HomeMy WebLinkAboutCapital Project Policy - revision to policy adopted 12-7-1996 3
(Adopted 12/7/96)
Orange County Board of Commissioners
Capital Funding Policy
A. Sources of Funds
The following sources of funds will be allocated for Capital Projects and Debt Service:
1. All proceeds from the Article 40 and Article 42 one half sales tax
The North Carolina General Statutes require that 30 percent of the Article 40 and 60
percent of the Article 42 sales tax revenue be earmarked for school capital projects or
debt service on debt issued for school capital projects.
2. Revenue from the property tax as follows:
• $800,000
• The equivalent of 2.7 cents on the tax rate based on valuation as of 1996-97.
This earmarking will be adjusted each revaluation cycle.
• The amount necessary to retire the 1992 School Bonds. (In 1997-98 this amount
is $4.7 million.)
• The amount of the reduction in the Human Services function of the County
budget(equivalent of one half of one percent of the budget or$50,000) in 1994-
95 for automation projects in Human Services.
• Utilities Extension Fund-This amount may vary in that it based on the increase
in property tax base as a result of expenditures in the Utilities Extension Capital
project. The amount currently planned is $35,000 for 1997-98 and $25,000 for
each year thereafter.
3. Impact Fees for each school system.
4. Public School Building Fund
5. Other revenues that are restricted including, payment-in-lieu, grant funds, rental revenue
and inmate fees as a result of the new jail addition.
B. Debt Service
Prior to funds being allocated for specific projects, all debt service, including private placement
financing will be subtracted from the unrestricted funding sources. As an exception, the
Orange County Schools are responsible for funding directly from their pay-as-you-go capital
allocations, that portion of the cost of a new high school in the Orange County School system
beyond the $12.5 million bonds approved by voters for that school in November 1997.
C. Allocation
All sources of unrestricted revenue, less debt service, is then allocated between County and
School projects based on 50 percent of the net amount for School projects and 50 percent of the
net amount for County projects. Funding between the two school systems will be allocated
based on the 20t day enrollment adjusted each year. For example, the 20`h day enrollment as of
September 1998 will be the basis of the 1999-2009 Capital Improvements Plan. These
percentages will be rounded to one decimal place.
4
Impact fees will be projected and allocated to each school system, although these fees may be
used to pay debt service. When impact fees are used to pay debt service, the equivalent amount
of the projected impact fee will be allocated to each school system. For the first three years of
the planning period (1997-98, 1998-99 and 1999-2000) impact fees are dedicated to the cost of
the new schools.
All funds allocated to capital projects are to be accounted for in a Capital Project Fund under
a Project Ordinance adopted by the Board of Commissioners. The Project Ordinance will
include a detailed break down of each cost category related to the project, as outlined in the
Sample Capital Project Ordinance at Attachment 1, which is incorporated by reference into
this policy..
D. Funding Levels
It is the intent of the Board of Commissioners to "hold harmless" School projects and County
projects as identified by the amount of funding projected in the 1996-2006 Capital
Improvements Plan. To achieve this intention,the following funding options will be used:
• The difference between the amount of general obligation debt service payments
at the peak year of the debt schedule and the actual debt service payment will be
earmarked for the Orange County Schools until the time that any shortfall that
would have been realized by that system is made up.
• For County projects,beginning in 1998-99 the equivalent of one cent on the
general fund property tax rate will be necessary. The Board of Commissioners in
adopting this policy instructed staff to identify other funding options rather than a
tax increase to make up this shortfall. The Board of Commissioners may
consider shifting the one cent capital reserve fund to be dedicated to County
projects (see Capital Reserve section below).
E. School/Parks Capital Reserve
The school/parks capital reserve fund, established by the Board of Commissioners in 1995-
96, receives annual allocations equivalent to one cent on the General Fund Property Tax
Rate (not adjusted for the 1997 revaluation of property but adjusted for revaluation of real
property beyond the 1997 revaluation.) This reserve will accumulate during 1996-97 and
1997-98 with these funds used for site acquisition for schools and or recreation, or the
combination of both. The Board of Commissioners will evaluate this reserve fund during
1998-99 to determine if this one cent reserve should continue.
F. School/Parks/Recreation
It is the intent of the Board of County Commissioners to evaluate each new proposed school in both
School Districts for joint use to include park and recreation use.
5
G. Recurring Capital
Recurring capital for each School System will be based on the equivalent of three cents on the
General Fund Property Tax Rate (not adjusted for the 1997 revaluation of real property but adjusted
each revaluation thereafter.) Funds will be allocated to each school system based on the State
Department of Public Instruction planning allocation which is the same method used to allocate
current expense appropriation.
H. Planning Period
During each fiscal year,the Board of Commissioners shall adopt a ten year Capital Improvements
Plan. The ten year plan shall include anticipated County capital expenditures costing $30,000 or
more(excluding equipment) and anticipated school capital expenditures costing $50,000 or more
(excluding equipment). Equipment costing $1,000 or more can be considered as part of the Capital
Improvements Plan. The first year of the adopted Ten Year Capital Improvements Plan shall be
incorporated into the next annual operating budget recommended by the County Manager.
6
Project Name
School System (if a School project)
Capital Project Ordinance
Project Number 6X-XXX-XXXX
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section 13.2
of Chapter 159 of the General Statutes of North Carolina, the following capital project is hereby
adopted.
Section 1. The project authorized provides funds to
This project will be financed with proceeds from
Section 2. The officers of the County are hereby directed to proceed with the project within the budget
contained herein.
Section 3. The following revenue is anticipated to complete this project:
Transfer from Other Funds $0
Bond Proceeds $0
Impact Fees $0
Other Revenues as Appropriate $0
Total Revenue $0
Section 4. The following amount is appropriated for this project:
Planning & Design Fees $0
Land and Associated Fees $0
Construction $0
Equipment and Furnishings $0
Technology $0
Other Line Items as Appropriate $0
Contingency $0
Total Project Costs $0
Section 5. This ordinance shall remain in effect from July 1, 199X until June 30, 199X.
Adopted this XXst day of , 199X.