HomeMy WebLinkAbout2018-116 Planning - Moffat Pipe Change Order #3CHANGE ORDER NO.: 3 Page 1 of 2 CHANGE ORDER CHANGE ORDER NO.: 3 DATE: April 11, 2018 Project: Historic Rogers Road Sewer Expansion Project Contractor: Moffat Pipe, Inc. Engineer /Architect: URS Corporation — North Carolina CONTRACTOR is directed to make the following changes in the Contract Documents. Description: Moffat Pipe, Inc. is requesting the following revisions to the substantial completion and final completion dates of the contract to account for delays in the project considered to be no fault of their own and beyond their control. Specifically they have been delayed with multiple resident concerns, unanticipated site conditions, and excessive weather delays. An itemized list of the number of days associated with specific issues can be found in Attachment A — HRRA Coordination Issues /Delays. These are delays experienced up to March 22, 2018 and does not account for potential future delays from rock blasting, or any other item. Moffat Pipe, Inc. is also requesting an additional $1,385.48 to remove a dead tree that is leaning over the shed located on 7704 Rogers Road property. An additional day for this work has already been included in the itemized list of delays listed seen in Attaclunent A. Moffat Pipe, Inc. is also requesting an additional 2 days and $4,737.03 to clear the trees along Rogers Road that have grown over the existing AT &T lines. The Contractors Change Order Request for this work can be found as Attachment B. CHANGE IN CONTRACT SUM OR PRICE: CHANGE IN CONTRACT TIME OR TIMES: Original Contract Price Original Contract Times $4,782,436.00 Final Completion: July 15, 2018 Net change from previous Change Orders No. 1 to Net change from previous Change Orders No. l to No.2 : - $110,233.03 No. 2 : 0 days Contract Sum or Price prior to this Change Order Contract Times prior to this Change Order $45672,202.97 Final Completion: July 15, 2018 Net Increase of this Change Order Net Increase of this Change Order $6,122.51 Eight six (86) calendar days Contract Sum or Price with all approved Change Contract Times with all approved Change Orders Orders $4,6781325.48 Final Completion: October 9, 2018 CHANGE ORDER NO.: 3 Page 2 of 2 RECOMMENDED: By:1�c Engineer Krista Paredes - Toledo, PE Date: Lill 1 111 REVIEWED: By: 4 Or ge C ty Craig Benedict, AICP Date: l t AC3Cntractor ED: BY : se DuClau Date: w C t 61 The adjustment in Contract Sum or Price and /or Contract Time or Times stated in this Change Order shall comprise the total price and/or time adjustment due or owed the CONTRACTOR for the work or changes defined in this Change Order. By executing the Change Order, the CONTRACTOR acknowledges and agrees that the stipulated price and /or time adjustments include the costs and delays for all work contained in the Change Order, including costs and delays associated with the interruption of schedules, extended overheads, delay, and cumulative impacts or ripple effect on all other non - affected work under this Contract. Signing of the Change Order constitutes full and mutual accord and satisfaction for the adjustment in Contract Sum or Price or Contract Time or Times as a result of increases or decreases in costs and time of performance caused directly and indirectly from the change, subject to the current scope of the entire work as set forth in the Contract Documents. Acceptance of the waiver constitutes an agreement between OWNER and CONTRACTOR that the Change Order represents an equitable adjustment to the Contract, and that CONTRACTOR waives all rights to file a claim on this Change Order after it is properly executed. IN WITNESS WHEREOF, the undersigned have caused the execution hereof. ATTEST: Secreta [Corporate Seal] P� P w � ° w � w e ° M Y � W r � n P CONTRACTOR: MOFFA PIPE, INC B J' Y� Nai Jesse DuClau Titl Contractor Address: 4901 Unicon Drive �a 1 Forest, NC 27587 Date: OWNER: Orange County By. Name: Bonnie Hainmersley Title: Oran g County Manager Date: Moffat Pipe, Inc. Moffat Pipe, Inc. 4901 Unicon Drive A WBE/DBE Company Wake Forest, NC 27587 Ph. (919) 295 -4630 Change Order Request Fax(919)295 -4631 To: AECOM of NC Change Order Request No: 3 Attn: Krista Paredes - Toledo PE Date: 4/3/18 Address: 1600 Perimeter Park Dr. Suite 400 MPI Job No: 1203 -17 Morrisville, NC 27560 Job Name: Historic Rogers Rd. Sewer Expansion CC: MPI Project Staff Description: Additional Clearing Item No. Description Quantity Unitl Unit Price Total 1 Utility Line Clearing (Rogers Road) 1 LS $4,737.03 $4,737.03 2 Specialty ClearingOutfall I (Sharpe) 1 LS $1,385.48 $1,385.48 Additional Calendar Days Requested: 3 TOTAL COR $6,122.51 We the undersigned accept this off-at Pipe, Inc. COR No. 3 and the terms and conditions contained herein. Payment for all work is due in full within 30 days of the completion of the work. A 1.5% late charge i J be applied to any accou t ast ue after 30 days. An additional 1.5% charge will be applied every 30 days thereafter until the account is paid in full. Proposal is good for 30 da s. Any item that is plus P - minu 101/o of bid quantity is subject to price adjustment. By: at Pi Date: Date: By: AECOM of NC Moffat Pipe,,.,. A WBE/DBE Company Change Order Request To: AECOM of NC Attn: Krista Paredes - Toledo PE Address: 1600 Perimeter Park Dr. Suite400 Morrisville, NC 27560 CC: MPI Project Staff Moffat Pipe, Inc. 4901 Unicon Drive Wake Forest, NC 27587 Ph. (919) 295 -4630 Fax (919) 295 -4631 Change Order Request No: 3 Date: 4/3/18 MPI Job No: 1203 -17 Job Name: Historic Rogers Rd. Sewer Expansion Description: Additional Clearing Item Description " Qty Unit Material Labor Equipment Subcontractor Total Cost 5% Mark Up on Subcontractors Cost/Unit Total MH /Unit Hrs Ext Rate Total Hrs Rate Total Hrs Rate Total MATERIALS $0. $0. $0. LABOR Project Manager $83.78 50.00 $0. Superintendent $59.29 S0.00 50. Foreman $49.17 S0.00 S0. Operator $29.78 S0.00 S0. Laborer 2 12 24 $24.53 5588.72 S588.7 EQUIPMENT John Deere 210D Excavator 1 EA S97.09 S0.00 S0. John Deere 350D Excavator 1 EA $155.99 50.00 S0. John Deere TC 62 Loader 1 EA 570.57 S0.00 S0. John Deere Skid Steer 1 EA $37.05 S0.00 S0. Medium Duty Roller 1 EA 530.80 $0.00 So. Ford F- 15D ( Project Manager) 1 EA S15.17 50.00 So. Ford F-350 (Superintendent) 1 EA 520.15 S0.00 $0. Ford F -450 ( Foreman Service Truck) 1 EA 527.23 $0.00 So. Kenworth Dump Truck 1 EA S69.94 $0.00 So. Small Tools 1 EA S30.00 $0.00 $0. SUBCONTRACTOR Wellsmont Landscaping 1 LS $3,800.00 $3,800.00 $3,800.00 $0. $o. Subtotals Malerials Labor Equipment Sub S0.00 $588.72 $0.00 $3,800.00 $4,388.7 7.5 - %Sales Tax $0. 15% Mark Up on Materials $0. 15% Mark Up on Labor and Equp $88.31 5% Mark Up on Subcontractors $190. Bond Rat $70.01 Total Cost $4,737.0 Doug Malinowski Owner /Operator 1005 Dimmocks Mill Rd. Hillsborough, NC 27278 LANDSCAPING 919-810-6282 Bill To Moffat Pipe, Inc. Attn: Accounts Payable 2708 Connector Dr Wake Forest No 27587 Invoice Date Invoice # 414!2018 3909 P.O, No. Terms Project Net 30 Owasa Item No. Description Qty Unit Rate Amount 1 TYee Work: Clear utility lines along easement as discussed Sales Tax 1 per 3,800.00 7.50% 3,800.00 0.00 Total $3,800.00 Moffat Pipe, A WHE/DBE Company Change Order Request To: AECOM of NC Attn: Krista Paredes - Toledo PE Address: 1600 Perimeter Park Dr. Suite400 Morrisville, NC 27560 CC: MPI Project Staff Moffat Pipe, Inc. 4901 Unicon Drive Wake Forest, NC 27587 Ph. (919) 295 -4630 Fax (919) 295 -4631 Change Order Request No: 3 Date: 4/3/18 MPI Job No: 1203 -17 Job Name: Historic Rogers Rd. Sewer Expansion Description: Additional Clearing Item Description * Qty Unit Material Labor Equipment Subcontractor Total Cost 5% Mark Up on Subcontractors Cost/Unit Total MHIUnit Hrs Ext Rate Total Hrs Rate Total Hrs Rate Total MATERIALS S0. S0. S0. LABOR Project Manager $83.78 $0.00 So. Superintendent $59.29 $0.00 S0. Foreman $49.17 $0.00 S0. Operator $29.78 $0.00 S0. Laborer 0 $24.53 $0.00 S0. EQUIPMENT John Deere 210D Excavator 1 EA $97.09 $0.00 $0. John Deere 350D Excavator 1 EA $155.99 $0.00 S0. John Deere TC 62 Loader 1 EA $70.57 $0.00 $0. John Deere Skid Steer 1 EA $37.05 $0.00 S0. Medium Duty Roller 1 EA $30.80 $0.00 $0. Ford F -150 (Project Manager) 1 EA $15.17 $0.00 $0. Ford F -350 (Superintendent) 1 EA $20.15 50.00 S0. Ford F -450 (Foreman Service Truck) 1 EA $27.23 $0.00 S0. Kenworth Dump Truck 1 EA $69.94 $0.00 S0. Small Tools 1 EA $30.00 $0.00 S0. SUBCONTRACTOR CS Tree Service 1 LS S1,300.00 $1,300.00 S1,300. S0. $0. Subtotals Materials Labor Equipment Sub $0.00 $0.00 So.00 $1,300.0 o $1.300,OC 7.5 _ %Sales Tax $0. 15% Mark Upon Material $0. 15% Mark Up on Labor and Equp $0. 5% Mark Up on Subcontractors S65.00 Bond Rate S204 Total Cost S1.385. (SA Certified Arborists on Staff (919) 355 -8299 WWW.CSTREESERVICES.COM Chris Bale_y SO - 5675AC, chris(d cstreeservices.coum Steve Kurtz SO-5683A, stevc(d,cstreeservices.ann 1612 Burgess Hill Ct., Apex, NC 27539 Fax (919) 892-9915 r , IF . VDIf.! nF &TRFF CA&F • 111 a Ark perli�rnre�l ;arc �uzlin to ANSI A300 & 7,13.3.1 indu:u v .st.indard.s li)r trr< CUFF, unIeS'i nntccl 01110 -ii ise Date: 2/20/2018 Site Map: Company: MPI Customer: Andrea Moffat Address: 4901 Unicon Drive Wake Forest, NC 27587 Phone: (919) 295 -4630 (919) 295 -4631 Job Name: MPI Rogers sewer 7704 Rogers Rd 180220 -1 Work Site: 7704 Rogers Rd Chapel Hill, NC # Tree Species Objectives and Specifications Qty Cost (See back for definitions, terms, and conditions.) 1 Dead Pine Cut and brought to ground 1 $1,300.00 Located behind shed to left of house (7704 Rogers Rd), dead Pine is broken at base and leaning over shed. Dead Pine cut and brought to ground. Debris moved into clearing easement and left onsite. Arborist: Steven Kurtz Subtotal: $1,300.00 Notes: Total: $1,300.00 Customer Signature Date All debris removed, chipped & raked clean. Stump grindings raked into a pile. This proposal is valid for 90 days, unless otherwise noted. T6JM (an affiliate of AECOM) Date: June 14, 2018 LETTER OF TRANSMITTAL TO: Craig Benedict FROM: Krista Paredes - Toledo, PE c/o Elaina Cheek URS Corporation — North Planning and Inspections Director Carolina 1600 Perimeter Park Drive Orange County Suite 400 131 W. Margaret Lane Morrisville, NC 27560 Hillsborough, NC 27278 URS JOB #: 31829996 OWASA# : 276 -54 RE: CHANGE ORDER #3 The following items are being sent: ❑Attached ❑ Under separate cover by ❑ Shop Drawings ❑ Prints ❑ Plans ❑ Samples ❑ Specifications ❑ Copy of Letter ❑ Other Item Copies Date Description 1 1 June 14, 2018 Change Order #3, executed 2 1 June 14, 2018 Att A — Itemized Delay List 3 1 June 14, 2018 Att B — Contractor's Change Order Request Transmittals for reasons checked: ❑ For Your Approval ❑ No Exceptions Taken ❑ Resubmit copies for approval ❑ For Your Use ❑ Make Corrections Noted ❑ Submit copies for distribution ❑ As Requested ❑ Amend and Resubmit ❑ Return all _ signed documents ❑ For Review and Comment ❑ Remarks: Copies: Keep the attachments for your records. If enclosures are not as noted, kindly notify us at once. URS Corporation — North Carolina 1600 Perimeter Park Drive, Suite 400 Morrisville, NC 27560 919- 461 -1100 r. ��� —�.c� Name: r `, +� krista Paredes - Toledo, PE Letter of Transmittal 6/14/2018 Attachment A HRRA Coordination Issues /Delays No. Description Property /Location CO Requested Days Negotiated Days Notes 1 PVC Pipe /Additional Manhole Animal Shelter /Duke Power 1 1 1 Added Manhole /Re- aligned Sewer 2 Rusch St. Access Notices Timothy Peppers N/A 0 0 Complaint From Peppers about not knowing about work. MPI handed notices to residents and spoke to them prior to work beginning. 3 Project Sign Relocation Rogers Rd @ Eubanks N/A 0.5 0.5 Move Sign at Eubanks and Rogers for Site Distance. 4 Ebi /Ferrell Clearing Limits Morgan /Ferrell /EBI Property N/A 0.5 0.5 Met with Property Owners regarding clearing limits /Re- staked limits and added property line staking (Additional) 5 Re- Staked Clearing Limits Outfall L /Outfall Q N/A 0 0 Clearing Limits are too wide, DWG files TCE is incorrect due to clarity. Corrected and re -sent. Had to re -stake A Run and Q Run. 6 Glenbrooke Clearing Concerns Outfall L N/A 0 0 Resident Concerned about clearing got too close to the tree, waited until she left and continued clearing. 7 Re- Staking @ Billabong Billabong Dead End. N/A 0 0 Residents Removed Staking at the end, re Staked and Painted on sidewalk 8 Ferriero Sewer Service Ferriero Property 2 0 0 Added Service - ALL ROCK 9 Miller Sewer Service Miller Property 2 0 0 Added Service - ALL ROCK 10 Additional Tree Removal Glenbrooke HOA 2 1 1 Tree Removed to appease Glenbrooke HOA after clearing was completed in the area. 11 Duke Power Guy Wires Morgan /Ferrell Property N/A 27 5 Guy Wires Preventing Clearing and Pipe installation Moved /Demobilized 2 times to accommodate. 12 Ferrell Cherry Tree Morgan /Ferrell Property N/A 2 2 Demobilized clearing until decision made on what to do with Cherry Tree. 13 Shed Removal Morgan /Ferrell Property N/A 0 0 Shed removal delayed due to residents out of town. 14 Merin Rd /Billabong Restoration Merin /Billabong Intersection N/A 0 0 Complaints from Chapel Hill due to construction activities. We swept restored the area and added stone. 15 Sandburg Rd. Access and Resident Notification Sandburg Ln N/A 3 3 Accessibility Questions with Residents regarding Access while work is being done on Sandburg. Provided Notices and alternative housing. 16 Sunkel Shed Relocation Sunkel Property N/A 0 0 2 Sheds to be removed - Clearing will work around it until removed. 17 AT &T Utility Conflicts along Sandburg Sandburg Ln N/A 0 0 Phone /Internet lines prevent installation of sewer lines. Polled Residents and narrowed dines lines in service. 18 Sandburg Waterline Revisions Sandburg Ln TBD 2 2 Added Gate Valve to 4" Waterline. 19 Manhole L -12 Revisions Sandburg Ln N/A 0.5 0 Had to explore and relocate manhole from Mr. Sunkel Driveway due to conflicts with Utilities 20 Manhole L -14 Revisions Sandburg Ln N/A 0.5 0 Had to explore and relocate Manhole and extend sewer service to allow for powerline separation. 21 Sandburg Lane Drainage - Regrading Sandburg Ln N/A 2 2 Regrading Sandburg Ln and Mrs. Bradshaw's Ditch /Driveway. Had to add pipe as requested byToCH 22 Easement Width off Merin Protestant Episcopal Church N/A 0.5 0.5 widened easement width along Merin Rd. Access Road. 23 Resident concerns along Merin Access Rd Protestant Episcopal Church N/A 0.5 0.5 Resident stopped work due to concerns with clearing operations. 24 Merin Road Shed Removal. Inman Property N/A 0 0 25 Animal Shelter Clearing Delay Animal Shelter N/A 5 5 Orange County Animal Shelter clearing halted due to notification questions from Manager. Demobilized /Remobilized at a much later date for completion 26 Existing Manhole revisions for Animal Shelter Service Animal Shelter N/A 1 0 Re -align sewer tap and rework bench due to existing service blocking proposed manhole core. 27 New Gate installed at Animal Shelter Animal Shelter 2 1 1 County Request New Gate installed at Animal Shelter 28 Purefoy Rd. Tie -in Manhole Revisions Purefoy Rd. N/A 0 0 Manhole Elevations not working out, revised tie -in elevations and revised inverts 29 Winstead -Mann Clearing Issues Winstead /Mann Property N/A 1 1 Resident stopped clearing and involved law enforcement. 30 1 D -Run Restaking (3 Times) Outfall D N/A 1 1 Residents Removing Staking 31 Additional Erosion Control along Outfall-A Outfall A N/A 1 1 Due to request from Haw River Assembly Inspection 32 Leaning Tree along Outfall I Sharpe TBD 1 1 Tree will need to be removed prior to beginning work 33 Bellin Sewer Shift /Tree Removal /Bore Removal /Service Revisions Bellin 2 0 0 Incorporated into CO 02 +8 Days for Tree /Sewer - 8 Days for Service Removal 34 Walking Trail Revisions /Restoration Glenbrooke Outfall L N/A 0 0 Glenbrooke HOA concerned about the walking trail restoration path will be restored post construction. 35 Rogers Rd. Clearing Conflicts Rogers Rd TBD TBD TBD AT &T Lines conflicting with 36 Outfall A (North) Beaver /Dewatering St Paul AME Church TBD TBD TBD Beavers have dammed and flooded A - Run Past Priscilla Ln. 37 Lair Court Light Pole /Aerial Drop Winters Property TBD TBD TBD 38 Peppers Temporary Power Relocations Peppers TBD TBD TBD Power line in conflict with clearing. Will need to be temporarily removed for clearing operations 39 jAccess for Jones Property During Construction Jones Property TBD TBD TBD No Access During Clearing/ Construction 40 Priscilla Lane Access Priscilla Ln. TBD TBD TBD No Access During Clearing /Construction /Silt Fence Blocking Driveway 41 Outfall A Rock Removal /Blasting Outfall A TBD TBD TBD Unable to remove Rock along Outfall A Via Blasting /Hoe- Ramming Subtotal (Working Days)j 52 1 28 Weather Delays Month Description Anticipated /Contract Actual/ Impact Requested Negotiated Notes eptembe Rain /Snow /Sleet Delays and Impact 8 5 0 0 October Rain /Snow /Sleet Delays and Impact 7 11 4 4 7,8,9,10,16,17,23,24,25,28,29 November Rain /Snow /Sleet Delays and Impact 8 7 0 0 7,8,9,10,13,14,19 December Rain /Snow /Sleet Delays and Impact 9 7 0 0 5,6,8,9,10,20,21 January Rain /Snow /Sleet Delays and Impact 10 15 5 5 4,11,12,13,14 ,17,18,19,23,24,25,28,29,30,31 February Rain /Snow /Sleet Delays and Impact 10 13 3 3 2 ,4,5,6,7,8,10,11,17,19,20,26,27 March Rain /Snow /Sleet Delays and Impact 10 TBD TBD TBD April Rain /Snow /Sleet Delays and Impact 9 May Rain /Snow /Sleet Delays and Impact 10 June Rain /Snow /Sleet Delays and Impact 9 July Rain /Snow /Sleet Delays and Impact 11 Subtotal 12 12 1of2 Attachment A 2 of 2 Rock Excavation Delays Month Description Quantity (CY) Requested Negotiated Notes September Rock Excavation 0 0 October Rock Excavation 0 0 November Rock Excavation 110.75 11 11 11/1, 11/9, 11/10, 11/14, 11/5, 11/16, 11/17, 11/20, 11/21, 11/28, 11/29, December Rock Excavation 4 4 4 12/9., 12/4, 12/6, 12/11 January Rock Excavation 0 0 February Rock Excavation 227.5 10 10 2/14, 2/15, 2/16, 2/19 2/20,2/21, 2/22, 2/26, 2/27, 2/28 March Rock Excavation 2 2 3/1,3/2 April Rock Excavation May Rock Excavation June Rock Excavation Subtotal 342.25 27 27 Anticipated 9 9 (Qty /8hrs /5 cy per hr) Per Section 3123 16 -E -1. Total Work 1 18 18 Subtotal- Anticipated Total Work Days 82 58 Total Calendar Days 115 82 2 of 2