HomeMy WebLinkAboutAgenda - 02-05-2019 6-b - Northern Campus Project Update 1 ORANGE COUNTY BOARD OF COMMISSIONERS ACTION AGENDA ITEM ABSTRACT Meeting Date: February 5, 2019 Action Agenda Item No. 6-b SUBJECT: Northern Campus Project Update DEPARTMENT: County Manager's Office ATTACHMENT(S): INFORMATION CONTACT: 1 - Northern Campus Schematic Design Travis Myren, Deputy County Manager, Cost Estimates 919-245-2308 2 - Value Engineering Strategies 3 - Scope Reductions 4 - Project Deferments PURPOSE: To review schematic design cost estimates for the County's Northern County Campus and consider budget adjustments to the project. BACKGROUND: The County's FY2018-19 Capital Investment Plan merged three independent projects into the Northern Campus development. This development, located off of Highway 70 in Hillsborough, is intended to include a replacement Detention Center, Environment and Agricultural Center, and Parks Operations Base. The Board of Commissioners appropriated approximately $28 million for the project. As currently designed, the new Detention Center would consist of one hundred forty-four (144) beds in approximately 48,900 square feet. The new facility would replace the existing 40,227 square foot detention facility located in downtown Hillsborough that was originally constructed in 1925 with additions and modifications occurring in the early 1980's and mid-1990's. The new 17,200 square foot Environment and Agricultural facility would replace the 19,087 square foot office building currently located on Revere Road that houses the Department of Environment, Agriculture, Parks and Recreation, Cooperative Extension, Farm Service Agency, and Soil and Water Conservation. Finally, the 8,500 square foot Parks Operations Base would replace scattered facilities at Millhouse Road Park used for office and equipment storage. The County has recently completed the schematic design phase of the project and updated cost estimates based on the building dimensions described above and programming needs of the future building occupants. Based on those estimates, the current authorized budget amount is not sufficient to complete the entire scope of the project. With no changes to the current project scope or value engineering, the project is projected to exceed the budgeted appropriation by approximately $13 million. Attachment 1 details the schematic design cost estimates and budgeted appropriations for each element of the project. 2 At least three factors have contributed to this difference. First, these projects have been included in the Capital Investment Plan for several years without budget escalation to recognize inflationary cost pressures. The Detention Center has been in the CIP since 2012. The Environment and Agricultural Center was originally included in the CIP in 2014, and the Parks Operations Base was included in 2013. In recent years, construction costs have escalated by five to seven percent annually. Second, the current construction environment is highly competitive, so an inflationary adjustment of seven percent (7%) is added to the projected costs. Finally, the original budget did not assume site acquisition costs or the associated increase in site preparation for a larger site compared to the original detention center site owned by the State. Several strategies can be used to reduce the cost of the Northern Campus Project. Repurpose Previously Appropriated Funds: The County had previously borrowed funds for Detention Center Design. Of this amount, approximately $718,000 is remaining to apply to the current Northern Campus Project. Value Engineering: Value engineering strategies can be used to change architectural and aesthetic features without impacting how the facilities function. The project team has identified $875,000 in value engineering strategies as detailed in Attachment 2. Project Scope Reductions: Elements of the project may be reduced or eliminated to produce savings. The staff team has identified $438,000 in potential scope reductions as detailed in Attachment 3. As part of the scope reduction exercise, the number of Detention Center beds was examined. The Detention Center capacity could be reduced by forty (40) beds which would eliminate any capacity to house federal inmates and would immediately fill the available beds. The elimination of federal inmates would also reduce operating budget revenue by $1.6 million. Project Deferments: Projects that are currently programmed in the Capital Investment Plan could be eliminated or deferred to a later date when the County's debt capacity would accommodate them. The Southern Human Services expansion and a portion of the Cedar Grove Park Phase 2 expansion could be postponed for a savings of $2.6 million. Components of the Northern Campus project could also be postponed. Postponing the Environment and Agricultural Center and the Parks Operations Base would defer $7.75 million in construction costs. Given the County's current debt profile, debt capacity will begin to increase in FY2023- 24. See Attachment 4. Using a combination of these strategies, current project costs may be reduced. The following table outlines different strategy combinations in four (4) different options. 3 Northern Campus Project Options Current Estimated Costs and Budget Option 1 Option 2 Option 3 Option 4 Estimated Project Costs-January 2019 $ 41,155,486 $ 41,155,486 $ 41,155,486 $ 41,155,486 Appropriated Budget $ (28,095,831) $ (28,095,831) $ (28,095,831) $ (28,095,831) DIFFERENCE $ (13,059,655) $ (13,059,655) $ (13,059,655) $ (13,059,655) Cost Reduction Strategies Repurpose Funds from Prior Jail Project $ 719,700 $ 719,700 $ 719,700 $ 719,700 Value Engineering Strategies $ 875,000 $ 875,000 $ 875,000 $ 875,000 Project Scope Reductions $ 438,000 $ 438,000 $ 438,000 $ - Other CIP Deferments $ 2,655,500 $ 2,655,500 $ 2,655,500 $ 2,655,500 Postpone EAC and Parks Ops. Construction $ 7,751,375 $ 7,751,375 $ - $ - Reduce Detention Center Capacity by 40 Beds $ 2,647,020 $ - $ - $ - TOTAL COST REDUCTION STRATEGIES $ 14,366,895 $ 11,719,875 $ 3,968,500 $ 3,530,500 DIFFERENCE $ 2,026,940.00 $ (620,080.00) $ (8,371,455.00) $ (8,809,455.00) Option 1 would fund a smaller Detention Center only. It employs a sufficient number of reduction strategies to create a positive project balance of approximately $2 million. Option 2 funds a 144 bed Detention Center but defers construction of the Environment and Agricultural Center and Parks Operations. This option would require an additional $620,000 in budget authorization. Option 3 completes all of the components of the project but eliminates project scope requested by the stakeholders. This option would require approximately $8.37 million in additional budget authorization. Option 4 completes all of the project components and funds the full project scope as requested by the project stakeholders. Option 4 would require an additional $8.8 million in authorized funds. FINANCIAL IMPACT: The options outlined above would have varying levels of budget impact. Each option is evaluated below in terms of its impact on the County's debt to revenue policy. 4 Northern Campus Options and Five Year Debt to General Fund Revenue Policy Policy Target Status Quo CIP Option 1 Option 2 Option 3 Option 4 FY 2020 15.00% 13.24% 13.24% 13.24% 13.24% 13.24% FYW1 151W. 14.52% 14.49% 14.53% 14.64% 14.65% FY 2022 15.00% 17.79% 17.71% 17.81% 18.12% 18.13% FY 2023 15.00% 16.25% 16.17% 16.27% 16.57% 16.58% FY 2024 15.00% 15.46% 15.38% 15.48% 15.73% 15.73% FY 2025 15.00% 13.86% 13.79% 13.89% 14.15% 14.17% The Board of County Commissioners has established a debt to general fund revenue policy of fifteen percent (15%). Given the amount of debt that the County has issued and plans to issue in the approved Capital Investment Plan, that target is exceeded in FY2022, 2023, and 2024. Adding budget authorization in Options 2, 3, and 4 will have some impact on this metric. Option 4, for example, adds $8.8 million to the project budget and increases the debt to revenue measure from 17.79% to 18.13% in 2022, an increase of 0.34%. SOCIAL JUSTICE IMPACT: The following Orange County Social Justice Goals are applicable to this item: • GOAL: CREATE A SAFE COMMUNITY The reduction of risks from vehicle/traffic accidents, childhood and senior injuries, gang activity, substance abuse and domestic violence. • GOAL: ESTABLISH SUSTAINABLE AND EQUITABLE LAND USE AND ENVIRONMENTAL POLICIES The fair treatment and meaningful involvement of people of all races, cultures, incomes and educational levels with respect to the development and enforcement of environmental laws, regulations, policies, and decisions. Fair treatment means that no group of people should bear a disproportionate share of the negative environmental consequences resulting from industrial, governmental and commercial operations or policies. • GOAL: ENABLE FULL CIVIC PARTICIPATION Ensure that Orange County residents are able to engage government through voting and volunteering by eliminating disparities in participation and barriers to participation. Proceeding with the Northern Campus Project will allow the County to improve safety and security in the Detention Center. The Campus will also employ sustainable environmental practices and produce renewable energy, and the campus components will engage the public through educational programming to increase civic participation. RECOMMENDATION(S): The Manager recommends that the Board approve Northern Campus Option 1, 2, 3, or 4 and authorize staff to present a budget amendment at an upcoming meeting to appropriate funds based on the Board-approved Option. 5 Attachment A Northern Campus Schematic Design Cost Estimates Site Detention EAC Park Ops Totals Acquisition $ 399,050 $ 399,050 Construction $ 6,136,334 $ 20,912,440 $ 5,149,700 $ 1,260,771 $ 33,459,245 Enhanced Energy Efficiency $ 2,144,124 $ 169,497 $ 118,608 $ 2,432,229 FF&E $ 500,000 $ 75,000 $ 50,000 $ 625,000 Owner Contingency $ 245,453 $ 836,498 $ 205,988 $ 50,431 $ 1,338,370 Professional Fees $ 175,000 $ 2,266,332 $ 671,380 $ 3,112,712 TOTAL CAMPUS COST ESTIMATE $ 6,955,837 $ 26,659,394 $ 6,271,565 $ 1,479,810 $ 41,366,606 Budget Appropriation $ 5,550,050 $ 16,825,780 $ 4,415,000 $ 1,305,001 $ 28,095,831 Difference 1 $ (1,405,787) $ (9,833,614) $ (1,856,565) $ (174,809) $ (13,270,775) 6 Attachment B Value Engineering Strategies Site Detention EAC Park Ops TOTAL Delete One of Three Multipurpose Rooms $ (384,800) Delete Precast Masonry Watertable to Brick $ (50,000) Delete Pop Up Roof at Entry/Sallyport $ (200,000) Replace Exterior Metal Wall Panels with Utility Brick $ (95,000) Contract Supply Video Visitation Equip $ (46,200) Reduce Parking by 25% $ (50,000) Delete Pop Up Roof at EAC $ (24,000) Convert West Hill Connector from Asphalt to Stone 1 $ (25,000) TOTAL VALUE ENGINEERING STRATEGIES 1 $ (25,000) $ (776,000) $ (74,000)1 1 $ (875,000) Reduction of 2,600 sq.ft.in Environment and Agriculture Center Included in Base Cost 7 Attachment C Project Scope Reductions Site Detention EAC Parks Ops TOTAL Convert Sallyport Walls to Fence Barrier $ (200,000) Delete Automatic Flush Valves in Public Areas $ (35,000) Eliminate Hearing Room for Magistrate $ (128,000) Eliminate Generator for Parks Ops $ (75,000) TOTAL SCOPE REDUCTIONS 1 0 $ (363,000) $ $ (75,000) $ (438,000) Detention Bed Space Reduction of 40 Beds Delete Two Housing Units-Eliminate Capacity for Federal Inmates 1 1 $(2,647,020) $ (2,647,020) 8 Attachment D Other Capital Investment Plan Deferments Postpone Southern HS Expansion $ (1,555,500) Postpone Cedar Grove Park Phase 2 $ (1,100,000) TOTAL OTHER CIP DEFERMENTS $ (2,655,500) Northern Campus Project Deferments Site Detention EAC Parks Ops TOTAL Postpone EAC Construction $ (6,271,565) $ (6,271,565) Postpone Parks Ops. Construction $ (1,478,810) $ (1,478,810) TOTAL NORTHERN CAMPUS DEFERMENTS $ (7,750,375)