 30,200
Replace windows NTE 105,000
Replace carpet, seal basement from first floor, abatement 61,969
Rework furniture for carpet installation &replace NTE 25,000
Rework and remove unused data cables from basement NTE 16,000
Seal Basement doors and install new higher access NTE 125,000
555,776
DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
SASSCOM-01 DEIAKER
,d►C�►e�- CERTIFICATE OF LIABILITY INSURANCE DATE{MMI°DIYYYYJ
02107/2019
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER.THIS
CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES
BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S),AUTHORIZED
REPRESENTATIVE OR PRODUCER,AND THE CERTIFICATE HOLDER.
IMPORTANT: If the certificate holder is an ADDITIONAL INSURED,the policy(ies)must have ADDITIONAL INSURED provisions or be endorsed.
If SUBROGATION 1S WAIVED, subject to the terms and conditions of the policy,certain policies may require an endorsement. A statement on
this certificate does not confer rig hts to the certificate holder in lieu of such endorsements).
PRODUCER License#1000009384 Co NA TncT
Hub International Carolinas PHONE EAx
PO Box 939 Arc,No,Ft):(336)228-0541 wc,No:(868)590-4281
Burlington,NC 27216 E--MAIL
INSURERS AFFORDING COVERAGE NAICR
_ INSURER A:Selective Insurance Company of America 12572
INSURED INSURER B:Accident Fund General Insurance Company .12304
Sasser Companies Inc INSURER C:
P 0 Box 10 INSURERD:
Whitsett, NC 27377
INSURER E
INSURER F
COVERAGES CERTIFICATE NUMBER: REVISION NUMBER:
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED, NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACTOR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES.LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS,
INSR TYPE OF INSURANCE ADDL SUER POLICY NUMBER POLICY EFF POLICY EXPLTR L1AIrT5
A X COMMERCIAL GENERAL LIABILITY EACH OCCURRENCE $ 1,000,000
CLAIMS-MADE l "I OCCUR S 2253759 0210112019 02/01/2020 DAMAGE TO RENTED $00,000
MED EXP(Any one arson s 15,000
PERSONAL&ADV INJURY 1,000,000
GEN'L AGGREGATE LIMIT APPLIES PER: GENERAL AGGREGATE a 3,000,000
POLICY PE OT LOG PRODUCTS-COMPIOP AGG 3,000,000
OTHER:
A AUTOMOBILE LIABILITY COMBINED SINGLE LIMIT 1,000,000
x ANY AUTO S 2253759 02/01/2019 02/01/2020 BODILY INJURY Per arson
OWNED SCHEDULED
AUTOS ONLY AUTOS E BODILY INJURY Per accident
AUTOS ONLY Al]TOS ONLY Pea'.'; nt AMAGE S
S
A )C UMRRELLA UAB x OCCUR EACH OCCURRENCE 10,000,000
EXCESS UAB CLAIMS-MADE S 2253759 02(01/2019 02/01/2020 AGGREGATE 10,000,000
QED RETENTION$
13 WORKERS COMPENSATION PER 07H
AND EMPLOYERS'LIABILITY YIN WCV6139124 02101/2019 0210112020 1,000,000 �
ANY PRO PRIETORIPARTNERIEXECuI IVE ❑ NIA E.L EACH ACCIDENT $
QFFIGERIM MBER EXCLUDED? 1'000,000
andatory�n NFi] E-L DISEASE-EA EMPLOYE $
Ifyes,describe under 11000,000
DESCRIPTION OF OPERATIONS below E.L.DISEASE"-POLICY LIMIT $
I
DESCRIPTION OF OPERATIONS I LOCATIONS r VEHICLES (ACORD 101,Additional Remarks Schedule,may be attached if more space Is required)
Orange County is an additional insured under the General Liability for work performed by the named insured for such additional insured,if required by
contract signed by an authorized representative of the named insured.
CERTIFICATE HOLDER CANCELLATION
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE
Orange Count THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN
9 y ACCORDANCE WITH THE POLICY PROVISIONS.
PO Box 8181
Hillsborough,NC 27278
AUTHORIZED REPRESENTATIVE
ACORD 25(2018103) 01988.2015 ACORD CORPORATION. All rights reserved.
The ACORD name and logo are registered marks of ACORD
DocuSign Envelope ID:57A4862B-43BE-4A6C-B2D2-A722FA813067
n rf 1 "1 �'
000��
Commercial Industrial HVAC
5012 Neal Road, Durham,NC 27705
Service: 919-680-6400, Office: 919-382-3330, Fax: 919-382-3332
Sasser Company's Inc. January 25, 2019
Attn: Mr. Kevin Sasser Revised January 29, 2019
Revised February 8, 2019
Re: Orange County Board of Elections Additional Thermostats Pricing
We Propose to:
Scope: Four(4) existing areas have one thermostat operating two
Indoor cassette units, separating Twined systems into individual zones
And offsetting set points will afford superior space temperature &humidity control
Provide & install Four(4) thermostats including hardware, conductors, conduit&
Programing
Controls Four(4) T-stats/controllers ++++++++++++ $1,408.00
Programing ++++++++++++++++++++++++ $1,174.00
Tech Labor
Controls tech 9 hours @ $95.00 +++++++++++++++++ $855.00
Controls Helper 9 Hours @ $45.00++++++++++++++++ $404.00
Hardware (wire mold, boxes, conductors, fasteners etc.) $255.00
Total For The Sum of++++++++++++++++++++++++++ $4,096.00
Respectfully Submitted
Rick Moser
President
NC License # 16104 H-1, H-2, H-3
This Proposal Valid For 30 Days