HomeMy WebLinkAbout2018-535 Planning - Moffat Pipe change order 4CHANGE ORDER NO.: 4 Page 1 of 4 101: KIM" CHANGE ORDER NO.: 4 DATE: September 5, 2018 Project: Historic Rogers Road Sewer Expansion Project Contractor: Moffat Pipe, Inc. Engineer /Architect: URS Corporation — North Carolina CONTRACTOR is directed to make the following changes in the Contract Documents. Description: Moffat Pipe, Inc. is requesting the following revisions to the substantial completion and final completion dates of the contract to account for delays in the project considered to be no fault of their own and beyond their control. Moffat Pipe, Inc. is requesting an additional 18 calendar days. The requested number of additional contract days are as follows: 17 calendar days for weather delays experienced between March 235 2018 and August 20, 2018, and one (1) calendar day associated with the additional work for items requested by OWASA on the May 25, 2018 punch list walkthrough. The requested number of delay days does not account for potential future delays, or delays associated with other concerns not specifically mentioned herein. Moffat Pipe, Inc. is also requesting an additional $4,000.00 to compensate them for two items identified and requested by OWASA on the May 25, 2018 punch list walkthrough, and additional staking due to homeowners removing surveyors stakes on multiple occasions. A more detailed explanation of each of the requested revisions to the Contract Price is below. 1) The two items identified on the punch list walkthrough that are not covered under the original construction contract are the addition of rip rap along the second stream crossing and spring well located on the Glenbrooke HOA property, and four (4) sewer valve covers for the tracer wire along the PVC pipe in Outfall R. An additional day for this work has already been included in the itemized list of delays listed seen in Attachment A. 2) Moffat Pipe was required to call out their subcontractor to re -stake easements approximately three times in two different locations due to homeowners removing the stakes even though OWASA communicated the need for the stakes and requested that homeowners not disturb them. The following lines shall be added to Section 00 4144, Unit Price Contract Bid Form. Item Bid Description Units Estimated Unit Price Extended No. Quantity Total 37 Sewer Valve Boxes for EA 4 $125.00 $500.00 Tracer Wire 38 Rip -Rap for Outfall L LS 1 $29500.00 $2,500 Ditch Crossing 39 Re- staking of Ebi LS 1 $500.00 $500.00 Property CHANGE ORDER NO.: 4 Page 2 of 4 40 Re- staking of additional LS 1 $500.00 $500.00 areas due to homeowner removal Total $4,000.00 0 The following shall be added to Section 0122 00, Unit Prices, Article 1.06: "BB. Item 37 — Sewer Valve Boxes for Tracer Wire 1. Work Included: a. Under this Item, the Contractor shall furnish all material, labor, and equipment for the installation of a sewer valve box to contain the ends of the tracer wire located along the PVC pipe installed from manhole SSMH -R3 to SSMH -R4, and from SSMH -R4 to SSMH- R5. b. Payment for this item will include, but not be limited to: 1) Excavating for valve box, backfilling including material as required, and restoration of seeding as needed. 2. Basis of Payment: a. The Contractor will be paid for the number of valve boxes installed and accepted by the Owner. 3. Payment: a. The unit price per valve box will be full compensation for providing all labor, materials, and equipment as may be required for the execution of work of these Items, accepted and complete." Item 38 — Rip -Rap for Outfall L Ditch Crossing 1. Work Included: a. Under this Item, the Contractor shall furnish and install permanent rip rap where new pipeline crosses existing ditch. b. Payment for this Item will include: 1) Required clearing, cleanup, and seeding. 2. Basis of Payment: a. The Contractor will be paid on a lump sum basis, at the applicable Contract price as listed in the itemized proposal. 3. Payment: b. The lump sum price will be full compensation for providing all labor, materials, and equipment as may be required for the execution of work of this Item, accepted and complete." "DD. Re- staking Item 39 — Restaking of Ebi Property Item 40 — Restaking of Other Areas 1. Work Included: a. Under this Item, the Contractor shall have their subcontractor re -stake those areas in which the property owners removed the stakes on multiple occasions. b. Payment for this Item will include, but not be limited to: 1) All required material, labor, and equipment necessary to perform the work. CHANGE ORDER NO.: 4 Page 3 of 4 2. Basis of Payment: c. The Contractor will be paid on a lump sum basis, at the applicable Contract price as listed in the itemized proposal. 3. Payment: d. The lump sum price will be full compensation for providing all labor, materials, and equipment as may be required for the execution of work of this Item, accepted and complete." CHANGE IN CONTRACT SUM OR PRICE: CHANGE IN CONTRACT TIME OR TIMES: Original Contract Price Original Contract Times $4,782,436.00 Final Completion: July 15, 2018 Net change from previous Change Orders No. 1 to Net change from previous Change Orders No.I to No.3 : - $104,110.52 No. 3: 86 days Contract Sum or Price prior to this Change Order Contract Times prior to this Change Order $456785325.48 Final Completion: October 9, 2018 Net Increase of this Change Order Net Increase of this Change Order $400.00 Eighteen (18) calendar days Contract Sum or Price with all approved Change Contract Times with all approved Change Orders Orders $4021325.48 Final Completion: October 27, 2018 RECOMMENDED: By L4aLl 0-.W 1 aJ1 a Engineer Krista Paredes - Toledo, PE Date: Ci (� 1'7 • ii�1 • Benedict, AICP Date: A M Date: The adjustment in Contract Sum or Price and /or Contract Time or Times stated in this Change Order shall comprise the total price and /or time adjustment due or owed the CONTRACTOR for the work or changes defined in this Change Order. By executing the Change Order, the CONTRACTOR acknowledges and agrees that the stipulated price and /or time adjustments include the costs and delays for all work contained in the Change Order, including costs and delays associated with the interruption of schedules, extended overheads, delay, and cumulative impacts or ripple effect on all other non - affected work under this Contract. Signing of the Change Order constitutes full and mutual accord and satisfaction for the adjustment in Contract Sum or Price or Contract Time or Times as a result of increases or decreases in costs and time of performance caused directly and indirectly from the change, subject to the current scope of the entire work as set forth in the Contract Documents. Acceptance of the waiver constitutes an agreement CHANGE ORDER NO.: 4 Page 4 of 4 between OWNER and CONTRACTOR that the Change Order represents an equitable adjustment to the Contract, and that CONTRACTOR waives all rights to file a claim on this Change Order after it is properly executed. IN WITNESS WHEREOF, the undersigned have caused the execution hereof: ATTEST: CONTRACTO MOFFAT PIPH, INC By: ro, or Name: Jesse uClau F/'0 Title: OContractor Address: 4901 Unicon Drive W e Forest, NC 27587 Date: (Q (' I T"' OWNER: Orange County By: Name: Bonnie Hammed le Title: Ora e County Manager Date: r