ORO Agenda Abstract
g Meetin Date: 1/24/19
C I T Y S C H O O L S Agenda Type: Discussion & Action
Agenda Item#: 7c
Subject: Approval of 2019-29 Capital Investment Plan
Division: Support Services Department: Facilities
Management
Person William J. Mullin, Executive Director Feedback
Responsible: of School Facilities Requested
From:
Agenda Item....Prior Submission Dates Public Hearing Required: No
Work Session No Date
Discussion and Action No Date
Attachment(s):
Recommended 2019-28 CIP
1) Funded Projects Plan
2) Unfunded: Major Expansions, Renovations and Projects
PURPOSE: To review the recommended 2019-29 Capital Investment Plan and approve a
plan to be forwarded to Orange County.
BACKGROUND: Attached is the recommended 2019-29 Capital Investment Plan. The CIP
format is similar to prior years and includes (1) a Funded Plan that aligns with anticipated
revenues and(2) an Unfunded Plan identifying district needs that exceed revenue projections.
The Funded Plan provides specific project information for the next 5 years and funding
projections for years 6 through 10. Only projects in FY 2019-20 will be funded when
approved by the County.
Over the past few years, district CIPs have undergone annual re-prioritization of projects as
plans to address needs identified in the 2013 Facility Needs Assessment of the 10 oldest
schools were modified. 2016 Bond funds are primarily devoted to the renovation and
expansion of Chapel Hill High School. The most immediate needs of the other older schools
are identified and prioritized in the CIP as funding allows. The major renovation,building
additions and expansion of the older schools, identified in the 2013 assessment, continues to
be listed in the Unfunded Plan.
FUNDED PLAN
Major facility improvement projects in FY 2019-20 include continued removal of asbestos
floor tile at Phillips Middle School as well as identification and correction of lower level
water infiltration problem, repair and restoration of Smith Middle School's 6 tennis courts,
window sealing at the oldest schools, establish a new playground at FP Graham Elementary
School, correct poor baseboard conditions throughout McDougle Elementary School, begin
replacement of HVAC units at Seawell Elementary School PODS, replacement of heat pumps
at Culbreth Middle School, new HVAC unit in Carrboro Elementary School's auditorium,
and replace the 23 year old chiller at East Chapel Hill High School.
The CIP Contingency line has a current balance of$1,695,473 accumulated over the past few
years. This year's plan does not add to the contingency in FY 2019-20 but rather directs all
available funds to specific projects. It is recommended that the current contingency be
maintained to address facility emergencies that may arise.
Chapel Hill High School's renovation project, funded from proceeds of the 2016 School
Bond referendum, is included in the Funded Plan. The high school project will continue
through 2020-21.
UNFUNDED PLAN
The major component of the Unfunded Plan is the scheduled funds needed to renovate and
expand the 7 remaining older schools identified in the 2013 Facilities Assessment. This
assessment identified building code corrections, facility upgrades, and expansions to bring
these schools as close as possible to the County's new school construction standards. As
future plans are developed to address funding requirements, each school's assessment will
need updating to reflect work that has been completed over the past 5 years and current
construction costs to finish the projects.
This year's SAPFO report has not been published. Of major concern is elementary school
capacity and whether projection formulas will be adjusted to reflect State mandated
reductions in class size. It is possible that SAPFO will indicate the need for additional
elementary school classrooms.
GENERAL FUND BALANCE DISCUSSION
Over the past few years, the district's General Fund Balance has been monitored and allowed
to accumulate above target levels. Initially, these funds were intended to supplement 2016
Bond funds and complete the Lincoln Center Campus redevelopment. However,
construction cost escalation made it impossible to implement both the Chapel Hill High
School and Lincoln Center plans.
Current available General Fund Balance and Cell Tower revenues total $7.1 million. Of this
amount, $2.3 million has been reserved for use at Chapel Hill High School project to
construct the CTE building. While the renovation project's sales tax refunds and municipal
reimbursements are expected to pay most of the cost of the CTE Building, General Fund
Balance will be necessary to meet cash flow requirements and therefore must be reserved.
With respect to the remaining General Fund Balance, the administration is pursuing options
for the Lincoln Center Development plan. If alternatives are not feasible, a list of other
district priorities will be submitted for consideration.
FINANCIAL IMPACT: As outlined in the attached schedules.
PERSONNEL IMPACT: None
RECOMMENDATION: Approve the recommended 2019-29 CIP
RESOLUTION: Be it, therefore, resolved that the Board of Education approves the 2019-29
Capital Investment Plan.
CHAPEL HILL-CARRBORO CITY SCHOOLS
CAPITAL INVESTMENTS PLAN 2019-2029 page 1 of 2
EXPENDITURES PENDING
2018-19 Budgeted Year 1 Year 2 Year 3 Year 4 Year 5 Five Year Years 6 to 10
PROJECT TITLE ottery Funded Project: 2019-20 2020-21 2021-22 2022-23 2023-24 Total 2024-29
ADA Requirements 35,000 35,000 35,000 50,000 50,000 50,000 220,000 250,000
Abatement Projects -
District Abatement Projects 150,000 50,000 50,000 50,000 50,000 50,000 250,000 250,000
Phillips:Continue Remove of Asbestos Floor Tile 150,000 150,000 300,000
Athletic Facilities
CHHS:Athletic Field Improvements -
Carrboro HS:Field Improvements 100,000 100,000
ECHHS:Field Improvements 175,000 91,418 266,418
SmithMdl:6 tennis courts rebuilt 300,000 300,000
Classroom/Building Improvements 75,000 -
Seawell:PODs Casework for HVAC 211,374 211,374
Phillips:4 Science Classrooms Casework -
Phillips:Correct water inflitration 175,000 175,000
MCDElm:corridors and classrooms 65,000 65,000
Playground Equipment:FPG,Seawell,Carrboro,E 482,246 200,000 200,000 200,000 1,082,246
Doors/Hardware/Canopies -
District Hardware and Door Replacements 50,000 75,000 100,000 100,000 100,000 100,000 475,000 375,000
Seawell:Expand canopies - 120,000
FPG:Canopy at Kiss n Go and Bus Circle - 150,000
Ephesus:Canopy at Kiss and Go 150,000 150,000
Electrical Systems 75,000 -
AII Schools:Electrical Installations 125,000 150,000 150,000 150,000 150,000 725,000 650,000
Energy Efficiency Improvemnets 231,867 -
Ephesus/Seawell:Replace pneumatic controls 200,000 200,000
MCDElm:continue conversion from pneumatic 200,137 200,137
ECHHS:Conversion to Digital Controls 200,000 304,070 504,070
Fire/Safety/Security Systems -
Security Systems:Camera Upgrades/Expansions/ 23,307 100,000 150,000 200,000 200,000 200,000 850,000 500,000
FPG Intercom System 100,000 100,000
ECHHS Intercom System - 125,000
Indoor Air Quality Improvements -
District IAQ Projects 25,000 50,000 50,000 50,000 75,000 75,000 300,000 250,000
Rental Space 140,000 143,000 145,000 148,000 150,000 726,000 800,000
Paving:Parking Lots/Driveways/Walkways 100,000 50,000 50,000
McD Mdl:bus driveway and parking lot paving 53,297 53,297
ECHHS:bus driveway and parking lot paving 75,000 75,000
Roofing/Building Waterproofing Projects
Glenwood/EstesHills/Ephesus/FPGraham:window seals 200,000
Smith:Roof project(at 20 years)/envelope seal 473,449 1,000,000 1,473,449 750,000
Scroggs/Phillips:brick pointing/envelope seal 154,650 154,650
ECHHS:Roof project(at 25 years) - 2,500,000
CarrboroHS:roof replacement(20 years) 3,125,000
Storm Water Management 200,000
Restorations/certifications 50,000 50,000 50,000 50,000 60,000 60,000 270,000
CHAPEL HILL-CARRBORO CITY SCHOOLS
CAPITAL INVESTMENTS PLAN 2018-2028 page 2 of 2
- PENDING
2018-19 Budgeted Year 1 Year 2 Year 3 Year 4 Year 5 Five Year Years 6 to 10
PROJECT TITLE ottery Funded Project 2019-20 2020-21 2021-22 2022-23 2023-24 Total 2024-29
Mechanical Systems 200,000 200,000
McDougle:HVAC Systems:replace pheumatic cor -
Rashkis:Chiller replacement 626,727
Sustainability Investment 100,000 100,000 100,000 100,000 400,000 232,512
Lighting conversions to LED/Energy Mgt Systems 100,000
Information Technology-IT 961,761 1,619,281 1,607,179 787,074 900,000 5,875,295 8,000,000
Article 46 Sales Tax-Funded Projects
-Technology:Student Access Computing Devices 548,706 570,654 593,480 617,219 642,000 2,972,059 3,476,782
-Improvements at Older Schools: - 3,476,782
Replacement 154,566 180,055 334,621
-MdDougleMdl:replace pneumatic controls/EMP
Controls 203,899 250,000 157,165 611,064
-CarrboroElm:Auditorium HVAC 150,000 150,000
-Glenwood:HVAC Energy Management Controls 150,000 150,000
-Ephesus:HVAC Controls 125,000 125,000
-Estes Hills/Glenwood/CarrboroElm:boiler
replacements 100,000 100,000
-Smith:chiller replacements 375,000 375,000
Bld 200,000 218,749 175,000 593,749
units 75,000 75,000
Units 285,000 225,000 510,000
-ECHHS:Chiller 2 Replacement/Cooling Tower 250,000 150,000 400,000
Contingency - 250,900 431,179 968,833 1,650,912
TOTAL CIP EXPENDITURES 815,174 5,048,790 5,143,652 4,634,034 4,734,630 4,838,235 23,499,341 25,857,803
CAPITAL FUNDING SOURCES
2018-19 Budgeted Year 1 Year 2 Year 3 Year 4 Year 5 Five Year Years 6 to 10
2019-20 2020-21 2021-22 2022-23 2023-24 Total 2024-29
Long Range Pay-As-You-Go Funds 2,352,423 2,436,568 2,485,299 2,535,005 2,585,705 2,637,420 12,679,998 13,999,740
Lottery Funds-Budgeted 815,174 851,650 851,650 851,650 851,650 851,650 4,258,250 4,258,250
Facility Improvements-5 Year Funding 600,900 607,300 607,300 - - - 1,214,600 -
Article 46 Sales Tax-1/4 Cent 1,097,411 1,153,272 1,199,403 1,247,379 1,297,274 1,349,165 6,246,493 7,599,813
TOTAL CIP FUNDING 4,865,908 5,048,790 5,143,652 4,634,034 4,734,630 4,838,235 24,399,341 25,857,803
(0) (0) 0 0
Projected through Five Year
2016 SCHOOL BOND-$72,108,000 2018-19 2019-20 2020-21 2021-22 1 2022-23 2023-24 Total
PROJECTS:
Chapel Hill High School Renovation Project 25,700,000 33,800,000 11,050,000 70,550,000
Lincoln Center Campus 1,558,000 1,558,000
CHAPEL HILL-CARRBORO CITY SCHOOLS
CAPITAL INVESTMENTS PLAN 2019-2029 UNFUNDED MAJOR EXPANSIONS,RENOVATIONS and PROJECTS
10 YEAR UNFUNDED NEW SCHOOLS
Year Year Year Year Year Year Year Year Year Year10 TEN YEAR
2019-20 2020-21 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 2/27/2028 2028-29 TOTAL
PROJECTS:
REMAINING FACILITY ASSESSMENT PROJESTS:
Lincoln Center Campus Redevelopment-inc.elementary cap 6,130,000 25,680,000 6,990,000 38,800,000
Ephesus-inc.capacity+137 BID2023 1,500,000 12,500,000 18,000,000 5,361,786 37,361,786
Seawell-inc.capacity+119 BID 2024 1,500,000 12,000,000 16,000,000 3,463,528 32,963,528
Estes Hills-inc.capacity+58 BID 2024 1,500,000 14,000,000 17,000,000 3,166,754 35,666,754
Phillips MS BID 2024 750,000 9,000,000 10,000,000 3,515,493 23,265,493
Carrboro Elm.-inc.capacity+52 BID 2026 1,500,000 12,000,000 16,000,000 3,069,737 32,569,737
FP Graham BID 2027 500,000 7,000,000 7,000,000 14,500,000
Culbreth MS BID 2028 750,000 6,950,000 7,700,000
OTHER MAJOR PROJECTS:
CarrboroHS:Stadium Visitor Bleachers 600,000 600,000
CarboroHS:Stadium Synthetic Field 1,250,000 1,250,000
CHHS:Stadium Visitor Bleachers 300,000 300,000
CHHS:Stadium Synthetic Field 1,250,000 1,250,000
CHHS:Baseball Field Bathroom/Concession Bld 1,200,000 1,200,000
ECHHS:Stadium Synthetic Field 1,250,000 1,250,000
ECHHS:Stadium Visitor Bleachers 300,000 300,000
Carrboro Elementary:Multi purpose field 150,000 150,000
Scro s:Athletic Field 200,000 200,000
Middle Schoiols:Tracks 500,000 500,000
ECHHS:Theater Lighting and Sound upgrade 900,000 900,000
CarrboroHS:Chillers and Cooling Towers at 20 ears 750,000 750,000
Morris Grove:Chillers and Cooling Towers at 20 ears 650,000 650,000
Rashkis:Roof Replacement and envelope at 20 ears 2,250,000 2,250,000
McDMdl/Elm:casework 400,000 400,000 800,000
Technology
Equity&Modernizing Classroom Instructional Technology 492,000 492,000 100,000 100,000 100,000 100,000 100,000 100,000 100,000 1,684,000
Building Additions
McDou le Middle School:Auditorium 750,000 6,000,000 1,000,000 7,750,000
TOTAL UNFUNDED PROJECTS 6,130,000 27,822,000 13,882,000 3,200,000 19,800,000 53,600,000 51,311,786 27,245,775 24,500,000 17,119,737 244,611,298
HAPEL IILL-
�ORO
C ITY SCHOOLS
Recommended
CAPITAL INVESTMENT PLAN
JANUARY 2019
Capital Projects Completed in 2018- 19
• Carrboro Elementary
— Replaced gym wood floor
— Cooling Tower replaced
— Multi Purpose Building HVAC unit (Spring Break)
• Ephesus Elementary
— Replaced the final 6 (of 13) HVAC rooftop units on the
main building
— Lighting converted to LED
• Glenwood Elementary
— Lighting to LED
Capital Projects Completed in 2018- 19
• FP Graham Elementary
— Designed replacement HVAC systems for Gym and
Media Buildings. BIDS in Feb/March
— Lighting converted to LED
• McDougle Elementary
— Completed new playground
• Seawell Elementary
— Replaced kitchen HVAC system
Capital Projects Completed in 2018- 19
• McDougle Middle
— Installed new HVAC system in server room
• Phillips Middle
— Finished Phase I removal of asbestos floor the
— Media Center renovation and new furniture
• Transportation Center
— Replaced the HVAC system for office area
Capital Projects Completed in 2018- 19
• District Projects
— Paving repairs at Ephesus, Glenwood, McDougle,
ECHHS
— Completed Phase 2 (of 3) Infrared Scan of
Electrical Systems
FUNDED PLAN
Capital Funding Sources
FY 2019-20
Pay-As-You-Go 21436,568
State Lottery 851,650
Article 46 Sales Tax 11153,272
Facility Imp. — 5 Year 607,300
Total 51048,790
FUNDED PLAN
2019-20 Capital Projects
• Phillips MS
— Removal of asbestos floor the (Phase 2)
— Correct water infiltration into lower level
• Smith MS — restoration of 6 tennis courts
• FP Graham — establish a new playground
• McDougle Elm — correct damaged baseboard
• Seawell — begin replacement of PODS HVAC units
• Carrboro Elm — replace auditorium HVAC unit
• Culbreth MS — replacement of heat pumps
• ECHHS — replace chiller
UNFUNDED PLAN
2013 Facilities Assessment - Schools and Capacity Impact
School Capacity Increase
Lincoln Center +189 elementary
+ 75 high school
Ephesus Elm +137 elementary
Seawell Elm +119 elementary
Estes Hills Elm + 58 elementary
Phillips Middle
Carrboro Elm + 52 elementary
FP Graham Elm
Culbreth MS
+555 elementary
+ 75 high school
SAPFO Projections
2019 Projections have not yet been published .
If class size reductions are implemented
according to current State guidelines, the
district's elementary school capacity will exceed
SAPFO's 105% level of service requiring
additional classrooms in 2021-22 .
District's "New" Schools
SCHOOL YEAR OPENED AGE
McDougle Middle School 1994 25
McDougle Elementary School 1996 23
East CH High School 1996 23
Scroggs Elementary School 1999 20
Smith Middle School 2001 18
Rashkis Elementary School 2003 16
Carrboro High School 2007 12
Morris Grove Elementary School 2008 11
Phoenix Academy 2009 10
Northside Elementary School 2013 6
GENERAL FUND BALANCE
• General Fund balance above 5.5% target 5/125/828
• Recurring Capital balance 1/535/848
• Cellular Tower Balance 485.1095
• Available Cash 7,146.1771
• CHHS CTE Building Reserve -21281.1277
• Remaining Available Balance 4/865/494
As of 12/31/18
Questions