HomeMy WebLinkAboutAgenda 6-a - Orange County Transportation Priority List for SPOT 6.0 FY 2022-2031 STIP 1
ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: February 5, 2019
Action Agenda
Item No. 6-a
SUBJECT: Orange County Transportation Priority List for SPOT 6.0 / FY 2022-2031 STIP
DEPARTMENT: Planning and Inspections
ATTACHMENT(S): INFORMATION CONTACT:
1. Projects in TARPO Nishith Trivedi, Transportation Planner,
2. Projects in DCHC MPO 919-245-2582
3. Projects in BG MPO Tom Altieri, Comprehensive Planning
4. Draft Resolution Supervisor, 919-245-2579
Craig Benedict, Planning Director, 919-
245-2592
PURPOSE: To consider a resolution endorsing lists of Orange County transportation projects to
the Burlington-Graham Metropolitan Planning Organization (BGMPO), Triangle Area Rural
Planning Organization (TARPO) and Durham-Chapel Hill-Carrboro Metropolitan Planning
Organization (DCHC MPO) for Strategic Prioritization of Transportation (SPOT)/Strategic
Transportation Improvement Program (STIP).
BACKGROUND: Biennially, the North Carolina Board of Transportation (BOT) adopts a ten
year STIP that funds and schedules transportation projects throughout the state for all modes of
transportation. The STIP implements Metropolitan and Rural Planning Organization's
(MPO/RPO) adopted Comprehensive Transportation Plan (CTP) and Metropolitan
Transportation Plan (MTP). The CTPs and MTPs are used by MPO/RPOs to determine which
projects are submitted for considered in the STIP using the SPOT process.
SPOT 5.0/STIP FY 2020-2029
Orange County has thirty-nine (39) projects in SPOT 5.0. This includes its member jurisdictions
- Hillsborough, Mebane, Chapel Hill, and Carrboro. Eight of them have been funded, and those
projects are:
• TIP - I-3306A: I-40 Widening from 1-85 to US 15/501
• TIP - 1-5984: 1-85 at NC-86 Interchange upgrade
• TIP - 1-0305: 1-85 Widening from Orange Grove Road to Durham County
• TIP - U-5304A, B, D, E, F: US 15/501 improvements from NC-86 to I-40 (Chapel Hill)
SPOT 6.0 Schedule and Process— FY 2022-2031
Between July 1, 2019 — September 30, 2019, MPO/RPOs across the state will submit their
limited number of projects — based on their population and total centerline miles — to the North
Carolina Department of Transportation (NCDOT) for inclusion in SPOT 6.0. These projects must
be approved by their respective Boards prior to submission. Orange County's process requires
that the Board of County Commissioners (BPCC) approve the list of County transportation
2
priorities prior to submission to the respective MPO/RPO. Each MPO/RPO has its own unique
process for determining which limited number of projects it submits to NCDOT.
• DCHC MPO will only submit projects listed in the adopted MTP
• TARPO will establish a subcommittee to determine which projects to submit
• BG MPO uses a multi-criteria process to determine which projects to submit
Before MPO/RPO Boards approve the projects for submission, they will conduct a 30 day public
comment period and public hearing.
SPOT 6.0 Project List— Staff and OUTBoard Recommendations
Based on changes to MPO/RPO SPOT project selection processes, staff is recommending
Orange County transportation priorities also change so that projects may compete better. Staff
has also met with member jurisdictions in Orange County to identify specific corridors they
would like addressed through SPOT/STIP or other funding opportunities. These changes and
potential corridors are provided as staff recommendations for Orange County Transportation
Priorities (Attachments 1 - 3). Many Orange County 2017 transportation priorities are carried
forward and highlighted in Green. Possible new priorities are provided in
• Staff is recommending removal of independent bike/pedestrian projects based on
Strategic Transportation Investment (STI) Law § 136-189.11 (d).(3).c.— The Department
shall not provide financial support for independent bicycle and pedestrian improvement
projects.
o Independent bike/ pedestrian projects can be pursued through "Federal Surface
Transportation Block Grant Direct Allocation".
o They require 20% local match and local administration.
• Staff recommends converting paved shoulder projects and independent bike/ pedestrian
projects to highway modernization projects with bike lanes.
o First 5 feet of sidewalk width is subject to NCDOT's Sidewalk Cost Share Policy —
50% for Orange County — and any additional width must be 100% locally funded.
• Staff recommends adding Old NC-86, NC-86, US-70 and NC-54 as County Priorities for
SPOT and other funding opportunities.
• OUTBoard recommendations are provided in Attachments 1 — 3. Below is a summary of
its recommendations:
o Carry forward previous County Priorities and recommend they be highway projects
with 11' travel lane and 5' paved shoulder, no curb and gutter or sidewalk.
■ Projects in town jurisdictions should be coordinated with the town with the
understanding towns may submit them to MPO.
o US-70 widening not recommended as possible project
■ Opposes more cars on road and find better ways to keep trucks on interstate
so they do not avoid the weigh station.
o Table NC-86 and NC-54 till MPO/RPO complete update to CTP
■ Recommend BOCC request TARPO request NCDOT study NC-86 and update
CTP before proceeding with possible project.
■ Await DCHC MPO action on NC-54 Corridor Study before proceeding with
possible project.
FINANCIAL IMPACT: There is no immediate financial impact associated with this item.
However, should the County seek any bicycle or pedestrian projects, it will be required to
provide 20 percent local match for the project's overall cost and to provide local administration.
All bike and pedestrian projects will require a resolution or letter of commitment from Orange
3
County indicating the County will provide the local match and administration if any such projects
are selected for funding. This would be choreographed with the County's budget process.
SOCIAL JUSTICE IMPACT: The following Orange County Social Justice Goal is applicable to
this item:
• GOAL: ESTABLISH SUSTAINABLE AND EQUITABLE LAND-USE AND
ENVIRONMENTAL POLICIES
The creation and preservation of infrastructure, policies, programs and funding
necessary for residents to provide shelter, food, clothing and medical care for
themselves and their dependents.
RECOMMENDATION(S): The Manager recommends that the Board approve/endorse the
resolution (Attachment 4) to submit transportation projects to the BGMPO, TARPO and DCHC
MPO for SPOT 6.0/STIP 2022-2031.
4
_ Current County priority as highway project
Attachment 1: Draft Triangle Area Rural Planning Organization(TARPO)Project List New Project
MPO/ AADT 2010- Crashes 2006- 2018 Results Recommendations
# RPO Project Description/Need 2016 2016 (SPOT 5.0)
Staff OUTBoard
Description:Modernize Old Greensboro Road(SR-1005)from Jones Ferry Road(SR-1942)to Alamance
County with NCDOT standard street cross-section 2B(60'row,11'travel lanes,with 5'paved shoulder), add
turn lanes and safety improvements at Jones Ferry Road(SR-1942),Hatch Road(SR-1944),Neville Road(SR- ,,,pest 2800-3000 Total 339 County priority
1945),Carl Durham Road(SR-1950),White Cross Road(SR-1951),Wildcat Creek Road(SR-1953),and 5 fatal redefined as
TARPOOld Greensboro Orange Chapel Clover Garden Road(SR-1956). 6 serious injury County Priority
1 /DCHC
(SR-1005)Road 45 minor injury highway project County priority as
CHC highway project
Improvement** Need:This project would provide a continuous paved bikeway segment from Carrboro through the 51 possible injury 22.36 Division Meets RPO
southwestern portion of Orange County to connect with other bikeway segments that comprise the state's 232 property SPOT process
Mountain to Sea bicycle route.The project is not likely to score very high using either the State's highway or east 4600-4800 damage
bike/pedestrian scoring factors because of its rural context and is only eligible for funding at the division tier.
Description:Widen Efland-Cedar Grove Road(SR 1004)from Highland Farm Road(SR 1332)to Carr Store
Road(SR-1352)with NCDOT standard street cross-section 2B(60'row,11'travel lanes,with 5'paved
shoulder), add turn lanes and safety improvements at Carr Street(SR-1357)and highland Farm Road(SR- north 1400-1800 Total 56 14.63 Division County priority
-Cedar Grove 1332). 1 serious injury redefined as
Efland
2 TARPO Road-Selo Grove
6 minor injury No local points highway project County priority as
Improvements** Need:The project improves travel time by increased design speed and improves safety with travel lane 11 possible injury recommended highway project
straightening and increased pavement width.This segment of Efland-Cedar Grove Road is a travel alternative 38 property Meets RPO
to NC 86 for traffic from northwestern Orange County to access 1-40/85,and as such,traffic is projected to south 2100-2200 damage Not funded SPOT process
continue to increase in future years.
Description:Modernize Orange Grove Road(SR-1106)from 1-85 to Dodson Crossroad(SR-1007)with NCDOT County Priority
standard street cross-section 2B(60'row,11'travel lanes,with 5'paved shoulder), add turn lanes and safety Total 102
improvements at Ode Turner Road(SR-1130),Dimmocks Mill Road(SR-1134),Crossroad Church Cemetery north 4700-4600 County priority
Road(SR-1131),Davis Drive(SR-1129),Kimbro Road(SR-1128)and Dodson Crossroads(SR-1102) 1 fatal Not submit to redefined as
Orange Grove Road 1 serious injury NCDOT for
TARPO 3 (SR-1006) 7 minor injury P5.0 highway project County priority as
/DCHC Need:This project would provide one segment of a bikeway connection through western Orange County from highway project
Improvement** Carrboro to the Buckhorn Road and Mebane area and improve the safety of the subject thoroughfare for both 13 possible injury Meets RPO
bicyclists and motorized vehicular travel.The project is not likely to score very high using the State's south 2400-3100 80 property No 20a o local SPOT process
administration
local
bike/pedestrian scoring factors because of its rural context and is only eligible for funding in the division tier. damage match ration
Description:Modernize Dairyland Road(SR-1177)from Orange Grove Road(SR-1006)to Old NC-86(SR-
1009)with NCDOT standard street cross-section 2B(60'row,11'travel lanes,with 5'paved shoulder), add County Priority
turn lanes and safety improvements at Orange Grove Road(SR-1006),Dodson Crossroads(SR-1102),Rocky Total 121
Ridge Road(SR-1113), Bethel Hickory Grove Church Road(SR-1104)and convert intersection at Old NC-86 west 940-970 2 fatal Not submit to County priority
Dairyland Road (SR-1009)to Roundabout. 2 serious injury NCDOT for redefined as
4 TARPO (SR-1177) 15 minor injury P5.0 highway project County priority as
/DCHC Improvement** Need:This project would provide one segment of a bikeway connection through western Orange County from 16 possible injury highway project
Meets
Carrboro to the Buckhorn Road and Mebane area and improve the safety of the subject thoroughfare for 86 property No 20%local
motorized vehicular travel.The project is not likely to score very high using the State's bile/pedestrian scoring east 5400-5200 damage match or local SPOT process
factors because of its rural context and is only eligible for funding at the division tier. administration
Description:Modernize Dodson Crossroad(SR-1102)from Orange Grove Road(SR-1006)to NC-54 with
NCDOT standard street cross-section 2B(60'row,11'travel lanes,with 5'paved shoulder), add turn lanes and County Priority
safety improvements at Orange Grove Road(SR-1106),Borland Road(SR-1126),Arthur Minnis Road(SR- north 830-1000 Total 62 County priority
1115),and Dairyland Road(SR-1177) Not submit to
2 serious injury redefined as
Dodson Crossroad NCDOT for
TARPO 8 minor injury highway project County priority as
5 (SR-1102) Need:This project would provide bicycle facilities to the Grady Brown Elementary School and Cedar Ridge P5.0
/DCHC 10 possible injury highway project
Improvement** High School from the area south of the schools and connect to a proposed bikeway facility on Orange Grove 42 property o Meets RPO
Road northward into Hillsborough.The project would also improve safety for motorized vehicular travel on this south 1800-1800 damage No 20/local SPOT process
segment of Orange Grove Road.The project is not likely to score very high using the State's bike/pedestrian match or local
scoring factors because of its rural context and is only eligible for funding in the division tier. administration
5
_ Current County priority as highway project
Attachment 1:Draft Triangle Area Rural Planning Organization(TARPO)Project List New project
Recommendations
MPO/ AADT 2010- Crashes 2006-
Map RPO Project Description/Need 2016 2016 2018 Results
Staff OUTBoard
Description:Modernize Mebane Oaks Road(SR 1007)from NC 54 to 1-85 with NCDOT standard street cross-
section 2B(60'row,11'travel lanes,with 5'paved shoulder),add turn lanes and safety improvements at Old
Hillsborough Road Road(SR-2126),Hebron Church Road(SR-1139),Yarborough Road(SR-1138),Oak Grove north 4400-3400 Total 161
Church Road(SR-1117),Jones Road(SR-1123),S Jim Minor Road(SR-2135),Nicks Road(SR-1119), 2 fatal New Project
Mebane Oaks Road Bradshaw Quarry Road(SR-1100),and NC-54 4 serious injury New County
6 TARPO (SR-1007) 19 minor injury N/A Meets RPO priority
Improvement** Need:This project would provide multimodal and safety improvements along a north-south corridor that 31 possible injury SPOT process
connects Orange and Alamance County.This corridor is growing more unsafe with increasing accidents,two of 105 property
south 2400-2400 damage
them being fatal.Intersection improvements such as crosswalks and turn lanes will reduce crash frequencies
and better manage traffic at key locations along the corridor.
Description:Modernize Old NC-86(SR-1009)from 1-40 to Eubanks Road(SR-1727)with NCDOT standard
street cross-section 2B(60'row,11'travel lanes,with 5'paved shoulder), add turn lanes at Davis Road(SR- north 5500-6300 Total 208
1129),and New Hope Church Road(SR-1723) 3 fatal
Old NC-86 3 serious injury New Project
TARPO Need:This project would provide multimodal and safety improvements along a north-south corridor for New County
7 (SR-1009) 15 minor injury N/A
/DCHC commuters travel between Hillsborough and Carrboro.This corridor is growing more unsafe with increasing Meets RPO priority
Improvement** accidents,three of them being fatal.Intersection improvements such as crosswalks and turn lanes will reduce 24 possible injury SPOT process
crash frequencies and better manage traffic at key locations along the corridor.Traffic along this corridor will south 4500-5000 163 property
continue increasing making the area more hazardous and will eventually exceed the capacity of the existing damage
road.
Description:Widen from NC-57 to Caswell County Line with additional lanes and multimodal facilities along the Total 609 Table
corridor and safety improvements at each intersection. north 4700-5700 g fatal
Need:This project would provide multimodal and safety improvements along a north-south corridor for 6 serious injury New Project BOCC request
46 minor injury TARPO to request
8 TARPO NC-86 Improvement** commuters travel between Orange and Caswell County.This corridor is growing more unsafe with increasing N/A
accidents,nine of them being fatal.Intersection improvements such as crosswalks and turn lanes will reduce south 11000- 111 possible Meets NCDOT restudy
crash frequencies and better manage traffic at key locations along the corridor.Traffic along this corridor will 11000 injury SPOT process corridor for
437 property possible CTP
continue increasing making the area more hazardous and will eventually exceed the capacity of the existing damage update
road.
Description:Widen NC-54 from Orange Grove Rd(SR 1006)to Butler Rd(SR 1951)/Dodsons Cross Rd(SR New Project
1102)and from Butler Rd(SR 1951)/Dodsons Cross Rd(SR 1102)to Old Fayetteville Road(SR-1107)/ East 12000- Total 340 Table
Inside DCHC with additional lanes and multimodal facilities along the corridor and safety improvements at each 15000 3 fatal TARPO Meets RPO
intersection. 8 serious injury 61.80 Region Await DCHC MPO
9 NC-54 Improvement*' SPOT process 35 minor injury action on Corridor
DCHC Need:NCDOT projections reveal that traffic on NC 54 from Orange Grove Road to Old Fayetteville Road will 61 possible injury 26.58 Division Study and
substantially exceed the existing roadway capacity by 2035,warranting an increase in capacity through West 9300- Fundable
widening.NC-54 West Corridor Study provides such recommendations necessary to address increasing traffic 10000 233 property through subsequent CTP
and crashes along corridor. damage Regional Impact and MTP update
Description:Widen from Mebane Oaks Road(SR-1007)to Orange Grove Rd(SR 1006)with additional lanes East 9300-10000 New Project
and multimodal facilities along the corridor and safety improvements at each intersection. Total 163 Table
1 fatal Meets RPO
4 serious injury Await DCHC MPO
10 TARPO NC-54 Improvement** Need:NCDOT projections reveal that traffic on NC 54 from Orange Grove Road to Old Fayetteville Road will 19 minor injury N/A SPOT process action Corridor
substantially exceed the existing roadway capacity by 2035,warranting an increase in capacity through West 5800-6000 20 possible injury Fundable Study and
widening.NC-54 West Corridor Study provides such recommendations necessary to address increasing traffic 119 property subsequent CTP
u
and crashes along corridor damagethrough date
Regional Impact p
Notes:
*STI Law§136-189.11.Transportation Investment Strategy Formula section(d).(3).c.—The Department shall not provide financial support for independent bicycle and pedestrian improvement projects.
**Sidewalk subject to NCDOT sidewalk cost share policy 40%Orange County for 1"5 feet of sidewalk and 100%Orange County for any additional sidewalk.
Attachment 1: Draft Triangle Area Rural Planning Organization(TARPO)Project List 6
TARPO SPOT G - Projects
Caswell Co. Person G
.i1N11Erri'0
t
s �1 oRv+�a° � lnvrs 5ron[ly Ap
r� 49 4 5 HAYNune6 kO
a'
��e�❑❑❑ � o¢ � u1 rLe RwrvpivRch' '� °w
i� ;r�2 �9 y. °r6 .f•!FF'1u KP RP � }:
Ra U 5" !
nr NO 'rv1� r y $6 P*AR�i
tl'� Rp
rt Kir ER Rp
¢9 Uw ( KEnIOF!Rd. A = µV' I�ARMR .
RD
A t
iNLL3MnLRp �' l
1 PA q
24 �a F� 1 IfJrRYS p9
i
1 R
� y q•, LEBAnOn
FM
70 �LC3 LLESf FI I E-.RVOr4ST [j
RP .7
q Hillsborough,_
ZF
Rp *OF'[CuR u� S i
70
i ��t kPr- g Li r pC1R PO
°M• ma w �i 5 d• oLnl+wu 1
YO "•fie
I � ronN[RN°RA y7 RQ
rc M 'IT 511iR1 Rp
�y Durham Co.
ARFNIfR
TP �• v
LnND ev LL ..7�n''IELP kp
Rp },
TF.EK Pd r� � � � � yPJ '•Yl;ri
1 J p ❑ ii 11 Ro
i Chapel Bill
U86 s
�yRo ► Car Qr�baro F;,g r }ittilr3C �P
� r"QkK�I' a r��i1���a��,N rkeF�' e`.vp.:f 5S• f r
��F � � I7}JI •A � Ft^.u� It:.i l-.rT;r�J
�l O
OLD aPf.EN58OAq +b')iiTn R71.tr. L
llr/.
4S4 1
' C )
� 3 � _�__. A� xrRG�'t� r•'' I
Project Locations — - �__ •�,;;;", ._. — _. �� — — —.s..
Municipal Boundaries
P
L N 1 in=3 miles
❑CHC MPO Boundary COY ■ �Mir
TARPO Boundary /� 0 2
B G MPO Boundary orange County Plnnning and Inupmc ion
7
_ Current County priority as highway project
Attachment 2: Draft Durham-Chapel Hill-Carrboro(DCHC)MPO Project List New Project
MPO/ AADT 2010- Crashes 2006- 2018 Results Recommendations
# RPO Project Description/Need 2016 2016 (SPOT 5.0)
Staff OUTBoard
Description:Widen US-70 and improve intersections from Buckhorn Road(SR-1114)to Durham County with NCDOT
standard street cross-section 4G(110'row,17.5'median,11'travel lanes,5'bike lane,c&g,and sidewalk),add turn lanes
and safety improvements at NC-86,St.Mary's Road(SR-1002),Efland Cedar Grove Road(SR-1004),Frazier Road(SR- West 6400-6200 Total 1148
1310),Richmond Road(SR-1312),Brookhollow Road(SR-1324),Faucette Mill Road(SR-1328),Miller Road(SR-1555), 10 fatal
Lawrence Road(SR-1561),Palmers Grove Church Road(SR-1562),Pleasant Green Road(SR-1567),Orange High School 12 serious injury
1 DCHC US-70 Road(SR-1588),and N Scotswood Boulevard(SR-2300). 100 minor injury N/A New Project Not
/BG Improvements 220 possible injury Recommended
Need: This is a major east-west corridor linking Mebane,Hillsborough and Durham through Orange County.Traffic continues 706 property
increasing with more commuters traveling from Mebane and Hillsborough into Durham.Many use this corridor to avoid 1-85.It East 12000- damage
is also designated at a Strategic Freight Corridor in the DCHC MPO adopted Freight Plan. 14000
Description:Reconstruct interchange at 1-85 and NC 86
1-85/NC 86 Funded
Need:This project would relieve existing and/or future expected congestion on the under-capacity existing interchange to
2 DCHC Interchange NIA Statewide Funded Funded
accommodate future capacity improvements to I-85 and increase operational efficiency at the on-ramp/off-ramp intersections
Improvements TIP I-5984
with NC 86.The new interchange would also be an opportunity to provide pedestrian and biking facilities across 1-85;these
facilities do not currently exist along the corridor.
Description:Widen NC 86 from U.S.70 Bypass to north of NC 57 to four(4)lanes with intersection improvements at U.S.70
Bypass and NC 57
Total 114
NC 86 Need:The segment of NC 86 between NC 57 and U.S.70 is highly congested.Traffic counts indicate that this segment of NC 1 serious injury County Priority
3 Improvements 86 is over capacity for average annual daily counts.Capacity improvements would ease congestion and improve travel time 5 minor injury Remain County
DCHC North of alongthis primary north-south corridor connecting the Town of Hillsborough to NC 57 and northern Orange County. 17,000-18,000 26 possible injury 51.02 Regional County priority priority
P Y 9 9 9 Y p 1 rY 9 P Y
Hillsborough Additionally,this area is identified in the Orange County Safe Routes to School Plan and the Town of Hillsborough 82 property 27.42 Division
Connectivity Plan as an area in need of improvements for pedestrians,particularly for school age residents of the Fairview damage
neighborhood that walk to Orange High School and Stanford Middle School.The Town of Hillsborough Connectivity Plan also
calls for bike lanes in this area as well.
Eno Mountain Description:Realign the intersection of Eno Mountain Road(SR 1148)and Mayo Street(SR 1192)with Orange Grove Road Eno 3800-4500 Total 38
SR 1006 and make safety improvements. 4 minor injury County Priority
Road/Mayo Street ( ) Y P Remain County
4 DCHC
at Orange Grove Mao 5300- 4 possible injury County priority priority
Rd. Need:The project would improve safety,reduce travel time,and improve traffic flow between residential and commercial Y5200 30 property 14.36 Division
areas in the Town of Hillsborough. property
e
Description:Modify the 1-85/1-40 Connector(SR 1239)interchange at U.S.70 to provide access from all directions. Total 54
Need:The project would enable traffic from northwestern Orange County to access 1-85 more easily without risking the many
1 fatal County Priority
U.S.70 Eastll-85l1- nts 5 minor injury Remain County
5 DCHC 40 Connector Poi of traffic conflict through Efland. Traffic has increased on Efland-Cedar Grove Road as an alternative to NC 86.Much 4100-4900 4 possible injury 18.43 Regional County priority priority
of that traffic currently"dog-legs'through Efland via Forrest Avenue to Mt.Willing Road to access 1-85/1-40.Traffic counts 44 property 13.03 Division
reveal that traffic has increased approximately 40%over the past 10 years on Mt.Willing Road just south of Forrest Avenue, damage
while traffic on U.S.70 east of Efland-Cedar Grove Road has increased only 2%.The project would dramatically improve
travel time for traffic from northwestern Orange County to 1-85/1-40 and would dramatically ease congestion during peak
periods in Efland.
Description:Modernize Old Greensboro Road(SR-1005)from Jones Ferry Road(SR-1942)to Alamance County with
NCDOT standard street cross-section section 2B(60'row,11'travel lanes,with 5'paved shoulder), add turn lanes and safety Total 339 County priority
improvements at Jones Ferry Road(SR-1942),Hatch Road(SR-1944),Neville Road(SR-1945),Carl Durham Road(SR- west 2800-3000 5 fatal redefined as
DCHC Old Greensboro 1950),White Cross Road(SR-1951),Wildcat Creek Road(SR-1953),and Orange Chapel Clover Garden Road(SR-1956). 6 serious injury County Priority highway County priority
6 /TARP (SR-1005)Road 45 minor injury project as highway
O Improvement" Need:This project would provide a continuous paved bikeway segment from Carrboro through the southwestern portion of 51 possible injury 22.36 Division project
Orange County to connect with other bikeway segments that comprise the state's Mountain to Sea bicycle route.The project east 4600-4800 232 property Meets RPO
is not likely to score very high using either the State's highway or bike/pedestrian scoring factors because of its rural context damage SPOT process
and is only eligible for funding at the division tier.
8
_ Current County priority as highway project
Attachment 2:Draft Durham-Chapel Hill-Carrboro(DCHC)MPO Project List New Project
Recommendations
MPO/ AADT 2010- Crashes 2006-
Map RPO Project Description/Need 2016 2016 2018 Results
Staff OUTBoard
Description:Modernize Dairyland Road(SR-1177)from Orange Grove Road(SR-1006)to Old NC-86(SR-1009)with
NCDOT standard street cross-section section 2B(60'row,11'travel lanes,with 5'paved shoulder), add turn lanes and safety Total 121 County Priority
improvements at Orange Grove Road(SR-1006),Dodson Crossroads(SR-1102),Rocky Ridge Road(SR-1113), Bethel west 940-970 2 fatal
DCHC Dairyland Road Hickory Grove Church Road(SR-1104)and convert intersection at Old NC-86(SR-1009)to Roundabout. 2 serious injury Not submit to County priority County priority
NCDOT for P5.0 redefined as
7 /TARP (rovem 7) 15 minor injury as highway
Need:This project would provide one segment of a bikeway connection through western Orange County from Carrboro to the highway
O Improvement** 16 possible injury project
Buckhorn Road and Mebane area and improve the safety of the subject thoroughfare for both bicyclists and motorized No 20%local project
vehicular travel.The project is not likely to score very high using the State's bike/pedestrian scoring factors because of its south 2400- 86 property match or local
rural context and is only eligible for funding in the division tier. 3100 damage administration
Description:Modernize Dodson Crossroad(SR-1102)from Orange Grove Road(SR-1006)to NC-54 with NCDOT standard
street cross-section section 2B(60'row,11'travel lanes,with 5'paved shoulder), add turn lanes and safety improvements at County Priority
Orange Grove Road(SR-1106),Borland Road(SR-1126),Arthur Minnis Road(SR-1115),and Dairyland Road(SR-1177) north 830-1000 Total 62
2 serious injury Not submit to County priority
DCHC Dodson Crossroad County priority
8 /TARP SR-1102 fined as
( ) Need:This project would provide bicycle facilities to the Grady Brown Elementary School and Cedar Ridge High School from 8 minor injury NCDOT for P5.0 redefined as highway
O Improvement the area south of the schools and connect to a proposed bikeway facility on Orange Grove Road northward into Hillsborough. south 1800- 42 property No 20%local project 10 possible injury highway project
The project would also improve safety for motorized vehicular travel on this segment of Orange Grove Road.The project is 1818 damage match or local
not likely to score very high using the State's bike/pedestrian scoring factors because of its rural context and is only eligible administration
for funding in the division tier.
Description:Modernize Orange Grove Road(SR-1106)from 1-85 to Dodson Crossroad(SR-1007)with NCDOT standard
street cross-section section 2B(60'row,11'travel lanes,with 5'paved shoulder), add turn lanes and safety improvements at north 4700- Total 102 County Priority
Ode Turner Road(SR-1130),Dimmocks Mill Road(SR-1134),Crossroad Church Cemetery Road(SR-1131),Davis Drive
(SR-1129),Kimbro Road(SR-1128)and Dodson Crossroads(SR-1102) 4600 1 fatal Not submit to County priority
DCHC Orange Grove 1 serious injury County priority
NCDOT for P5.0 redefined as
9 /TARP Road Improvement—
7 minor injury as highway
Need:This project would provide one segment of a bikeway connection through western Orange County from Carrboro to the highway
O Improvement** 13 possible injury project
Buckhorn Road and Mebane area and improve the safety of the subject thoroughfare for both bicyclists and motorized No 20%local project
vehicular travel.The project is not likely to score very high using the State's bike/pedestrian scoring factors because of its south 2400- 80 property match or local
rural context and is only eligible for funding in the division tier. 3100 damage administration
Description:Widen NC-54 from Orange Grove Rd(SR 1006)to Butler Rd(SR 1951)/Dodsons Cross Rd(SR 1102)and from East 12000-
Butler Rd(SR 1951)/Dodsons Cross Rd(SR 1102)to Old Fayetteville Road(SR-1107)/Inside DCHC with additional lanes 15000
and multimodal facilities along the corridor and safety improvements at each intersection. New Project Table
Total 340
Need:NCDOT projections reveal that traffic on NC 54 from Orange Grove Road to Old Fayetteville Road will substantially 3 fatal Meets RPO Await DCHC
exceed the existing roadway capacity by 2035,warranting an increase in capacity through widening.NCDOT traffic figures
DCHC 8 serious injury 61.80 Region SPOT process MPO action on
NC-54 already indicate that traffic along the segment of NC 54 from Butler Road/Dodsons Cross Road to Neville Road is at capacity 10 /TARP y 9 9 p y 35 minor injury Corridor Study
Improvement** and will only continue to substantially exceed capacity in future years.It is likely that traffic along the segment of NC 54 from
O 61 possible injury 26.58 Division Fundable and
Neville Road to Old Fayetteville Road is also at or over capacity.Specific user input on the subject corridor reveals the lack of West 9300- 233 property through subsequent
usable gaps in traffic streams at intersecting streets during peak periods that otherwise might be created by signalization. 10000 damage Regional CTP and MTP
User input also reveals the presence of extensive travel lane delay on the NC 54 facility as a result of the lack of adequate Impact update
storage for left and right turns at some intersecting streets and entrances to businesses along the corridor.
Description:Intersection and safety improvements along Lebanon Road(SR-1306)from Mill Creek Road(SR-1345)to East 2600—3000 Total 100
Efland-Cedar Grove Road(SR-1004) 2 serious injury
11 DCHC Lebanon Road 12 minor injury N/A New Project New County
/BG 11 possible injury priority
Need:Road continues experiencing increasing traffic and crashes,intersection and safety improvements along the corridor 75 property
will help provide safe travel for all users. West 2100-2300 damage
9
_ Current County priority as highway project
Attachment 2:Draft Durham-Chapel Hill-Carrboro(DCHC)MPO Project List New Project
Recommendations
MPO/ AADT 2010- Crashes 2006-
Map RPO Project Description/Need 2016 2016 2018 Results
Staff OUTBoard
Description:Modernize Old NC-86(SR-1009)from 1-40 to Eubanks Road(SR-1727)with NCDOT standard street cross-
section 2E(60'row,1 T travel lane,5'bike lane,c&g,and sidewalk),add turn lanes at Davis Road(SR-1129),and New Hope north 5500- Total 208
Church Road(SR-1723) 6300 3 fatal
DCHC Old NC-86(SR- 3 serious injury New Project
Need:This project would provide multimodal and safety improvements along a north-south corridor for commuters travel New County
12 /TARP ovem between Hillsborough and Carrboro.This corridor is growing more unsafe with increasing accidents,three of them being fatal. 15 minor injury N/A Meets RPOprocess
priority
O Improvement** 24 possible injury
Intersection improvements such as crosswalks and turn lanes will reduce crash frequencies and better manage traffic at key south 4500- 163 property SPOT process
locations along the corridor.Traffic along this corridor will continue increasing making the area more hazardous and will 5000 damage
eventually exceed the capacity of the existing road.
Description:Improve current Dimmocks Mill Rd(#735154S)grade separation and close Bellvue St(#735152D)rail crossing County Priority
Dimmocks Mill Need:The NCRR trestle on Dimmock's Mill currently does not allow trucks or pedestrians to safely cross underneath the Remain County
13 DCHC Trestle N/A 52.84 Statewide County priority
railroad.By restructuring this trestle and reconfiguring the intersection,this area will provide a safe crossing between priority
Improvements 8 Regional
Hillsborough and destinations south for all users.Additionally,improving this trestle will allow large trucks to avoid using
22.
Churton Street and will helpereate a back entrance to West Hillsborough.
2.86 Division
Description:Improve the current trestle at Exchange Park Lane to accommodate Pedestrian traffic to support a pedestrian
link from the proposed train station to downtown Hillsborough. County Priority
Exchange Park Need:Currently,the NCRR trestle on Exchange Park Lane only accommodates one vehicle at a time and provides no safe N/A 2 1 Remain County
14 DCHC Lane Rail Trestle accommodations for pedestrians.Once the Hillsborough Train Station is constructed,Exchange Park Lane will be the only 6.5 Statewide County priority priority
Improvements safe pedestrian route from the Train Station to Downtown Hillsborough.With substantial pedestrian demand forecast between Regional
the Train Station and Downtown Hillsborough,creating a safe pedestrian environment is a crucial need in this area. 12.4.46 Division
Description:Construct one additional lane between Patriot's Pointe Drive and New Grady Brown School Road(SR 1221)to
include both pedestrian and bicycle improvements along the roadway.The 1-40 bridge would be widened to accommodate Total 43 Not submit to
Orange Grove Rd. County priority
Widening with both pedestrian and bicycle amenities and one additional travel lane. 1 serious injury NCDOT for P5.0 redefined as County priority
15 DCHC Bicycle and 4700-4600 5 minor injury highway as highway
Pedestrian Need:There are significant safety issues along this stretch of roadway for motorists,but also for pedestrians and bicyclists. 6 possible injury No 20%local project project
Improvements** Increased traffic along Orange Grove Road has led to a significant safety risks for all users of the roadway. 31 property match or local
damage administration
Description:Construct a roundabout at the intersection of Old NC 86,Dairyland Road(SR 1004/1113/1177),and Homestead 1999 Division County Priority Remain County
.
Road(SR 1777)in Calvander outside of Carrboro. priority
Calvander Part of Old NC-
priority
DCHC DCHC Roundabout Need:Included at the request of the Orange Unified Transportation Board,this project would enhance safety at this N/A 86 modernization Coordinating SOT ID th Coordinating
intersection and improve traffic flow,while also facilitating a safe left turns for bicyclists. H170 99) municipality with
municipality
Description:Provide one(1)bus to serve a new route for Orange Public Transportation providing service to major trip
Orange County generators in Hillsborough
Public Need:This project would provide a fixed route for underserved areas of Orange County(not being covered by the Removed from
17 DCHC Transportation Hillsborough Circulator)to major points of interest such as medical,employment,retail,municipal and social services.The N/A SPOT in favor of OCPT OCPT
Circulator 11 project is currently in the unfunded category of the Orange County Bus and Rail Investment plan,yet remains a priority for our DO LRT
Vehicles County Board of commissioners.It is only eligible for funding at the Division Needs tier.
Description:Construct bicycle facilities on Old NC 86 from Farm House Road in Carrboro to Homestead Road(SR 1777). Not submit to County priority Remain County
NCDOT for P5.0 priority
18 DCHC Old NC 86 Bike Need:Cyclists routinely use Old NC 86 as a key conduit for major rides in rural Orange County.Recent bicycle counts N/A o Coordinating
Lanes conducted by NCDOT and NC State's ITRE indicate that 160 cyclists use the stretch of Old NC 86 between Hillsborough No 20/o local with Coordinating
Road(SR 1009)and Homestead Road(SR 1777)each day with more on the weekends.This section is also particularly match or local municipality with
narrow and includes a narrow gravel shoulder,which can present a hazard for cyclists.Widening this section to include administration municipality
bicycle lanes will provide a safe space for bicyclists in this heavily trafficked bicycle corridor.
10
_ Current County priority as highway project
Attachment 2:Draft Durham-Chapel Hill-Carrboro(DCHC)MPO Project List New Project
Recommendations
MPO/ AADT 2010- Crashes 2006-
Map RPO Project Description/Need 2016 2016 2018 Results
staff OUTBoard
Description:Improve Homestead Road(SR 1777)from Old NC 86(SR 1009)to NC 86 to include bicycle lanes and sidewalks
in sections of the corridor where they do not exist. Not submit to Remain County
County priority
Homestead Road NCDOT for P5.0 priority
Need:There are three(3)schools in the vicinity of Homestead Road:Chapel Hill High School,Smith Middle School,and
19 DCHC Bike Lanes and Seawell ElementarySchool.Man students live within walkingand biking distance of Chapel Hill High School and must walk N/A Coordinating
Sidewalks** y g p g No match
o local with Coordinating
or cycle along or across Homestead Road on a daily basis.Provision of bikeway and pedestrian facilities is necessary to give match or local with
students a comfortable and safe lace to travel separate from that of motorized vehicular traffic.Homestead Road is also a municipality
P P administration municipality
commuting route for adult utilitarian bicyclists connecting residential areas to other arteries serving employment centers
Not submit to County priority Remain County
Description:Construct bicycle lanes on Eubanks Road(SR 1727)from Old NC 86(SR 1009)to NC 86. NCDOT for P5.0 priority
20 DCHC Eubanks Road Bike N/A Coordinating
Lanes Need:This project would provide a separate facility for both recreational and commuter bicyclists to reduce/eliminate the No 20%local with Coordinating
bike/automobile modal conflict along this corridor.The project would also provide access to the Morris Grove Elementary match or local municipality with
School on Eubanks Road. administration municipality
Description:Construct bike lanes and sidewalks from US 15-501 to Bennett Road and bike lanes from Bennett Road to the
Chatham County line. Not submit to
Mt.Carmel Church NCDOT for P5.0
21 DCHC Road Need:This project would provide a continuous paved bikeway facility from Chapel Hill through southeastern Orange County N/A County priority Remain County
Bike/Pedestrian into Chatham County.The project connects to another project submitted by Chatham County to construct bike lanes along No 20%local priority
Improvements** Mt.Carmel Church Road from the Orange County line to Old Farrington Point Road.This segment is listed as a Statewide match or local
bicycle facility in the DCHC MPO MTP and is a continuation of the state's Mountain to Sea bicycle route through Orange administration.
County.
Description:Construct a sidewalk along the west side of Orange High School Road from Harold Latta Road to U.S.70,
construct a sidewalk along the south side of Harold Latta Road from Cloverfield Drive to Orange Grove Road,install high
Orange High visibility crosswalks and in-road signage at school entrances and exits on Orange Grove Road,and construct a sidewalk Not submit to
School along entrance roads to CW Stanford Middle School. NCDOT for P5.0
22 DCHC Road/Harold Latta N/A County priority Remain County
Need:Orange High School Road serves two schools north of U.S.70,Orange High School and CW Stanford Middle School. No 20%local priority
Road Sidewalk There are currently no dedicated pedestrian facilities along Orange High School Road to accommodate students accessing match or local
Improvements** the schools from residential areas to the north and east.The project would provide safe and comfortable pedestrian administration.
connections from these areas to the schools.The Orange County Safe Routes to School Action Plan identifies these sidewalk
and crosswalk improvements as central elements in the plan for both Orange High School and CW Stanford Middle School.
Description:Construct a pedestrian bridge over 140 alongside Orange Grove Road(SR 1006),construct a sidewalk along the
north side of Orange Grove Road(SR 1006)from the pedestrian bridge to Timbers Drive,construct sidewalks along both
sides of New Grady Brown School Road with a midblock crossing,and construct a sidewalk along one side of Oakdale Drive
from Cheshire Drive to Orange Grove Road. Not submit to Seek other
NCDOT for P5.0
Orange Grove Prohibited by funding source
Need:I-40 separates two schools,Grady Brown Elementary and Cedar Ridge High School,from residential areas north of I-
23 DCHC Road/1-40 40 The schools are within walking distance of residential areas,but bicyclists and pedestrians must share the roadway with N/A No 20%local. STI (e.g.DEAPR,
Pedestrian Bridge* §136-189
motor vehicles crossing the existing narrow two(2)-lane bridge that carries Orange Grove Road over 1-40.The bridge is too match or local .11 Federal SDBG-
narrow to accommodate a pedestrian walkway.Lack of an adequate pedestrian crossing presents an unsafe environment for administration DA)
students to walk to the schools.The Orange County Safe Routes to School Action Plan identifies the pedestrian bridge and
supporting sidewalk improvements as central elements in the plan for Grady Brown Elementary School.
Description:Construct a pedestrian bridge across 1-85 to connect southern Hillsborough neighborhoods with Collins Ridge,
Daniel Boone Village,and Downtown Hillsborough. Not carried Seek other
forward by MPO Prohibited by funding source
24 DCHC 1-85 Pedestrian Need:Neighborhoods to the south of 1-85,such as those along Cates Creek Parkway and Beckett's Ridge Drive,lack N/A STI (e.g.DEAPR,
Bridge* pedestrian and bicycle connections to commercial amenities and neighborhoods north of the highway.Constructing a bridge No 20%local
across 1-85 would create a safe access point for pedestrians and bicyclists and link areas of Hillsborough south of I-85 to match or local §136-189.11 Federal SDBG-
Downtown Hillsborough and commercial amenities along Churton Street.Receiving sidewalks will be present on both sides of administration DA)
the proposed pedestrian bridge.
11
_ Current County priority as highway project
Attachment 2:Draft Durham-Chapel Hill-Carrboro(DCHC)MPO Project List New Project
Recommendations
MPO/ AADT 2010- Crashes 2006-
Map RPO Project Description/Need 2016 2016 2018 Results
staff OUTBoard
Description:Widen Dairyland Road(SR 1004/1113/1177)from Union Grove Church Road(SR 1111)to Orange Grove Road Not submit to
(SR 1006)to include four(4)-foot paved shoulders. County priority
NCDOT for P5.0 redefined as County priority
Paved nd Road p j p g y g g y 0
25 DCHC Need:This project would provide one segment of a bikeway connection through western Orange Count from Carrboro to the N/A highwayas highway
Paved Shoulders Buckhorn Road and Mebane area and improve the safety of the subject thoroughfare for both bicyclists and motorized No 20 o local project project
vehicular travel.The project is not likely to score very high using the State's congestion and benefit-cost scoring factors and is match st local (See#7)
onlyeligible for fundingat the division tier. administration
Description:Construct a multi-use path connecting English Hill Lane to Buttonwood Drive.
Not submit to Seek other
Trail Connection Need:Project is recommended as an improvement in the Orange County Safe Routes to School Action Plan.An existing NCDOT for P5.0 Prohibited by funding source
26 DCHC from English Hill barrier to pedestrians toward Orange High School and CW Stanford Middle School exists between residential areas along N/A STI (e.g.DEAPR,
Lane to and east of Buttonwood Drive and residential areas along and west of English Hill Lane.The improvement would provide a No 20%local DBG-
S 11 Federal
Buttonwood Dr.* direct pedestrian connection from highly populated residential areas further west from the schools and make walking match or local §136-189. al
distances safer and more manageable. administration.
Description:Construct a multi-use path connecting the southwest corner of Patriots Pointe to Timbers Drive to shorten
walking distances for pedestrians.
Not submit to Seek other
Trail Connection NCDOT for P5.0 Prohibited by funding source
from Patriot's Need:Project is recommended as an improvement in the Orange County Safe Routes to School Action Plan.An existing
27 DCHC Pointe to Timbers barrier to pedestrians exists between Patriots Point Apartments and Timbers Drive such that long walking distances are N/A No 20%local STI (e.g.DEAPR,
§136-189
Dr.* required for pedestrians from Patriots Pointe to access the New Grady Brown Elementary School and Cedar Ridge High match or local .11 Federal SDBG-
School along Orange Grove Road with no designated pedestrian facilities.The improvement would provide a direct administration. DA)
pedestrian connection from Patriots Point to Timbers Drive and Orange Grove Road in the direction of the schools that make
walking distances more manageable
Notes:
*STI Law§136-189.11.Transportation Investment Strategy Formula section(d).(3).c.—The Department shall not provide financial support for independent bicycle and pedestrian improvement projects.
**Sidewalk subject to NCDOT sidewalk cost share policy 40%Orange County for 1"5'of sidewalk,100%Orange County for any additional sidewalk.
Attachment 2: Draft Durham-Chapel Hill-Carrboro(DCHC)MPO Project List 12
DCHC SPOT 6 - Projects
i
Caswell Co. ! Person Co.
RD
p
❑ tiy� a --'-to- --__--ram.:_.;:�..
, % &.COH RD
J 4 R d
� w Ipl i] 4
•J �,� � ��41:J7N� } iAVvS�iCfRf Ian ❑ F S
NAWKIN5 A❑ 15� CKE
,{LVm
W [
r LITi[[RIV 3 +
.[. ,f.
PEAR d
PO 1
n � I
FIp 'a
I y9d y R,O QO
4� yGy � •W� KEHIGYJ A❑ �f( �e•��y T'I'1-R8
r�f•I� # ""MR � � PSR❑ �k d�
i
HALL$U%L Rd r FI? A
4
.1 R
j~ }I,l y p LCWNON•RD F - I P �s G
J � W �� �j rT•� z py �
--~Mebane:: 70 9
,�; liillsbarough� $ �v
• �tsr Its:xu
L-f I yr coif
-� aI x� ~I3 4r e
L 70A Ao
}�JIJ ,�• 70 RV
� �� V ` 4 ��❑ rs �C' vWrq°[c c DurhAnl c u.
�c uI
ftLA1d0
4 eRo S IReI At
M
Q � �+fnlllR
pA
{[LF I6LQAp O
-
•.
❑ TCERR�
`• o ChapeE•HiillwAURD
1,6
i` ti 6F 9
Rd'Na9 a I/ t oa r'rbo ro.1�4%� s -�vs
J ��e 9`0 op w �.st 5171 i
sn:Ll[+rRn
c� .4
•.-, �'T o- a� a�ri•pn��:FrG,y
iLL�GRFER PO-T'" U l
— Project Locations 5r
—� F p✓ a �
Municipal Boundaries AO RG" !
B G MPO Boundary - - - - - -- - L
ORANGE /. Mlles
DCHC MPO Boundary 0 2
Chatham C n. Ckange Counly Planni rlo and Inspection
7ARPO Boundary EIC IMV2019
13
_ Current County priority as highway project
Attachment 3:Draft Burlington-Graham Metropolitan Planning Organization(BGMPO)Project List New Project
MPO/ Recommendation
# RPO Project Description/Need AADT 2010-2016 Crashes 2006-2016 2018 Results
(SPOT 5.0) Staff OUTBoard
Description:Widen US-70 and improve intersections from Buckhorn Road(SR-1114)to Durham Total 1148
County with NCDOT standard street cross-section 4G(110'row,17.5'median,11'travel lanes,5' West 6400-6200 10 fatal
bike lane,c&g,and sidewalk),add turn lanes and safety improvements at NC-86,St.Mary's Road
DCHC/BG improvements— (SR-1002),Efland Cedar Grove Road(SR-1004),Frazier Road(SR-1310),Richmond Road(SR- 12 serious injury N/A New Project Not
i mpro 1312),Brookhollow Road(SR-1324),Faucette Mill Road(SR-1328),Miller Road(SR-1555), 100 minor injury Recommended
Lawrence Road(SR-1561),Palmers Grove Church Road(SR-1562),Pleasant Green Road(SR- East 12000-14000 220 possible injury
1567),Orange High School Road SR-1588,and N Scotswood Boulevard SR-2300. 706 property damage
County Priority
2 BG Mattress Factory Description:Construct a new interchange at the existing grade-separated crossing of Mattress N/A County priority Remain County
Road Interchange Factory Road and 1-85/1-40 Not submit to priority
NCDOT for P5.0
Description:Extend Mattress Factory Road northward across East Washington Street and the North 2200-2000
Total 18 County Priority
Mattress Factory 1 serious injury
3 BG Road Extension to NCRR/Norfolk Southern railroad right-of-way to intersect U.S.70 and close the existing railroad 3 minor injury Not submit to County priority Remain County
U.S.70 crossover road connecting East Washington Street and U.S.70 approximately 240 feet to the east 1 possible injury NCDOT for P5.0 priority
of the intersection of Mattress Factory Road and East Washington Street. South 1300-1800 13 property damage
Total 124 County Priority
Buckhorn Road
Description:Widen Buckhorn Road from U.S.70 to West Ten Road(SR1144)to multiple lanes with North 6800-6600 2 serious injury Remain County
4 BG ( 1114) bicycle and pedestrian facilities with grade separation over railroad to US-70. 14 minor injury Not submit to County priority priority
Widening— 18 possible injury NCDOT for P5.0
South 2500-3000 90 property damage
Total 100
Lebanon Road East 2600—3000 2 serious injury
Description:Intersection and safety improvements along Lebanon Road(SR-1306)from Mill Creek New County
5 DCHC/BG (SR-1306) Road(SR-1345)to Efland-Cedar Grove Road(SR-1004) 12 minor injury N/A New Project priority
Improvements** 11 possible injury
West 2100-2300 75 property damage
Notes:
*STI Law§136-189.11.Transportation Investment Strategy Formula section(d).(3).c.—The Department shall not provide financial support for independent bicycle and pedestrian improvement projects.
**Sidewalk subject to NCDOT sidewalk cost share policy 40%Orange County for 1"5'of sidewalk,100%Orange County for any additional sidewalk.
Attachment 3:Draft Burlington-Graham Metropolitan Planning Organization(BGMPO)Project List 14
BGMPG SPOT 5 - Projects
► i
I
11
3 w �OC�. Ogg
IRA RD
I �
1
l�QAN�Rq 1
I
!
J
I
1 '-),—,Mebane I _ -
ti
�'
! I
I `1
7
I_
i I--,
t O
� � yyES7 TEN Rp -
} SI M1K Rp �
s � x
S � p
� n
4�
CypN
Nag
Project Locations
Municipal BoundarycR°
B-G MPO Boundary 1 in-3.00D fee
1
e ORANGE I Fe n
DCHC MPO Boundary !TT ^ D 2.000
TARPO Boundary Orange Counly PIrM2019d lnspaldivn OC
RES-2019-007 15
Attachment 4: Draft Resolution Endorsing Transportation Projects for State Funding
ORANGE COUNTY BOARD OF COUNTY COMMISSIONERS
A RESOLUTION ENDORSING ORANGE COUNTY'S LIST OF TRANSPORTATION PROJECTS
FOR THE BURLINGTON-GRAHAM AND DURHAM-CHAPEL HILL-CARRBORO METROPOLITAN
PLANNING ORGANIZATIONS (BGMPO AND DCHC MPO) AND THE TRIANGLE AREA RURAL
PLANNING ORGANIZATION FOR CONSIDERATION OF INCLUSION IN THE 2020 — 2029
STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM
WHEREAS, the North Carolina Board of Transportation (BOT), every two years, prepares a Statewide
Transportation Improvement Program (STIP) that identifies transportation projects to be implemented
over the next ten years with State and Federal funding; and
WHEREAS, the North Carolina BOT solicits input for identifying transportation projects of local and
regional importance to be included in the FY 2022-2031 STIP; and
WHEREAS, the BGMPO and TARPO Transportation Advisory Committees and the DCHC MPO
Board are charged with the development of a Metropolitan Transportation Improvement Program
(MTIP) or regional priority list; and
WHEREAS, Orange County is a member jurisdiction of the BGMPO, TARPO and DCHC MPO; and
WHEREAS, Orange County gives priority to identified safety needs on existing roads and bridges, to
transportation projects that encourage alternatives to automobile travel, to projects that minimize
adverse impacts on the natural environment and cultural sites, and to those projects that foster
economic development in the County's designated Economic Development Districts; and
WHEREAS, Orange County strongly encourages the North Carolina Department of Transportation
(NCDOT) to design all highway projects, where appropriate, to accommodate bicycle and pedestrian
traffic to provide alternative means of transportation that may result in reduced automobile traffic and
related air and water impacts; and
WHEREAS, Orange County encourages the NCDOT to design all new or replacement bridges with
sufficient clearance to allow wildlife to cross safely under them, and to allow pedestrian passage along
any existing or planned trail-system connectors; and
WHEREAS, Orange County has outlined its transportation needs within the BGMPO, TARPO and
DCHC MPO planning areas in attachments to this resolution;
NOW, THEREFORE, BE IT RESOLVED by the Orange County Board of Commissioners that the
Board endorses the following list of transportation projects to be submitted for scoring by the State
and to ultimately be considered for inclusion in the FY 2022-2031 STIP.
Burlington-Graham MPO:
1) Mattress Factory Road Interchange: Construct a new interchange at the existing grade-
separated crossing of Mattress Factory Road and 1-85/1-40. ,Uurrent County Priority)
2) Mattress Factory Road Extension to U.S. 70: Extend Mattress Factory Road northward across
East Washington Street and the NCRR/Norfolk Southern railroad right-of-way to intersect U.S.
70 and close the existing railroad crossover road connecting East Washington Street and U.S.
70 approximately 240 feet to the east of the intersection of Mattress Factory Road and East
Washington Street. kuurrent county Priority)
RES-2019-007 16
Attachment 4: Draft Resolution Endorsing Transportation Projects for State Funding
3) Buckhorn Road (SR 1114) Widening: Widen Buckhorn Road from U.S. 70 to West Ten Road
(SR1144) to multiple lanes with bicycle and pedestrian facilities. (Current County Priority)
4) Lebanon Road Improvements: Intersection and safety improvements along Lebanon Road
(SR-1306) from Mill Creek Road (SR-1345) to Efland-Cedar Grove Road (SR-1004). (New
County Priority)
Triangle Area RPO:
1) Old Greensboro Road Paved Shoulders: Modernize Old Greensboro Road (SR-1005) from
Jones Ferry Road (SR-1942) to Alamance County with NCDOT standard street cross-section
2B (60' row, 1 l' travel lanes, with 5' paved shoulder), add turn lanes and safety improvements
at Jones Ferry Road (SR-1942), Hatch Road (SR-1944), Neville Road (SR-1945), Carl
Durham Road (SR-1950), White Cross Road (SR-1951), Wildcat Creek Road (SR-1953), and
Orange Chapel Clover Garden Road (SR-1956). (Current County Priority as highway project)
2) Efland-Cedar Grove Road Improvements: Widen Efland-Cedar Grove Road (SR 1004) from
Highland Farm Road (SR 1332) to Carr Store Road (SR 1352) with NCDOT standard street
cross-section 2B (60' row, 11' travel lanes, with 5' paved shoulder), add turn lanes and safety
improvements at Carr Street (SR-1357) and highland Farm Road (SR-1332). (Current County
Priority as highway project)
3) Orange Grove Road Improvements: Modernize Orange Grove Road (SR-1106) from 1-85 to
Dodson Crossroad (SR-1007) with NCDOT standard street cross-section 2B (60' row, 11'
travel lanes, with 5' paved shoulder), add turn lanes and safety improvements at Ode Turner
Road (SR-1130), Dimmocks Mill Road (SR-1134), Crossroad Church Cemetery Road (SR-
1131), Davis Drive (SR-1129), Kimbro Road (SR-1128) and Dodson Crossroads (SR-1102)
(Current County Priority as highway project)
4) Dairyland Road Improvements: Modernize Dairyland Road (SR-1177) from Orange Grove
Road (SR-1006) to Old NC-86 (SR-1009) with NCDOT standard street cross-section 2B (60'
row, 11' travel lanes, with 5' paved shoulder), add turn lanes and safety improvements at
Orange Grove Road (SR-1006), Dodson Crossroads (SR-1102), Rocky Ridge Road (SR-
1113), Bethel Hickory Grove Church Road (SR-1104) and convert intersection at Old NC-86
(SR-1009) to Roundabout. (Current County Priority as highway project)
5) Dodsons Crossroads Improvements: Modernize Dodson Crossroad (SR-1102) from Orange
Grove Road (SR-1006) to NC-54 with NCDOT standard street cross-section 213 (60' row, 11,
travel lanes, with 5' paved shoulder), add turn lanes and safety improvements at Orange
Grove Road (SR-1106), Borland Road (SR-1126), Arthur Minnis Road (SR-1115), and
Dairyland Road (SR-1177). (Current County Priority as highway projects)
6) Mebane Oaks Road Improvements: Modernize Mebane Oaks Road (SR 1007) from NC 54 to
1-85 with NCDOT standard street cross-section 2B (60' row, 11' travel lanes, with 5' paved
shoulder), add turn lanes and safety improvements at Old Hillsborough Road Road (SR-
2126), Hebron Church Road (SR-1139), Yarborough Road (SR-1138), Oak Grove Church
Road (SR-1117), Jones Road (SR-1123), S Jim Minor Road (SR-2135), Nicks Road (SR-
1119), Bradshaw Quarry Road (SR-1100), and NC-54. (New County Priority)
7) Old NC-86 Improvements: Modernize Old NC-86 (SR-1009) from 1-40 to Eubanks Road (SR-
1727) with NCDOT standard street cross-section 2B (60' row, 11' travel lanes, with 5' paved
shoulder), add turn lanes at Davis Road (SR-1129), and New Hope Church Road (SR-1723).
(New County Priority)
RES-2019-007 17
Attachment 4: Draft Resolution Endorsing Transportation Projects for State Funding
Durham-Chapel Hill-Carrboro MPO:
1) NC 86 Improvements North of Hillsborough: Widen NC 86 from U.S. 70 Bypass to north of NC
57 to four (4) lanes with intersection improvements at U.S. 70 Bypass and NC 57. (Current
County Priority)
2) Eno Mountain Road/Mayo Street at Orange Grove Road: Realign the intersection of Eno
Mountain Road (SR 1148) and Mayo Street (SR 1192) with Orange Grove Road (SR 1006)
and make safety improvements. (County Priority)
3) U.S. 70 East/1-85/1-40 Connector: Modify the 1-85/1-40 Connector (SR 1239) interchange at
U.S. 70 to provide access from all directions. (County Priority)
4) Old Greensboro Road Paved Shoulders: Modernize Old Greensboro Road (SR-1005) from
Jones Ferry Road (SR-1942) to Alamance County with NCDOT standard street cross-section
2B (60' row, 11' travel lanes, with 5' paved shoulder), add turn lanes and safety improvements
at Jones Ferry Road (SR-1942), Hatch Road (SR-1944), Neville Road (SR-1945), Carl
Durham Road (SR-1950), White Cross Road (SR-1951), Wildcat Creek Road (SR-1953), and
Orange Chapel Clover Garden Road (SR-1956). (Current County Priority as highway project)
5) Dairyland Road Improvements: Modernize Dairyland Road (SR-1177) from Orange Grove
Road (SR-1006) to Old NC-86 (SR-1009) with NCDOT standard street cross-section 2B (60'
row, 11' travel lanes, with 5' paved shoulder), add turn lanes and safety improvements at
Orange Grove Road (SR-1006), Dodson Crossroads (SR-1102), Rocky Ridge Road (SR-
1113), Bethel Hickory Grove Church Road (SR-1104) and convert intersection at Old NC-86
(SR-1009) to Roundabout. (Current County Priority as highway projects)
6) Dodson Crossroad Improvements: Modernize Dodson Crossroad (SR-1102) from Orange
Grove Road (SR-1006) to NC-54 with NCDOT standard street cross-section 213 (60' row, 11,
travel lanes, with 5' paved shoulder), add turn lanes and safety improvements at Orange
Grove Road (SR-1106), Borland Road (SR-1126), Arthur Minnis Road (SR-1115), and
Dairyland Road (SR-1177). (Current County Priority as highway projects)
7) Orange Grove Road Improvements: Modernize Orange Grove Road (SR-1106) from 1-85 to
Dodson Crossroad (SR-1007) with NCDOT standard street cross-section 2B (60' row, 11'
travel lanes, with 5' paved shoulder), add turn lanes and safety improvements at Ode Turner
Road (SR-1130), Dimmocks Mill Road (SR-1134), Crossroad Church Cemetery Road (SR-
1131), Davis Drive (SR-1129), Kimbro Road (SR-1128) and Dodson Crossroads (SR-1102).
(Current County Priority as highway projects)
8) Lebanon Road Improvements: Intersection and safety improvements along Lebanon Road
(SR-1306) from Mill Creek Road (SR-1345) to Efland-Cedar Grove Road (SR-1004). (New
County Priority)
9) Old NC-86 Improvements: Modernize Old NC-86 (SR-1009) from 1-40 to Eubanks Road (SR-
1727) with NCDOT standard street cross-section 213 (60' row, 11' travel lanes, with 5' paved
shoulder), add turn lanes at Davis Road (SR-1129), and New Hope Church Road (SR-1723).
(New County Priority)
10)Dimmocks Mill Trestle Improvements: Improve current Dimmocks Mill Rd (#735154S) grade
separation and close Bellvue St (#735152D) rail crossing. (Current County Priority)
RES-2019-007 18
Attachment 4: Draft Resolution Endorsing Transportation Projects for State Funding
11)Exchange Park Lane Rail Trestle Improvements: Improve the current trestle at Exchange Park
Lane to accommodate Pedestrian traffic to support a pedestrian link from the proposed train
station to downtown Hillsborough. (Current County Priority)
12)Orange Grove Rd. Widening with Bicycle and Pedestrian Improvements: Construct one
additional lane between Patriot's Pointe Drive and New Grady Brown School Road (SR 1221)
to include both pedestrian and bicycle improvements along the roadway. The 1-40 bridge
would be widened to accommodate both pedestrian and bicycle amenities and one additional
travel lane. (Current County Priority as highway projects)
13)Calvander Roundabout: Construct a roundabout at the intersection of Old NC 86, Dairyland
Road (SR 1004/1113/1177), and Homestead Road (SR 1777) in Calvander outside of
Carrboro. (County Priority)
14)Old NC-86 Bike Lanes: Construct bicycle facilities on Old NC 86 from Farm House Road in
Carrboro to Homestead Road (SR 1777). (County Priority)
15)Homestead Road Bike Lanes and Sidewalks: Improve Homestead Road (SR 1777) from Old
NC 86 (SR 1009) to NC 86 to include bicycle lanes and sidewalks in sections of the corridor
where they do not exist. (County Priority)
16)Eubanks Road Bike Lanes: Construct bicycle lanes on Eubanks Road (SR 1727) from Old NC
86 (SR 1009) to NC 86. (County Priority)
17)Mt. Carmel Church Road Bike/Pedestrian Improvements: Construct bike lanes and sidewalks
from US 15-501 to Bennett Road and bike lanes from Bennett Road to the Chatham County
line. (County Priority)
18)Orange High School Road/Harold Latta Road Sidewalk Improvements: Construct a sidewalk
along the west side of Orange High School Road from Harold Latta Road to U.S. 70, construct
a sidewalk along the south side of Harold Latta Road from Cloverfield Drive to Orange Grove
Road, install high visibility crosswalks and in-road signage at school entrances and exits on
Orange Grove Road, and construct a sidewalk along entrance roads to CW Stanford Middle
School. (County Priority)
Upon motion of Commissioner seconded by Commissioner
the foregoing resolution was adopted this the 5t" day of February, 2019.
1, Donna Baker, Clerk to the Board of Commissioners for the County of Orange, North Carolina, DO
HEREBY CERTIFY that the foregoing is a true copy of so much of the proceedings of said Board at a
meeting held on February 5, 2019, as relates in any way to the adoption of the foregoing and that said
proceedings are recorded in the minutes of said Board.
WITNESS my hand and the seal of said County, this day of 2019.
Clerk to the Board of Commissioners