Minutes 1 Orange County Planning Board 2 December 18, 2017 3 Regular Meeting 4 5
6 MEMBERS PRESENT: Lydia Wegman (Chair), At-Large Chapel Hill Township Representative; Tony Blake (Vice-Chair), 7
Bingham Township Representative; Patricia Roberts, Cheeks Township Representative; Paul Guthrie, At-Large 8
Chapel Hill Township; Kim Piracci, At-Large; Township; Alexander Gregory, Chapel Hill Township Representative; 9
David Blankfard, Hillsborough Township Representative; Randy Marshall, At-Large; Adam Beeman, Cedar Grove 10
Township; Hunter Spitzer, At-Large; 11 12 MEMBERS ABSENT: Buddy Hartley, Little River Township Representative; Laura Nicholson, Eno Township 13
Representative; 14
15 STAFF PRESENT: Craig Benedict, Planning Director; Michael Harvey, Current Planning Supervisor; Meredith Kern, 16
Administrative Assistant; 17
18 OTHERS PRESENT: Cheryl Sadgrove, Minutes Preparer; Jim Parker, Summit Engineering; Ariel Gamboa, Summit 19
Engineering; Ed Sirgany, Summit Engineering; 20
21 AGENDA ITEM 1: CALL TO ORDER AND ROLL CALL 22 23
Lydia Wegman called the meeting to order at 7:02 p.m. and noted new members were present. 24
25
Adam Beeman said he moved here in 2008 and lives in Cedar Grove. He is interested in making sure the county 26
moves forward in a nice, controlled manner rather than what he experienced up north. 27
28
Hunter Spitzer said he is a sophomore at UNC. He has lived in Hillsborough all his life, is interested in planning and 29
wanted to get involved. 30
31 AGENDA ITEM 2: INFORMATIONAL ITEMS 32
a. a) Planning Calendar for December and January 33
• January 10 – Planning Board Meeting 34
• January 23 – BOCC public hearing on this matter 35
• January 26 – BOCC retreat. Planning Board members are not required to attend. 36
37 AGENDA ITEM 3: APPROVAL OF MINUTES 38 November 1, 2017 39
40 MOTION by Paul Guthrie to approve the November 1, 2017, Regular Meeting Minutes. Seconded by Tony Blake. 41 VOTE: Unanimous 42 43 AGENDA ITEM 4. CONSIDERATION OF ADDITIONS TO AGENDA 44
No additions to the agenda. 45 46 AGENDA ITEM 5: PUBLIC CHARGE 47 48
Introduction to the Public Charge 49
The Board of County Commissioners, under the authority of North Carolina General Statute, 50
appoints the Orange County Planning Board (OCPB) to uphold the written land development laws 51
of the County. The general purpose of OCPB is to guide and accomplish coordinated and 52
harmonious development. OCPB shall do so in a manner, which considers the present and future 53
needs of its citizens and businesses through efficient and responsive process that contributes to 54
and promotes the health, safety, and welfare of the overall County. The OCPB will make every 55
Approved 1/10/2018
effort to uphold a vision of responsive governance and quality public services during our 56
deliberations, decisions, and recommendations. 57
58
59 Public Charge 60
The Planning Board pledges to the citizens of Orange County its respect. The Board asks its 61
citizens to conduct themselves in a respectful, courteous manner, both with the Board and with 62
fellow citizens. At any time, should any member of the Board or any citizen fail to observe this 63
public charge, the Chair will ask the offending member to leave the meeting until that individual 64
regains personal control. Should decorum fail to be restored, the Chair will recess the meeting until 65
such time that a genuine commitment to this public charge is observed. 66
67
Lydia Wegman read the public charge aloud. 68
69 AGENDA ITEM 6: CHAIR COMMENTS 70
There were no comments. 71
72 AGENDA ITEM 7: MASTER PLAN DEVELOPMENT APPLICATION – SETTLER’S POINT - To review comments made at the 73
November 14 quarterly public hearing, proposed revisions to conditions as a result of comments, and to make a 74
recommendation on the proposed revisions concerning an application for an MPD-CZ (Master Plan Development 75
Conditional Zoning). The proposed project encompasses approximately 195 acres in the Hillsborough Economic 76
Development District (EDD) south of Interstate 40 on both sides of Old Highway 86. The public hearing for this item 77
has been extended until January 23, 2018. Additional review of remaining aspects of the application and an 78
additional recommendation by the Planning Board is scheduled for the January 10, 2018, Planning Board meeting. 79
Presenter: Michael Harvey, Current Planning Supervisor 80 81
Michael Harvey directed the board to the abstract on Page 11. He reviewed that this item was heard at the November 13, 82
2017, quarterly public hearing. It was referred back to the Planning Board for additional review because there were 83
modifications to several conditions and there was additional information on the transportation impact analysis (TIA). It is not 84
staff’s intention to ask the Planning Board to make a final vote this evening. Staff is asking for votes on direction. The Planning 85
Board is not asked to provide a final decision at this meeting because additional discussion is expected on the Major 86
Transportation Corridor (MTC) buffer in January. Staff is continuing to work with the applicant to address the comments made 87
at the public hearing. He noted that the applicant is represented here this evening. 88
89
Michael Harvey reviewed that the transportation analysis addendum is located on Page 20. Staff comments begin on page 41. 90
The summary of major questions/responses from the November public hearing starts on Page 62. General information about 91
the Conditional Zoning District starts on Page 77. An excerpt of the October Planning Board minutes begins on Page 80. The 92
November public hearing minutes start on Page 101. The revised conditions of approval start on Page 123. 93
94
Michael Harvey said he planned to walk the board through the revised conditions. 95
96
Kim Piracci asked for an explanation of the MTC buffer. Michael Harvey answered it’s a 100-foot buffer for all nonresidential 97
development along major highways, so it applies along Interstate 40. A 50 percent break in the buffer is allowed but it is to be 98
otherwise undisturbed. 99
100
Lydia Wegman requested that any images that would help explain the buffer be displayed. Michael Harvey shared an image 101
provided by the applicant. 102 103
Paul Guthrie asked if the interstate adjacent to this property has the standard 300-foot right of way and does the North 104
Carolina Department of Transportation (DOT) have control of it. Michael Harvey answered that to his knowledge it is under 105
control of DOT and it is 300 feet wide. The buffer is obviously wider in areas that have off ramps. And it’s in control of the state 106
through the federal government. 107 108
Michael Harvey showed an image provided by the applicant that indicates where the100-foot buffer is to be located. He 109
Approved 1/10/2018
reviewed that the applicant is proposing no breaks in the buffer for District 1. He noted that District 3 had been removed from 110
the proposal completely. In District 2, the applicant is allowed to create visual breaks in the MTC buffer. The developers plan 111
to stick to the 50 percent breaks. The image indicated where the intermittent breaks would be located. 112
113
Patricia Roberts asked whether 50 percent breaks is an Orange County law. Michael Harvey answered yes. 114
115
Kim Piracci noted the breaks are 50 percent of width (along the border of the property) and not in depth. Michael Harvey 116
affirmed that. He said the Orange County Board of Commissioners has expressed some concern that the applicant is also 117
proposing to do some selective clearing within the MTC buffer for utility infrastructure and roadway networks. This will be 118
discussed more in this review. 119
120
Paul Guthrie asked whether there is any knowledge of long-term expansion of I-40 in that area. Michael Harvey said 121
expanding has to occur in the 300-foot right of way unless the federal government procures more land. There is talk of 122
expanding I-40 into three lanes as it is in Durham. He believes that can be accommodated with the existing right of way. 123 124
Michael Harvey said on Page 13, the first condition up for discussion is Condition 6, contained in Attachment 7, granting 125
Orange Rural Fire Department denial authority. The applicant has indicated they don’t mind the fire department being a review 126
party but they don’t think the fire department should have power to deny the application. Instead, the applicant suggests the 127
power to deny the application be left to the fire marshals from the Town of Hillsborough and Orange County. The Orange 128
County Board of Commissioners has requested this board’s opinion on whether Orange Rural Fire Department should have 129
denial authority. Typically, fire departments review such applications but do not have authority to deny them, Michael Harvey 130
said. 131
132
Tony Blake said the intent was they be included in the review but not have approval or denial. The main thing is they be 133
involved. Michael Harvey asked for a show of consensus to modify the condition to allow Orange Rural Fire Department to 134
have review but not denial authority. 135
136
MOTION by Randy Marshall that Orange Rural Fire Department have a review but not action to approve or deny the 137
application. Seconded by Hunter Spitzer. 138 VOTE: Unanimous 139
140
Michael Harvey continued with the presentation. He reviewed the next condition to be discussed involves the MTC 141
buffer. The applicant does not propose any disturbance breaks in District 1, which is the industrial district. The 142
applicant had asked for clearing 60 percent of the buffer instead of 50 percent in District 2. The Orange County Board 143
of Commissioners expressed reservation about allowing the additional clearing. The applicant has since submitted to 144
staff that they will abide by the ordinance allowing clearance of 50 percent of the buffer. They have delineated a 145
clearing limited to 50 percent. They are not limited due to the clearing associated with the utility easement. Regarding 146
additional allowances for modifications to the MTC buffer, the applicant has shown a 100-foot buffer going up to the 147
utility easement and then the applicant is asking for a variable width MTC buffer instead of 100 feet. Based on the 148
narrative reviewed at the Oct. 4, 2017, Planning Board meeting and the public hearing, the MTC buffer would be 149
cleared for accesses and stormwater feature construction. The Planning Board is asked to give feedback on the 150
proposed variable width of the MTC buffer, proposed to be 50 feet instead of 100 feet in some places. 151
152
Kim Piracci asked for clarification because she is unclear why it’s sometimes 50 feet and sometimes 100 feet. 153
Michael Harvey answered the variable width would be to accommodate an access road, parking and a stormwater 154
feature. 155
156
Paul Guthrie asked if the buffer is intended to be a sound buffer and a visual buffer. Michael Harvey answered right 157
now it serves as both but it borders a major highway and there are already significant breaks in the buffer, including 158
the interchange, which allows sound to travel. While the Orange County Board of Commissioners realized allowing 159
50 percent breaks in the buffer would have a sound impact, they also understood that it allowed marketing of the site. 160
161
David Blankfard asked for clarification about the parcel to the north. Michael Harvey answered that the applicant is 162
choosing to propose a solid buffer for District 1. 163
164
Approved 1/10/2018
Hunter Spitzer asked why the developer is asking for more clearing. Michael Harvey reviewed that it is for an access 165
road, parking and a stormwater feature. 166
167
Tony Blake asked if the breaks are for signage. Michael Harvey answered no, there are signage regulations and they 168
are not permitted in the buffer. The breaks are for the purpose of drivers on the interstate being able to see the 169
development. No billboards are allowed. There are still signage limitations. 170
171
Lydia Wegman asked to hear from the developer on the variable buffer request. 172
173
Jim Parker spoke representing the developer. He said as much as we like to preserve buffers and trees, this is an 174
economic development parcel that needs visibility from the highway. The end users who will use this property will 175
want to be seen from the highway. If we can’t provide that, we’ll lose opportunity. The visibility would be one of the 176
key reasons businesses would want to locate here. 177
178
Lydia Wegman asked if stormwater accommodation and parking is secondary to visibility to the road. Jim Parker 179
confirmed that. 180
181
David Blankfard asked have you started developing what you plan to do in that area for signage. Jim Parker 182
answered no, we’ve laid out some building footprints to give us an idea of how the circulation could work. What we 183
anticipate is plausible in terms of parking. The hotel would be located where you would expect it to be on one of the 184
highest points with good visibility from both directions. This is an economic development area at an interchange. 185
Again, we are supportive of trees and buffers that protect residential developments. Neither the motorists nor the 186
businesses that would locate there care about the buffer. The businesses want to be seen. 187
188
Paul Guthrie asked, from Jim Parker’s general perception, would this development fill out quickly. Jim Parker 189
answered if the economy stays as it is and sewer service is extended quickly, it will. Since we have made it public in 190
the last 2 or 3 months, we have had a lot of interest but no one is going to sign until they know it’s coming and they 191
can count on it. But to answer your question, I think it will. 192
193
Kim Piracci asked if the two little restaurants would be fast food restaurants. Jim Parker answered affirmatively. He 194
said he was hoping for a sit-down restaurant but businesses in this type of development all work together. 195
196
Kim Piracci asked if there has been a feasibility study of the best use of this land. Jim Parker answered we have 197
done our own studies, which are nonscientific and I don’t know if any are. On our team, we have brokers who deal 198
with this day to day and know how to bring commercial users. They are excited about the property and opportunity. 199
200
Hunter Spitzer checked that the reduction of the depth of the buffer is also for visibility. Jim Parker answered yes, in 201
addition to parking and access drives. 202
203
Lydia Wegman asked if 100 or 75 feet would be problematic. Jim Parker said he’s not trying to be flippant but if they 204
thought they could get by with 75 feet of buffer, they would have asked for that. They are asking for what they need. 205
206
Craig Benedict said they have re-landscaped that parking lot with a tree every 10 parking spaces. Any encroachment 207
has to be re-landscaped in accordance to what use is going on in there. 208
209
Michael Harvey said in summary, regarding the MTC buffer issue for this project, the applicant had requested 60 210
percent breaks and county commissioners did not react with great comfort to that request. The applicant has said 211
they’ll stick with 50 percent breaks but they are asking for reducing the remaining buffer from 100 feet to 50 feet in 212
some places. Michael Harvey asked for the general reaction of the reduction of the buffer from 100 to 50 feet. 213
214
Kim Piracci said I’m remembering all the local residents at the public hearing were very concerned about the noise. I 215
don’t like the idea of cutting all those trees. The developer can come up with another way. Once a tree is cut down, 216
it’s gone. Planting a bush doesn’t make it better. 217
218
Hunter Spitzer said considering the board didn’t want the 60 percent break, the commissioners probably don’t want 219
Approved 1/10/2018
the variable buffer. Michael Harvey said the board wanted to hear feedback from this board and didn’t take a 220
negative or positive reaction to the request. 221
222
Craig Benedict said District 1 has no breaks even though that would be allowed by code. The Master Plan zoning 223
brings forth the variability. Regarding the resident comments, there were some from Davis Road to the southwest 224
and some comments from the northwest. The northwest is on the north side of the interstate, so anything we remove 225
to the south of the interstate isn’t going to impact residents on the north side of the interstate, he said. 226
227
Patricia Roberts said it’s interstate. It’s going to take a lot more than 100 feet to reduce that noise. If you live near the 228
interstate, you get used to that noise. She would like to see as much development close to the interstate as possible 229
to keep the rural areas rural. Coming from Durham, there is no development at the interchanges in Orange County 230
and then there is when you reach Alamance County. Our taxes are too high because we don’t have a commercial tax 231
base. 232
233
Tony Blake said when I look at the map, it looks like there is additional buffer along parcels 3, 5, 6 and part of Parcel 234
9. He’s inclined to say you could get away with 50-foot buffer on Parcels 3, 5, 6 and maybe the first part of Parcel 9 235
and then have the 100-foot buffer up to the second wet area. It just seems to me like there is compromise here. I 236
agree with Patricia Roberts that this is the place you’re going to want development if you’re going to have any. And 237
Orange County really needs it. 238
239
Adam Beeman said there is nothing worse than driving up and down the interstate and not being able to see what’s 240
at the exit. He wants to be able to see where the hotel is. 241
242
Michael Harvey said the applicant has one clarification. There will be a 100-foot buffer along the property line that is 243
not along the interstate. The applicant offered additional buffer for the people who live on the other side of that 244
property line, following the District 3 boundary. He said the stream buffer is obviously required to remain in tact. 245
Obviously, there would not be a 100-foot buffer at the road access point. Kim Piracci checked that it would be written 246
down. Michael Harvey said he believes it already is. 247
248
Kim Piracci asked whether the trees are old growth. Craig Benedict answered the trees are mostly pines and are 60 249
to 80 years old. 250
251
Paul Guthrie asked if most utility corridors will be underground and will they follow transportation routes. Michael 252
Harvey answered obviously Orange County tries to work with utility partners for some semblance of rationality. In 253
some instances, the county is successful. Sometimes you have to take a path of least resistance (for sewer and gas). 254
Electric is dictated where it ties into substations. Utilities are more adept at dictating where they need to go than at 255
taking direction from government entities. 256
257
Paul Guthrie said some uses on these parcels could be heavy users of utilities and he wonders how far in advance 258
utilities are planned. Michael Harvey answered utility companies are involved in the reviews early on. Predominately, 259
underground utilities are used for these larger sites. Gas could be a potential issue here because the developer could 260
have to secure easements. Water is secured. The Town of Hillsborough has to sign off on every site plan that there is 261
adequate capacity for both water and sewer. 262
263
Paul Guthrie said from my experience, what you say regarding utilities dictating where they go is largely accurate. 264
But if you stand up to the utility, something will happen. Michael Harvey said he has been in Orange County 13 years 265
and he has stood up to a lot of people, but utility companies tend to not back down on where they need to locate 266
utilities. Tony Blake asked if Duke Energy owns the easement. Michael Harvey confirmed. 267
268
Kim Piracci said her taxes went up 27 percent this year so she is on board with development. In terms of the buffer, 269
she’d rather see 100 feet because she likes trees. 270
271
David Blankfard asked how often the MTC buffer has been reduced to 50 feet. Craig Benedict answered that the 272
county hasn’t had development to use it. Michael Harvey said the county came close to it with the proposed 273
Buckhorn Village development, which didn’t get developed. 274
Approved 1/10/2018
275
Patricia Roberts if Buckhorn Village didn’t get built because the developers didn’t get the buffer reduction they 276
wanted. Michael Harvey answered no, it was approved but the downturn in the economy killed it. 277
278
Lydia Wegman said she is supportive of the plan. 279
280
Michael Harvey said the next condition is regarding architectural landmark and portal signs. That will be presented at 281
the January meeting. He clarified there will not be external illumination. 282
283
Regarding land use for elementary, middle and secondary schools, the county has reached out to the Orange County 284
Schools Board of Education. The county had expressed concern about schools being located at an industrial site and 285
is waiting to hear from the school board. The concern is about allowing schools in District 1 near industrial sites. Tony 286
Blake asked would that preclude having a corporate training site. Michael Harvey answered no, just schools teaching 287
pre-K through 12th grade. 288
289
Paul Guthrie said there would be episodes of heavy traffic if schools were allowed. Will there be adequate access at 290
peak times? Michael Harvey said that has been asked and the developer is looking at that. 291
292
Patricia Roberts asked if there is a need for more schools right now. Michael Harvey answered there is not 293
anticipated need for a school according to the Schools Adequate Public Facilities Ordinance (SAPFO) for 10 years. 294
He said there is thought that a school should be closer to Gravelly Hill Middle School or Efland Elementary School. 295
He thinks the developer was looking to the future. 296
297
Craig Benedict said we do have SAPFO. There is not a need for an elementary or middle school in the next 10 years. 298
Cedar Ridge High School is being expanded now. School land-banking opportunities are most likely needed in the 299
western area of the county due to the growth in Mebane. A school use was more pertinent when District 3 was being 300
considered. That would have been residential and even though it was proposed to be senior housing, a school in that 301
residential area would be more appropriate. He added that having a school in an area where you want tax base 302
would not be the best use. 303
304
Michael Harvey reviewed there is an additional condition that looped water systems would be required to provide 305
additional water flow and pressure in each district. The developer has tweaked alternate language saying looped 306
water systems may be required and are ultimately the responsibility of the developer. County staff will be meeting 307
with the applicant to further work on this language. 308
309
Tony Blake said if you’re going to make this a “could” or “may,” you should define what adequate flow pressure is. 310
Michael Harvey said he thinks Craig Benedict wanted something specific to address a concern he had about water 311
pressure. 312
313
Tony Blake said water pressure is a measurable thing. Craig Benedict said we’ll be moving toward saying it will meet 314
fire code and building code. We’re not going to mandate something that’s not necessary. We’ll put some sort of 315
standards in there. It will be based on occupancy code. If there is a multi-story hotel, the pressure may need to be 316
higher in that area. 317
318
Tony Blake said flow is critical for the rating of the insurance. 319
320
Lydia Wegman checked that staff and the developer will continue to discuss. Michael Harvey confirmed. 321
322
Michael Harvey continued his presentation. He said the developer had several conditions associated with the TIA 323
and external and internal traffic improvements. He reviewed the existing conditions map. He reviewed where 324
stoplights would be installed in Phase 1. He said the developer wanted everyone to know there was supposed to be 325
a stoplight at that intersection at Waterstone. The developer is planning to install it if it doesn’t get there first for 326
Waterstone. 327
328
David Blankfard asked for clarification about the lights, that it would be located at the exit. Michael Harvey said it was 329
Approved 1/10/2018
supposed to be installed with Waterstone but they would be doing it as part of this project. 330
331
Michael Harvey reviewed where there would be an installation of a left turn lane on Service Road and on Old 332
Highway 86. 333
334
Michael Harvey then showed the 2022 buildout map. There would be two lanes of through traffic on Old Highway 86. 335
There would be a stoplight wherever the access to District 2 is built. He noted Davis Road remains unimproved. He 336
said two individuals raised concern that Davis Road would become a five-lane road. In his 13 years, he’s not seen 337
that plan. 338
339
Michael Harvey said Ed Sirgeny with Summit Engineering is present to answer questions. Michael Harvey said 340
District 1 is meant to be served by Service Road. Staff would like the developer to work on having another access. 341
Staff also needs additional time to review some of Jim Parker’s comments on the TIA. 342
343
Tony Blake asked about a super street. Michael Harvey answered I’m not going to say it’s totally abandoned because 344
it may have to happen. The developer has done its best to show we’re not going to get to the point to compel Service 345
Road to have to right turn and U-turn. Tony Blake said the concern was how to make a U-turn with a tractor trailer. 346
347
Craig Benedict said a memo was received the day of the public hearing from DOT saying there was no need for a U-348
turn. Now they’re saying you can have 900,000 square feet of warehousing or equivalent. After that would be the 349
trigger point in District 1 of having to come up with another connection farther to the south. It still allows the left turn 350
movement for a long period of time. Service Road was created when I-40 was built. DOT put it where they thought it 351
could be signalized. Now they want more space between a signal and the interstate ramp. That much can be built 352
without the need for the U-turn. 353
354
Michael Harvey said the applicant was required by staff to provide the breakdown, which he shared. It included land 355
use, size, units, adjacent street traffic volumes weekday morning and afternoon peak hours. 356
357
Jim Parker said Tony Blake, if your question is if other accesses have been explored beside Service Road, yes. 358
359
Tony Blake asked if anyone has approached DOT about combining the exit ramp and Service Road. Jim Parker 360
answered no, DOT used to do that but they don’t like that anymore. We understand there is a limit to this working 361
fluidly. Level of service is going to dictate the service road functioning. DOT is not going to allow level of service to 362
decline beyond a certain point. We will continue to try to look for alternatives to make the whole thing work. 363
364
Tony Blake said with this zoning, it doesn’t come back before the Planning Board or Orange County Board of 365
Commissioners so I want to make sure we hash it out as much as we can. 366
367
Michael Harvey said that’s not quite accurate. Right now there is access from Service Road. Any access to Old 368
Highway 86 would come back for a modification. If Jim Parker and his cohorts can find a way to get an alternative 369
access, there is going to be tweaking of the application. Every site plan application has to have a TIA. This 370
assessment is required in Orange County when the traffic trips is expected to exceed 800 trips a day but for this 371
project it is for every project regardless of the expected trips per day. 372
373
Tony Blake spoke in favor of aligning the access along the power easement. Jim Parker said we have looked at a lot 374
of options. At this point, none of them are 100 percent viable. 375
376
Kim Piracci said I’m assuming that if traffic circles were appropriate, you would consider that. 377
378
Michael Harvey said any viable traffic alternative would be studied but may not be appropriate here because tractor 379
trailers would be using this road. Traffic circles aren’t a bad thing but it’s not as viable here as in other locations in 380
Orange County. 381
382
Michael Harvey asked for other comments on the TIA. He said it sounds like the board is comfortable with the revised 383
condition, eliminating the U-Turn, revising the catch points on travel trips with the understanding that every project 384
Approved 1/10/2018
gets a TIA, and let the developer look for a long-term second access. Lydia Wegman said she concurred with that 385
statement. 386
387
Craig Benedict said he would be meeting on Thursday with the two new board members on this project. He will talk 388
about the traffic impact analysis with them. There are about 14 improvements. It’s going to be important for the 389
general public and elected officials to understand them. 390
391
Michael Harvey said in conclusion, there were requested revisions of the concept plan. He reminded everyone they 392
don’t have a project yet. This is to provide an idea of where buildings and stormwater features would go. The county 393
commissioners suggested a tree survey be done. A detailed tree survey is not possible in the timeframe given to the 394
applicant. Staff will work with the developers. 395
396
Michael Harvey said the developer has provided a better buffer plan. He thinks there is a greater comfort level and 397
the Planning Board will look at this again in January. Orange County has one of the most restrictive buffer programs 398
in the state for streams and wetlands. These developers have said they will comply with all those requirements. For 399
us, the buffer program is very established. 400
401
Michael Harvey reviewed there was some concern about outdoor lighting and on Page 16, staff has provided 402
information on the county’s current outdoor lighting standards. Because we are a community that requires full cut-off 403
fixtures, you are not going to see some of the light pollution you see in other communities, especially as seen at 404
Hampton Pointe. There were still be some glow. The applicant has looked into the viability of turning off some lights 405
at night but the developer has said some lights have to be left on to secure the property. There will be some 406
measures to buffer the lighting. He said the ordinance addresses light glare and light overpass. 407
408
Kim Piracci wanted confirmation that Michael Harvey did say in Orange County the lights have to be full cut-off. Craig 409
Benedict confirmed and answered that change was made about 10 or 12 years ago. You want some lighting out 410
there for the safety and comfort of the business and the patrons. 411
412
Lydia Wegman asked if this would be coming back in January. Michael Harvey said he will have a more formal 413
response from the applicant in January. He noted this does not seem to be a concern of the board. 414
415
Michael Harvey said on Page 17, there is the condition addressing retail space. The Town of Hillsborough has 416
expressed concern about retail and its effect on redevelopment in town and recommended limiting retail to 20 417
percent. He said the applicant has suggested limiting retail to 30 percent, not to exceed 78,540 square feet. He 418
shared the staff response, which includes that staff believes Orange County is blessed to have two interstates in the 419
general area. The county doesn’t think retail should be limited. Michael Harvey said there is sufficient travel trips 420
above the Interstate 40 and Interstate 85 areas to support two distinct travel nodes in this area. The joint planning 421
land use plan as adopted by the town and county agrees that retail is viable in this area. The county staff encourages 422
the town to support the 30 percent limit on retail. 423
424
David Blankfard asked if the developer wants more than 30 percent. Jim Parker said no, 78,540 square feet is 425
reasonable for this area. He said it is aggressive but doable. He said as Michael Harvey said, this is an interstate 426
market. There is another interstate market closer to town that may or may not end up being an interstate market. It 427
may end up being more conducive to something else. This is a drop in the bucket compared with that one. 428
429
Craig Benedict said Walmart’s and Targets are 130,000 square feet, so we’re not talking about big-box retail. He said 430
if we get to 900,000 square feet of office and warehouse and industrial, you want supportive retail so people can 431
shop and eat in that area. The market for this retail is two-fold. One is the interstate market, plus the internal capture 432
of the development of the other employment whether it’s warehouse or hotel. 433
434
Hunter Spitzer asked if combined retail is stores and restaurants. Craig Benedict answered affirmatively, adding there 435
is potential for maybe dry cleaning, barbers, hair salons, and restaurants. 436
437
Lydia Wegman said 30 percent makes sense. Tony Blake agreed. 438
439
Approved 1/10/2018
Michael Harvey said a county commissioner suggested a condition to limit business hours. The applicant has 440
indicated that such a condition is incredibly problematic. Staff has not pursued a condition on that. Lydia Wegman 441
said that makes sense. 442
443
Michael Harvey reviewed the applicant has addressed the concern of overall buffer impacts of the project and there 444
will be more discussion in January. 445
446
Paul Guthrie asked what the terrain would be around the stormwater ponds. Will they be empty and full depending on 447
the rainfall, he asked. Michael Harvey answered as the stormwater facilities haven’t necessarily been submitted for 448
review, he doesn’t know if they will be full constantly or only full as there is inundation. Typically, there is landscaping 449
around the feature. A stormwater facility doesn’t necessarily mean a big pond. It can be a rain garden. It can be a 450
subterranean facility. Since there will be a push for capturing stormwater, he thinks the facility will be minimal. There 451
are some limitations we’ll have to live with within state law. He thinks the developer will avoid big mosquito pits 452
because it’s bad for development. 453
454
Paul Guthrie said he wanted more specifics. Michael Harvey said any time a stormwater feature is developed, the 455
county requires the developer secure a maintenance agreement and submit documentation. Development in Orange 456
County is held to a stormwater standard. It will be addressed on every feature. Developers are required to post bonds 457
to maintain the stormwater features. 458 459
Craig Benedict reminded the board the next meeting is not Jan. 3 but instead Jan. 10. 460
461 AGENDA ITEM 8: POPULATION AND EMPLOYMENT PROJECTIONS - To receive information on population 462
and employment projections for Orange County. 463
464 Presenter: Craig Benedict, Planning Director 465
466
Craig Benedict reviewed the abstract. He reviewed that comments can go straight to the Metropolitan Planning 467
Organization. Every four or five years, the MPO puts together projections. This is the 2045 Metropolitan 468
Transportation Plan Preferred Option. He reviewed that Orange County is also a participant in the Burlington 469
Metropolitan Planning Organization. He reviewed that commissioners Barry Jacobs and Penny Rich are on the policy 470
board that meets in Durham. He reviewed the MPO has a 20-year plan. And there is also a 10-year State 471
Transportation Improvement Program (STIP). This includes MPTO’s TIPS plus rural projects. 472
473
Craig Benedict reviewed that a statistical poll company estimates the populations. He said we still question some of 474
that analysis. He shared the slide that lists all the goals and objectives. There are state, regional and local funding 475
priorities. He explained our input into local projects has to score well. 476
477
Craig Benedict shared the slide with the population projections. The projection was 200,000 in 2040 but now the 478
projection is for 195,000 in 2045. That’s important for us to gauge where our service needs are, he said. 479
480
Craig Benedict said from 2005 to 2015 there has been some loss of employment. He said this was due to the 481
recession and hasn’t recovered. Tony Blake asked if there are more retired people. Mr. Benedict answered the 482
projections are taking land use into consideration. Also, previous years people thought we could compete with Wake 483
and Durham counties. But from the land use side and ability to develop, the “ground truth” is different. 484
485
Craig Benedict noted Chapel Hill and Carrboro will have more multi-family homes but in the rest of the county more 486
single-family homes. Hunter Spitzer asked why not single-family development in Chapel Hill. Craig Benedict 487
answered there isn’t much green space left and so developers are developing what is left with multi-family units and 488
it’s been noted that families are moving into three-bedroom, multi-family units. 489
490
Craig Benedict shared the employment projection slides. He summarized that the projection would call for two of the 491
former Blue Cross/Blue Shield buildings every year for a total of more than 13 million additional square feet by 2045. 492
Craig Benedict said those are aggressive employment projections. Kim Piracci asked where the standards of space 493
per employee comes from. Craig Benedict answered it is a blended industry standard. 494
Approved 1/10/2018
495
Craig Benedict reviewed that light rail is still being pursued between the University of North Carolina-Chapel Hill and 496
North Carolina Central University. Nodes are being identified. 497
498
Craig Benedict shared a slide of projected rural sprawl called Household Distribution. He noted Orange County’s 499
rural buffer was created in 1987. 500
501
Craig Benedict reviewed the employment distribution slide. Tony Blake asked if walkability is being considered 502
because that would be only a quarter mile from the light rail stop. Craig Benedict said a quarter mile to a job and 503
upwards of a half mile to home. 504
505
Craig Benedict noted the projects of the MPO are in the agenda packet as well. 506
507
Lydia Wegman asked if these are projects that have been approved. Craig Benedict said of the 10 projects, some of 508
those are in the first five years. 509
510
Craig Benedict noted this is the public comment period for this plan. Comments can be made directly to the MPO 511
staff. 512
513
Lydia Wegman asked if there is a website for comments and if the Orange County Planning Board can submit 514
comments collectively. Craig Benedict said members can say, “I am a member of the Orange County Planning Board 515
and I think X.” Or members can speak with himself or Tom Altieri to fashion comments in a more constructive way 516
and staff can send them on to commissioners Jacobs and Rich. 517
518
Randy Marshall asked if OUTBoard and Planning Board should consolidate comments on this. OUTBoard worked on 519
transportation plans and he thinks it would be informative. Craig Benedict said the Planning Board could have a 520
hybrid meeting with the OUTBoard. 521
522
Lydia Wegman asked when comments are due. Craig Benedict answered Jan. 10. Lydia Wegman noted the 523
Planning Board does not have time to coordinate comments with other boards. Craig Benedict said he would 524
communicate with the Planning Board and OUTBoard on how their comments can be submitted in time. 525
526
AGENDA ITEM 9: COMMITTEE/ADVISORY BOARD REPORT 527 a. Board of Adjustment 528
b. Orange Unified Transportation 529 530
No report provided. 531 532 AGENDA ITEM 10: ADJOURNMENT 533 MOTION by Paul Guthrie to adjourn the December 18th Planning Board Meeting at 9:27 p.m. Seconded by David 534
Blankfard. 535 VOTE: Unanimous 536 537
____________________________________ 538
Lydia Wegman, Chair 539
540