ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: March 19, 2019
Action Agenda
Item No. 8-h
SUBJECT: Adoption of a Prequalification Policy for Contractors
DEPARTMENT: County Manager's Office
ATTACHMENT(S): INFORMATION CONTACT:
Attachment 1: Prequalification Policy Travis Myren, 919-245-2308
Attachment 2: Prequalification
Assessment Tool
PURPOSE: To approve a contractor prequalification policy as part of the bidding process for
the Orange County Northern Campus development as required by North Carolina General
Statutes. The prequalification policy may also be applied to future capital projects.
BACKGROUND: In June 2018, the County contracted with Bordeaux Construction of Raleigh,
NC to serve as its Construction Manager at Risk for the Northern Orange County Campus
development. As the Construction Manager at Risk, Bordeaux Construction will solicit bids and
hire all subcontractors to construct the project.
Prior to the bidding process, State Statutes require the County to adopt a prequalification policy
so that only firms that are qualified to perform the work are able to submit bids. General Statute
143-128 states,
The construction manager at risk shall use the prequalification process determined by the
public entity in accordance with G.S. 143-135.8, provided that public entity and the
construction manager at risk shall jointly develop the assessment tool and criteria for that
specific project, which must include the prequalification scoring values and minimum
required score for prequalification on that project.
The construction manager at risk shall award the contract to the lowest responsible,
responsive bidder, taking into consideration quality, performance, the time specified in
the bids for performance of the contract, the cost of construction oversight, time for
completion, compliance with G.S. 143-128.2, and other factors deemed appropriate by
the public entity and advertised as part of the bid solicitation.
The proposed prequalification policy is attached as Attachment 1. Under this policy, a
Prequalification Committee composed of two representatives from the Construction Manager at
Risk and one representative from the County would review the prequalification applications from
2
contractors using an objective assessment tool. The assessment tool is attached as Attachment
2. Contractors that are prequalified are allowed to submit bids on the project.
Contractors that the Committee has denied prequalification have the opportunity to appeal. The
first appeal is to the Prequalification Committee, and the second is to a Prequalification Official.
The policy designates the County's Chief Financial Officer as the Prequalification Official.
This process will allow the Construction Manager to establish a guaranteed maximum price
(GMP) from subcontractors. Once the guaranteed maximum price is in place, the Construction
Manager at Risk must manage and control construction costs to not exceed the GMP. Any
costs that exceed the GMP that are not change orders directed by the owner are the financial
liability of the Construction Manager at Risk.
FINANCIAL IMPACT: The prequalification process is included in the Construction Manager at
Risk fee.
SOCIAL JUSTICE IMPACT: The following Orange County Social Justice Goal is applicable to
this item:
• GOAL: ENSURE ECONOMIC SELF-SUFFICIENCY
The creation and preservation of infrastructure, policies, programs and funding necessary
for residents to provide shelter, food, clothing and medical care for themselves and their
dependents.
RECOMMENDATION(S): The Manager recommends that the Board approve the
prequalification policy contained in Attachment 1.
3
Attachment 1
ORANGE COUNTY
PREQUALIFICATION POLICY
A. Governing Law (Session Law 2014-42)
This policy is in effect for all prequalifications on Orange County work, including single prime
project delivery and construction manager at risk first-tier subcontractors. G.S. 143-135.8(b)(2)
requires the governmental entity to "adopt an objective prequalification policy applicable to all
construction or repair work prior to the advertisement of the contract for which the
governmental entity intends to prequalify bidders."
B. Requirements for Prequalification Criteria Form and Assessment
1. Uniform, consistent, and transparent in its application to all bidders.
2. All bidders who meet the prequalification criteria to be prequalified are allowed to
bid on the construction or repair work project.
3. Criteria must be rationally related to construction or repair work.
4. The bidder is not required to have been previously awarded a construction or repair
project by the governmental entity.
5. Bidders are permitted to submit history or experience with projects of similar size,
scope, or complexity
6. Assessment process of prequalification is stated in this policy.
7. A process for a denied bidder to protest is stated below in this policy.
8. A process for notifying a denied prequalified bidder is stated below in this policy.
C. Review of Application
1. Prequalification Committee — The County and/or construction manager shall agree
upon the members of the prequalification committee. The County Finance Officer shall
be the Prequalification Official. The Prequalification Official shall not be on the
prequalification committee. The prequalification committee will review prequalification
applications submitted by the firms and will determine each firm's prequalification
eligibility for the project.
2. Review of Application — The prequalification committee shall use the objective
assessment process form as adopted by the Orange County Asset Management Services
Department. The prequalification committee shall approve or deny the applications in
accordance with the prequalification criteria and scoring system based upon the
applicants' initial response to the County's solicitation for qualified bidders. With the
possible protests and appeals on prequalification and the times associated with
responses, the County and/or construction manager should have the advertisement for
prequalification out to potential applicants approximately two (2) months prior to actual
bid date.
3. Notice of Decision — All firms that submitted applications for prequalification shall be
promptly notified of the prequalification committee's decision, including the reason for
denial, via e-mail. Notice shall be provided prior to the opening of bids for the project
and with sufficient time for the firm to appeal the denial of prequalification.
4. Informal Meeting - Upon denial, the applicant may request an informal meeting with
the County's representative and/or construction manager to receive feedback and
4
suggestions for improvement. The County's representative and/or construction manager
shall hold a feedback session for the applicants who do not appeal the decision within 2
weeks of the request.
5. Firms wishing to appeal the decision shall follow the appeals process described below.
D. Appeals Procedure
l. The firm may appeal the denial of Prequalification as noted below.
a. Initial Protest — A firm denied prequalification may protest the prequalification
committee's decision by filing a written appeal via hand-delivery or e-mail to the
applicable prequalification committee within three (3) business days of emailed
notice that the firm has been denied prequalification. The written appeal shall
clearly articulate the reasons why the firm is contesting the denial (i.e., explains
how the firm satisfied all required criteria for prequalification in the government's
solicitation in their initial response) and attach all documents supporting the
firm's position. The prequalification committee may contact the firm regarding
the information provided prior to ruling on the protest. The Prequalification
Committee should review the written protest within five (5) business days. If the
prequalification committee is satisfied that the firm should be prequalified, the
firm shall be notified that it is prequalified to bid on the project and allowed to
participate in the bid process. If the prequalification committee upholds its denial,
the firm shall be notified in writing via e-mail.
b. Appeal — Within three (3) business days of the County's emailed notice of the
Prequalification Committee's written protest decision, the denied prequalified
firm may appeal the prequalification committee's decision, in writing, via hand-
delivery or e-mail, to the Prequalification Official (see C.1 above). The
Prequalification Official should review the appeal within five (5) business days.
In the event the Prequalification Official is unable to review in a timely manner,
he/she may designate a representative that is not a member of the prequalification
committee to handle the appeal.
C. Decision on Appeal — The decision of the Prequalification Official or
Representative on the appeal shall be final, and the firm shall be promptly
notified of the decision.
d. General Rules for Protests and Appeals — Firms submitting prequalification
applications shall be provided an e-mail address for the communication with the
County and/or construction manager during the protest and appeal process. The
firm shall provide at least two e-mail addresses for use by the County and/or
construction manager in communicating with the firm. In the event the
Prequalification Official or Representative is unable to render a decision on either
the initial protest or the appeal prior to the bid date, the firm shall be allowed to
submit a bid on the project subject to a final decision on the protest or appeal. If
the firm's bid is opened prior to a final decision on the protest or appeal and the
bid is not the lowest monetary bid for the project, the appeal shall be terminated
and rendered moot. Bids received from firms who have been ruled disqualified to
bid shall not be opened. A firm's failure to comply with any requirements of the
protest and appeals procedures of this section shall result in the firm's protest or
appeal being terminated and rendered moot.
{M4VA5A91190CX} Page 2 of 2
5
Attachment 2
Prequalification Ratings Matrix for First-Tier Subcontractors under CM @ Risk
Project Name: Orange County Northern Campus
Bid Package No./Description:
1 2 3 4 5 6 7 8
Yes or N/A=1 E E E E E E E E
point for z z z z z z z z
acceptance
and No=0
points for not
`o `o `o `o `o `o `o `o
accent—, u u u u u u u u
Part A Section# Description Yes or No Pts Pts Pts Pts Pts Pts Pts Pts
Part A-1.GENERAL COMPANY INFORMATION Yes or No
Part A-2.BUSINESS TYPE Yes or No
Part A-3.LICENSING INFORMATION Yes or No
Part A-4.TYPE OF SCOPE OF WORK/AVERAGE SIZE/LARGEST PROJECT Yes or No
Part A-5.SIZE OF COMPANY Yes or No
Part A-6.CURRENT WORKLOAD Yes or No
Part A-7.CURRENT WORKLOAD Yes or No
Part A-S.LITIGATIONS AND CLAIMS Yes or No
Part A-9.HUB OR DIVERSITY PLAN
Part A-SUPPLEMENTAL INFORMATION
Audited Financials Yes or No
Bonding Company Letter Yes or No
Current Insurance Ceni ica meeting OC-15 Article 34 Yes or No
Letter from Insurance Company rtating EMR Yes Or No
OSHA 3W Reports Yes or No
Copy of HUB Certifcation,if claimed in Secton 2 Yes Or No
Copy of Licenses for Specific work,if requ fired in S,dion 3 Yes or No
Part A Acceptance=Subtotal 15 out of 15 points
Part B Section# Description Yes or No Pts Pts Pts Pts Pts Pts Pts Pts
Part B-1.INFORMATION
Part B-2.UPDATED COMPANY INFORMATION
2a Current Backlog and Bond ing Ca p-ty Avail,ble Yes or No
21,Attach bonding letter from Surety,If over$300k Yes or No
2C List of Projects—king With CMAR in last 5 yea rs Yes or No
Part B-3.PROJECT SPECIFICS
3a Assigned Superintendent resume and experience Yes Or No
3b Relevant project experience of assigned Superintendent Yes Or No
3C Assigned Project Manager resume and experience Yes or No
3d Relevant project experience of assigned Project Manager Yes Or No
3e Related Project Experience Yes or No
3f.1 Available Craftsman for Trade Prequalifying for Yes or No
3f.1 Self performance for Trade Prequalifying for Yes or No
Part B Acceptance=Subtotal 10 out of 10 points
TOTAL POINTS=25 points out of 25 points
All scores of 25 points will be prequalified.
note;if an item is not applicable("n/a'),then the CMAR shall make the line"n/a"for all subcontractors seeking prequalification for that bid package