HomeMy WebLinkAboutORD-2019-008 Greene Tract Southern Access Driveway and Approval of Budget Amendment #6-C 1
ORD-2019-008
ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: March 7, 2019
Action Agenda
Item No. 8-j
SUBJECT: Greene Tract Southern Access Driveway and Approval of Budget Amendment
#6-C
DEPARTMENT: Asset Management Services
ATTACHMENT(S): INFORMATION CONTACT:
Angel Barnes, Capital Projects Manager,
919-245-2628
Travis Myren Deputy County Manager, 919-
245-2308
John Roberts, County Attorney, 919-245-
2318
PURPOSE: To approve funding of $35,000 for the installation of the Greene Tract southern
access driveway and to approve Budget Amendment #6-C.
BACKGROUND: Recent litigation involving the fence blocking the southern access to the
Greene Tract was unsuccessful, resulting in a loss of a southern access road to the Greene
Tract. The Town of Chapel Hill has agreed to pay for 50% of the cost to construct a gravel drive
along an existing undeveloped public right of way to provide the County and Towns with a
southern access to the Green Tract.
Since this project was not anticipated as part of the Capital Investment Plan, a budget
amendment is necessary to fund this project. Staff recommends that the funds be re-purposed
from the completed Telephone System Replacement Capital Project to fund the project. This
budget amendment provides for the re-purposing of funds and amends the following Capital
Project Ordinances:
Telephone System Replacement Project(-$17,500) - Project# 30037
Revenues for this project:
Current FY 2018-19 FY 2018-19
FY 2018-19 Amendment Revised
Alternative Financing $560,000 $17,500 $542,500
Total Project Funding $560,000 ($17,500) $542,500
Appropriated for this project:
Current FY 2018-19 FY 2018-19
FY 2018-19 Amendment Revised
Equipment $500,000 $0 $500,000
Professional Services $60,000 ($17,500) $42,500
Total Costs $560,000 ($17,500) $542,500
2
Greene Tract Improvements Project($35,000) - Project# 10066
Revenues for this project:
Current FY 2018-19 FY 2018-19
FY 2018-19 Amendment Revised
Alternative Financing $15,000 $17,500 $32,500
Reimbursement from Town of $15,000 $17,500 $32,500
Chapel Hill
Total Project Funding $30,000 $35,000 $65,000
Appropriated for this project:
Current FY 2018-19 FY 2018-19
FY 2018-19 Amendment Revised
Equipment $0 $0 $0
Professional Services $0 $0 $0
Construction $30,000 $35,000 $65,000
Total Costs $30,000 $35,000 $65,000
FINANCIAL IMPACT: The original budget of $30,000 was part of Budget Amendment #4,
which the Board of County Commissioners approved on December 11, 2018. The original
budget did not anticipate installing a new drive - only making modifications to the existing drive.
The total project is now estimated at $65,000 with both Orange County and the Town of Chapel
Hill sharing equally in the cost of $32,500 each.
SOCIAL JUSTICE IMPACT: There is no Orange County Social Justice Goad applicable to this
item.
RECOMMENDATION(S): The Manager recommends that the Board approve the installation to
complete the Greene Tract southern access driveway project, and approve Budget Amendment
#6-C.