HomeMy WebLinkAbout2019-042 Planning - Moffat Pipe change order 7 CHANGE ORDER NO . : 7 Page 1 of 2 CHANGE ORDER CHANGE ORDER NO . . 7 DATE : January 22 , 2019 Project : Historic Rogers Road Sewer Expansion Project Contractor : Moffat Pipe , Inc . Engineer/Architect : URS Corporation — North Carolina CONTRACTOR is directed to make the following changes in the Contract Documents . Description : Due to a request by the NCDOT to have the rims of manholes SSMH -E1 and SSMH -E2 at grade instead of elevated 1 . 0 ' above grade as shown on the NCDOT approved plans , Moffat is to remove and reset these two manhole cones and rim and frames . Item Bid Description Units Estimated Unit Price Extended No . Quantity Total 46 Remove and Reset Lump Sum 1 $ 5 , 928 . 93 $ 59928 . 93 Manholes SSMH - E1 and SSMH - E2 along NCDOT ROW Net Adjustment of this Change Order $ 5 , 928 . 93 This work will require one ( 1 ) additional calendar day . Moffat is also requesting an additional twenty- one ( 21 ) calendar days to account for weather and production delays in the project for the period of October 24th, 2018 thru January 21 st, 2019 . This brings the total requested calendar days for Change Order No . 7 to twenty -two (22 ) calendar days . These delays are considered to be no fault of their own and beyond their control . A breakdown of the delay days can be found in Attachment A . CHANGE IN CONTRACT SUM OR PRICE : CHANGE IN CONTRACT TIME OR TIMES : Original Contract Price Original Contract Times $4 , 7829436 . 00 Final Completion : July 15 , 2018 Net change from previous Change Orders No . 1 to Net change from previous Change Orders No . 1 to No . 6 : $ 174 , 754 . 51 No . 6 : 248 days Contract Sum or Price prior to this Change Order Contract Times prior to this Change Order $ 499575190 . 51 Final Completion : February 28 , 2019 Net Increase of this Change Order Net Increase of this Change Order $ 5 , 928 . 93 Twenty -two (22 ) calendar days Contract Sum or Price with all approved Change Contract Times with all approved Change Orders Orders $ 499635119844 Final Completion : March 22 , 2019 CHANGE ORDER NO . : 7 Page 2 of 2 t RECOMMENDED : REVIEWED : ACCE ED . aaaa�) ZA44690K Engineer OranK County on ract r Krista Paredes -Toledo , PE Craig Benedict, AICP ess DuC u Date : 1ok Date : Date . The adjustment in Contract Sum or Price and/or Contract Time or Times stated in this Change Order shall comprise the total price and/or time adjustment due or owed the CONTRACTOR for the work or changes defined in this Change Order . By executing the Change Order, the CONTRACTOR acknowledges and agrees that the stipulated price and/or time adjustments include the costs and delays for all work contained in the Change Order, including costs and delays associated with the interruption of schedules , extended overheads , delay , and cumulative impacts or ripple effect on all other non- affected work under this Contract . Signing of the Change Order constitutes full and mutual accord and satisfaction for the adjustment in Contract Sum or Price or Contract Time or Times as a result of increases or decreases in costs and time of performance caused directly and indirectly from the change , subject to the current scope of the entire work as set forth in the Contract Documents . Acceptance of the waiver constitutes an agreement between OWNER and CONTRACTOR that the Change Order represents an equitable adjustment to the Contract, and that CONTRACTOR waives all rights to file a claim on this Change Order after it is properly executed . IN WITNESS WHEREOF , the undersigned have caused the execution hereof CONTRACT R . MOFFAT P E , WC ATTEST : By : Name : Jesse DuClau Title : Contractor . FAtpryo; 17 Address : 49 1 Un con Drive �.�p•,,,,,,,, " , , ..,,,'�/,p�,,��� Ilest, NC27587 aWe opDate : o �S�I •,,� ��non„ „ +`��, �,`, OWNER : Orange County Y By : Name : Bonnie Hammersley Title : Or nge County Manager Date : Poe/S Change Order 7 Request Attachment A Weather Delays Anticipated / Month Description Contract Actual / Impact Requested Notes Oct 24 - Rain /Snow/Sleet Delays and Impact 7 9 2 10/9 , 10, 11 , 12 , 17, 20, 21 , 26, 27 Nov Rain /Snow/Sleet Delays and Impact 8 13 5 11/ 1 , 2 , 5 , 6 , 7 , 9 , 12 , 13 , 14, 15 , 16, 17 , 24 Dec Rain /Snow/Sleet Delays and Impact 9 17 8 12/ 1 , 2 , 9 , 10, 11 , 12 , 13 , 14, 15 , 16, 17 , 20, 21 , 22 , 23 , 28 , 31 - Jan 21 Rain /Snow/Sleet Delays and Impact 10 7 0 1/3 , 415 , 13 , 14, 20, 21 Subtotal 15 Work Delays Month Description Days Notes Jan Additional Work Associated with MH adjustments 1 Subtotal 1 Total Work Days 16 Total Calendar Days 22 Total this request 22