HomeMy WebLinkAboutAgenda - 02-23-2017 - Abstract for Joint Meeting Discussions 1
ORANGE COUNTY BOARD OF COMMISSIONERS
HILLSBOROUGH BOARD OF COMMISSIONERS
JOINT MEETING
AGENDA ITEM ABSTRACT
Meeting Date: February 23, 2017
SUBJECT: Joint Meeting Discussion Items
DEPARTMENT: County Manager/Town
Manager/Town Planning &
Economic Development/
County Planning & Economic
Development/County
Planning/County
Housing/County Transit
ATTACHMENT(S): INFORMATION CONTACT:
As noted in "Background" section Bonnie Hammersley, 245-2300; Eric
Peterson, 732-1270; Margaret Hauth, 732-
1270; Travis Myren, 245-2300; Steve
Brantley, 245-2326; Craig Benedict, 245-
2592; Theo Letman, 245-2007; Greg
Wilder, 245-2300
PURPOSE: To discuss topics of mutual interest between the governing boards of Orange
County and the Town of Hillsborough.
Information on the topics below is provided based on the following parameters directed to staff:
* staff asked to be ready to provide/present basic background information if requested in
the course of the discussion
** staff asked to prepare a brief (e.g. one paragraph) written summary/update on topic in
advance of meeting to accompany agenda, with links to additional information if
warranted.
BACKGROUND:
1. Residential Growth/Affordable Housing
This subject area provides the opportunity for the two governing boards to discuss the following
items:
a) Overview of approved/pending Hillsborough residential growth**
2
Approved & Under Construction
Project name Approved units Permitted Completed Remaining
Bellevue apartments 114 114 0 114
Cates Creek Apartments 270 270 207 63
Corbin Creek Woods 18 18 18 0
Corbinton Commons(SF only) 70 10 1 69
Elfin Pond 104 44 34 70
Fiori Hill 46 0 0 46
Forest Ridge 233 69 44 189
Lennar townhomes(Waterstone) 200 0 0 200
Waterstone Estates 136 119 99 37
Waterstone Terrace 114 84 62 52
Total 1305 728 465 840
Pipeline
Project name Approved units Type
515 N 24 condos
Collins Ridge 1038 master plan approval only
Corbinton Commons 141 senior apartments
Approved,not under construction 1203
Under Review
Project name Requested units Type
Collins Ridge-Phase 1 326 apartment
152 townhome
194 detached
Under review 672
The Boards can discuss issues related to this item as necessary, and staff will be
available at the meeting.
No Attachments
b) Affordable housing in conjunction with approved or pending residential
growth**
Waterstone deeded 2.25 acres in the townhome neighborhood to The Community
Home Trust for development as affordable townhomes. The Trust has since
deeded the property to Habitat for Humanity. The town expects to receive a
Special Use Permit modification for its April Public hearing to review the
development plans for Habitat to construct 24 senior targeted affordable units on
this parcel. Waterstone is also committed to provide $5,000 per affordable unit to
the property owner at the time of building permit issuance for each affordable unit.
Forest Ridge is making a $1,000 per dwelling unit payment in lieu to the town
before each permit is issued in this 240-unit development. The town has
committed $5,000 to the Community Empowerment Fund to help with deposit
assistance for income eligible residents seeking rental housing in Hillsborough.
The town has not developed a plan for the remaining funding, although Habitat
has requested some financial support for the Waterstone townhomes.
Collins Ridge has committed to the gift of 3 acres to CASA for that organization to
develop 60-88 affordable rental units. The property must be transferred no later
than 30 days after receiving the first building permit.
3
The Boards can discuss issues related to this item as necessary, and staff will be
available at the meeting.
No Attachments
c) Potential Orange County Bond/Additional Affordable Housing Opportunities
(e.g., Orange County owned parcels*, Housing Choice Vouchers, land
banking, Habitat for Humanity, safe housing and minimum standards)
The Boards can discuss issues related to these items as necessary, and staff will
be available at the meeting.
No Attachments
d) Infrastructure/Utility Issues and Limits;
(e.g. water/sewer capacity*, service boundary agreement, annexation of
existing neighborhoods*)
The Boards can discuss issues related to these items as necessary, and staff will
be available at the meeting.
No Attachments
2. Economic Development
This subject area provides the opportunity for the two governing boards to discuss the following
items:
a) Downtown Improvements and Redevelopment
(update of downtown improvements**, downtown redevelopment
opportunities*, former Colonial Inn update
All needed NCDOT approvals are finally in-hand for the downtown access project.
The Town has a contractor and is finalizing the contract details so that work can
begin when weather allows. The east side work adjacent to the courthouse will be
done first, and then work will move to Tryon Street and move south. Staff expect
to hold a public information meeting very soon to keep the merchants involved.
There is also an email list for merchants and other to receive regular updates.
Work will continue through the summer. Once the sidewalk work is completed,
NCDOT will have to schedule resurfacing of Churton Street. Once that is
scheduled and complete the stamped crosswalk improvements will be the final
step. Stephanie Trueblood is the primary contact for this project and all
communications with merchants and the public will route through her.
The Boards can discuss issues related to these items as necessary, and staff will
be available at the meeting.
No Attachments
4
b) Economic Development District (EDD) Development and Infrastructure*
(update on sewer extension**; commercial development recruitment*)
Orange County, in conjunction with Town of Hillsborough Planning, has amended
land uses and zoning within the Hillsborough Area Economic Development
District. This area is under County planning jurisdiction but subject to the
coordinated planning agreement. An interlocal utility agreement that will set forth
utility extension provisions if installed or paid by the county is under review by joint
staffs.
This agreement is intended to focus and facilitate future economic development
by preinstalling infrastructure under 1-40 which often is a critical decision point for
site selection. Monies have been budgeted for primarily sewer extensions but a
partnership with the Town of Hillsborough for a water main loop outside of the
EDD could augment pressures in the larger zone. Orange County will be
advertising a Request for Qualifications (RFQ) for engineering design services for
this Capital Investment Plan (CIP) project in the coming weeks including Town of
Hillsborough participation.
A 271 acre development proposal was submitted for the southeast and southwest
quadrant of 1-40 using a conditional zoning district. The majority of the project is
planned for light industrial/research and commercial/retail/service with a
component of senior housing. This is under sufficiency review by staff and will be
shared with the Town of Hillsborough consistent with the joint courtesy review
agreement.
The Boards can discuss issues related to these items as necessary, and staff will
be available at the meeting.
No Attachments
c) Other Economic Development Updates
(US 70/Cornelius Corridor, West Hillsborough, 85/NC 10 area**)
Staff has been working with the Sheetz gas station for close to 2 1/2 years to get a
new gas station permitted on an approximately 1 acre portion of the old Paliouras
truck stop property across from Home Depot. Site plan and building plans have
been approved for some time. The Town provided courtesy review comments on
the site plan and approved the use of existing utility infrastructure (i.e. water and
sewer) in support of the proposed gas station. NC Department of Transportation
has also been involved in reviewing/approving the site plan. Delays on the
commencement of construction of Sheetz are related to the property owner's lack
of progress on completing required grading/infrastructure installation (i.e.
stormwater systems) including allowing permits, most notably erosion control and
grading permits, to lapse. Staff has remained in contact with Sheetz officials to
offer assistance as needed and Orange County Erosion Control has worked with
the property owner to keep the project moving forward. It is hoped construction on
the Sheetz facility will begin soon. There are rumors of a restaurant being located
adjacent to Sheetz but no formal site plan has been submitted denoting same. A
food truck has taken up operation(s) on the Paliouras property consistent with the
County's recently adopted food truck ordinance.
5
The Boards can discuss issues related to these items as necessary, and staff will
be available at the meeting.
No Attachments
d) Tourism and Arts (in coordination with Orange County Visitors
Bureau/Hillsborough Visitors Center/Tourism Board/Arts Commission/etc.)
The Boards can discuss issues related to these items as necessary, and staff will
be available at the meeting.
No Attachments
3. Transit/Transportation
This subject area provides the opportunity for the two governing boards to discuss the following
items:
a) Managing transportation/traffic impacts of new growth (Transportation
Improvement Plan Churton Street/Orange Grove Road update**; Rail Station
update**; circulator route update**; Go Triangle bus routes*; interstate
improvements and `by-pass' strategies*, Mayo-Eno Mountain project*; other
traffic mitigation projects*)
NCDOT has Kimley Horn under contract to design this project. Some preliminary
meetings were held last year. The alignment of the road has not yet been
determines. The best crossing type and location for the railroad is being
evaluated. Once that is determined, the remainder of the project will be more
certain. The project reschedule is unchanged in the draft Transportation
Improvement Plan (TIP) with Right of Way scheduled in 2020 and construction in
2023.
The rail station remains a committed funded project. There are some studies and
computer modelling requested by Norfolk Southern and the NC railroad whenever
a new passenger station is proposed to determine the potential impacts on freight.
The timing and necessity of these studies has not yet been settled among all the
parties.
The NCDOT Rail staff have suggested that the two new incoming administrations
at the state and federal level get settled in the first quarter of 2017 before any
further forward motion on this project occurs. It is expected there will be a
meeting with Rail Division staff in March to receive an update.
OPT Service Expansion Status:
• New Approved Services (June 2017)
— Efland-Hillsborough Commuter Loop
6
- Orange-Alamance Connector (US 70 midday) - CMAQ Grant
- Rural Zonal Routes - 2 days per week flexible routes
OPT Equipment Update:
• 3 Buses 28 foot, 20 passenger capacity ordered with bike racks and route
display signs.
- Delivery expected March 2017
• 2 FY2018 Replacement buses requested - Capital Grant pending approval
• Technology
- Software upgrade - contract approved
- Implementation February-March
• Mobile Data Terminals (MDTs)
• Passenger Call Back System
• Auto Scheduling
OPT Human Resource Changes
• New Transit Director- Theo Letman on staff as of Jan. 9, 2017
• Two part-time drivers hired - one completed training
• Continuous recruitment
• Three new hires pending
ORANGE COUNTY RIDERSHIP DATA FY2015-2 016
H Ilh,boroug,h EHills'boc'orugh [-NI to Hill Hillsborough Hill to Hull
Circulator Hill Po HM Hill to Hill Circulator Md tday Circulator Midday
Mtmith Riders. Midday Rdde, Midday Rde, Riders..Other 'iota/ R derVDay Hiders/Day R dens/IH o Riders/Hour
Jul'15 1,156 150 2,885 4,191 53 7 5.84 2.27
Aug 1,176 77 172 2„956 4,381 56 12 6.22 1.58
S42p 1,081 393 3,331 4,805 51 19 5.72 1.56
Oct 1,158 369 3,654 5,181 53 17 5.85 1.40
Nov 1,105 293 3„186 4,584 58 15 6.46 1,29
Dec L212 337 2,943 4A92 61 17 6.73 1.40
Jan 16 1,222 321 2,606 4,149 68 18 7.54 1.49
Feb L245 409 3,127 4,781 62 20 6.92 1.70
Mar 1,458 436 3,229 5,123 66 20 736 1.65
Apr 1,383 309 2,407 4,099 66 15 7.32 1.23
May L215 430 3,148 4,793 58 20 6.43 1.71
Jun 1,460 424 2,950 4,834 66 19 7.37 1.61
14,871 227 3,893 36,422 55,413
ORANGE COUNTY RIDERSHIP DATA FY2016-2017
'i,isb,roingh liii b 5cough Hal to Hill H ill yboreugh Hill tw Hull
Circulator Hill to Hid Hill tv Hill Circulator Midday Circulator Midday
Month Riders Midday R4deol MiddayRdees Riders Other Total Klaus/Day Riders/Day Rider./Hour Riders/Hour
Jul 16 L472 278 2,684 4,434 74 14 8.18 1.16
Aug. 1„842 531 3,165 5,538 80 23 8.90 1.92
Sep 1,436 531 3,450 5,417 68 25 7.60 2.11
Oct 1,480 584 3,386 5,450 70 28 7.83 2.32
Nov 1,56 0 593 3,273 5,426 78 30 8.67 2.47
Dec 1,426 4.14 2,866 4,706 75 22 8.34 1.82
Jan 17
FL_^fs _
Mar ...
Apr _ .
May .. _ ..
Jun .
9,216 - 2,.931 18,824 30,971
Efficiency
Peer Groom Average Boardir gs pel Hour 3.60 3.60
The Boards can discuss issues related to these items as necessary, and staff will
be available at the meeting.
No Attachments
7
b) Ped/Bike issues and strategies (Hillsborough connectivity plan**; sidewalks
across jurisdictions*; bikeshare program; Mountains to Sea Trail
connections*)
The town's connectivity plan addresses bicycle, pedestrian, and transit
improvements in town, along with other amenities in the public right of way. The
document is a component of our comprehensive plan and is regularly updated.
The bulk of this year's updates reflect the recent investments by the towns and
others to improve walkability and connectivity in town. The recommended
improvements focus on high traffic areas where safety is a concern for mixed
modal travel. The town's development code refers to this plan in requiring
developers to construct sidewalks.
The updated plan is approximately 100 pages long. The document begins on
page 34 of this linked plan set (the first 33 pages are pans for Collins Ridge)
https://www.hillsboroughnc.gov/media/plans/planning-board-plans-1-19-2017.pdf
The Boards can discuss issues related to these items as necessary, and staff will
be available at the meeting.
No Attachments
4. Intergovernmental Relations & Collaboration
This subject area provides the opportunity for the two governing boards to discuss the following
items:
a) Other opportunities/issues between Orange County and Hillsborough
(Fiber Cable Infrastructure*)
The Boards can discuss issues related to this item as necessary, and staff will be
available at the meeting.
No Attachments
b) Engagement with other towns
The Boards can discuss issues related to this item as necessary, and staff will be
available at the meeting.
No Attachments
c) Engagement with Orange County Schools
The Boards can discuss issues related to this item as necessary, and staff will be
available at the meeting.
No Attachments
8
FINANCIAL IMPACT: There is no direct financial impact associated with discussion of these
topics. There are no action items requiring formal Board decisions.
SOCIAL JUSTICE IMPACT: There is no Social Justice Goal impact associated with discussion
of the items above.
RECOMMENDATION(S): The Managers recommend the Boards discuss the topics listed and
provide appropriate direction to the respective staffs.