HomeMy WebLinkAboutRES-2018-052 Resolution approving a policy for additional code enforcement inspections for residential projectsRES-2018-052
A RESOLUTION BY THE ORANGE COUNTY BOARD OF COMMISSIONERS
APPROVING A POLICY FOR ADDITIONAL CODE ENFORCEMENT INSPECTIONS
FOR RESIDENTIAL PROJECTS.
WHEREAS, North Carolina General Statute (NCGS) 153A-352 allows a county
to request approval of regular and routine inspections of residential buildings or
structures in addition to those specific inspections required by NC Building Code from
the North Carolina Building Code Council; and
WHEREAS, the North Carolina Building Code Council has requested that the
Orange County Board of Commissioners approve a resolution authorizing and
supporting the Orange County Inspection Division to perform the listed additional
inspections upon request by the Permit applicant, before acting upon the Inspections
Division's petition; and
WHEREAS, Orange County Inspections Division, in order to facilitate the safe
construction of residential buildings and structures, developed the inspection list
designed for greatest flexibility for the public while verifying construction at the most
efficient and effective phase; and
WHEREAS, Orange County building partners need the maximum flexibility to
manage their projects and have critical building portions verified when most efficient and
convenient to their project schedule; and
WHEREAS, to protect the safety and welfare of Orange County residents
through enforcement of the NC State Building Codes upon residential properties in
Orange County, the Inspections Division needs the availability of the presented
additional inspections to ensure critical portions of the building remain accessible and
verifiable to the Building Safety Officials-, and
WHEREAS, the Board of County Commissioners finds the request consistent
with the County's comprehensive plan goals, objectives and policies;
NOW, THEREFORE, BE IT RESOLVED that the Orange County Board of
Commissioners hereby agrees, via this formally adopted policy resolution, for the
Orange County Inspections Division to perform the listed inspections as identified in
Exhibit 1 of this resolution, beyond what is required by N.C. State Building Codes, when
approved by the North Carolina Building Code Council.
This the 4 day of September, 2018.
ATTEST: �,..��J-'`' - -��
Mark D'orosin, Qair
Orange County Board of Commissioners
Donna Baker, Clerk to the Board of County Commissioners
EXHIBIT 1 of Resolution
Example of Inspections Being Required by Orange County
Below is the comprehensive list of Inspections Staff is requesting that the Orange County Board of
County Commissioners support and accept as policy which will be conveyed to the NC Building Code
Council for a request of approval:
Deck footing Modular marriage wall
Concrete form Brick lintel [bolted]
Foundation projection
Pre -brick / stone veneer
Water proofing
Temporary electrical [saw service]
Masonry fireplace
Temporary electrical final
Building pre -slab
Temporary mechanical final
Garage Slab
Building floor framing
Plumbing in slab
Deck final
Mechanical in slab I Electrical pool bond
Electrical in slab I Electrical change of service
Electrical in trench I Electrical service relocation
Plumbing in trench Factory fireplace
Mechanical in trench I Restore electrical service
Gas pipe in trench Plumbing final
Plumbing rough -in Electrical final
Mechanical rough -in I Mechanical final
Electrical rough -in I Pool fina
Gas pressure test
Requested Inspections:
Deck footing: Decks are often built toward the end of a project or by a separate subcontractor.
Having a separate inspection allows the Builder to schedule whenever this footing is ready.
Concrete forme Formed concrete and pre -cast foundations require additional inspection
considerations to accommodate multiple construction sequences and verification of
reinforcement or connections that may be in addition to other areas of the building system that
have conventional foundation systerns. This allows basements to be verified prior to crawl
space foundations being ready.
Foundation projection: The placement of foundations and piers upon the footing is critical for a
stable foundation system. It is not uncommon for footing to be dug out of place. It also is typical
for masons to simply build upon the misplaced footing or enlarge the footing to accommodate
the pier or foundation. Inspectors typically use this inspection to verify foundation placement,
mortar joints and correct block orientation.
Water-proofing- This is only required for Basement houses but is a critical safety feature of dry
and stable project. The application of water-proof material is typically done with the final
foundation construction. Staff offers this separate inspection to grant flexibility to when this
application ieverified.
Masonry fireplace- Masonry fireplaces are not common but have specific criteria needed to
ensure the system functions and performs as intended. An entire chapter of the Residential
Code is devoted to these fireplaces. These systems are built by specialty contractors at various
stages ofthe house construction process. Having its own inspection ensures adequate attention
im provided thus ensuring this meets nninirnunn Code standards.
Building pre-slab: Building slabs can be complex systems, sometimes being the footing,
foundation and floor of a building or just a floor for basements, porches or on elevated
construction. A basement slab is inspected differently than a monolithic system where the
footing and slab are one. This inspection allows the needed flexibility to schedule what specific
type of inspection im needed for the project.
Garage Slab.- Garage slabs are typically poured after the building is constructed when the
majority of heavy construction is completed but when the surface can be used for staging
materials or fabricating elements.
Plumbing in slab.- The building "trades" are done by independent subcontractors who typically
manage their own schedules and inspection preparation. The required inspection list limits
these subcontractors to schedule their inspection when all trade contractors are ready. This
inspection is necessary prior to the actual building slab preparation where thickened slab
footings are formed, vapor barriers and reinforcement are installed.
Mechanical in slab: Similar to Plumbing in slab mechanical myatarno we would offer flexibility to
subcontractors to schedule when they are ready independent from other trades.
E|ecir|nm| in slab: Similar to Plumbing and W1eohenioo| in slab inspections.
Hectrica| in. trench: Electrical installations outside the building typically are below ground and
often done by several system subcontractors. This may include trenches for septic, well pump
systems, outdoor lighting or service/feeders to other buildings or structures. Offering the
flexibility ofseparate inspections would extend greater control and efficiency to each
subcontractor.
Plumbing in trench: Similar to Beothoa| in trench. This typically would be for septic or sewer
drains and water service piping installations.
Mechanical in trench: Similar to Beothoa| in trench. This commonly would be for [;E[) thermal
trenches.
Gas pipe in trench: Similar to Electrical in trench. This would be for gas piping to the house or an
outdoor appliance /equipment.
Plumbing rough -in: Staff recognizes that each trade subcontractor is independent from the other
trades. Offering a standalone inspection extends flexibility and efficiency to the subcontractor to
have the system verified when they are prepared. These further offers the ability to install partial
systems that may need special consideration prior to the completed installation; such as holding
off installing a tub or shower until bathroom nearly completed.
Nflechanical rough -in: Similar to Plumbing rough -in.
Electrical rough -in: Similar to Plumbing rough -in
Gas pressure test: This inspection recognizes that the installation may be done by separate
subcontractor from other Mechanical system and that tests of the piping system may need to be
delayed while the rest of the Mechanical system is ready for inspection.
Factory fireplace: Factory fireplaces are often installed by specialty installation technicians who
are independent from the mechanical contractor. This offers the ability to have these different
systems installed and inspected at different points of construction.
Modular marriage wall: This inspection is associated with multiunit modular houses. These
houses are built to NC residential Code in a factory and transported in sections to the job site.
This inspection recognizes this connection is not necessarily the only framing that will be done
for the completed project.
Brick lintel [bolted]: Installation of bolted brick lintels is per design documents and done when
convenient for masons to complete their cladding work.
Pre -brick / stone veneer: Weather proof cladding such as brick and adhered stone require
specific support and connection details is verified to ensure compliant installations. Staff is
seeking to offer flexibility and efficiency to the process by allowing this installation when
construction process best suits the scaffolding and equipment necessary for application.
Temporary electrical [saw service]: Construction sites run most efficiently when utility power is
provided for workers to operate their tools and equipment. Offering this inspection recognizes
that anyone may provide temporary electrical construction service equipment to a project, for
safety inspections are necessary.
Temporary electrical final: Construction projects can be complicated and need electrical systems
energized for testing or climate control to complete construction.
Temporary mechanical final: Combined with temporary electrical final the house systems can be
operated prior to Certificate of Compliance /Occupancy.
Building floor framing: This inspection ensures that the load transfer systems of the entire
building are adequately provided and that the girder systems are correctly installed when it is
most convenient to verify and able to be repaired or corrected without unnecessary effort or
expense.
Deck final: This inspection recognizes that decks are often constructed by subcontractors
outside the typical final construction process.
Staff supports the flexibi|ity, with this inapeotion, to complete this portion of project prior to the
completed project.
Electrical pool bond- Residential ovvinnrning pools one unique projects that require specialized
verification of safety elements not found anywhere else in Residential construction. Pools are
normally installed by independent specialty contractors outside the construction processes of
the house itself.
Electrical change of service: When electrical power is upgraded due to renovations or
remodeling the re-establishment of that electrical power requires a special inspection vvhi|o
other work onthe electrical system continues.
Electrical service relocation- This inspection will address when an addition or renovation project
needs the existing electrical service location -to be moved to another part of the building and re-
energized for continued electrical power to other portions of the building. This allows a
temporary interruption of the power system in preparation for more extensive work to come.
Restore electrical service: Power can be interrupted to a Building or structure due to natural
disasters, fires, accident, vacancy or Power Company actions. Staff ia asked to inspect the
oyotanns for safety prior to authorizing the Utility Power Company to energize the system.
Plumbing final: Similar to rough-in inspections these trade subcontractors are independent from
the others and Staff wishes to offer the flexibility to schedule the inspection when the
preparations are completed.
EUectdoa|Unai Similar to Plumbing Final.
Mechanical final: Similar to Plumbing Final
Pool final: This inspection recognizes that pool subcontractors complete the pool installation
independently from the main building or before other phases of work being done by other
contractors.
EiKhubit 2 of Resolution
PLANNING & INSPECTIONS DEPARTMENT
Michael D. Rettie, Chief Building Official
Building Inspections 131 W. Margaret Lane
(919) 245 -2600
Suite 101
(919) 644 -3347 (FAX) ORANGE COUN
P. O. Box 8181
www.orangecountync.gov ),R I : _t_,:l _ Hillsborough, NC 27278
Resolution Petition Explanation
Pursuant to S.L. 2013 -118 Orange County Inspections Division requests to have
additional Inspections approved:
Staff has been instructed by the North Carolina Building Code Council to solicit
approval from the Orange County Board of County Commissioners for the additional
Code enforcement inspections Staff is requesting to be approved for Orange County.
Orange County Inspections Division has vested almost 20 years into fostering a
working partnership with our Building Community. Over this time Staff has developed an
efficient list of inspections. These inspections are crafted to give flexibility of scheduling
for Builders when, in the construction schedule and process, the issue is most efficiently
verified and repairs can be effectively made with minimal cost or delay.
In 2013 when S.L. 2013 -118 was enacted, Orange County sought input from our
construction Partners who, over- whelming, requested that Staff continue working with
the established inspections protocol as Staff had in the past. Staff adjusted the
inspections to include sub - inspections of the NC Administration and Policies Code
section 107 list of 8 (7 for residential projects) inspections allowed. Staff's choice was
predicated upon the understanding that residential projects need the flexibility of
sequencing when Code issues could most efficiently be verified. Staff believed that this
was not asking for "additional inspections" but rather that Staff were making the list
more efficient and effective for the construction process, by expanding each of the
seven inspections into their natural sub - sections. To date, Orange County has received
no documented complaints regarding how Staff schedule or inspect construction
projects in Orange County. According to Staff's regulatory agency NCDOI, Building
Inspectors, statewide, performed over 2.7 million inspections last year and there were
only two documented complaints regarding the type of inspection requested as having
exceeded what was authorized by this Bill (since the Law was enacted).
On February 1, 2018 the NC Code Official Qualification Board's chairman Bill
Thunberg expressed that the Qualification Board's position is for Code Enforcement
Officials to be held responsible for conducting residential inspections not specifically
listed in section 107 of the Administrative Code and Policies. Upon receiving this
position and reviewing the formal Interpretation regarding these inspections, put forth by
NCDOI in April 2016, Orange County has restructured the required inspections to ONLY
those 8 specifically listed in this Code section. The response from Orange County's
building partners has been displeasure for this adjustment. Staff have been asked (by
nearly 100% of permit Applicants) to allow the traditional inspection practices to
continue, which had been working without complaint.
Orange County Inspections petitioned the NC Building Code Council in March of
2014 to approve 46 separate additional Inspections. These petitions were not
addressed nor acted upon by the Council. On March 12, 2018 Orange County
Inspections attempted to submit new petitions for 35 residential inspections to the NC
Building Code Council. At that time Staff was informed that the Council did not have a
policy for how to process these requests. Staff was instructed to provide an example of
our petition and return for the June 11, 2018 meeting to re- submit our request for these
additional Inspections. At that June meeting the NC Building Code Council declined
hearing the petitions without prior approval by the Orange County Board of County
Commissioners and Town of Hillsborough's Board of Commissioners.
Orange County Inspections Division maintains that restricting our building
partners to only the 8 listed inspections creates unnecessary obstacles that may lead to
our Building Safety Officials overlooking deficiencies and hazards due to the
consolidation of the opportunities to perform Staff's sworn duties in an efficient and
effective manner. What Staff is required to inspect has not been changed or diminished,
only when Staff are able to view the process.
Since adjusting to the Listed 8 inspections, Orange County Inspections Division
is facing limitations of the Permitting computer systems that cannot adequately track the
multiple "partially approved" inspections that are necessary to function within the
limitation of the 8 inspections. Similarly requiring Orange County's Building Partners to
hold -off, consolidate and adjust their scheduling to adhere to the fewer types of
inspection options is costly, inefficient and arguably unnecessary.
This request for a policy approval from the Orange County Board of
Commissioners for the Orange County Inspections Division to add additional
inspections would serve to facilitate a more timely and efficient inspection process
(historically experienced prior to this Bill's enactment). This Policy would ensure the
builder and sub - contractor has the flexibility and control over their scheduling and
sequence of inspections and to effectively continue with Orange County's proven
protocol. Orange County Inspections has a 98% rate of performing inspections for the
next business day. Delays and increased cost of construction expected in the
construction process, as a result from these additional inspections, is not supported by
the history and experience over 20 years, as is argued by the NC Home Builders
Association.
Orange County Inspections Division maintains the focus upon working as
partners with the building community and stakeholders. Staff provides information freely
and works with these partners to meet their needs whenever possible. Staff seeks to be
fair and consistent in our application of the minimum Code requirements. Staff listens to
concerns and work to mitigate issues for all parties.
The following table illustrates the comparable historic sub - inspections within the 8
master inspection categories notes in NCACP Section 107.
Historic
When Historic EQUIVALENT TO
When 8 Required
Inspection
Inspection NCACP SECTION
Inspection are
Is scheduled 107 8 REQUIRED
scheduled
INSPECTION
Saw Service
When Electric is needed for N/A
Indicating "Saw Service" on
construction.
application grants authority
to perform this inspection.
Building Footing
When excavation is Footing
When all excavations for
complete, may be divided
the project site are
into sections for phasing.
complete.
Deck Footing
When excavation is Footing
With Footing
complete for deck /porch: no
sequencing.
Projection
When CMU or forms are Foundation
After all excavations for
placed upon footing. Only
footings are approved:
one course of block needed,
Foundation is before
masons may be working
grading either interior or
during inspection. N/A
exterior
concrete forms.
Foundation
Concrete forms complete, Foundation
Concrete forms in- place,
crawl space is graded,
masonry complete. Partial
damp - proofing applied, crawl
approval for required Water -
drain provided and mud sill
Proofing. No grading and
placed.
NO floor framing permitted.
Modular foundation
When Pier and tie -downs Foundation
When installation is
installed for on -frame
complete, prior to setting
modular buildings
the house.
Floor Framing
May be combined with Building Framing
Verified with whole Building
foundation. Floor system
framing.
with point -load blocking,
A special Inspection needed
multiply members installed
for pre -cast foundations to
BEFORE sheathing.
address floor system to
stabilize walls stem.
Water- Proofing
Basement foundations prior Foundation
Verified with Foundation
to backfill placement
Concrete form
Used for concrete foundation Foundation
Scheduled in partially
and reinforced Masonry
approved sequences for
walls. Maybe scheduled for
multiple pours.
multiple pours.
Building Slab
For all structural and non- Under -Slab
After Under -Slab inspection
structural slabs. After all [Building]
approval.
trade approvals when and
slab is prepared for concrete
placement. Multiple may be
scheduled for different
phases.
Garage Slab
When slab is prepared for Under -Slab
With [Building] Slab.
concrete placement. NO [Building]
-sequence
Plumbing,
In any sequence when utility Under -slab
Prior to Foundation when all
Mechanical or
system is tested and ready.
utilities are under test and
Electrical in slab
ready.
Trenches
Plumbing, Mechanical, Rough -in
Included in Trade Rough -in
Electrical, Gas pipe trench
Inspection.
inspections maybe
scheduled whenever ready,
no sequence.
Masonry Fireplace
When firebox to the first flue
Foundation
All prior foundation
liner and hearth extension
Inspections partially
are complete. No Sequence
approved, scheduled when
firebox to first flue liner is
complete. Prior to Framing
or Rough-in.
Factory Fireplace
Stand -alone Mechanical
Rough -in
Part of the overall Rough -in
rough -in. When system is
inspection.
installed.
Gas Pressure test:
When piping that will be
Rough -in
Part of overall Rough -in
Rough -in and Final
concealed is tested. No
Inspection.
sequence.
Pre - Brick, Pre -Stone
Prior to cladding after
Building Framing
Inspected with Building
weather - proofing and
Framing.
windows /doors installed.
Representative pattern of
Brick ties, weep flashing and
Lath installed with weep
screeds for stone veneers.
No sequence
Brick Lintels
Bolted Lintels when installed
Building Framing
With Building Framing
prior to loading with brick.
Modular Marriage
When sections are joined
Building Framing
Partial Building Framing
wall
together
approval required.
Pool Bond
When bonding relating to
Rough -in
Combined with all Trade
swimming pools are
Rough -ins
complete
NFPA 13D sprinkler
When designed system is
Rough -in.
With Trade Rough -in
system
complete and test provided.
Inspections.
Maybe part of Plumbing
Inspections when a
multipurpose system. No
other sequence.
Pre - Insulation
During construction to verify
Building Framing
With Building Framing
air - barrier installation. No
Inspection
sequence
Restore Electrical
Maybe scheduled when
Final
After Insulation approved.
Service, Relocate
needed.
Service, Change -of-
service
Temporary
Application required: After
Electrical Final and
Both systems are complete.
Mechanical and
wall finishes and either
Mechanical Final
Signing application grants
Electrical service
entire systems are complete
authority to perform these
or approved partial systems.
inspections in addition to
Must both be approved for
Standard list.
release of utility
Deck Final
When complete, No
Final
Project complete
sequence, or with Building
Final.
Pool Final
When Swimming Pool is
Final
With Final Inspections
complete
Consultation
No sequence. Brings
N/A
Inquire when Inspector on
Inspector to job site to
site for scheduled
address questions.
inspection only.
Partial Inspections
Applicant may select to have
N/A
Must follow schedule, may
unique portion of building
schedule partials within this
inspected to meet
schedule to facilitate
scheduling needs.
technical feasibility issues.