Fairview Park and Public Campus
Draft Project Timetable
February, 2005
October-December, 2004 Authorization to conduct topographic, biological and cultural
surveys of the site
November 2004 Memorandum of Agreement adopted by Town and County
January-March 2005 Surveys underway, members of Work Group solicited
Apri12005 Appointments made to Fairview Park and Campus Master
Plan Committee, Opportunities and Constraints staff report
prepazed
May 2005 Committee Meeting #1 (Opportunities and Constraints report
presented, initial facility/design ideas solicited)
June 2005 Committee Meeting #2 (Design charette)
August 2005 Committee Meeting #3 (Complete chazette /develop draft
recommendations/MasterPian)
September 2005 Committee Meeting #4 (Final meeting -recommendations
and Master Plan)
October-November 2005 Master Plan presented to County and Town BoC for
review/approval
November 2005? A proval of Master Plan
One month after Master
Plan Approval (MPA) Land swap reviewed and considered. County BOCC
approves submittal of site plan for pazk
3 months after MPA Site plan considered and approved by Town
8 months after MPA Park construction/biddocumenu prepared, bids solicited and
received
9 months after MPA Bid award to BOCC for action
10 months after MPA Pazk Construction begins
22 months after MPA Park opening (tentative)
Draft timetable, subject to change