HomeMy WebLinkAboutAgenda - 06-05-2018 6-c - Limited Obligation Series 2018 Bonds
ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: June 5, 2018
Action Agenda
Item No. 6-c
SUBJECT: Limited Obligation Series 2018 Bonds
DEPARTMENT: Finance and Administrative
Services
ATTACHMENT(S): INFORMATION CONTACT:
Resolution
Gary Donaldson, 919-245-2453
Paul Laughton, 919-245-2152
Bob Jessup, 919-933-9891
PURPOSE: To adopt a resolution for the issuance of Series 2018 Limited Obligation Bonds
(LOBS) with a not to exceed amount of $8.8 million to support the County’s FY 2017-18 Capital
Investment Plan (CIP). The financing resolution 1) gives final approval to allow the financing to
proceed; 2) approves the form of the official statement; 3) states the County's commitment to
comply with federal tax and securities laws; and 4) authorizes staff to complete the financing.
BACKGROUND: Pursuant to North Carolina General Statute 160A-20, the County seeks to
issue approximately $8.1 million in Series 2018 Limited Obligation Bonds.
The County conducted a public hearing at its May 15, 2018 Board of County Commissioners
(BOCC) meeting and received approval from the BOCC to proceed with the financing. The
notice of public hearing was advertised in The Herald Sun and The News of Orange.
If the Board adopts the resolution, the County plans to close on this financing on June 19, 2018.
Key terms of the financing include:
1) Issuing approximately $8.1 million to finance capital investment projects, equipment and
vehicles for the current fiscal year;
2) Estimate of maximum debt service applicable to these CIP projects would require the
highest debt service of $1.2 million in FY 2019-20; and
3) The tax rate equivalent for the estimated highest debt service is approximately .67 cents
FINANCIAL IMPACT: The Series 2018 Limited Obligation Bonds are included and compliant
with County’s CIP and Debt Affordability Plan.
SOCIAL JUSTICE IMPACT: The following Orange County Social Justice Goal is applicable to
this item:
• GOAL: ENSURE ECONOMIC SELF-SUFFICIENCY
The creation and preservation of infrastructure, policies, programs and funding necessary
for residents to provide shelter, food, clothing and medical care for themselves and their
dependents.
RECOMMENDATION(S): The Manager recommends that the Board approve the attached
resolution.
1
PIA
RES- 2018 -035
Resolution providing final approval of terms and
documents for 2018 County installment financing
WHEREAS --
The Board of Commissioners has previously determined to carry out the
acquisition and construction of various public improvements, as identified in the
County's capital improvement plan, and in particular the projects shown on Exhibit
A.
The Board has made a tentative determination to carry out the financing by
using an installment financing, as authorized under Section 160A -20 of the North
Carolina General Statutes. This financing plan also includes the use of limited
obligation bonds, which represent interests in the installment payments to be made
by the County that can be sold to investors.
The County staff has made available to the Board the draft documents listed
on Exhibit B (the "Documents "), and a draft of an official statement designed to
provide information about the County and the financing to prospective investors in
the bonds. These items relate to the County's carrying out the financing plan.
This resolution provides the County Board's final approval of the financing
terms and the substantially final financing documents.
BE IT THEREFORE RESOLVED by the Board of Commissioners of Orange
County, North Carolina, as follows:
1. Determination To Proceed with Financing -- The Board confirms its
decision to carry out the proposed installment financing as described above.
Under the financing plan, the County will receive funds from the sale of the
limited obligation bonds to carry out the projects. The County will repay the funds
over time, with interest. The County will secure its repayment obligation by granting
a mortgage -like interest in some or all of the following facilities: (a) the County's
Government Services Annex at 208 S. Cameron St. in Hillsborough, (b) the County's
3
Emergency Operations Center on Meadowlands Drive in Hillsborough, (c) the
County's Visitors Center on Franklin St. in Chapel Hill, and (d) the proposed site of
the new Northern County Campus.
2. Approval of Documents; Direction To Execute Documents -- The
Board approves the forms of the Documents submitted to this meeting. The Board
authorizes the Chair and the County Manager, or either of them, to execute and
deliver those Documents to which the County is a party. The Documents in their
respective final forms must be in substantially the forms presented, with changes as
the Chair or the County Manager may approve. The execution and delivery of any
Document by an authorized County officer will be conclusive evidence of that
officer's approval of any changes.
The Documents in final form, however, must provide for the principal amount
of limited obligation bonds to not exceed $8,800,000, an annual true interest cost of
the financing not to exceed 4.50% and a financing term not to extend beyond
December 31, 2038. The amount financed under the Documents may include
amounts to pay financing expenses and other necessary and incidental costs.
3. Sale of Bonds; Approval of Official Statement - The Board appoints
Robert W. Baird & Co. to underwrite a public offering of the proposed limited
obligation bonds.
The Board approves the draft official statement submitted to this meeting as
the form of the preliminary official statement pursuant to which the underwriter
will offer the bonds for sale. The preliminary official statement as distributed to
prospective investors must be in substantially the form presented, with such
changes as the Finance Officer may approve. The Board directs the Finance Officer,
after the sale of the bonds, to complete and otherwise prepare the preliminary
official statement as an official statement in final form.
The Board authorizes the use of the preliminary official statement and the
final official statement (collectively, the "Official Statement ") by the underwriter in
connection with the sale of the bonds.
The Board acknowledges that it is the County's responsibility, and ultimately
the Board's responsibility, to ensure that the Official Statement in its final form
C!
neither contains an untrue statement of a material fact nor omits to state a material
fact required to be included therein for the purpose for which such Official
Statement is to be used or necessary to make the statements therein, in light of the
circumstances under which they were made, not misleading.
4. Officers To Complete Closing - The County Manager, the Finance
Officer and all other County officers and employees are authorized to take all proper
steps to complete the financing in accordance with the terms of this resolution.
The Board authorizes the County Manager to hold executed copies of all
financing documents authorized by this resolution in escrow on the County's behalf
until the conditions for their delivery have been completed to her satisfaction, and
then to release the executed documents for delivery to the appropriate persons or
organizations.
Without limiting the generality of the previous paragraphs, the Board
specifically authorizes the County Manager (a) to approve and enter into, on behalf
of the County, any additional agreements appropriate to carry out the financing plan
contemplated by this resolution, and (b) to approve changes to any documents
previously signed by County officers or employees, provided that the changes do not
substantially alter the intent from that expressed in the form originally signed. The
County Manager's authorization of the release of any document for delivery will
constitute conclusive evidence of her approval of any changes.
In addition, the County Manager and the Finance Officer are authorized to take
all appropriate steps for the efficient and convenient carrying out of the County's on-
going responsibilities with respect to the financing. This authorization includes,
without limitation, contracting with third parties for reports and calculations that
may be required under the Documents, this resolution or otherwise with respect to
the bonds.
5. Other Financing Participants - Sanford Holshouser LLP will serve as
the County's bond counsel. Davenport & Company LLC will serve as the County's
financial adviser. The Bank of New York Mellon Trust Company, N.A., will serve as
Trustee under the Trust Agreement.
6. Miscellaneous Provisions - The Board authorizes all County officers
5
and employees to take all further action as they may consider desirable to carry out
the purposes of this resolution. In particular, the Board directs the Clerk to this
Board to apply the County's seal to the final form Documents, and to attest to the
application of the seal. The Board ratifies all prior actions of County officers and
employees to this end. Upon the unavailability or refusal to act of the County
Manager, the Chair or the Finance Officer, any other of those officers may assume
any responsibility or carry out any function assigned in this resolution. In addition,
the Vice Chair or any Deputy or Assistant Clerk may carry out or exercise any rights
or responsibilities assigned in this resolution to the Chair or the Clerk. The Board
repeals all other Board proceedings, or parts of proceedings, in conflict with this
resolution, to the extent of the conflict. This resolution takes effect immediately.
Exhibit A - list of improvements with estimated amounts
Improvement Description
Estimated
Amount
Northern Campus Site Acquisition
$ 394,500
Government Services Annex Building
350,000
HVAC Projects
122,000
Roofing Projects
102,444
IT Infrastructure
700,000
Communications Systems
920,000
Cedar Grove Community Center
75,000
Facility Accessibility and Security Improvements
30,000
Vehicle Replacements
1,106,514
Miscellaneous County equipment
184,000
Chapel Hill HS Architecture and Facility Improvements
601,000
Classroom and Building Improvements (OCS)
254,000
Food Services (OCS)
145,000
Passmore Center Renovations
550,000
Information Technologies
500,000
IT Broadband Connectivity
60,000
IT Governance Council Initiatives
690,503
911 Center Improvements
177,832
Conservation Easements
500,000
Cedar Grove Park, Phase II
60,000
Parks and Recreation Facility Renovations
195,000
Affordable Housing Land Banking
293,000
TOTAL ESTIMATED PROJECT COSTS
$ 8,010,793
The County also expects to use some financing proceeds to pay Financing
Costs.
LV
Exhibit B -- Draft Documents
(a) A draft dated May 8, 2018, of a Trust Agreement to be dated on or
about June 1, 2018 (the "Trust Agreement "), between the County and The Bank of
New York Mellon Trust Company, N.A. (the "Trustee "), providing for the advance of
funds to the County, for the issuance of limited obligation bonds, for the County's
obligation to repay the amounts advanced, and for the County's responsibilities for
the use and care of the collateral.
(b) A draft dated May 8, 2018, of a Deed of Trust and Security Agreement to
be dated on or about June 1, 2018, from the County to a deed of trust trustee for the
Trustee's benefit, providing for a security interest in property to secure the County's
obligations under the Trust Agreement.
(c) A draft of a Bond Purchase Agreement to be dated on or about June 21,
2018, providing for the underwriter's obligation to purchase the bonds. The final
form of this Agreement will set out the final principal amount, principal payment
schedule and interest rates for the bonds, and the other terms and conditions for the
underwriter's obligation to purchase the bonds.