HomeMy WebLinkAboutAgenda - 03-22-2018 Abstract for Joint Meeting Discussion Items
ORANGE COUNTY BOARD OF COMMISSIONERS
CHAPEL HILL TOWN COUNCIL
JOINT MEETING
AGENDA ITEM ABSTRACT
Meeting Date: March 22, 2018
SUBJECT: Joint Meeting Discussion Items
DEPARTMENT: County Manager/Town
Manager/County & Town
Planning/County Asset
Management Services/County
Arts
ATTACHMENT(S):
As noted in “Background” section
INFORMATION CONTACT:
Bonnie Hammersley, 245-2300; Roger
Stancil, 968-2743; Travis Myren, 245-2300;
Ben Hitchings, 968-2731; Loryn Clark, 968-
2743; Craig Benedict, 245-2575; Jeff
Thompson, 245-2625; Katie Murray, 245-
2335
PURPOSE: To discuss topics of mutual interest between the governing boards of Orange
County and the Town of Chapel Hill.
BACKGROUND:
1. Duke Energy-Neighborhood Energy Saver Program
Duke Energy is an electric and natural gas utility serving customers in the Southeast and
Midwest. The Duke Energy Neighborhood Energy Saver Program uses a community
approach to swiftly reduce energy bills for a large number of participants. Duke Energy
utilizes census and other data to identify low-income neighborhoods of approximately
1,000 homes. Then, working with local leaders to build neighborhood engagement and
buy-in, and conducting energy assessments, energy-saving improvements, and
participant education at no cost, the program is able to upgrade hundreds of homes in a
cost- and time-efficient manner while reducing carbon pollution. Program representatives
work with local leaders in interested neighborhoods to hold community events that explain
the upgrade process and its benefits. The Program’s free upgrades eliminate the barrier
of up-front costs, and its focus on partnering with community leaders to build
neighborhood engagement and buy-in overcomes common trust concerns associated
with utility-sponsored programs.
Representatives of the Program will be at the meeting to make a presentation, and the
governing boards can discuss this item as necessary.
Attachment 1 – March 8, 2018 Memo with Powerpoint Presentation
1
2. Update on Major Project Developments
a) Carraway Village/Glen Lennox/Wegmans/Eastowne/Blue Hill District (Formerly
the Ephesus Fordham Area)
Town of Chapel Hill staff provided the attached presentation addressing these items.
Staff will provide any other information at the meeting, and the governing boards can
discuss issues related to these items as necessary.
Attachment 2 – Chapel Hill Development Project Update
b) Millhouse Road Property Analysis
The Board of Orange County Commissioners has allocated $2 million in the County’s
Capital Budget to address preservation and retention of manufactured homes parks
and/or to assist in the acquisition of property and land banking for future residential
development as an affordable housing alternative. Following the establishment of the
land banking program, local housing partners, including Orange County and the Town
of Chapel Hill, began evaluating opportunities and obstacles in redeveloping an
existing manufactured home park or developing new affordable housing units to
address the needs of park residents at risk. A summary of the results from the Mobile
Home Park Survey Report were presented to County and Town elected officials
during the Assembly of Governments meeting in January.
Due to the potential redevelopment of existing manufactured home communities in
the Town of Chapel Hill, Orange County is exploring the opportunity to locate
displaced manufactured home park residents on County owned property near the
town. One site identified for a potential manufactured home park is the Millhouse
Road Park site. This 78-acre site, comprised of two parcels, is zoned RB (Rural
Buffer).
On January 23, 2018, the Board of Orange County Commissioners authorized staff to
proceed with a rezoning process as well as appropriate site investigations to
determine whether this property is able to accommodate affordable housing for
displaced residents. Because of the property’s location in the Rural Buffer, it is bound
by density limitations detailed within the Joint Planning Land Use Plan. These density
regulations limit residential development to one dwelling unit per two acres of
property. As part of the rezoning effort, Orange County will pursue the recombination
of the two parcels which make up the 78-acre Millhouse Road Park site which would
allow for clustering home sites and allowing the balance of the property to be used for
park purposes. The County is also exploring community water and sewer solutions
that could be used as an alternative to extending public lines to the site since it is
outside of the area where public water and sewer service may be installed.
The Millhouse Road Park site is within the “Joint Courtesy Review Area”, as
designated by the Joint Planning Agreement. As such, both the Towns of Carrboro
2
and Chapel Hill will have an opportunity to review the rezoning proposal and offer
recommendations. The County may not formally adopt the proposed zoning
amendment until the Towns have made recommendations or until the expiration of
forty-five (45) days following the referral of the rezoning proposal, whichever occurs
first. The County also recognizes that access to public transportation will be
important to the viability of this site as an affordable housing community. The County
is committed to working with the Town of Chapel Hill to establish safe and effective
public transit access to the site.
The County has retained site consultants to complete the site examination and
development cost estimates. The results of these studies will be presented to the
Board of Orange County Commissioners for direction prior to the summer break.
Staff will provide any other information at the meeting, and the governing boards can
discuss issues related to this item as necessary.
No Attachments
c) Eubanks Road Waste and Recycling Center
The Eubanks Road Solid Waste & Recycling Center improvement project includes
the modernization of the existing Waste & Recycling Center and the relocation of the
main landfill entrance and scale house from the south side of Eubanks Road to the
north side of Eubanks Road. The improvements are part of an approved long range
plan to establish two District Centers with increased services and extended hours
which are complemented by Neighborhood Centers that are smaller and offer fewer
services but are conveniently located throughout the County.
Eubanks Road is the second of the planned District Centers. The improvements
increase the Center’s size and capacity and offer customers one stop service. The
$3.1 million dollar project includes the addition of five (5) 40 cubic yard stationary
compactors for trash and mixed recyclables, two (2) larger stationary compactors for
bulky waste, food waste composting, cooking oil recycling, textile recycling, plastic
bag recycling, and a number of other services including mattress drop-off and
hazardous waste recycling. With the addition of the compactors, the department will
save on fuel and maintenance costs over the life of the Center. The Center offers
safer unloading for users and a better experience due to the newly paved user area.
The Center also has bio-retention and dry detention storm-water ponds for modern
flow control and treatment of storm-water runoff. Finally, moving the scales will result
in much safer traffic flow for the commercial and residential customers who use them.
After a year of construction, the grand opening is set for April 17, 2018 at 2:00 PM.
Following the opening, the temporary site on Millhouse Road will close as well as the
Household Hazardous Waste facility on the south side of Eubanks Road.
Staff will provide any other information at the meeting, and the governing boards can
discuss issues related to this item as necessary.
3
No Attachments
d) Southern Branch Library
The County has authorized approximately $6.4 million to construct a library facility in
the Town of Carrboro. The facility will be located at 203 South Greensboro Street.
The County and the Town of Carrboro have entered into a Development Agreement
to collocate some Town offices with the County library facility on this site. A design
firm has been selected to negotiate a professional services agreement for this project.
Negotiations with the selected design firm are expected to be complete before the
summer break. Design for the facility will occur through the fall of 2018. Construction
is anticipated to start in the winter of 2019 and be completed in the spring of 2021.
Staff will provide any other information at the meeting, and the governing boards can
discuss issues related to this item as necessary.
No Attachments
e) Southern County Campus
The Board of Orange County Commissioners authorized the first phase of remodeling
and expansion of the Southern County Campus in FY2017-18. This campus includes
includes the Seymour Senior Center and the Southern Human Services facility. The
first phase of the project includes an expansion of the Seymour Center, straightening
the roadway entrance, and adding parking space for the Seymour Center. The Board
of Orange County Commissioners is scheduled to review the schematic design of
Phase 1 in June of 2018. Development design and construction documents are
anticipated to be complete in the winter of 2018, and construction is anticipated to be
complete is the late winter of 2020. The Town of Chapel Hill planning staff will
complete a technical review of the design documents as governed by the master plan
special use permit.
The second phase of this project includes remodeling the existing Southern Human
Services facility to improve the health and dental clinic areas and office spaces
occupied by the Department of Social Services. Construction of the second phase is
scheduled to begin in FY2019-20.
Staff will provide any other information at the meeting, and the governing boards can
discuss issues related to this item as necessary.
No Attachments
3. Discussion on Improving Collaboration on Gateway Area Planning
Staff will be available to answer questions at the meeting, and the governing boards can
discuss issues related to this item as necessary.
4
No Attachments
4. Collaborative Economic Development Efforts & Challenges
a) Launch
Staff will be available to answer questions at the meeting, and the governing boards
can discuss issues related to this item as necessary.
No Attachments
b) Arts
The nationwide Arts and Economic Prosperity Survey 5 confirmed that the nonprofit
arts sector of Orange County is an annual $130 million industry that generates $5
million for local government and draws almost two million attendees each year.
Despite this impact and the large number of artists who call Orange County home,
the local arts industry is missing key components needed to grow and sustain a
thriving, authentic arts culture. The Orange County Arts Commission (OCAC) has
recently concluded research to determine these areas of need. By working in
collaboration with town staff, local officials, and area arts organizations, the OCAC
plans to begin work to address these identified challenges, resulting in a healthier
arts industry and an even greater economic impact.
Staff will provide any other information at the meeting, and the governing boards can
discuss issues related to this item as necessary.
No Attachment
c) Infrastructure
The infrastructure item is intended to provide the Boards with an opportunity to raise
questions or initiate a discussion on water and sewer, transportation, or other
infrastructure improvements.
Staff will provide any other information at the meeting, and the governing boards can
discuss issues related to this item as necessary.
No Attachments
5. Affordable Housing Updates
a) Chapel Hill Dashboard
The Town has developed a new Affordable Housing Dashboard, a dynamic,
interactive tool to track progress towards the Town’s affordable housing goals and
5
provide users with information about the Town’s investment in affordable housing
throughout the community. The current Dashboard tool builds on the affordable
housing data reported to the Town Council through our Affordable Housing Quarterly
Report. The Town continues to build the Dashboard to include further affordable
housing information and increase the community’s knowledge and ability to explore
the Town’s affordable housing work.
Staff will provide any other information at the meeting, and the governing boards can
discuss issues related to this item as necessary.
No Attachments
b) Town’s Affordable Housing Bond Referendum
In support of the Chapel Hill 2020 theme of creating a place for everyone, on
February 21, 2018 the Town Council adopted a framework to develop and preserve
affordable housing opportunities in Chapel Hill. Staff also developed annual and five-
year targets for development and preservation of affordable housing. The Council
also reviewed an investment plan that identifies General Obligation (G.O.) bonds as
the most effective and efficient funding source to support the investment plan. The
proposed referendum, for up to $10.0 million of Affordable Housing Bonds, would be
scheduled for November 6, 2018. The amount of the proposed referendum is based,
in part, on the target number of affordable housing units and the average subsidy per
unit. On March 21, the Council is scheduled to consider a preliminary resolution to
pursue a bond referendum in November.
Staff will provide any other information at the meeting, and the governing boards can
discuss issues related to this item as necessary.
No Attachments
c) Town Homestead Road Project
The Town has engaged a design firm to create a concept plan for development of a
Town-owned site located at 2200 Homestead Road site. Town staff has met with
potential community partners and held two public meetings. Town staff is currently
incorporating feedback received to date into a single concept plan for submittal to the
Town’s Community Design Commission in April and the Town Council in June.
Staff will provide any other information at the meeting, and the governing boards can
discuss issues related to this item as necessary.
No Attachments
6
d) Town Plans for Redevelopment of Public Housing Sites
The Town of Chapel Hill owns and manages 336 currently occupied public housing
apartments in 12 communities throughout Town and one in Carrboro, ranging from
two bedroom to 5 bedroom units. The Town is creating a Public Housing Master Plan.
The purpose of the Plan is to guide the Town’s decision making related to the
maintenance, development and redevelopment potential of the Town’s public housing
inventory. The first phase of the plan included an inspection of all properties using
federal standards and an appraisal of all the neighborhoods. The second phase is
currently underway and will provide a detailed structural and physical assessment of
all 336 living units and condition of all buildings. Town staff is scheduled to provide
an update on the Master Plan process in May.
Staff will provide any other information at the meeting, and the governing boards can
discuss issues related to this item as necessary.
No Attachments
e) Manufactured Housing Relocation Opportunities
County and Town of Chapel Hill staff have been engaged in a variety of activities to
respond to the potential displacement of manufactured home park residents. The
Town has been engaged with residents in the Lakeview Park while the County has
been working with residents of the Homestead Park to prepare for potential
displacement.
Discussions with the Towns of Carrboro, Chapel Hill and Hillsborough began before
and have continued since the Board of Commissioners’ approval of the Manufactured
Home Work Group recommendations. Discussions have focused on the
development of a coordinated approach between the jurisdictions and sharing
pertinent information. Below is a timeline of events and activities related to
preparation for potential housing displacements.
• January 2018 – Orange County staff learned of a potential manufactured
home park closure, and Town of Chapel Hill staff shared notice regarding the
potential closure and redevelopment of the Lakeview Mobile Home Park.
• January 16, 2018 – County staff held a meeting of the Manufactured Home
Park Work Group to receive input and comments on a draft Rapid Response
Protocol.
• January 23, 2018 – County staff presented a proposal to use a portion of the
County-owned Millhouse Road property as a potential site for a new
manufactured home park to the Board of Orange County Commissioners. The
Board approved moving forward with completing a full assessment of the
proposed site, including an environmental and engineering study, as well as
initiation of the rezoning process, as applicable.
7
• January 30, 2018 – The approved Manufactured Home Work Group
recommendations, along with a synopsis of the proposed Millhouse Road
project, were presented at the 2018 Assembly of Governments meeting.
Additional input and comments were gathered as to the creation of a
comprehensive and coordinated strategy regarding the Manufactured Home
Park Initiative.
• January 30, 2018 – The Town of Chapel Hill developed a response strategy for
the proposed closure of the Lakeview Mobile Home Park and shared that
information with Orange County staff.
• February 1, 2018 – County staff learned of the proposed displacement of
residents at the Homestead Mobile Park located in an unincorporated part of
the County outside of Chapel Hill. The Homestead Mobile Home Park
includes approximately nine (9) homes that could be affected by the closure.
Staff had a conversation with the Park owner to discuss the situation.
Conversations with the Park owner have continued.
• February 9, 2018 – County staff convened an initial meeting of the Rapid
Response Team to plan for a community meeting with the Homestead Mobile
Home Park residents. The County Manager invited Chapel Hill-Carrboro City
Schools and Orange County Schools to be a part of the Manufactured Home
Park Work Group and the Rapid Response Team.
• February 24, 2018 – A meeting was held with the residents of the Homestead
Mobile Home Park to gather their input and comments, as well as ascertain
their needs given the proposed displacement. Three families met with staff.
County staff continues to conduct due diligence on the Millhouse Road site
and other identified strategies, including identifying cost centers and gathering
applicable pricing information.
• On March 6, 2018, Rehabilitation Specialists in the Housing and Community
Development Department conducted an inspection of three of units at the
Homestead Mobile Home Park. The Specialists determined that none of the
manufactured homes could be moved safely without significant investment.
• On March 7, 2018, graduate interns working in the Housing and Community
Development Department, along with other UNC-Chapel Hill graduate
students, held a “phone-a-thon” to contact the 100 manufactured home park
owners in the County to gather information and identify available vacancies. In
mid-April 2018, an information session will be held with manufactured home
park owners to provide information gathered during the “phone-a-thon.”.
• The County’s Rapid Response Team met on March 13, 2018 to review a draft
proposal of services for residents of the Homestead Mobile Home Park. A
representative from Orange County Schools participated in the meeting to
discuss school assignment issues as students move within the District.
• On March 17, 2018, staff will met again with the residents of Homestead
Mobile Home Park to discuss and evaluate potential options for relocation.
8
• On March 20, staff will propose two options for relocation services and
assistance to the Board of Orange County Commissioners. One option would
assist residents in locating alternative affordable housing in existing multifamily
units dedicated to serving low and very low income individuals and families.
The other options would initiate a contract with Empowerment Inc. to provide
Relocation Coordinator Services including serving as a property manager for
new manufactured housing units.
The Town of Chapel Hill continues to implement the Lakeview Strategy. The Town
has held two meetings with Lakeview residents, and is in the process of development
housing options for Council consideration based on the input from residents.
Additionally, the Planning Department is conducting an analysis of publicly owned
land parcels. An update will be provided to the Town Council in March.
Staff will provide any other information at the meeting, and the governing boards can
discuss issues related to this item as necessary.
No Attachments
f) Green Tract
The Greene Tract is a 164 acre parcel of which 104 acres is jointly owned by Orange
County, Chapel Hill, and Carrboro. The remaining sixty (60) acres is owned by
Orange County and has been designated as the Headwaters Preserve.
In late 2016, the owners of the jointly owned portion of the Greene Tract agreed to
have the Town Mayors and Board Chair consider different preservation and
development options for the property. This discussion resulted in three alternatives
that illustrate high, medium, and low development intensities. All of the alternatives
include an elementary school site, a site for a future park, the preservation of
significant environmental and cultural areas, and a preliminary road network and
infrastructure design. The three alternatives also consider the project area’s current
environmental conditions, elements of the 2002 Joint Governments Resolution, the
Rogers Road Task Force report, the Mapping Our Community’s Future report, and
previous land use discussions. These three alternatives are contained in Attachment
5f-3.
In addition to the high, medium, and low development intensity scenarios, the Mayors
and Chair requested an examination of the entire Greene Tract, including the
Headwaters Preserve, in an effort to preserve the most environmentally sensitive
areas and to develop the most appropriate areas of the entire 164 acre Tract. As a
result, staff amended the proposed conceptual plan, reconfiguring the Headwaters
Preserve and the jointly owned areas. This reconfiguration maintains the same total
acreage for each of the areas but aligns them differently. The reconfigured tracts
were drafted with environmental staff from the Town of Chapel Hill, the Town of
Carrboro, and Orange County in order to create new parcels which endeavored to
protect environmental features and habitats located on site. The proposed
9
reconfigured Headwaters Preserve area alternatives are also contained in Attachment
5f-3.
Attachment 5f-4 includes land use and density outcomes for the different alternatives.
Attachment 5f-5 includes potential affordable housing outputs based on different
affordable housing proportions.
The Board of Orange County Commissioners had a preliminary discussion about
planning for the Greene Tract on February 20. Based on this discussion, the Board
of Commissioners asked staff to communicate the following preferences with the
other owners of the property:
• Modify the headwaters preserve configuration, with the goal of creating, or
protecting, the natural north-south corridor, with the exact boundaries to be
determined;
• Begin with the highest developable areas;
• Seek input from the Towns of Chapel Hill and Carrboro with the goal of
communicating the Town’s preferences by May 1;
• Set up the walking tour as soon as possible; and
• Host a community meeting, presenting that which has been learned, between
the walking tour and May 1.
The Board of Commissioners expressed interest in continuing the dialogue with Town
elected officials on a timeline that could allow for final directions to staff prior to the
summer break. A guided walking tour of the property is scheduled for March 23 with
two tours, one beginning at 9:00 and the other beginning at 2:00.
Staff will provide any other information at the meeting, and the governing boards can
discuss issues related to this item as necessary.
Attachment 5f-1 – Conceptual Plan Overview
Attachment 5f-2 – Environmental and Cultural Features Map
Attachment 5f-3 – Land Use Conceptual Plans
Attachment 5f-4 – Land Use and Density Outcomes
Attachment 5f-5 – Affordable Housing Potential
g) OWASA Policy
The Orange Water & Sewer Authority (OWASA) is governed by a nine member Board
of Directors. The Chapel Hill Town Council appoints five members, the Carrboro
Board of Aldermen appoints two members, and the Orange County Board of
Commissioners appoints two Board Members. The OWASA Board adopts the annual
budget; sets rates, fees and charges; approves bond issues to fund capital projects;
makes policy decisions; and appoints the Executive Director, General Counsel and
independent auditor.
The fees associated with connecting to OWASA infrastructure have been cited as
one of the barriers to constructing low cost, affordable housing. This item is intended
to serve as a point of discussion for how the appointing Boards could work with their
10
appointees to the OWASA Board of Directors to potentially reduce the cost of the
connections for affordable housing developments.
Staff will provide any other information at the meeting, and the governing boards can
discuss issues related to this item as necessary.
No Attachments
SOCIAL JUSTICE IMPACT: There is no direct Social Justice Goal impact associated with the
discussion of these topics.
FINANCIAL IMPACT: There is no direct financial impact associated with the discussion of
these topics. There are no action items requiring formal decisions.
RECOMMENDATION(S): The Managers recommend the governing boards discuss the topics
listed and provide appropriate direction to the respective staffs.
11
1
Date: March 8, 2018
To: The Honorable Members of the Orange County Board of Commissioners
Through: Donna Baker, Clerk to the Board
From: Indira Everett, District Manager, Duke Energy
Valencia Roner, Program Manager, Duke Energy
Subject: Duke Energy Neighborhood Energy Saver Program
Executive Summary
Duke Energy is bringing its Neighborhood Energy Saver (NES) Program to Orange County in
April to service a neighborhood in Chapel Hill identified as having a significant need for home
energy efficiency. The chosen neighborhood consists of about 1,300 Duke Energy customers.
The goal is to service a minimum of 70% of the neighborhood.
A kick-off event has been scheduled for Tuesday, April 10, 2018 at the Hargraves
Community Center, 216 N Roberson St, Chapel Hill, NC 27516 from 6:30 to 8 pm. Free
food will be served and childcare shall be provided at no cost. Customers identified within the
designated boundaries shall be notified by mail through a letter and postcard as well as by
program energy efficient technicians days leading up to the event.
The Duke Energy Neighborhood Energy Saver Program offers free walkthrough energy
assessments designed to help customers learn how their homes use energy and how can
their monthly electric bills can be lowered. This service is available to customers living in
select, census-defined communities identified by Duke Energy in coordination with such
community stakeholders as EmPOWERment, Inc.
As part of this special program, customers in select neighborhoods may receive up to 16
energy saving products installed at no cost:
• Energy-efficient light bulbs
• Water-saving shower heads and faucet aerators
• Air Conditioning/heating system filters (a year’s supply)
• Other energy-efficient upgrades available for your home
Customers’ participation in the NES program is strictly voluntary.
Eligibility
This service is available to residential customers living in select, census-defined
communities identified by Duke Energy. All contact with eligible customers shall be
initiated by Duke Energy. Customers will receive a postcard and letter notifying them of
the program’s local neighborhood kick-off event. Just before and immediately following the
event, Energy Efficiency Technicians will leave a notice on the doors of Duke Energy
ORANGE COUNTY | NORTH CAROLINA
12
2
residential customers informing them when we are scheduled to be on their street for
program service delivery. Appointment arrangements are also available.
For additional information, visit http://duke-energy.com/nes.
Background
The Neighborhood Energy Saver Program (NES) is coming to the community Chapel Hill and
Orange County. Eligibility is determined in coordination of information from the U.S. Census as
well as other data used to identify key neighborhoods recognized as having residents who could
benefit from such a service.
NES has served over 120,000 customers since 2009. .
Financial Impact
There is no financial impact to Orange County, the Town of Chapel Hill or their residents and
Duke Energy Customers.
Attachments
Please see the accompanying PowerPoint presentation.
13
Neighborhood Energy Saver Program
March 8, 2018
14
Neighborhood Energy Saver Program
An energy efficiency program targeting DEC’s
income-qualifying customers
Delivered by neighborhood segments
Provides each resident:
1.Home energy assessment
2.Installation of several energy conservation measures
(ECMs)
3.Energy education that will enable the residents to
make behavioral changes to reduce and control
energy usage
15
NES Target Market –Eligibility
Eligible neighborhoods are those defined segments
of Duke Energy customers where approximately
50% of the households have incomes equal to or
less than 200% of the federal poverty level*.
*Federal Poverty Income Guidelines issued by the US DOE
16
NES Energy Conservation Measures
LED/Energy Efficient Bulbs
(15)
Water Heater Wrap* &
Insulation for Water Pipes
Water heater temperature
check & adjustment
Low Flow Faucet Aerator
(2)
Low Flow Showerhead (2)
Wall Plate Thermometer
AC Winterization Kit (3)
A year’s supply of HVAC
filters
Change Filter Calendar
Air Infiltration Reduction
Measures
* Electric water heaters only
17
Neighborhood Kick-Off Event
Approximate
Neighborhood
Size: 1,300
Tuesday, April 10th
6:30 pm – 8:00 pm
Hargraves Community Center
216 N Roberson St, Chapel Hill,
NC 27516
For More Information:
855.231.5273
18
NES
Chapel Hill Neighborhood Collaborators
19
NES Kick-Off Events
Residents receive:
•FREE catered meal
•Demonstration on the FREE
energy-savings products they’ll
receive when participating
•Four to chances to WIN a $25
gift card
•FREE Event Childcare
20
Crew Installs the Energy Measures and
Explains Energy Savings
21
Small Business Energy Saver Program
SBES offers turn-key energy efficiency upgrades
with significant discounts exclusively for small
business customers.
The program offers:
A free, no obligation energy assessment
Specific energy-saving recommendations for
small businesses
Complete, upfront coverage for up to 80
percent of all materials and installation costs
Convenient installation scheduled around the
small business’s needs
Interest-free financing available!
855.776.4723
22
Eligibility
Non-residential customer accounts with average annual demand of 100 kW or less
Participation per business entity limited to 5 premises per year
Measures
Lighting (T5 & T8 fluorescents, LEDs: interior & exterior)
Refrigeration (improvements for small groceries & convenience stores)
Incentive
Up to 80%: Based on est. kWh savings vs. project cost
Program Administrator:
http://www.duke-energy.com/north-carolina-business/energy-
management/small-business-energy-saver.asp
SBES Program Details 23
Neighborhood Energy Saver Program
For more information:
http://duke-energy.com/nes
Or Call
855.231.5273
24
Neighborhood Energy Saver Program
Thank You
25
06/02/97 1
26
06/02/97 2
MIXED‐USE DEVELOPMENT
Location: 3000 Eubanks Rd., between MLK Jr. Blvd. and Millhouse Road
Description: Phase 1A ‐Demo, clearing and grading, erosion control
Phase 1B ‐Buildings 1‐11, including 400 dwelling units and 8,844 s.f. of commercial
FA.
Approvals: Special Use Permit approved in 2015; Zoning Compliance Permit
approved for Phase 1A and 1B in 2016.
Status: Building construction is on‐going and the first units are anticipated to open
in late summer/early fall of 2018.
2
27
06/02/97 3
DEVELOPMENT AGREEMENT COMPLIANCE PERMIT
Location: South of Brandon Road and east of Fordham Blvd.
Description: Development of 215 apartment units in a 4‐story building, in
accordance with the Glen Lennox Development Agreement. An internally wrapped
parking deck will be provided to serve the apartments and future office building.
The project includes construction of a new road, Glen Lennox Drive, which will
connect Fordham Boulevard with Maxwell Road, and dedicated left turn lanes with
signalization will be provided on south‐bound Fordham Boulevard.
Status: The permit was approved in September and construction is anticipated to
begin in spring of 2018. Submittal of a Development Agreement Compliance Permit
to permit an office building directly adjacent to the apartment building is
anticipated inspring of 2018.
28
06/02/97 4
SPECIAL USE PERMIT
Location: 125 Old Durham Road
Description: 130,000 sq. ft. floor area; 750 parking spaces; existing zoning
Community Commercial and Neighborhood Commercial‐Conditional. Access to the
site via Old Durham Road and ingress only via 15‐501 Service Road.
Status: Council approved Special Use Permit in October 2017. Town will be issuing
permit shortly to allow demolition and rough grading. Site work is currently
expected to begin in late summer of 2018, with construction on the store to begin
in the fall of 2018, and completion expected in the spring of 2020.
29
06/02/97 5
SPECIAL USE PERMIT
Location: 100 & 600 Eastowne Drive
Description: Applicant request to demolish four existing office buildings and
construct one medical office building totaling 150,000 square feet with structured
parking.
Status: Applicant presented concept plan to Town Council in January 2018.
Applicant submitted Special Use Permit application in March 2018. Possible
decision by Town Council in June 2018.
30
06/02/97 6
FORMDISTRICT PERMIT
Location: 1300 Fordham Blvd.
Description: The existing Days Inn Hotel is proposed to be demolished and replaced
by one building, split into two sections by a pedestrian walkway, pass‐through, and
driveway. The southern portion of building, closer to S. Elliott Road is proposed to
be six stories.294,593 square feet,273 dwelling units. The property is zoned
Walkable Mixed‐Use‐7 (WX‐7).
Status: The Community Design Commission issued aCertificate of Appropriateness
in October2017,and the Town Manager issued a Form District Permit in December
2017. The Town is working with applicant on public‐private partnership to construct
stormwater storage and park amenity. Construction is expected to begin in March
2018.
31
06/02/97 7
FORMDISTRICT PERMIT
Location: 1736 Fordham Blvd. (6.5 acre “bow tie” site, including former Crown
Honda/Volvo dealership).
Description: Approved project thatincludes two buildings with 328 dwelling units.
The zoning is Walkable Mixed Use–5 and ‐7 (WX‐5 and 7). The project includes the
construction of a new street connecting the Fordham Blvd. service road and Legion
Rd, streetscape improvements on all three streets, and stormwater management
and treatment features.
Status: Town Manager issued a Form District Permit in October 2017. Construction
is expected to begin in March2018.
32
06/02/97 8
CERTIFICATEOF APPROPRIATENESS
Location: 1740 Fordham Blvd. (site of Hong Kong Buffet and Quality Inn)
Description: A proposal to build a 97‐room Tru (Hilton) Hotel at the Hong Kong
Buffet site in a multi-phase development. Additional phases are anticipated to
include a 100‐room hotel and a 260‐unit multi‐family development. The property is
zoned WX‐5 and WX‐7. The property is adjacent to the Hillstone development.
Status: The application was presented to the Community Design Commission in
February 2018. A Form District Permit application has not yet been submitted.
33
Greene Tract Conceptual Plans
Information on Factors Considered During Creation Process
The staff-created conceptual plans for the Greene Tract are a result of several months
of iterations and input from a variety of staff from the three jurisdictions. While planning
staffs were the lead on creating the conceptual plans, input was also sought and
incorporated from environmental and stormwater staffs.
The following information addresses some anticipated questions regarding why the
conceptual plans are presented as they are.
Environmental Features
Although the Greene Tract lies entirely within the planning jurisdiction of the Town of
Chapel Hill, 104 acres of the Greene Tract are co-owned by Orange County and the
Towns of Chapel Hill and Carrboro while 60 acres are owned solely by Orange County.
Planning staffs chose to apply the most stringent development regulation of the
three jurisdictions when determining stream and wetland buffers and preservation of
other environmental features such as forest types. For example, if one jurisdiction
requires a 50-foot stream buffer and another requires a 65-foot stream buffer, a 65-foot
stream buffer was used as the stream buffer on the conceptual plan.
The Upland Hardwood Forest areas were slated for preservation as at least one
jurisdiction would normally request/require preservation of these types of forests if a
development proposal were made.
Road Configuration
All previous planning efforts of the Greene Tract/Rogers Road area have strongly stated
that Purefoy Drive and/or Lizzie Lane should not be the only access to the Greene
Tract. Connections to the south, north, and/or east must be made. The early iterations
of maps (not included in materials) sought to avoid a stream crossing and connected to
Merin Road, near the southeast corner of the Greene Tract, by traversing the area
between two stream buffer areas. However, this configuration was revised as
environmental and stormwater staff members stated that a stream crossing would be
preferable to impacting the Upland Hardwood Forest areas while also bisecting
preserve connectivity.
Staffs have spoken with Norfolk Southern railroad representatives regarding a crossing
on the east side of the Greene Tract. While Norfolk Southern is amendable to reviewing
any requests, the railroad generally requires closure of at least one existing
crossing for each new crossing. Staff has not been able to identify existing
crossing(s) that could be proposed for closure in order to make a connection from
the Greene Tract to Weaver Dairy Road Extension to the east.
34
A connection to the north (to Eubanks Road) might be possible through an edge
corridor of the “Neville Tract” if an alternative site can be found to conduct the Solid
Waste activities occurring on the Neville Tract.
Reconfigured Preserve Area
Quarterly “Managers, Mayors, Chair” (MMC) meetings have been taking place to
provide the opportunity for staffs and the Town/County managers, Town mayors, and
County chair to meet and receive updates/guidance on Rogers Road sewer system and
planning issue status, including progress on Greene Tract planning. Staff received
direction to consider the reconfiguration of the County-owned 60-acre portion of the
Greene Tract to encumber the most preservation-worthy lands. Staffs conducted
the analysis and the conceptual plans incorporate a reconfigured County-owned
preserve area.
If a reconfigured preserve area is desired, future work would include re-platting the
parcels to reflect different parcel boundaries and ownership from those that currently
exist.
35
[[(>
[[(>
[[(>
[[(ñ
[[(ñ
[[(ñ
[[(ñ
[[(ñ
[[(ñ
[[(ú[[(ú
[[(ú
[[(ú
[[(ú
[[(ú
[[(ú
LIZZIE LN
MERI
N
R
D
PH
O
E
N
I
X
D
R
SANDBERG
LN
PUREFOY DR
¯0 200Feet
1 in = 400 feet
Access Trail Easement
Wetlands
Greene Tract
[[(ú Foot Bridge
[[(ñ Mature Hardwood
[[(ñ Significant Tree
[[(>Historic Site
Joint Owned Property (104 ac.)
County Owned Property (60 ac.)
Proposed Headwaters Preserve (County Owned)
Proposed Joint Owned Property (104 ac.)
Historic Road Bed
Mixed Hardwood/Pine Forest
Upland Hardwood Forest
Parcels
Ephemeral Stream
Intermittent Stream
Perennial Stream
Unknown Stream
Orange County and Chapel Hill
Buffers/Wetlands
Greene Tract - Environmental & Cultural Features
Cultural and Envrionmental Features DataSource: Town of Chapel Hill StormwaterManagement (Oct. 2017)
36
Land Use Categories
Proposed Joint Owned Preserve: Includes areas of existing wetlands and streams located on the Greene Tract. Wetland
and stream information is based on information collected from Town of Chapel Hill, Town of Carrboro, and Orange County
staff. Buffer standards were determined based on a review of the Towns’ and County’s standards and utilizing the most
restrictive. Additional analysis and delineation will be required moving forward. These areas would not be developed, but
will remain as natural preserve areas in the future.
Additional Preserve: Includes areas for future preservation and upland hardwood forest which are not contained in the
required preserve areas. In addition to the acreage proposed to be preserved, approximately 10 – 20% of the acreage pro-
posed for development will be utilized for open space to provide areas of on-site preserve and connections to other areas
of offsite preserve.
Proposed Headwaters Preserve (County Owned): Includes the original 60 acres designated for preservation by the Towns
and County.
Elementary School Site: Includes acreages allocated for a future elementary school site. The proposed school site has been
relocated to the southern portion of the site due to environmental constraints and is not included as part of the original 18
acres designated for development in the Rogers Road Task Force Report. Chapel Hill—Carrboro City Schools staff has re-
viewed the proposed alternatives and provides support for the proposed location.
Recreational Facility Site: The proposed recreational facility site is also located on the southern portion of the Greene Tract
in order to provide access to the future elementary school students. Chapel Hill—Carrboro City Schools staff provides sup-
port for the proposed recreational facility site, which could also support community usage.
Development: Includes areas proposed for development in the short term. The location for this category was determined
based on site elevations and proximity to existing infrastructure. In addition, the proposed location for development in-
cludes the original 18 acres identified for affordable housing in the Rogers Road Task Force Report. Includes possible loca-
tions for on-site stormwater facilities.
Road: The preliminary roadway design was based on existing environmental concerns and elevations contained on site. The
proposed alternatives recognize a need for additional roadway connections in the future.
Land Banking: Includes areas without environmental concerns and access to infrastructure which may provide an oppor-
tunity for future development. These areas will remain undeveloped in the short term, but may be evaluated for develop-
ment (i.e. residential, commercial, health services, and/or park/recreational facility) in the long term (5-10 years) depend-
ing on the needs of the community and planning partners at that time.
Greene Tract Land Use Conceptual Plan
Additional consideration will be required for several elements of
the Greene Tract:
Roadway design
Site infrastructure (i.e. water, sewer, fiber)
Open space, recreational facility, and tree canopy preserva-
tion
Environmental (i.e. wetlands, streams, buffers, stormwater
regulations)
Low Impact Development
Cultural and historical features
Density, land use, and zoning regulations
Transit
Alternatives must provide three levels of
development and incorporate:
School site
Recreational facility site
Park space
Natural preservation areas
Development
Road network and infrastructure
Environmental buffers
Cultural areas of significance
Three alternatives were drafted which included a project area of approximately 164 acres of land
divided into proposed land uses based on the project area’s environmental conditions, elements
of the 2002 Chapel Hill Resolution, Rogers Road Task Force report, Mapping Our Community’s
Future report, and local government leaders’ objectives for the Greene Tract.
Further evaluation will impact and alter the proposed alternatives in the future
Site plan review process will address additional land use issues and help shape the plan for the Greene Tract
37
4.7 ac
60 ac
46.2 ac
10.8 ac
20.8 ac 4.3 ac
1.2 ac
1.9 ac
0.2 ac
2.7 ac
6 ac
5.7 acPUREFOY DR
LIZZIE LN
MERI
N
R
D
PH
O
E
N
I
X
D
R
SANDBERG
LN
BILLABON G LN
Additional Preserve
Headwaters Preserve (CountyOwned)
Proposed Joint OwnedPreserve
Development
Elementary School Site
Road
Land Banking
Approximate Land AreaNeeded for StormwaterManagement
Ephemeral Stream
Intermittent Stream
Perennial Stream
Unknown Stream
Parcels
Wetlands
Greene Tract Land Use Conceptual Plan - Alternative 1 (High)
¯0 200Feet
1 in = 400 feet
(Headwaters Existing)
38
SA
N
D
B
E
R
G
L
N
MERI
N
R
D
LIZZIE LN
PUREFOY DR
4.7 ac
60 ac
5.7 ac
20.8 ac 4.3 ac
10.8 ac
36.6 ac
17.4 ac
4.2 ac
Additional Preserve
Headwaters Preserve (CountyOwned)
Proposed Joint Owned Preserve
Development
Elementary School Site
Road
Land Banking
Approximate Land Area Neededfor Stormwater Management
Additional Wetland Buffer(150')(recommended byenvironmental staff)
Ephemeral Stream
Intermittent Stream
Perennial Stream
Unknown Stream
Parcels
Wetlands
Greene Tract Land Use Conceptual Plan - Alternative 2 (Medium)
¯0 200Feet
1 in = 400 feet
(Headwaters Existing)
39
SA
N
D
B
E
R
G
L
N
MERI
N
R
D
PUREFOY DR
LIZZIE LN
4.7 ac
60 ac
20.8 ac 4.3 ac
10.8 ac
5.7 ac26.9 ac 6.1 ac 18.8 ac
3.6 ac
2.8 ac
¯0 200Feet
1 in = 400 feet
Additional Preserve
Headwaters Preserve(County Owned)
Proposed Joint OwnedPreserve
Development
Elementary School Site
Road
Land Banking
Approximate Land AreaNeeded for StormwaterManagement
Additional Wetland Buffer(150')(recommended byenvironmental staff)
Ephemeral Stream
Intermittent Stream
Perennial Stream
Unknown Stream
Parcels
Wetlands
Greene Tract Land Use Conceptual Plan - Alternative 3 (Low)(Headwaters Existing)
40
LIZZIE LN
MERI
N
R
D
PH
O
E
N
I
X
D
R
SANDBERG
LN
PUREFOY DR
·Orange County Planning and InspectionsBrian Carson (11/8/2017)
0 200Feet
1 in = 400 feet
Headwaters Preserve (County Owned)
Joint Owned Property (104 ac.)
Proposed Joint Owned Property (104 ac.)
Proposed Headwaters Preserve (County Owned)
Parcels
Possible Modifications to Headwaters Preserve Area41
21 ac.
60 ac.
LIZZIE LN
MERI
N
R
D
PH
O
E
N
I
X
D
R
SANDBERG
LN
PUREFOY DR
·Orange County Planning and InspectionsBrian Carson (11/30/2017)
0 200Feet
1 in = 400 feet
Proposed Headwaters Preserve (County Owned)
Proposed Joint Owned Property
Proposed Joint Ownership Preserve
Parcels
Total Preserve AreaPossible Modifications to Headwaters Preserve Area 42
18 ac
4.7 ac60 ac
2.9 ac
10.8 ac
5.7 ac
20.8 ac
41.1 ac
LIZZIE LN
MERI
N
R
D
PH
O
E
N
I
X
D
R
SANDBERG
LN
PUREFOY DR
·Orange County Planning and InspectionsBrian Carson (1/11/2018)
0 200Feet
1 in = 400 feet
Proposed HeadwatersPreserve (County Owned)
Proposed Joint OwnedPreserve
Development
Elementary School Site
Recreational Facility
Road
Land Banking
Approximate Land AreaNeeded for StormwaterManagement
Ephemeral Stream
Intermittent Stream
Perennial Stream
Unknown Stream
Parcels
Wetlands
Greene Tract Land Use Conceptual Plan - Alternative 1 (High)(Headwaters Modified)
43
60 ac 11.1 ac
4.7 ac
5.5 ac
1.4 ac
4 ac
2.5 ac10.8 ac
20.8 ac
5.7 ac
35.9 ac
1.2 ac
0.4 ac
LIZZIE LN
MERI
N
R
D
PH
O
E
N
I
X
D
R
SANDBERG
LN
PUREFOY DR
·Orange County Planning and InspectionsBrian Carson (1/11/2018)
0 200Feet
1 in = 400 feet
Additional Preserve
Proposed Headwaters Preserve(County Owned)
Proposed Joint Owned Preserve
Development
Elementary School Site
Recreational Facility
Road
Land Banking
Approximate Land Area Neededfor Stormwater Management
Additional Wetland Buffer(150')(recommended byenvironmental staff)
Ephemeral Stream
Intermittent Stream
Perennial Stream
Unknown Stream
Parcels
Wetlands
Greene Tract Land Use Conceptual Plan - Alternative 2 (Medium)(Headwaters Modified)
44
60 ac
22.5 ac
2.5 ac10.8 ac
20.8 ac3.6 ac
12.9 ac
24.6 ac
5.7 ac
0.4 ac
0.2 ac
LIZZIE LN
MERI
N
R
D
PH
O
E
N
I
X
D
R
SANDBERG
LN
PUREFOY DR
·Orange County Planning and InspectionsBrian Carson (1/11/2018)
0 200Feet
1 in = 400 feet
Additional Preserve
Proposed Headwaters Preserve(County Owned)
Proposed Joint Owned Preserve
Development
Elementary School Site
Recreational Facility
Road
Land Banking
Approximate Land Area Neededfor Stormwater Management
Additional Wetland Buffer(150')(recommended byenvironmental staff)
Ephemeral Stream
Intermittent Stream
Perennial Stream
Unknown Stream
Parcels
Wetlands
Greene Tract Land Use Conceptual Plan - Alternative 3 (Low)(Headwaters Modified)
45
Pros
More acreage designated for development in the
short term
Provides greatest opportunity for highest number of
affordable housing and market rate housing to help
meet housing demand in the urban area
More acreage available for development to offset
infrastructure costs
Allows for double road frontage to offset road and
infrastructure costs
More development and residential units to support
transit
Cons
Additional stormwater treatment will be needed due to greater
amount of potential development and increased impervious surfaces
Protects the least amount of mixed hardwood/pine forest from short
term development
Only allows for the required 80 foot wetland buffer
Depending on density, may have greater traffic impacts to Purefoy
Drive and Merin Road
Pros
Proposes 150 foot wetland buffer adjacent to wildlife
corridor
Allows for additional areas of preserve
Provides opportunity for a mid-range of affordable
housing and market rate housing to meet the general
housing demand
More acreage available for development to offset in-
frastructure costs
Allows for double road frontage to offset road and
infrastructure costs
Cons
Less acreage is available for development in the short term or to off-
set infrastructure costs
Less opportunity for affordable housing and market rate housing to
help meet housing demand in the urban area
Pros
Proposes 150 foot wetland buffer adjacent to
wildlife corridor
Allows for additional areas of preserve
Strives to protect the existing wildlife corridor and
provide for landscape connectivity
Protects the greatest amount of Mixed Hardwood/
Pine Forest from short term development
Depending on density, may have less traffic impacts to
Purefoy Drive and Merin Road
Cons
Less acreage is available for development in the short term
Provides lowest opportunity for affordable housing and market rate
housing to help meet housing demand in the urban area
Less acreage available for development to offset infrastructure costs
Does not allow for double road frontage to offset road and infra-
structure costs
Less development and residential units to support transit
Alternative 1
Illustrates a high development option with
the greatest amount of acreage designated
for development compared to the other
alternatives.
Alternative 2
Illustrates a moderate development option
by shifting acreage away from the develop-
ment land use with the transfer of acreage
to additional preserve and land banking. Al-
so allows for a 150 buffer along a portion of
the existing wetlands located onsite.
Alternative 3
Illustrates a low development option by
shifting additional acreage away from the
development land use category to the addi-
tional preserve and land banking.
Preserve Development Land Banking
20.8 ac. 20% 78.5 ac. 75.5% 4.7 ac. 4.5%
Based
on
59.1
acres
Low Density
(4-6 units/acre)
Medium Density
(6-10 units/acre)
High Density
(10-20 units/acre)
236 - 354 354 - 591 591 - 1182
Preserve Development Land Banking
23.8 ac. 22.9% 66 ac. 63.4% 14.2 ac. 13.7%
Based
on
47
acres
Low Density
(4-6 units/acre)
Medium Density
(6-10 units/acre)
High Density
(10-20 units/acre)
188 - 282 282 - 470 470 - 940
Preserve Development Land Banking
34.3 ac. 33% 43.6 ac. 41.9% 26.1 ac. 25.1%
Based
on
24.6
acres
Low Density
(4-6 units/acre)
Medium Density
(6-10 units/acre)
High Density
(10-20 units/acre)
98 - 147 147 - 246 246 - 492
46
Alternative 1 (High) – Potential Number of Residential Units
Based on
59.1 Acres
Low Density
4 - 6 units/acre
Medium Density
6 - 10 units/acre
High Density
10 - 20 units/acre
236 - 354 units 354 - 591 units 591 - 1182 units
Potential Number of Affordable Housing Units
15% 35 – 53 units 53 – 88 units 88 – 177 units
20% 47 – 70 units 70 – 118 units 118 – 236 units
35% 82 – 123 units 123 – 206 units 206 – 413 units
Alternative 2 (Medium) – Potential Number of Residential Units
Based on
47 Acres
Low Density
4 - 6 units/acre
Medium Density
6 - 10 units/acre
High Density
10 - 20 units/acre
188 - 282 units 282 - 470 units 470 - 940 units
Potential Number of Affordable Housing Units
15% 28 – 42 units 42 – 70 units 70 – 141 units
20% 37 – 56 units 56 – 94 units 94 – 188 units
35% 65 – 98 units 98 – 164 units 164 – 329 units
Alternative 3 (Low) – Potential Number of Residential Units
Based on
24.6 Acres
Low Density
4 - 6 units/acre
Medium Density
6 - 10 units/acre
High Density
10 - 20 units/acre
98 - 147 units 147 - 246 units 246 - 492 units
Potential Number of Affordable Housing Units
15% 14 – 22 units 22 – 36 units 36 – 73 units
20% 19 – 29 units 29 – 49 units 49 – 98 units
35% 34 – 51 units 51 – 86 units 86 – 172 units
Affordable Housing Potential
47